A device and construction method for convenient soil extraction in steel pipe piles
By setting up a steel frame platform and mud suction machine on the top of the steel pipe pile, the S-type positioning plate and the rail connection are simplified, and the problems of large volume and low construction efficiency are solved, and convenient and efficient steel pipe piles are realized Soil extraction reduces sewage generation and environmental pollution.
Patent Information
- Application Number
- CN202011162043.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-10-27
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2040-10-27
AI Technical Summary
The existing steel pipe pile soil extraction equipment has large volume, low construction efficiency, complex operation, and reverse circulation drilling method will produce a large amount of sewage, pollute the environment, and low construction efficiency.
Design a convenient soil extraction device, including setting up a steel frame platform on the top of the steel pipe pile, installing a mud suction machine, the straw of the mud suction machine extends into the bottom of the steel pipe pile to absorb the soil, and discharge the soil through the drain opening, adopt S The connection method of type positioning sheet and rail simplifies installation and disassembly, reduces equipment volume and improves construction efficiency.
The soil extraction device has a small size, convenient loading and unloading, convenient construction and simple operation, greatly improving construction efficiency, reducing sewage generation, reducing environmental pollution, and improving construction efficiency.
Smart Images

Figure CN112431202B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of civil engineering construction, and particularly relates to a device and a construction method for conveniently taking soil from a steel pipe pile. Background Art
[0002] At present, one of the methods for taking soil from steel pipe piles is to use large ship-borne equipment to pump mud, which is large in size and complicated to operate; another method for taking soil from the pipe is to use a circulating water pump to pump mud, which is inefficient and labor-intensive. If reverse circulation drilling is used to take soil, soil particles will be taken away by water, which will produce a large amount of sewage, pollute the environment, and have low construction efficiency. The efficiency of taking soil from steel pipe piles directly affects the construction efficiency of the entire project. Summary of the invention
[0003] The purpose of the present invention is to provide a device and a construction method for conveniently taking soil from a steel pipe pile, so as to solve the problems mentioned in the prior art that the existing soil taking equipment in the pipe is large in size, has low construction efficiency, and has a complicated operation method.
[0004] The first technical solution adopted by the present invention is a device for convenient soil extraction from a steel pipe pile, comprising a steel frame platform arranged on the top of the steel pipe pile, at least one mud suction machine is arranged above the steel frame platform, and the suction pipe of the mud suction machine extends into the interior of the steel pipe pile.
[0005] A steel frame platform is provided on the top of the steel pipe pile, and a sludge suction machine is arranged on the steel frame platform. The suction pipe of the sludge suction machine extends into the bottom of the steel pipe pile to absorb the soil, and then discharges the soil through the soil discharge port of the sludge suction machine. The soil taking device is small in size, easy to load and unload, convenient in construction, simple in operation, and greatly improves the construction efficiency.
[0006] Preferably, the steel frame platform includes an installation platform and at least one placement platform, the installation platform is movably sleeved on the top of the steel pipe pile, and the placement platform is suspended outside the steel pipe pile.
[0007] The installation platform is used for installing the soil taking device, and the placement platform is used for placing the sludge suction machine. When there are multiple placement platforms, they can be evenly distributed on the installation platform.
[0008] Preferably, a plurality of S-shaped positioning pieces are evenly arranged on the outer side of the circumference of the upper end of the steel pipe pile, and the S-shaped positioning piece includes an upper hook and a lower hook, the upper hook cooperates with the steel pipe pile, and the lower hook cooperates with the installation platform.
[0009] The installation method of the mounting platform on the steel pipe pile can be installed through multiple S-shaped positioning pieces. This installation method is simple, easy to operate, and stable and firm.
[0010] Preferably, the placement platform and the sludge suction machine are connected by rails on both sides, the two sides of the placement platform are concave rails, and the two sides of the sludge suction machine are convex rails, and positioning pieces are provided on the concave rails.
[0011] The placement platform and the sludge suction machine are connected by a rail, which makes it easy to install and disassemble. Positioning pieces are set on the concave rail to position the sludge suction machine, making its construction stable and firm.
[0012] Preferably, the front positioning piece of the concave rail is a positioning front plate, a plurality of positioning grooves are evenly arranged below the concave rail, and a positioning rear plate is arranged in the positioning grooves.
[0013] The upper and lower positioning of the sludge suction machine is achieved through concave and convex rails, and the left and right positioning of the sludge suction machine is achieved through a positioning front plate and a positioning rear plate, and the positioning is simple and stable.
[0014] Preferably, the positioning front plate and the positioning rear plate are covered with buffer pads, and the contact surfaces of the concave rail and the convex rail are covered with buffer pads.
[0015] The setting of the buffer pad can avoid the vibration of the sludge suction machine during installation or construction, which will affect the service life of the sludge suction machine, and can also reduce construction noise.
[0016] Preferably, a plurality of micro holes are evenly arranged on the outer circumference of the upper portion of the straw.
[0017] The setting of micro holes in the suction pipe increases the air flow and is beneficial to the construction of the sludge suction machine.
[0018] Preferably, the discharge port of the dredge suction machine is connected to a receiving bag or a receiving pipe.
[0019] The soil discharge port is directly connected to the receiving bag, through which the soil can be directly transported; or directly connected to the receiving pipe, which leads directly to the transport destination, making soil transport more convenient and quick.
[0020] Preferably, the upper side of the placement platform is supported by diagonal connecting rods.
[0021] The oblique connecting rod forms a tripod with the side of the installation platform and the top surface of the placement platform. The structure is stable and firm, so that the concave slot of the placement platform is horizontal, ensuring that the dredge suction machine moves horizontally on the concave slot.
[0022] The second technical solution adopted by the present invention is a construction method for a convenient soil taking device in a steel pipe pile, which is specifically implemented according to the following steps:
[0023] Step 1, assembly and adjustment of the soil taking device; first determine the number of placement platforms, then install the convex rail of the mud suction machine in conjunction with the concave rail of the placement platform, finally adjust the position of the mud suction machine, and install the positioning front plate and the positioning rear plate.
[0024] Step 2, installation of the soil taking device; first, evenly install multiple S-shaped positioning pieces on the top of the steel pipe pile through the upper hook, install the installation platform through the lower hook, then adjust the soil taking device to make it level, and finally extend the suction tube into the bottom of the steel pipe pile, and connect the soil discharge port to the receiving bag or receiving pipe.
[0025] Step 3, taking and releasing soil: first, the suction tube sucks the soil through the drive of the mud suction machine, and the soil is discharged from the soil discharge port and received by the receiving bag or the receiving pipe to the soil transportation destination.
[0026] Step 4, disassembly; first vertically detach the steel frame platform from the hook below the S-shaped positioning piece and move it to a safe position, then detach the S-shaped positioning piece from the steel pipe pile to complete the disassembly work, and then remove the sludge suction machine from the placement platform one by one.
[0027] Beneficial effects of the present invention:
[0028] The present invention has a steel frame platform movably arranged on the top of the steel pipe pile, and a mud suction machine is arranged on the steel frame platform. The suction pipe of the mud suction machine extends into the bottom of the steel pipe pile to absorb mud, and then discharges the mud through the mud suction machine soil discharge port. The soil taking device has the advantages of small size, convenient loading and unloading, convenient construction, simple operation, and greatly improved construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] Figure 1 It is a schematic diagram of the three-dimensional structure of a device for conveniently taking soil from a steel pipe pile according to the present invention;
[0030] Figure 2 It is a front view structural schematic diagram of the device for conveniently taking soil from a steel pipe pile according to the present invention;
[0031] Figure 3 It is a schematic structural diagram of the S-shaped positioning piece of the present invention;
[0032] Figure 4 It is a schematic diagram of the rail connection structure of the present invention;
[0033] Figure 5 It is a schematic diagram of the side view structure of the rail connection of the present invention.
[0034] Explanation of the reference numerals: 1-steel pipe pile; 2-steel frame platform; 201-installation platform; 202-placing platform; 3-mud suction machine; 4-suction pipe; 5-discharge port; 6-S-shaped positioning plate; 7-upper hook; 8-lower hook; 9-concave rail; 10-convex rail; 11-positioning front plate; 12-positioning groove; 13-positioning rear plate; 14-oblique connecting rod. DETAILED DESCRIPTION
[0035] The technical solution of the present invention will be described clearly and completely below in conjunction with the accompanying drawings and specific implementation methods. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0036] In the description of the present invention, it should be understood that the terms "center, lateral, longitudinal, up, down, front, back, left, right, vertical, horizontal, top, bottom, inside, outside" and the like indicate directions or positional relationships based on the attached Figure 1 The orientation or positional relationship shown is only for the convenience of describing the present invention and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0037] The first technical solution of the present invention is a device for conveniently taking soil from a steel pipe pile, and its three-dimensional structural schematic diagram is shown as follows: Figure 1 As shown, its front view structural diagram is as follows Figure 2 As shown, it includes a steel frame platform 2 arranged on the top of the steel pipe pile 1, and at least one mud suction machine 3 is arranged above the steel frame platform 2. The suction pipe 4 of the mud suction machine 3 extends into the interior of the steel pipe pile 1.
[0038] A movable steel frame platform 2 is supported by a steel pipe pile 1, and a sludge suction machine 3 is arranged on the steel frame platform 2. A suction pipe 4 of the sludge suction machine 3 extends into the bottom of the steel pipe pile 1 to absorb soil, and then the soil is discharged through a soil discharge port 5 of the sludge suction machine 3. The soil taking device has the advantages of small size, convenient loading and unloading, convenient construction, simple operation, and greatly improved construction efficiency.
[0039] In order to transport soil more conveniently and quickly, a receiving bag is connected to the soil discharge port 5, and the soil is directly transported through the receiving bag, or a receiving pipe is connected to the soil discharge port 5, and the receiving pipe directly leads to the soil transportation destination, making it more convenient and quick to transport soil.
[0040] In order to increase the air flow of the sludge suction machine 3 and enable the sludge suction machine 3 to operate smoothly, a plurality of micro holes are evenly arranged on the upper periphery of the suction pipe 4 , which may be arranged above the horizontal plane inside the steel pipe pile 1 .
[0041] The soil extraction device is suitable for use when the steel pipe pile 1 contains mud-water mixture, soil or small rocks. The existing mud suction machine 3 has a large size distribution and different powers. The power and size of the mud suction machine 3 can be determined according to the soil extraction amount, the diameter of the steel pipe pile 1, etc., and can be customized according to needs.
[0042] An installation platform 201 is set on the steel frame platform 2, and the installation platform 201 is movably mounted on the top of the steel pipe pile 1, so that the soil-taking device can be flexibly installed and disassembled. At least one placement platform 202 is also set on the installation platform 201. The placement platform 202 is suspended outside the steel pipe pile 1 and is used to place the dredge suction machine 3. In order to improve the construction efficiency of the soil-taking device, multiple placement platforms 202 can be evenly arranged on the installation platform 201, and multiple dredge suction machines 3 can be used to jointly construct and take soil. According to the amount of soil taken, a suitable installation platform 201 can be selected, that is, a suitable number of dredge suction machines 3 can be selected for construction.
[0043] In order to realize the rapid disassembly and assembly of the earth-taking device, the steel frame platform 2 is movably arranged on the top of the steel pipe pile 1, wherein a positioning ring can be welded at a lower position on the top of the steel pipe pile 1, and the outer diameter of the positioning ring is larger than the inner diameter of the installation platform 201. The installation platform 201 is put under the top of the steel pipe pile 1 and falls on the positioning ring to realize positioning and installation.
[0044] Preferably, a plurality of S-shaped positioning pieces 6 are evenly arranged on the outer side of the upper circumference of the steel pipe pile 1, and the structural schematic diagram thereof is shown in FIG. Figure 3 As shown, the S-shaped positioning piece 6 includes an upper hook 7 and a lower hook 8, the upper hook 7 cooperates with the steel pipe pile 1, and the lower hook 8 cooperates with the installation platform 201. This embodiment is simple and easy to operate, and is stable and firm.
[0045] The placement platform 202 and the sludge suction machine 3 can also be connected in a variety of ways, wherein they can be connected by rails on both sides. The schematic diagram of the rail connection structure is shown in FIG. Figure 4 As shown, the schematic diagram of the side view structure of the rail connection is as follows Figure 5 As shown, the two sides of the placement platform 202 are concave rails 9, and the two sides of the sludge suction machine 3 are convex rails 10. The concave and convex cooperate to achieve the up and down positioning of the sludge suction machine 3. A positioning member is set on the concave groove 9. The positioning member can be a positioning front plate 11 set in front of the convex rail 10 at the target location for the sludge suction machine to be installed, and a plurality of positioning grooves 12 are evenly set below the concave rail. A positioning rear plate 13 is set in the positioning groove 12. The positioning front plate 11 and the positioning rear plate 13 achieve the left and right positioning of the sludge suction machine 3. Make its installation and construction stable and firm.
[0046] In order to place the dredge suction machine 3 horizontally on the placement platform 202, the upper side of the placement platform 202 is supported by an inclined connecting rod 14. The inclined connecting rod 14 forms a tripod with the side of the mounting platform 201 and the top surface of the placement platform 202. The structure is stable and firm, so that the concave slot 9 of the placement platform 202 is horizontal, ensuring that the dredge suction machine 3 moves horizontally on the concave slot 9.
[0047] In order to avoid vibration of the sludge suction machine 3 during installation or construction, thereby affecting the service life of the sludge suction machine 3, and to reduce noise, buffer pads are covered on the positioning front plate 11 and the positioning rear plate 13, and buffer pads are also covered on the concave and convex contact surfaces of the concave groove 9 and the convex rail 10.
[0048] Theoretical calculation of whether soil can be taken:
[0049]
[0050] P is related to the vacuum degree. If the vacuum coefficient is a, then P = aπr 2 , r is the radius of the straw, and N is the friction between the soil and the pipe wall.
[0051] N=b G, G is the deadweight of soil per unit volume, and b is the friction coefficient.
[0052]
[0053] set up k is the suction coefficient,
[0054] but (Restrictions that need to be met)
[0055] Example: r = 0.1m, G = 1kg, k = 40-50 (take k = 40)
[0056]
[0057] If the formula is satisfied, soil can be absorbed.
[0058] The second technical solution of the present invention is a construction method for a convenient soil taking device in a steel pipe pile, which is specifically implemented according to the following steps:
[0059] Step 1, assembly and adjustment of the soil taking device; first, according to the amount of soil to be taken and the diameter of the steel pipe pile 1, select the appropriate power and number of the mud suction machine 3, that is, select the steel frame platform 2 with an appropriate number of placement platforms 202; then, install the mud suction machine 3 by matching the convex rail 10 with the concave rail 9 of the placement platform 202; then adjust the position of the mud suction machine 3, and install the positioning front plate 11 and the positioning rear plate 13.
[0060] Step 2, installation of the soil taking device; first, multiple S-shaped positioning pieces 6 are evenly installed on the top of the steel pipe pile 1 through the upper hook 7, and then the installation platform 201 is installed through the lower hook 8. Finally, the soil taking device is adjusted to make it horizontal, the suction tube 4 is extended into the bottom of the steel pipe pile 1, and the soil discharge port 5 is connected to the receiving bag or receiving tube.
[0061] Step 3, taking and releasing soil; first, the motor of the mud suction machine 3 drives the suction pipe 4 to suck the mud, and the mud enters the circulation bin for mud and water separation. The separated mud is discharged from the soil discharge port 5, and the separated water flows into the steel pipe pile through the suction pipe 4. The mud discharged from the soil discharge port 5 is received by a receiving bag or a receiving pipe to the soil transportation destination.
[0062] Step 4, disassembly; first vertically disengage the steel frame platform 2 from the hook 8 below the S-shaped positioning piece 6 and move it to a safe position, then disengage the S-shaped positioning piece 6 from the steel pipe pile 1, complete the disassembly work, and then disassemble the sludge suction machine 3 from the placement platform 202 one by one.
[0063] In summary, in order to solve the problems mentioned in the prior art such as the large size, low construction efficiency, and complicated operation method of the existing in-pipe soil-taking equipment, the present invention movably sets a steel frame platform 2 on the top of the steel pipe pile 1, and a mud suction machine 3 is provided on the steel frame platform 2. The suction pipe 4 of the mud suction machine 3 extends into the bottom of the steel pipe pile 1 to absorb the soil, and then discharges the soil through the soil discharge port 5 of the mud suction machine 3. The soil-taking device is small in size, easy to load and unload, convenient to construct, simple to operate, and greatly improves the construction efficiency.
[0064] In the description of this specification, the description with reference to the terms "one embodiment", "example", "specific example", etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.
[0065] The preferred embodiments of the present invention disclosed above are only used to help explain the present invention. The preferred embodiments do not describe all the details in detail, nor do they limit the invention to only specific implementation methods. Obviously, many modifications and changes can be made according to the content of this specification. This specification selects and specifically describes these embodiments in order to better explain the principles and practical applications of the present invention, so that those skilled in the art can understand and use the present invention well. The present invention is limited only by the claims and their full scope and equivalents.
Claims
1. A construction method for a convenient soil taking device in a steel pipe pile, characterized in that: Follow the steps below to implement it: Step 1, assembly and adjustment of the soil taking device; first determine the number of placement platforms (202), then install them by matching the convex clamping rail (10) of the sludge suction machine (3) with the concave clamping rail (9) of the placement platform (202), and finally adjust the position of the sludge suction machine (3), install the positioning front plate (11) and the positioning rear plate (13), and also include a steel frame platform (2) arranged on the top of the steel pipe pile (1), at least one sludge suction machine (3) is arranged above the steel frame platform (2), the suction pipe (4) of the sludge suction machine (3) extends into the steel pipe pile (1), the steel frame platform (2) includes an installation platform (201) and at least one placement platform (202), the installation platform (201) is movably sleeved on the top of the steel pipe pile (1), and the placement platform (202) is suspended outside the steel pipe pile (1); The placement platform (202) is connected to the sludge suction machine (3) via rails on both sides, the placement platform (202) has concave rails (9) on both sides, the sludge suction machine (3) has convex rails (10) on both sides, and the concave rails (9) are provided with positioning pieces; The front positioning member of the concave rail (9) is a positioning front plate (11), a plurality of positioning grooves (12) are evenly arranged below the concave rail (9), a positioning rear plate (13) is arranged in the positioning groove (12), and the contact surfaces of the positioning front plate (11), the positioning rear plate (13), the concave rail (9) and the convex rail (10) are all covered with buffer pads; A plurality of micro holes are evenly arranged on the outer circumference of the upper portion of the straw (4), and the upper side edge of the placement platform (202) is supported by an oblique connecting rod (14); Step 2, installation of the soil taking device; first, multiple S-shaped positioning pieces (6) are evenly installed on the top of the steel pipe pile (1) through the upper hook (7), and the installation platform (201) is installed through the lower hook (8). Next, the soil taking device is adjusted to make it horizontal. Finally, the suction pipe (4) is inserted into the bottom of the steel pipe pile (1), and the soil discharge port (5) is connected to the receiving bag or receiving tube. Multiple S-shaped positioning pieces (6) are evenly arranged on the outer side of the circumference of the upper end of the steel pipe pile (1). The S-shaped positioning pieces (6) include an upper hook (7) and a lower hook (8). The upper hook (7) cooperates with the steel pipe pile (1), and the lower hook (8) cooperates with the installation platform (201); Step 3, taking and releasing soil; first, the suction pipe (4) sucks the soil through the drive of the suction mud machine (3), and the soil is discharged from the soil discharge port (5) and received by a receiving bag or a receiving pipe to a soil transportation destination. The suction mud machine (3) is provided with a soil discharge port (5), and the soil discharge port (5) is connected to the receiving bag or the receiving pipe; Step 4, disassembly; first, vertically disengage the steel frame platform (2) from the hook (8) below the S-shaped positioning piece (6) and move it to a safe position, then disengage the S-shaped positioning piece (6) from the steel pipe pile (1), complete the disassembly work, and then disassemble the sludge suction machine (3) from the placement platform (202) one by one.