A protection method and protection structure based on root rot treatment of fan foundation ring
By pouring a protective ring beam on the foundation ring of the wind turbine and filling it with polysulfide sealant, the problem of corrosion of the foundation ring and water corrosion channels of the seaside wind power station was solved, achieving better anti-corrosion capabilities and a long life of the tower structure.
Patent Information
- Application Number
- CN202110260684.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-03-10
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2041-03-10
AI Technical Summary
The foundation ring of the wind turbine tower in the seaside wind power station is prone to corrosion and rot and water corrosion channels after many years of operation, resulting in a local harsh environment and affecting the operating life of the tower structure.
The roughened original foundation concrete surface is used, caulking strips and reinforcing bars are installed to form a formwork, the protective ring beam is poured, and the surface of the protective ring beam is filled with polysulfide sealant to form a groove to prevent water vapor from penetrating, thus solving the difference in thermal expansion between different materials. Causing crack problems.
Through the use of flexible interface structure and polysulfide sealant, the formation of water gaps is avoided, the anti-corrosion ability of the foundation ring is improved, and the operating life of the tower structure is extended.
Smart Images

Figure CN112900515B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of wind turbine foundation ring protection, and in particular to an anti-corrosion protection method suitable for treating root rot of a wind turbine tower body foundation ring in coastal areas with high corrosion. Background Art
[0002] The existing wind turbine tower structure in China is generally made of steel structure, especially the embedded parts of the tower before and after 2010, which are basically steel structure foundation. For wind power stations located at the seaside, after years of operation, the joint between the foundation ring and the top of the wind turbine foundation concrete is corroded by salt spray and natural decay, which will cause corrosion and root rot, and even corrosion channels, forming a water-logged gap. In the high-temperature natural environment, a high-humidity, high-heat and high-salt local microclimate is generated, which creates a more severe environment for corrosion and root rot. Therefore, the outer wall of the steel foundation ring must be cleaned of the root rot layer and re-sprayed for anti-corrosion treatment.
[0003] However, even if the rotten root layer on the outer wall of the foundation ring is cleaned and re-sprayed for anti-corrosion treatment, if no isolation and protection measures are taken, over time, water accumulation and corrosion channels will still appear in the foundation ring, forming a local harsh environment, causing the foundation ring to quickly corrode and rot, thereby affecting the service life of the tower structure. Summary of the invention
[0004] In view of the local harsh environment where the foundation ring of a wind turbine tower is prone to corrosion, the present invention provides a protection method and a protection structure based on the root rot treatment of the wind turbine foundation ring. While protecting the foundation ring, it can prevent the generation of cracks, solve the problem of water accumulation and corrosion channels caused by cracks, improve the operating environment of the foundation ring, thereby improving the anti-corrosion ability of the foundation ring and ensuring the operating life of the tower structure.
[0005] In order to achieve the above object, the present invention provides the following solutions:
[0006] A method for protecting a fan foundation ring after root rot is treated, characterized by comprising the following steps:
[0007] 1) Roughening of the original foundation concrete surface: Roughening of the original foundation concrete surface;
[0008] 2) Install the caulking strip: install the caulking strip in a circular ring around the surface of the base ring;
[0009] 3) Formwork installation and base surface treatment: insert reinforcement around the outside of the foundation ring to form a circle array, use slats to splice and fix them in the circle array to form a circular formwork, form a casting base surface inside the circular formwork, and clean the base surface;
[0010] 4) Casting of protective ring beam: Cast concrete in the formwork to form a protective ring beam, which is tightly attached to the foundation ring and has the caulking strip located on the surface of the protective ring beam;
[0011] 5) Remove the caulking strips: remove the caulking strips to form a groove on the original position of the caulking strips for the protective ring beam;
[0012] 6) Polysulfide sealant filling: clean the groove and then fill the groove with polysulfide sealant;
[0013] 7) Wait for the formwork to be removed: 24 hours after the pouring of the protective ring beam is completed, the formwork will be removed.
[0014] As a further improvement of the method of the present invention, in step 1), a pneumatic pick is used to roughen the original foundation concrete surface within the range of -1 cm from the sealing line, and the roughening rate is greater than 80%.
[0015] As a further improvement of the method described in the present invention, in step 2), the top height of the caulking strip is flush with the top height of the template in the subsequent steps; the caulking strip adopts a plastic wire trough, and the opening direction of the plastic wire trough is toward the surface of the foundation ring; cable tie assemblies are provided at both ends of the caulking strip, and after the caulking strip surrounds the surface of the foundation ring, the two ends are tightened and connected together by the cable tie assembly to fix the caulking strip on the surface of the foundation ring.
[0016] As a further improvement of the method described in the present invention, in step 3), before inserting the dowel bars, an electric drill is used to drill dowel holes on the original foundation concrete surface, and the dowel holes are evenly arranged in a circular shape at intervals of 1m on the outside of the foundation ring, and then the dowel bars are inserted into all the dowel holes; the slats are flexible single-layer strips, and the splicing between the slats is processed by short slat outer span nailing; the base surface is cleaned by manual slag cleaning combined with high-pressure wind blowing to ensure that there is no slag and dust on the base surface before pouring concrete.
[0017] As a further improvement of the method described in the present invention, in step 4), the concrete is manually mixed concrete or commercial concrete, and the concrete strength is the same as the original foundation concrete grade; before pouring, the pouring bin surface is moistened by spraying water mist, and the bin surface is moistened but no water accumulates; manual leveling is adopted, and a soft shaft vibrator is used for vibration guidance, and during vibration, the vibrator and shovel are prevented from touching the caulking strips; after pouring, the plastic film is covered for self-curing.
[0018] As a further improvement of the method described in the present invention, in step 6), after the protective ring beam reaches 30% of the design strength, the groove is cleaned and the polysulfide sealant is used for filling the seams; the groove is cleaned by using a tool screwdriver and high-pressure air to remove debris in the groove; the polysulfide sealant is used for filling the seams with a two-component polysulfide sealant, and the A and B components are manually weighed according to the proportion in the instructions and mixed evenly with a putty knife, and the mixture is ready for use; a manual glue gun is used to inject the polysulfide sealant into the groove, and the injection amount and injection speed are controlled during the injection, and the glue is moved at a uniform speed in one direction to ensure that the glue is filled to prevent bubbles from being generated by moving too fast or reciprocating, and the glue injection machine must be ready for use to prevent blocking the gun muzzle; the surface is smoothed by a manual corner knife, and if necessary, the polysulfide sealant can be directly hooked with a corner knife to fill the seams and smooth the surface.
[0019] The present invention also provides a protective structure based on the root rot treatment of the fan foundation ring, including original foundation concrete and a foundation ring arranged on the original foundation concrete, characterized in that it also includes a protective ring beam cast by concrete, the protective ring beam is arranged on the original foundation concrete and around the foundation ring, the inner wall of the protective ring beam is tightly attached to the outer wall of the foundation ring, a circle of grooves is provided at the junction between the surface of the protective ring beam and the foundation ring, and the grooves are filled with polysulfide sealant.
[0020] As a further improvement of the structure described in the present invention, the protection ring beam is in a circular ring structure, the width of the protection ring beam is 30 cm, and the height of the protection ring beam is determined according to the terrain. A high protection ring beam is used in low-lying areas prone to water accumulation, otherwise a short protection ring beam is used.
[0021] As a further improvement of the structure of the present invention, the specification of the groove is 2cm*3cm.
[0022] The beneficial effects of the present invention are:
[0023] 1. A rigid and flexible protection structure system: By protecting the rigid bond between the ring beam and the original foundation concrete and the flexible transition of the polysulfide sealant between the ring beam and the steel structure foundation ring, the problem of structural cracks caused by different thermal expansion coefficients between different materials is solved, the deformation requirements of concrete shrinkage and thermal expansion and contraction of the foundation ring are met, the generation of local harsh environment of water accumulation in the gap is avoided, the operating environment of the foundation ring is improved, thereby improving the anti-corrosion ability of the foundation ring and ensuring the operating life of the tower structure.
[0024] 2. Grooved flexible interface structure: A groove is set at the junction between the surface of the protective ring beam and the foundation ring, and polysulfide sealant is filled in the groove to form a flexible barrier, which avoids the infiltration of water vapor from the upper part, prevents steam and water from contacting the easily corrosive metal surface, improves the corrosion resistance of the foundation ring structure, and ensures the service life of the tower body.
[0025] 3. Groove presetting device: A plastic caulking strip is wrapped around the designated position of the outer wall of the foundation ring as a groove presetting device. The groove can be formed after the protective ring beam is cast, and the two ends of the caulking strip are connected and disconnected by a cable tie assembly, which is simple and convenient.
[0026] 4. Protective ring beam formwork system: A flexible single-layer strip wooden board combined with a reinforcing bar ring array is used to form a protective ring beam casting formwork. Installation and disassembly can be carried out quickly, and it is simple and easy. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 The construction structure of the present invention is schematically shown Figure 1 ;
[0028] Figure 2 The construction structure of the present invention is schematically shown Figure 2 ;
[0029] Figure 3 The construction structure of the present invention is schematically shown Figure 3 ;
[0030] Figure 4 It is an overall schematic diagram of the completed structure of the present invention;
[0031] Figure 5 A schematic diagram of the groove of the completed structure of the present invention;
[0032] Figure 6 This is a schematic diagram of the polysulfide sealant filling of the completed structure of the present invention;
[0033] Marking instructions: 1-original foundation concrete, 2-foundation ring, 3-protective ring beam, 31-groove, 32-polysulfide sealant, 4-caulking strip, 5-formwork, 51-inserted reinforcement, 52-lath. DETAILED DESCRIPTION
[0034] The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.
[0035] This solution has been successfully used in the Dongfang Gancheng Wind Power Station of Hainan Xinfengyuan Industrial Co., Ltd. and the Zhanhua Wind Power Project of Shandong Binzhou Yueshui Power Energy Co., Ltd.
[0036] like Figure 1 As shown, a protection method based on the treatment of root rot in the foundation ring of a wind turbine comprises the following steps:
[0037] 1) Roughening the surface of the original foundation concrete 1: Use a pneumatic pick to roughen the surface of the original foundation concrete 1 within the range of -1cm from the sealing line, with a roughening rate greater than 80%. Because the protective ring beam 3 needs to be cast on the surface of the original foundation concrete 1 in the subsequent steps, the roughening surface can make the original foundation concrete 1 and the protective ring beam 3 seamlessly connected, and no water seepage channel will be formed.
[0038] 2) Installation of caulking strip 4: The caulking strip 4 is installed in a circular ring shape around the surface of the base ring 2, and the top height of the caulking strip 4 is flush with the top height of the template 5 in the subsequent steps. The caulking strip 4 uses a plastic wire trough, and the opening direction of the plastic wire trough faces the surface of the base ring 2. Cable tie assemblies are provided at both ends of the caulking strip 4. After the caulking strip 4 surrounds the surface of the base ring 2, the two ends are tightened and connected together by the cable tie assembly, so that the caulking strip 4 is fixed to the surface of the base ring 2.
[0039] 3) Installation of template 5 and treatment of base surface: Use an electric drill to drill and set rebar holes on the original foundation concrete 1 surface. The rebar holes are evenly arranged in a circle at intervals of 1m on the outside of foundation ring 2. The depth of the rebar hole is 10cm. If the rebar hole touches the foundation steel bar, the position can be adjusted appropriately. After the drilling is completed, insert φ12 rebars 51 into all the rebar holes to form a rebar circle array. The height of the rebar 51 is the sum of the height of the template 5 and the hole depth. Flexible single-layer strip slats 52 are spliced and fixed in the rebar 51 circle array to form a circular template 5 on the outside of foundation ring 2. The splicing between the slats 52 is treated by short slats outside the seam nailing. A casting base surface is formed inside the circular template 5, and the base surface is cleaned. The base surface is cleaned by manual slag removal combined with high-pressure wind blowing to ensure that there is no slag and dust on the base surface before concrete pouring.
[0040] 4) Casting of protective ring beam 3: Cast concrete in the formwork 5 to form a protective ring beam 3, which is in close contact with the foundation ring 2, and the caulking strip 4 is located on the surface of the protective ring beam 3. The concrete is made of manually mixed concrete or commercial concrete, and the concrete strength is the same as the original foundation concrete 1. Before casting, the casting bin surface is moistened by spraying water mist, and the bin surface is moist but no water accumulates; the bin is manually leveled and the soft shaft vibrator is used for vibration guidance. When vibrating, avoid objects such as the vibrator and shovel from touching the caulking strip 4; after casting, cover with plastic film for self-curing.
[0041] 5) Removal of caulking strip 4: 5 to 6 hours after the casting of the protective ring beam 3 is completed, the cable tie assembly is loosened manually with the help of a flat head screwdriver, and the caulking strip 4 is pried up and removed from the opposite side along its opening direction with the screwdriver. After the caulking strip 4 is removed, Figure 2 As shown, the protective ring beam 3 forms a groove 31 at the original position of the caulking strip 4.
[0042] 6) Polysulfide sealant 32 filling: such as Figure 3As shown, when the protective ring beam 3 reaches 30% of the design strength, the groove 31 is cleaned and the polysulfide sealant 32 is used to fill the gap. The groove 31 is cleaned by using a tool screwdriver and high-pressure air to remove the debris in the groove 31. A two-component polysulfide sealant 32 is used. The A and B components are weighed manually according to the ratio of 100:10 to 100:14 (mass ratio) in the manual and mixed evenly with a putty knife, and it is ready to use. A manual glue gun is used to inject polysulfide sealant 32 into the groove 31. When injecting glue, the injection amount and injection speed are controlled, and the glue is moved at a uniform speed in one direction to ensure that the glue is filled to prevent bubbles from being generated by moving too fast or reciprocating. The glue injection machine must be ready to use to prevent blocking the gun muzzle. Manual corner knife is used to smooth the surface. If necessary, the corner knife can be used to directly hook the polysulfide sealant 32 to fill the gaps and smooth the surface.
[0043] 7) Waiting for forced demolition: After the protection ring beam 3 is poured for 24 hours, the plate formwork is removed. During the removal process, the dowel 51 is manually shaken and pulled out, and then a little external force is applied to remove the formwork 5, which can be recycled and reused.
[0044] The protective structure can be completed by adopting the above method.
[0045] like Figure 4 As shown, the protection structure is as follows:
[0046] A protection structure based on the treatment of the root rot of the wind turbine foundation ring, comprising the original foundation concrete 1 and the foundation ring 2 arranged on the original foundation concrete 1. The inner wall of the protection ring beam 3 made of concrete is close to the outer wall of the foundation ring 2, and the protection ring beam 3 is a circular ring structure. The lower part of the protection ring beam 3 is connected to the original foundation concrete 1. The width of the protection ring beam 3 is 30cm, and the height is determined according to the terrain around the wind turbine. A high protection ring beam 3 structure can be selected for low-lying and water-prone locations, otherwise a short protection ring beam 3 structure can be used. Figure 5 As shown, a circle of grooves 31 is provided at the junction between the surface of the protection ring beam 3 and the foundation ring 2, and the specification of the grooves 31 is 2cm*3cm. Figure 6 As shown, the groove 31 is filled with polysulfide sealant 32, so that a flexible waterproof protection structure is formed between the protective ring beam 3 and the foundation ring 2 to meet the deformation requirements of concrete shrinkage and thermal expansion and contraction of the foundation ring 2.
[0047] This solution has the following features:
[0048] 1. A rigid and flexible protection structure system: The rigid combination of concrete between the protective ring beam 3 and the original foundation concrete 1 and the flexible transition of polysulfide sealant 32 between the protective ring beam 3 and the steel structure foundation ring 2 solves the problem of structural cracks caused by different thermal expansion coefficients between different materials, meets the deformation requirements of concrete shrinkage and cold expansion and hot contraction of the foundation ring 2, avoids the generation of local harsh environment of water accumulation in the gap, improves the operating environment of the foundation ring, thereby improving the anti-corrosion ability of the foundation ring and ensuring the operating life of the tower structure.
[0049] 2. Grooved flexible interface structure: A groove 31 is set at the junction between the surface of the protective ring beam 3 and the foundation ring 2, and polysulfide sealant 32 is filled in the groove 31 to form a flexible barrier, which avoids the infiltration of water vapor from the upper part, prevents the contact of steam and water with the easily corrosive metal surface, improves the anti-corrosion ability of the foundation ring 2 structure, and ensures the service life of the tower body.
[0050] 3. Groove presetting device: A caulking strip 4 made of plastic is wound around a designated position on the outer wall of the foundation ring 2 as a groove 31 presetting device. The groove 31 can be formed after the protective ring beam 3 is poured, and the two ends of the caulking strip 4 are connected and disconnected by a cable tie assembly, which is simple and convenient.
[0051] 4. Protective ring beam formwork system: A casting formwork 5 for protecting the ring beam 3 is formed by combining a flexible single-layer strip wood board with a circle array of inserted reinforcement 51. The installation and disassembly can be carried out quickly, and it is simple and easy.
[0052] The above embodiments are only used to illustrate the present invention and are not intended to limit the present invention in any form. Any person with ordinary knowledge in the technical field may make partial changes or modifications to the technical contents disclosed in the present invention without departing from the scope of the technical features of the present invention, and the equivalent embodiments without departing from the technical features of the present invention are still within the scope of the technical features of the present invention.
Claims
1. A protection method based on the treatment of root rot in the foundation ring of the wind turbine. Features The following steps are involved: 1) Roughening of the original foundation concrete surface: Roughening of the original foundation concrete surface; 2) Install the caulking strip: The caulking strip is installed in a circular ring shape around the surface of the base ring, and the top height of the caulking strip is flush with the top height of the template in the subsequent steps; the caulking strip adopts a plastic wire trough, and the opening direction of the plastic wire trough faces the surface of the base ring; cable tie assemblies are provided at both ends of the caulking strip. After the caulking strip surrounds the surface of the base ring, the two ends are tightened and connected together by the cable tie assembly to fix the caulking strip on the surface of the base ring; 3) Formwork installation and base surface treatment: insert dowels around the outside of the foundation ring to form a dowel ring array, and use slats to splice and fix them in the dowel ring array to form a circular template. The casting base surface is formed inside the circular template, and the base surface is cleaned; before inserting dowels, use an electric drill to drill dowel holes on the original foundation concrete surface. The dowel holes are evenly arranged in a circle at intervals of 1m on the outside of the foundation ring, and then dowels are inserted into all dowel holes; the slats are flexible single-layer strips, and the splicing between the slats is treated by short slats outer span nailing; the base surface is cleaned by manual slag removal combined with high-pressure wind blowing to ensure that there is no slag and dust on the base surface before concrete pouring; 4) Casting of protective ring beam: Cast concrete in the formwork to form a protective ring beam, which is tightly attached to the foundation ring and has the caulking strip located on the surface of the protective ring beam; 5) Remove the caulking strips: remove the caulking strips to form a groove on the original position of the caulking strips for the protective ring beam; 6) Polysulfide sealant filling: clean the groove and then fill the groove with polysulfide sealant; 7) Wait for the formwork to be removed: 24 hours after the pouring of the protective ring beam is completed, the formwork will be removed.
2. A protection method based on the treatment of root rot in the foundation ring of a wind turbine according to claim 1, Features: In step 1), a pneumatic pick is used to roughen the original foundation concrete surface within the range of -1 cm from the sealing line, and the roughening rate is greater than 80%.
3. A protection method based on the treatment of root rot in the foundation ring of a wind turbine according to claim 1, Features: In step 4), the concrete is manually mixed concrete or commercial concrete, and the concrete strength is the same as the original foundation concrete grade; before pouring, the pouring bin surface is moistened by spraying water mist, and the bin surface is moistened but no water accumulates; the bin is manually leveled, and the soft shaft vibrator is used for vibration guidance, and the vibrator and the shovel are prevented from touching the caulking strips during vibration; after pouring, the plastic film is covered for self-curing.
4. A method for protecting a wind turbine foundation ring from root rot according to claim 1, Features: In step 6), when the protective ring beam reaches 30% of the design strength, the groove is cleaned and the polysulfide sealant is used to fill the gap; Groove cleaning uses a tool screwdriver and high-pressure air to remove debris in the groove; polysulfide sealant filling uses two-component polysulfide sealant. Manually weigh components A and B according to the proportion in the instructions and mix them evenly with a putty knife, and they are ready to use after mixing; a manual glue gun is used to inject polysulfide sealant into the groove. During injection, the injection amount and speed are controlled, and the glue is moved at a constant speed in one direction to ensure that the glue is filled to prevent bubbles from being generated by moving too fast or reciprocating. The glue injection machine must be ready to use after mixing to prevent clogging of the gun muzzle; manual corner knife is used to smooth the surface, and the corner knife is used to directly hook the polysulfide sealant for filling and smoothing.
Citation Information
Patent Citations
Fan foundation rapid repairing method
CN110700334A
Foundation ring type fan foundation reinforcing device and reinforcing method
CN111962579A
Aerogenerator basis stagnant water protection device
CN206267171U
New and old concrete interface waterproof sealing structure
CN206956791U
Protection structure based on fan foundation ring rotten root treatment
CN215330099U