A shield tunnel fully prefabricated internal structure and construction method
Through fully prefabricated internal structure and construction methods, the construction problems of curved plates and lane plates in shield tunnels are solved, rapid and efficient construction is achieved, construction safety and quality are improved, and single-story is suitable for roads, municipal and other fields. Lane shield tunnel.
Patent Information
- Application Number
- CN202110279816.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-03-16
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2041-03-16
AI Technical Summary
During the construction of the internal structure of the existing shield tunnel, the assembly construction problems of curved plates and side-span lane plates have not been effectively solved, resulting in slow construction speed, high labor costs and large safety hazards, low degree of prefabrication, construction efficiency and quality It's hard to guarantee.
Adopt a fully prefabricated internal structure and construction method, including prefabricated intermediate box culverts, curved plates and lane plates, prefabricated through factory and quickly installed on site, using connectors and bite connections to achieve rapid overlap and tight connections, and improve construction speed and security.
It has achieved rapid and efficient construction of the internal structure of the shield tunnel, reduced labor costs, improved construction safety and quality, and improved prefabrication. It is suitable for single-story lane shield tunnels in highways, municipal and other fields.
Smart Images

Figure CN112983465B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of shield tunnel construction, and in particular to a fully prefabricated internal structure of a shield tunnel and a construction method. Background Art
[0002] With the development of the transportation industry, shield tunnels are widely used in the construction of tunnels in the fields of municipal administration, highways, etc. Due to the limitations of prefabricated construction technology and the internal space of shield tunnels, the degree of prefabrication of the internal structure of shield tunnels is low, and the prefabrication and assembly on the construction site are interspersed with cast-in-place processes, which seriously restricts the construction quality and speed of the internal structure of shield tunnels.
[0003] The existing shield tunnel internal structure construction has achieved the assembly construction of the intermediate box culvert, but the assembly construction problem of the side span lane slab and curved slab has not been effectively solved.
[0004] For curved slabs, cast-in-place construction is currently the main method used. However, the cast-in-place process has complicated construction operations and slow construction speed. A large number of personnel such as reinforcement workers and formwork workers are required during the construction process, which has high labor costs. In addition, there are many construction machines in the tunnel and the working space is small. The involvement of a large number of personnel will create greater safety hazards.
[0005] For the construction of side span lane slabs, in addition to the cast-in-place construction process, some projects consider a construction plan that combines cast-in-place and prefabrication. During the construction process, the lane slab beams are cast first, and then the prefabricated side span lane slabs are installed on the beams. This plan realizes the prefabrication of the lane slabs to a certain extent, but the main load-bearing beams still need to be cast on-site, the degree of prefabrication is low, and the on-site prefabrication assembly and cast-in-place processes are interspersed, the construction efficiency is low, the economy is poor, and the construction quality is difficult to guarantee.
[0006] Therefore, it is necessary to design a fully prefabricated internal structure of a shield tunnel to overcome the above problems. Summary of the invention
[0007] The purpose of the present invention is to overcome the defects of the prior art and provide a shield tunnel fully prefabricated internal structure and construction method, which at least solves some of the problems in the prior art.
[0008] The present invention is achieved in that:
[0009] The present invention provides a fully prefabricated internal structure of a shield tunnel, comprising a prefabricated intermediate box culvert, a prefabricated lane slab, prefabricated curved plates on both sides and a tunnel lining structure of the shield tunnel, wherein the prefabricated curved plates, the prefabricated intermediate box culvert and the prefabricated lane slab are all located in a tunnel space enclosed by the tunnel lining structure, and the two prefabricated curved plates are respectively located on both sides of the prefabricated intermediate box culvert, and the prefabricated curved plates, the prefabricated intermediate box culvert and the prefabricated lane slab enclose a side box culvert.
[0010] Preferably, a supporting corbel for supporting the prefabricated lane slab is provided on the top of the prefabricated intermediate box culvert, and a joint connected to the steel bars of the prefabricated lane slab is provided on the supporting corbel, and the joint is filled with concrete.
[0011] Preferably, a connector is embedded in the tunnel lining structure, and a strip bolt hole is provided at a position of the prefabricated arc plate corresponding to the connector. The connector corresponds to the strip bolt hole, and the connector and the strip bolt hole are connected via connector bolts.
[0012] Preferably, the two ends of the prefabricated lane slab along the transverse direction of the tunnel are respectively supported on cast-in-place corbels and supporting corbels on the top of the prefabricated intermediate box culvert, and the steel frame of the cast-in-place corbels is prefabricated integrally with the prefabricated curved slab.
[0013] Preferably, the gaps in the strip bolt holes, the steel reinforcement skeleton of the cast-in-place corbels, and the cavities in the prefabricated arc-shaped plates and the tunnel lining structure are all filled with concrete.
[0014] Preferably, there are several prefabricated lane slabs, each of which is snap-connected in sequence along the longitudinal direction of the tunnel, each of which is provided with a snap joint at one end along the longitudinal direction of the tunnel, and each of which is provided with a snap interface at the other end along the longitudinal direction of the tunnel, the snap interface is snap-connected with adjacent snap joints, and the connecting gap between two adjacent prefabricated lane slabs is filled with concrete.
[0015] Preferably, the prefabricated driveway slab is a prefabricated reinforced concrete slab, and reserved steel bars are provided on the overlapping sides with the cast-in-place corbel and the supporting corbel.
[0016] Preferably, the prefabricated curved plate is a truss steel bar composite plate.
[0017] Preferably, the bottom of the prefabricated intermediate box culvert is supported on the tunnel lining structure by a support with adjustable height.
[0018] The present invention provides a construction method for a fully prefabricated internal structure of a shield tunnel, comprising:
[0019] S1. The factory manufactures a prefabricated intermediate box culvert. The prefabricated intermediate box culvert should reserve steel bars connected to the prefabricated lane slab, set supporting brackets for placing the prefabricated lane slab and adjustable supports for the prefabricated intermediate box culvert. After the prefabricated intermediate box culvert is prefabricated, it is transported to the site for installation, and the installation height of the prefabricated intermediate box culvert is fine-tuned according to the construction situation;
[0020] S2. The prefabricated curved plate is manufactured in the factory. The steel frame of the cast-in-place corbel should be prefabricated integrally with the prefabricated curved plate. The prefabricated curved plate should reserve strip bolt holes. The arrangement position of the strip bolt holes corresponds to the connectors embedded in the tunnel lining structure.
[0021] S3. The prefabricated curved plate is transported to the site, hoisted to the corresponding position above the tunnel lining structure for installation. The tunnel lining structure should be pre-buried with connectors, and the connector layout position corresponds to the layout position of the strip bolt holes. The prefabricated curved plate is installed with connector bolts through the strip bolt holes and connected to the connector. Concrete is poured to fill the gaps in the strip bolt holes and the gaps between the prefabricated curved plate and the tunnel lining structure, and the installation and construction of the prefabricated curved plate and cast-in-place corbels are completed.
[0022] S4. The factory manufactures prefabricated lane slabs, reserves steel bars for connecting the prefabricated lane slabs with cast-in-place corbels and supporting corbels, transports the prefabricated lane slabs to the site, and after the post-cast concrete between the prefabricated curved slabs and the tunnel lining structure and the concrete of the cast-in-place corbels reach the designed strength, hoists the prefabricated lane slabs to the top of the cast-in-place corbels and supporting corbels for assembly, then connects the steel bars at the joints and pours the concrete to complete the installation of the prefabricated lane slabs;
[0023] S5. Repeat the above operations S1 to S4 to complete the installation of the tunnel longitudinal fully prefabricated lane slab structure. After the longitudinal overlap of the lane slab is completed, grouting is injected to fill the gap to ensure that the longitudinal connection of the lane slab is tight.
[0024] The present invention has the following beneficial effects:
[0025] 1. In the present invention, the lane plate and the arc plate are all prefabricated components, which have matching sizes and connection methods with the tunnel lining structure, can be quickly installed, improve the construction speed, reduce the construction work surface, and ensure safe and efficient construction.
[0026] 2. In the present invention, the cast-in-place corbel steel frame and the prefabricated arc-shaped plate are integrally prefabricated, and the integral structure is formed by connecting the connectors with connector bolts and pouring concrete to fill the gaps and connect them with the tunnel lining structure, so the construction speed is fast and the stress-bearing performance is good.
[0027] 3. In the present invention, the prefabricated roadway slabs are connected along the longitudinal direction of the tunnel using a bite-type structure and matching joints, and the gaps are filled with grouting, so that the roadway slabs are tightly connected. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0029] Figure 1 A schematic diagram of a fully prefabricated internal structure of a shield tunnel provided by an embodiment of the present invention;
[0030] Figure 2 A schematic diagram of a prefabricated curved plate and a cast-in-place corbel reinforcement skeleton provided in an embodiment of the present invention;
[0031] Figure 3 The prefabricated curved plate is unfolded and the arrangement diagram of the reserved strip bolt holes is provided in the embodiment of the present invention;
[0032] Figure 4 A schematic diagram of the connection between the prefabricated curved plate and the lining structure provided in an embodiment of the present invention;
[0033] Figure 5 A schematic diagram of a prefabricated driveway slab provided in an embodiment of the present invention;
[0034] Figure 6 A schematic diagram of the longitudinal overlap connection of prefabricated driveway slabs provided in an embodiment of the present invention. DETAILED DESCRIPTION
[0035] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0036] like Figure 1-Figure 6The embodiment of the present invention provides a fully prefabricated internal structure of a shield tunnel, comprising a prefabricated intermediate box culvert 2, a prefabricated lane slab 3, prefabricated curved plates 1 on both sides and a tunnel lining structure 5 of the shield tunnel, wherein the prefabricated curved plates 1, the prefabricated intermediate box culvert 2 and the prefabricated lane slab 3 are all located in a tunnel space enclosed by the tunnel lining structure 5, the bottom of the prefabricated intermediate box culvert 2 is supported on the tunnel lining structure 5 by a support 17 with adjustable height, the two prefabricated curved plates 1 are respectively located on both sides of the prefabricated intermediate box culvert 2, the prefabricated curved plates 1, the prefabricated intermediate box culvert 2 and the prefabricated lane slab 3 enclose a side box culvert, the top of the prefabricated intermediate box culvert 2 is provided with a supporting bracket for supporting the prefabricated lane slab 3, the supporting bracket is provided with a joint 4 connected to the steel bars of the prefabricated lane slab 3, and the joint 4 is filled with concrete, and the joint 4 is an extruded sleeve, a cone One of a threaded sleeve and a reverse thread sleeve, a connector 8 is pre-embedded in the tunnel lining structure 5, and a strip bolt hole 13 is provided at the position of the prefabricated curved plate 1 corresponding to the connector 8, and the connector 8 corresponds to the strip bolt hole 13, and the connector 8 is connected to the strip bolt hole 13 through a connector bolt 9, and the two ends of the prefabricated lane slab 3 along the transverse direction of the tunnel are respectively supported on the cast-in-place corbel 7 and the supporting corbel on the top of the prefabricated intermediate box culvert, and the prefabricated curved plate 1 is a truss steel bar composite plate, and the truss steel bar composite plate includes a steel mesh 11 and a prefabricated curved plate steel bar skeleton 12, and the steel bar skeleton 10 of the cast-in-place corbel 7 is prefabricated integrally with the prefabricated curved plate 1, and the gaps in the strip bolt holes 13, the steel bar skeleton of the cast-in-place corbel 7, the prefabricated curved plate 1 and the cavity of the tunnel lining structure 5 are all filled with concrete 6.
[0037] The prefabricated lane slabs 3 have several pieces, each of which is interlocked in sequence along the longitudinal direction of the tunnel. Each of the prefabricated lane slabs 3 is provided with an interlocking joint 14 at one end along the longitudinal direction of the tunnel, and an interlocking interface 15 is provided at the other end along the longitudinal direction of the tunnel. The interlocking interface 15 is interlocked with the adjacent interlocking joints 14, and the connection gap between two adjacent prefabricated lane slabs 3 is filled with concrete. The prefabricated lane slabs 3 are prefabricated reinforced concrete slabs, and reserved steel bars 16 are provided on the overlapped sides with the cast-in-place corbels 7 and the supporting corbels.
[0038] The fully prefabricated internal structure of the shield tunnel provided by the present invention further improves the degree of prefabrication and ensures the quality of connection of prefabricated components such as prefabricated lane slabs and prefabricated curved slabs, thereby realizing rapid and high-quality construction of the lane slab structure, and is suitable for single-layer lane shield tunnels in the fields of highways, municipal engineering, etc.
[0039] The fully prefabricated internal structure of the shield tunnel includes a prefabricated roadway slab 3, a prefabricated intermediate box culvert 2, a prefabricated curved slab 1 and a cast-in-place corbel 7.
[0040] The prefabricated intermediate box culvert 2 is provided with a supporting corbel for placing the prefabricated lane slab 3, and a joint 4 is reserved for connecting with the steel bars of the prefabricated lane slab 3. An adjustable support 17 is provided at the bottom to facilitate fine-tuning of the installation height of the prefabricated intermediate box culvert 2 according to the construction conditions. After being prefabricated in the factory, it is transported to the site and installed on the tunnel lining structure 5.
[0041] The prefabricated curved plate 1 is a truss reinforced plate, and its structure is as shown in the attached figure. Figure 2 As shown, the arc, arc length and longitudinal length match the tunnel lining structure 5. The tunnel lining structure 5 should be pre-buried with connectors 8, and strip bolt holes 13 are reserved at the corresponding positions of the prefabricated arc plate 1. After the prefabrication is completed in the factory, the prefabricated arc plate 1 is transported to the site. After the prefabricated arc plate 1 is hoisted to the corresponding position above the tunnel lining structure 5, the connector bolts 9 are passed through the strip bolt holes 13 to connect with the pre-buried connectors 8 on the tunnel lining structure 5, and concrete 6 is poured to fill the gaps in the strip bolt holes 13 and the cavities of the prefabricated arc plate 1 and the tunnel lining structure 5, so as to realize the connection between the prefabricated arc plate 1 and the tunnel lining structure 5.
[0042] The steel frame 10 of the cast-in-place corbel 7 and the prefabricated curved plate 1 are integrally prefabricated in a factory, and after the installation is completed, the concrete 6 is poured to complete the cast-in-place corbel construction.
[0043] The prefabricated lane slab 3 is a prefabricated reinforced concrete slab, and a reserved steel bar 16 is provided on the overlapping side with the corbel. After being prefabricated in the factory, it is transported to the site for installation. The steel bars of the prefabricated lane slab 3 and the prefabricated intermediate box culvert 2 are connected by joints 4 such as extruded sleeves, tapered thread sleeves, and reverse thread sleeves. Concrete is poured at the joints 4 to complete the connection between the prefabricated lane slab 3 and the supporting corbel.
[0044] The prefabricated lane slab 3 is provided with a matching interlocking connection structure and matching joints along the longitudinal direction of the tunnel. After being prefabricated in the factory, it is transported to the site for assembly, and grouting is injected to fill the gaps to achieve longitudinal overlap of the prefabricated lane slab 3.
[0045] In the present invention, the prefabricated curved plate 1 is a truss steel prefabricated plate, and the steel frame 10 of the cast-in-place corbel 7 is integrally prefabricated with the prefabricated curved plate 1, and an integral force system is formed with the tunnel lining structure 5 by connecting the connector bolts 9 with the connector 8 and pouring concrete 6 to fill the gap.
[0046] The prefabricated curved plate 1 and the tunnel lining structure 5 have matching curvature, arc length and longitudinal length. The reserved connectors 8 of the tunnel lining structure 5 and the strip bolt holes 13 of the prefabricated curved plate 1 are arranged at corresponding positions, which is convenient for quick installation.
[0047] The prefabricated lane slab 3 is provided with a snap-fit connection structure and matching joints along the longitudinal direction of the tunnel, and grouting is used to fill the gaps.
[0048] The present invention also provides a construction method for a fully prefabricated internal structure of a shield tunnel, comprising:
[0049] 1) The factory manufactures the prefabricated intermediate box culvert 2, the prefabricated intermediate box culvert 2 should reserve steel bars connected to the prefabricated lane slab 3, and set supporting brackets for placing the prefabricated lane slab 3 and adjustable prefabricated intermediate box culvert supports 17. After the prefabricated intermediate box culvert 2 is prefabricated, it is transported to the site for installation, and the installation height of the prefabricated intermediate box culvert 2 is fine-tuned according to the construction situation;
[0050] 2) The prefabricated curved plate 1 is manufactured in the factory. The steel frame 10 of the cast-in-place corbel 7 should be prefabricated integrally with the prefabricated curved plate 1. The prefabricated curved plate 1 should reserve strip bolt holes 13. The arrangement position of the strip bolt holes 13 corresponds to the connectors 8 embedded in the lining structure 5.
[0051] 3) The prefabricated curved plate 1 is transported to the site, hoisted to the corresponding position above the tunnel lining structure 5 for installation, the tunnel lining structure 5 should be pre-buried with a connector 8, the layout position of the connector 8 corresponds to the layout position of the strip bolt hole 13, the prefabricated curved plate 1 is installed with a connector bolt 9 through the strip bolt hole 13, connected to the connector 8, and concrete 6 is poured to fill the gap of the strip bolt hole 13 and the gap between the prefabricated curved plate 1 and the tunnel lining structure 5, completing the installation and construction of the prefabricated curved plate 1 and the cast-in-place corbel 7;
[0052] 4) The factory manufactures the prefabricated lane slab 3, reserves the steel bars for connecting the prefabricated lane slab 3 with the cast-in-place corbel 7 and the supporting corbel, transports the prefabricated lane slab 3 to the site, and after the post-cast concrete 6 between the prefabricated curved slab 1 and the tunnel lining structure 5 and the concrete of the cast-in-place corbel 7 reach the designed strength, hoists the prefabricated lane slab 3 to the top of the cast-in-place corbel 7 and the supporting corbel for assembly, then connects the steel bars at the joint 4 and pours the concrete, completing the installation of the prefabricated lane slab 3;
[0053] 5) Repeat the above steps 1 to 4 to complete the installation of the tunnel longitudinal fully prefabricated lane slab structure. After the longitudinal overlap of the lane slab is completed, grouting is performed to fill the gap to ensure that the longitudinal connection of the lane slab is tight.
[0054] The above is only the basic principle of the fully prefabricated internal structure of the shield tunnel of this patent, and does not limit the fully prefabricated internal structure of the shield tunnel of this patent to any specific quantity, size, shape, layout, material, or overlap method. Therefore, all corresponding modifications and equivalents that may be used are within the scope of the patent applied for by this invention (design).
[0055] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A fully prefabricated internal structure of a shield tunnel, characterized in that: The invention relates to a tunnel lining structure comprising a prefabricated intermediate box culvert, a prefabricated lane slab, prefabricated curved plates on both sides, cast-in-place corbels and a shield tunnel, wherein the prefabricated curved plates, the prefabricated intermediate box culvert and the prefabricated lane slab are all located in a tunnel space enclosed by the tunnel lining structure, and the two prefabricated curved plates are respectively located on both sides of the prefabricated intermediate box culvert, and the prefabricated curved plates, the prefabricated intermediate box culvert and the prefabricated lane slab enclose a side box culvert; a supporting corbel for supporting the prefabricated lane slab is provided on the top of the prefabricated intermediate box culvert, and a joint connected to the steel bars of the prefabricated lane slab is provided on the supporting corbel, and the joint is filled with concrete; the tunnel lining A connector is embedded in the masonry structure, and a strip bolt hole is provided at a position of the prefabricated curved plate corresponding to the connector, and the connector corresponds to the strip bolt hole, and the connector is connected to the strip bolt hole through the connector bolts; the two ends of the prefabricated lane slab along the transverse direction of the tunnel are respectively supported on the cast-in-place corbel and the supporting corbel on the top of the prefabricated intermediate box culvert, and the steel frame of the cast-in-place corbel is prefabricated integrally with the prefabricated curved plate; the prefabricated lane slab is a prefabricated reinforced concrete slab, and reserved steel bars are provided on the overlapping sides with the cast-in-place corbel and the supporting corbel; the prefabricated curved plate is a truss steel bar composite plate.
2. The fully prefabricated internal structure of a shield tunnel as claimed in claim 1, characterized in that: The gaps in the strip bolt holes, the steel reinforcement skeleton of the cast-in-place corbels, the cavities of the prefabricated arc-shaped plates and the tunnel lining structure are all filled with concrete.
3. The fully prefabricated internal structure of a shield tunnel as claimed in claim 1, characterized in that: There are several prefabricated lane slabs, and each of the prefabricated lane slabs is interlocked and connected in sequence along the longitudinal direction of the tunnel. One end of each of the prefabricated lane slabs along the longitudinal direction of the tunnel is provided with an interlocking joint, and the other end of each of the prefabricated lane slabs along the longitudinal direction of the tunnel is provided with an interlocking interface. The interlocking interface is interlocked and connected with adjacent interlocking joints, and the connecting gap between two adjacent prefabricated lane slabs is filled with concrete.
4. The fully prefabricated internal structure of a shield tunnel as claimed in claim 1, characterized in that: The bottom of the prefabricated intermediate box culvert is supported on the tunnel lining structure through a support with adjustable height.
5. A construction method for a fully prefabricated internal structure of a shield tunnel, applied to the fully prefabricated internal structure of a shield tunnel as claimed in any one of claims 1 to 4, characterized in that: include: S1. The factory manufactures a prefabricated intermediate box culvert. The prefabricated intermediate box culvert should reserve steel bars connected to the prefabricated lane slab, set supporting brackets for placing the prefabricated lane slab and adjustable supports for the prefabricated intermediate box culvert. After the prefabricated intermediate box culvert is prefabricated, it is transported to the site for installation, and the installation height of the prefabricated intermediate box culvert is fine-tuned according to the construction situation; S2. The prefabricated curved plate is made in the factory. The steel frame of the cast-in-place corbel should be prefabricated integrally with the prefabricated curved plate. The prefabricated curved plate should reserve strip bolt holes. The arrangement position of the strip bolt holes corresponds to the pre-buried connectors on the tunnel lining structure. S3. The prefabricated curved plate is transported to the site, hoisted to the corresponding position above the tunnel lining structure for installation. The tunnel lining structure should be pre-buried with connectors, and the connector layout position corresponds to the layout position of the strip bolt holes. The prefabricated curved plate is installed with connector bolts through the strip bolt holes and connected to the connector. Concrete is poured to fill the gaps in the strip bolt holes and the gaps between the prefabricated curved plate and the tunnel lining structure, and the installation and construction of the prefabricated curved plate and cast-in-place corbels are completed. S4. The factory manufactures prefabricated lane slabs, reserves steel bars for connecting the prefabricated lane slabs with cast-in-place corbels and supporting corbels, transports the prefabricated lane slabs to the site, and after the post-cast concrete between the prefabricated curved slabs and the tunnel lining structure and the concrete of the cast-in-place corbels reach the designed strength, hoists the prefabricated lane slabs to the top of the cast-in-place corbels and supporting corbels for assembly, then connects the steel bars at the joints and pours the concrete to complete the installation of the prefabricated lane slabs; S5. Repeat the above operations S1 to S4 to complete the installation of the tunnel longitudinal fully prefabricated lane slab structure. After the longitudinal overlap of the lane slab is completed, grouting is injected to fill the gap to ensure that the longitudinal connection of the lane slab is tight.