Structure and construction method of dark-excavated tunnel passing under the floor of existing buildings and structures with super-dense adhesion

By canceling the initial support roof of the tunnel, using structural support concrete cushions such as I-shaped steel and L-angle steel, and performing waterproof and tight patching in the second lining structure, the problem of channel height extrusion and waterproofing in the tight patch underpass solution is solved. , achieves the effect of increasing channel height and cost savings.

CN113931638BActive Publication Date: 2024-11-15BEIJING GENERAL MUNICIPAL ENG DESIGN & RES INST +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202111271469.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-10-29
Publication Date
2024-11-15
Estimated Expiration
2041-10-29

AI Technical Summary

Technical Problem

When the existing underpass scheme is penetrated under existing structures by under-excavation tunnels, the existence of the initial roof plate will squeeze the height of the channel, affecting its permanent use function, and cause adverse effects and waterproof damage to the existing structure, and construction will be carried out. Higher cost.

Method used

Using the ultra-secret underpass method, the initial support roof plate of the tunnel is cancelled. By setting structures such as I-shaped steel and L-angle steel on both sides of the tunnel, supporting the concrete cushion layer, reducing the longitudinal linear change and transition length of the channel, and in The waterproof layer is tightly bonded in the second lining structure to ensure the waterproofness and structural integrity of the existing base plate.

Benefits of technology

Without destroying the existing bottom plate structure and waterproofing, the channel height is increased, the channel usage function is improved, the project cost is reduced, and the construction safety is comparable to that of tightly applied underwear.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113931638B_ABST
    Figure CN113931638B_ABST
Patent Text Reader

Abstract

The structure and construction method of a dark excavation tunnel that is super-closely attached to the bottom plate of an existing building and structure include the bottom plate of the existing building and structure, including a raft plate, a waterproof layer and a protective layer from top to bottom, and grouting is constructed to reinforce the stratum in the areas on both sides of the dark excavation tunnel; a closed initial support structure is constructed in the dark excavation tunnel area, which is composed of an upper initial support side wall and a lower initial support side wall and a bottom plate, and a plain concrete cushion layer of the bottom plate of the existing building and structure is retained between the top of the upper initial support side wall and the waterproof layer and the protective layer, and the plain concrete cushion layer is closely attached to the waterproof layer and the protective layer; a new waterproof layer is arranged closely attached to the waterproof layer and the protective layer in the closed initial support structure; and a side wall waterproof layer, a bottom plate waterproof layer and a protective layer are constructed, which are closely attached to the side wall waterproof layer, the bottom plate waterproof layer and the protective layer, and a new waterproof layer on the top, and a closed secondary lining structure is constructed. The present invention does not destroy the structure and waterproofing of the existing bottom plate, cancels the dark excavation initial support top plate, and increases the height of the passage.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of underground engineering dark excavation, and is a structure and method for safely passing under existing buildings and structures by mining method, and is specifically a dark excavation tunnel structure and construction method for passing under the bottom plate of existing buildings and structures in an ultra-close manner. Background Art

[0002] Existing underground tunnels can be divided into two types according to the vertical distance between the structures: close-distance tunnels and close-fitting tunnels. Figure 1 and 2 As shown. The close-distance underpass scheme refers to the vertical distance (H) between the primary support of the dark-excavated tunnel and the bottom plate of the building, and the distance is less than or equal to the gross span (L) of the dark-excavated tunnel; the close-fitting underpass scheme H is 0, but there is still a primary support top plate (thickness is generally 250-350mm) between the secondary lining of the dark-excavated channel and the bottom plate of the existing building. When H is greater than the dark excavation L, it will have a greater adverse effect on the function of the tunnel, is not economical, and is often not recommended. The close-distance underpass scheme requires advance reinforcement of the soil, which will increase investment and construction period, and the force transmission path between the structures during construction and use is unclear. The close-fitting underpass scheme is more conducive to saving investment and controlling risks. Therefore, the close-fitting underpass scheme is becoming more and more popular.

[0003] The close-fitting underpass solution also has its shortcomings: the existence of the primary support top plate of the dark-cut tunnel will squeeze the height of the passage and affect its permanent use function. The functions of the primary support top plate of the dark-cut tunnel can be roughly summarized into two parts: the first part is to retain soil; the second part is to form a closed frame structure together with other parts of the tunnel primary support to ensure stable force. In the case of close-fitting underpass, the first part of the function can be replaced by the bottom plate of the existing building, and the second part of the function can be solved by planting reinforcement or installing expansion bolts in the existing bottom plate of the tunnel primary support side wall (see Figure 3 ). However, this solution will have an adverse effect on the existing structure and destroy its waterproofing.

[0004] In view of the shortcomings of the close-fitting underpass scheme, it is necessary to improve the underpass dark-excavation tunnel construction method. It is urgent to invent a technology that can eliminate the initial support top plate of the dark excavation, increase the height of the channel without destroying the existing bottom plate structure or waterproofing, and reduce the sudden changes and transition lengths of the longitudinal line of the channel at the underpass node, so as to better ensure its permanent use function and save investment. Summary of the invention

[0005] The present invention provides a dark-digging tunnel structure and a construction method for ultra-closely passing under the bottom plate of an existing building structure, the purpose of which is to eliminate the initial support top plate of the dark-digging tunnel in the close-passing scheme, and to increase the channel height and reduce the sudden change and transition length of the longitudinal line shape of the channel at the underpass node without destroying the existing bottom plate structure or waterproofing, so as to better ensure its permanent use function and save investment.

[0006] The technical solution of the present invention is as follows:

[0007] A construction method for a dark-excavated tunnel that passes through the bottom plate of an existing building or structure in an ultra-close fit includes the bottom plate of the existing building or structure. The bottom plate 1 of the existing building or structure includes a raft 11, a waterproof layer and a protective layer 12, and a plain concrete cushion layer 13 from top to bottom. The following steps are performed under the plain concrete cushion layer:

[0008] (1) In the areas on both sides of the dark excavated tunnel 2, an advance small guide tube 21 is constructed, and grouting is performed to reinforce the strata in the areas on both sides;

[0009] (2) The core soil is reserved to excavate the upper section II of the tunnel, and the upper initial support side wall 3 is constructed. The foot locking anchor pipe 32 is set at the foot, and the plain concrete cushion layer 13 under the raft is retained in the arch. A plurality of transversely arranged I-beams 4 are promptly erected along the longitudinal interval of the tunnel; the I-beams are closely attached to the plain concrete cushion layer, and promptly form support for the plain concrete cushion layer to reduce the deformation of the existing bottom plate. The connection node between the I-beam and the initial support side wall grid steel frame 31 needs to be processed as follows:

[0010] ① Use L angle steel 42 to seal the side wall grid steel frame 31; set the side wall grid steel frame under the plain concrete cushion layer 13;

[0011] L angle steel 42 is welded to the main reinforcement 311 of the side wall grid steel frame in T-shape;

[0012] ② The two ends of the I-beam 4 are connected to the L-angle steel 42 through a vertical additional steel plate 43;

[0013] The top surfaces of the I-beam and the additional steel plate, and the top surfaces of the additional steel plate and the L-angle steel are aligned and closely attached to the plain concrete cushion layer, the bottom of the additional steel plate exceeds the bottom of the I-beam, the additional steel plate and the L-angle steel are welded together on three sides, and the I-beam and the additional steel plate are welded together on three sides;

[0014] ③ Multiple longitudinal connecting ribs 41 with a horizontal spacing of no more than 500 mm are welded and connected on one side of the lower part of the I-beam to integrally connect the bottoms of the I-beams;

[0015] (3) Excavate the lower section IV of the tunnel; construct the lower initial support side wall and bottom plate 5 to form the overall closed initial support of the dark excavated tunnel;

[0016] (4) After laying the bottom slab waterproofing and protective layer 10 in the initial support, the secondary tunnel slab 6 is constructed;

[0017] (5) Construct waterproofing of the side walls and the second lining side wall 7 on the second bottom slab to the construction joint under the second lining top slab in the initial support. After the second lining side wall reaches the design strength, the full-floor scaffolding is not removed and the second lining side wall is pressed tightly. According to the monitoring situation, the arch I-beam 4 and the plain concrete cushion 13 under the raft slab in the initial support are removed in sections. The length of each section shall not exceed 7m.

[0018] (6) A new waterproof layer is laid under the waterproof layer and the protective layer 12 under the raft slab, and a secondary lining top plate 8 is constructed to be in close contact with the new waterproof layer under the raft slab. The secondary lining top plate 8 is integrally connected with the secondary lining side wall 7 and the secondary bottom plate 6 to form an integral secondary lining structure. Grouting is performed behind the secondary lining structure to finally complete the construction of the dark-excavated tunnel structure of the present invention.

[0019] The method for constructing a tunnel that is ultra-closely connected to the bottom plate of an existing building is characterized in that when the L angle steel 42 is T-welded to the main reinforcement 311 of the side wall grid steel frame, the weld height should not be less than 6 mm and 0.6d (d is the diameter of the main reinforcement of the grid steel frame), whichever is greater; when the additional steel plate is welded to the L angle steel on three sides and the I-beam is welded to the additional steel plate on three sides, the fillet weld leg size should not be less than 1.5t 1 / 2 , and shall not be greater than t-(1-2mm) (t is the smaller value of the thickness of the steel plate connected by welding, and "-" is a minus sign);

[0020] A dark-excavated tunnel that passes under the bottom plate of an existing building and structure in an ultra-close fit, comprises the bottom plate of the existing building and structure, wherein the bottom plate comprises a raft plate 11, a waterproof layer and a protective layer 12 from top to bottom, and grouting reinforcement is arranged in the areas on both sides of the dark-excavated tunnel; a closed initial support structure is arranged in the dark-excavated tunnel area, which is composed of an upper initial support side wall 3 and a lower initial support side wall and a bottom plate 5 of the dark-excavated tunnel, and a plain concrete cushion layer 13 of the bottom plate 1 of the existing building and structure is retained between the top of the upper initial support side wall 3 and the waterproof layer and the protective layer 12, and the plain concrete cushion layer 13 is closely attached to the waterproof layer. layer and protective layer 12; in the closed initial supporting structure, a new waterproof layer is arranged closely below the waterproof layer and protective layer 12; in the closed initial supporting structure, a side wall waterproof layer and a bottom plate waterproof and protective layer 10 are arranged closely following the side wall waterproof layer and the bottom plate waterproof and protective layer 10, and the new waterproof layer on the top, and a closed second lining structure is arranged, including a second lining top plate 8, a second lining side wall 7 and a second bottom plate 6, the second lining top plate 8 sandwiching the waterproof layer and protective layer 12 and the new waterproof layer closely following the raft slab; a grouting layer is arranged behind the second lining structure to constitute the dark excavated tunnel.

[0021] The dark-dug tunnel that passes under the bottom plate of an existing building and structure in an ultra-close fit is characterized in that the upper initial support side wall 3 is provided with a locking foot anchor pipe 32 at the foot.

[0022] The dark-excavated tunnel that passes under the bottom plate of an existing building in an ultra-close fit is characterized in that a side wall grid steel frame 31 is provided in the upper initial support side wall 3 and the lower initial support side wall.

[0023] The described ultra-closely concealed tunnel that passes under the floor of an existing building is characterized in that the construction joints 9 between the secondary lining top plate 8 , the secondary lining side wall 7 and the secondary bottom plate 6 are all arranged on the secondary lining side wall 7 .

[0024] Effects of the Invention

[0025] The ultra-close-fitting dark excavation scheme of the present invention that passes through the bottom slab of an existing building is as safe as close-fitting dark excavation, does not damage the structure and waterproofing of the existing bottom slab, and by eliminating the initial support top slab of the dark excavation, increases the height of the passage, improves the use function of the passage, and reduces the project cost. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 It is a schematic diagram of the structure of the close-range underpass solution in the prior art.

[0027] Figure 2 This is the structural intent of the close-fitting underpass solution of the prior art.

[0028] Figure 3 This is a schematic diagram of the prior art close-fitting underpass solution and the connection of the primary support with the existing base plate through expansion bolts.

[0029] Figure 4 This is a schematic diagram of grouting to reinforce the stratum in step 1 of the present invention.

[0030] Figure 5 This is a schematic diagram of the structure of the upper section II excavated in step 2 of the present invention and the construction of the upper initial support side wall 3.

[0031] Figure 6 This is a schematic diagram of the connection structure between the I-beam and the existing bottom plate and the side wall grille of the present invention.

[0032] Figure 7 This is a schematic diagram of the structure of excavating the lower section IV in step 3 of the present invention and constructing the lower initial support side wall and bottom plate 5.

[0033] Figure 8 The schematic diagram of the structure of laying a waterproof layer and constructing a secondary substrate 6 in step 4 of the present invention is shown in FIG.

[0034] Fig. 9 This is a schematic diagram of the structure of laying a waterproof layer in step 5 of the present invention and constructing the secondary lining side wall 7.

[0035] Fig.10 This is a schematic diagram of the structure of laying a waterproof layer and constructing a secondary lining top plate 8 in step 6 of the present invention.

[0036] Description of the accompanying drawings:

[0037] The existing building structure bottom plate 1, raft plate 11, waterproof layer and protective layer 12, plain concrete cushion layer 13, dark excavated tunnel 2, advanced small guide tube 21, upper initial support side wall 3, side wall grid steel frame 31, side wall grid steel frame main reinforcement 311, locking foot anchor pipe 32, I-beam 4, longitudinal connecting reinforcement 41, L angle steel 42, additional steel plate 43, anchor reinforcement 44, welded steel bar 45, lower initial support side wall and bottom plate 5, secondary bottom plate 6, secondary lining side wall 7, secondary lining top plate 8, construction joint 9, waterproof protective layer 10 (the material of the tunnel waterproof protective layer of the present invention is C20 fine stone concrete), (existing technology) expansion bolt and arch frame connection 101. DETAILED DESCRIPTION

[0038] The specific implementation modes of the present invention are described in detail below with reference to the accompanying drawings.

[0039] See also Figure 4-10 As shown, a construction method of a dark excavated tunnel that passes through the bottom plate of an existing building and structure in an ultra-close fit includes the bottom plate of the existing building and structure. The bottom plate 1 of the existing building and structure includes a raft 11, a waterproof layer and a protective layer 12, and a plain concrete cushion layer 13 from top to bottom. The following steps are performed under the plain concrete cushion layer:

[0040] (1) See Figure 4 As shown, in the areas on both sides of the dark excavated tunnel 2, an advance small guide tube 21 is constructed, and grouting is performed to reinforce the strata in the areas on both sides;

[0041] (2) See Figure 5 As shown, the core soil is reserved to excavate the upper section II of the tunnel, the upper initial support side wall 3 is constructed, the foot locking anchor pipe 32 is set at the foot, the plain concrete cushion layer 13 under the raft is retained in the arch, and a plurality of transversely arranged I-beams 4 are timely erected along the longitudinal interval of the tunnel under the plain concrete cushion layer 13; the I-beams are closely attached to the plain concrete cushion layer, and in order to timely form support for the plain concrete cushion layer and reduce the deformation of the existing bottom plate, the connection node between the I-beams and the side wall grid steel frame 31 in the initial support needs to be processed as follows: See Figure 6 As shown,

[0042] ① Use L angle steel 42 to seal the side wall grid steel frame 31; set the side wall grid steel frame under the plain concrete cushion layer 13; I-beams are horizontally set between the side wall grid steel frames on both sides; L angle steel 42 is connected to the main reinforcement 311 of the side wall grid steel frame by T-type welding;

[0043] ② The two ends of the I-beam 4 are connected to the L-angle steel 42 through a vertical additional steel plate 43;

[0044] The top surfaces of the I-beam and the additional steel plate, and the top surfaces of the additional steel plate and the L-angle steel are aligned and closely attached to the plain concrete cushion layer, the bottom of the additional steel plate exceeds the bottom of the I-beam, the additional steel plate and the L-angle steel are welded on three sides, and the I-beam and the additional steel plate are welded on three sides;

[0045] ③ Multiple longitudinal connecting ribs 41 with a horizontal spacing of no more than 500 mm are welded and connected on one side of the lower part of the I-beam to integrally connect the bottoms of the I-beams;

[0046] (3) See Figure 7 As shown, the lower section IV of the tunnel is excavated; the lower initial support side wall and bottom plate 5 are constructed to form the overall closed initial support of the dark excavated tunnel;

[0047] (4) See Figure 8 As shown, after laying the bottom slab waterproofing and protective layer 10 in the initial support, the second tunnel substrate slab 6 is constructed;

[0048] (5) See Fig. 9 As shown, waterproofing of the side wall and the second lining side wall 7 on the second bottom slab to the construction joint under the second lining top slab are constructed in the initial support. After the second lining side wall reaches the design strength, the full-floor scaffolding is not removed and the second lining side wall is pressed tightly. According to the monitoring situation, the arch I-beam 4 and the plain concrete cushion 13 under the raft slab in the initial support are removed in sections, and the length of each section shall not be greater than 7m.

[0049] (6) See Fig.10 As shown, a new waterproof layer is laid under the waterproof layer and the protective layer 12 under the raft slab, and a second lining top plate 8 is constructed to be in close contact with the new waterproof layer under the raft slab. The second lining top plate 8 is integrally connected with the second lining side wall 7 and the second bottom plate 6 to form an overall second lining structure. Grouting is performed behind the second lining structure to finally complete the construction of the dark-excavated tunnel structure of the present invention.

[0050] In the construction method of a dark-digging tunnel that passes through the bottom plate of an existing building structure in an ultra-close fit, when the L angle steel 42 is T-welded to the main reinforcement 311 of the side wall grid steel frame, the weld height should not be less than the larger value of 6 mm and 0.6d (d is the diameter of the main reinforcement of the grid steel frame); when the additional steel plate is connected to the L angle steel by three-sided welding, and the I-beam is connected to the additional steel plate by three-sided welding, the fillet weld leg size should not be less than 1.5t 1 / 2 , and shall not be greater than t-(1-2mm) (t is the smaller value of the thickness of the steel plate connected by welding, and "-" is a minus sign);

[0051] See also Fig.10As shown, a dark-excavated tunnel that passes under the bottom plate of an existing building and structure in an ultra-close fit of the present invention comprises the bottom plate of the existing building and structure, wherein the bottom plate of the existing building and structure comprises a raft 11, a waterproof layer and a protective layer 12 from top to bottom, and grouting reinforcement strata are arranged in the areas on both sides of the dark-excavated tunnel; a closed initial support structure is arranged in the dark-excavated tunnel area, which is composed of an upper initial support side wall 3, and a lower initial support side wall and a bottom plate 5 of the dark-excavated tunnel, and a plain concrete cushion layer 13 of the bottom plate 1 of the existing building and structure is also retained between the top of the upper initial support side wall 3 and the waterproof layer and the protective layer 12, and the plain concrete cushion layer 13 is close to the bottom plate of the existing building and structure. The waterproof layer and protective layer 12 are attached below; a new waterproof layer is arranged in the closed initial supporting structure, closely attached to the waterproof layer and protective layer 12 below; a side wall waterproof layer and a bottom plate waterproof and protective layer 10 are arranged in the closed initial supporting structure, closely attached to the side wall waterproof layer, the bottom plate waterproof and protective layer 10, and the new waterproof layer on the top, and a closed second lining structure is arranged, including a second lining top plate 8, a second lining side wall 7 and a second bottom plate 6, the second lining top plate 8 sandwiches the waterproof layer and protective layer 12 and the new waterproof layer double-layer waterproof and closely attached to the raft slab; a grouting layer is arranged behind the second lining structure to constitute the dark excavated tunnel.

[0052] The described ultra-closely concealed tunnel that passes under the bottom plate of an existing building structure has an upper initial support side wall 3, and a locking foot anchor pipe 32 is set at the foot.

[0053] In the dark-dig tunnel that passes under the bottom plate of an existing building in an ultra-close fit, a side wall grid steel frame 31 is provided in the upper initial support side wall 3 and the lower initial support side wall.

[0054] In the ultra-closely concealed tunnel that passes under the floor of an existing building, the construction joints 9 between the secondary lining top plate 8 , the secondary lining side wall 7 and the secondary bottom plate 6 are all arranged on the secondary lining side wall 7 .

[0055] The principle of the ultra-close-fitting underground excavation method of the present invention is: when excavating a tunnel, an I-beam is used to replace the traditional primary support top plate, so as to provide timely support to the existing bottom plate and form a closed frame structure with other parts of the tunnel primary support to ensure stable force; when constructing the secondary lining, force conversion is carried out, the arch I-beam is removed, and the secondary lining top plate is directly close to the existing bottom plate, thereby increasing the height of the passage.

[0056] Example

[0057] The 3# and 4# channel shafts, dark excavation structures and waterproofing projects of a certain project were tested. The dark excavation section of the 4# channel under the stadium floor is about 23 meters long. Because the clear height of the channel is limited, the primary support top plate is not allowed between the secondary lining top plate and the stadium floor. The technology of the present invention was used for construction. At present, the tunnel construction has been tested. Monitoring shows that all indicators are within the required range.

[0058] The following is an example of the construction of a dark excavation tunnel using the step method (other dark excavation methods can be used as a reference), and the specific steps and key node methods are briefly described as follows (other construction details are the same as the above specific implementation methods and will not be repeated): Figure 4-10 As shown;

[0059] (1) In the area on both sides of the dark excavated tunnel 2, advance small guide pipes are constructed and grouting is performed to reinforce the stratum; see Figure 4 ,

[0060] (2) Reserve core soil, excavate the upper section II, construct the upper initial support side wall 3, install locking anchor pipes at the foot, retain the original raft slab cushion layer at the arch, and promptly install I-beams underneath it; see Figure 5 ,

[0061] In order to ensure that the I-beam is in close contact with the existing floor cushion, form support in time, and reduce the deformation of the existing floor, the connection node between the I-beam and the side wall grid steel frame needs to be processed as follows:

[0062] ① Use L angle steel to seal the ends of the side wall grille steel frame, and set the side wall grille steel frame under the plain concrete cushion layer 13; the L angle steel and the main reinforcement of the side wall grille steel frame are T-welded, and the weld height should not be less than 6mm and should not be less than 0.6d (d is the diameter of the main reinforcement of the grille steel frame).

[0063] ② The two ends of the I-beam are connected to the L-angle steel through additional steel plates. The top surfaces of the I-beam and the additional steel plates, and the top surfaces of the additional steel plates and the L-angle steel are aligned, and the other three sides are connected by welding. The size of the fillet weld leg shall not be less than 1.5t 1 / 2 , and shall not be greater than t-1~2mm (t is the smaller value of the thickness of the connecting steel plate).

[0064] ③ Set longitudinal connecting ribs with a horizontal spacing of 500mm on one side of the lower part of the I-beam to connect the bottoms of each I-beam as a whole.

[0065] (3) Excavate the lower section IV and construct the lower initial support side wall and bottom plate 5 to form the overall closed initial support of the dark excavated tunnel;

[0066] (4) Lay the waterproof layer and construct the secondary baseboard structure 6,

[0067] (5) Lay the waterproof layer and construct the construction joint from the second lining side wall 7 to the bottom of the second lining top plate. After the side wall reaches the design strength, the full-floor scaffolding is not removed and the side wall is pressed tightly. According to the monitoring situation, the arch I-shaped steel and the original raft cushion layer in the initial support are removed in sections (the length of each section shall not exceed 7m).

[0068] (6) Lay a waterproof layer, construct a secondary lining top plate 8, form a secondary lining structure, and inject grout behind the secondary lining to finally form the dark excavation tunnel structure of the present invention. Fig.10, including a second lining top plate 8 which is in close contact with the existing bottom plate and forms a closed tunnel structure with the side walls and bottom plate below.

Claims

1. A construction method for a dark-excavated tunnel that passes through the bottom slab of an existing building or structure in an ultra-close fit, comprising the bottom slab of the existing building or structure, wherein the bottom slab of the existing building or structure (1) comprises, from top to bottom, a raft slab (11), a waterproof layer and a protective layer (12), and a plain concrete cushion layer (13), and the following steps are performed under the plain concrete cushion layer: (1) constructing an advance small guide pipe (21) in the area on both sides of the dark excavated tunnel (2), and grouting to reinforce the strata in the area on both sides; (2) The core soil is reserved to excavate the upper section of the tunnel (II), and the upper initial support side wall (3) is constructed. A locking foot anchor pipe (32) is installed at the foot, and the plain concrete cushion layer (13) under the raft is retained at the arch, and a plurality of transversely arranged I-beams (4) are promptly erected thereunder along the longitudinal direction of the tunnel; the I-beams are closely attached to the plain concrete cushion layer, and promptly form support for the plain concrete cushion layer, thereby reducing the deformation of the existing bottom plate. The connection node between the I-beam and the initial support side wall grid steel frame (31) needs to be processed as follows: ① Using L-angle steel (42) to seal the side wall grid steel frame (31); arranging the side wall grid steel frame under the plain concrete cushion layer (13); The L angle steel (42) is T-welded to the main reinforcement (311) of the side wall grid steel frame; ② The two ends of the I-beam (4) are connected to the L-angle steel (42) via a vertical additional steel plate (43); The top surfaces of the I-beam and the additional steel plate, and the top surfaces of the additional steel plate and the L-angle steel are aligned and closely attached to the plain concrete cushion layer, the bottom of the additional steel plate exceeds the bottom of the I-beam, the additional steel plate and the L-angle steel are welded together on three sides, and the I-beam and the additional steel plate are welded together on three sides; ③ Welding a plurality of longitudinal connecting ribs (41) with a horizontal spacing of no more than 500 mm on one side of the lower portion of the I-beam to integrally connect the bottoms of the I-beams; (3) Excavating the lower section IV of the tunnel; constructing the lower initial support side wall and bottom plate (5) to form the overall closed initial support of the dark excavated tunnel; (4) After laying the bottom slab waterproofing and protective layer (10) in the initial support, construct the tunnel secondary slab (6); (5) Construct waterproofing of the side walls and the secondary lining side walls (7) on the secondary bottom slab to the construction joint under the secondary lining top slab in the primary support. After the secondary lining side walls reach the designed strength, the full-floor scaffolding is not dismantled and the secondary lining side walls are pressed tightly. Based on the monitoring situation, the arch I-beams (4) and the plain concrete cushion layer (13) under the raft slab in the primary support are dismantled in sections. The length of each section to be dismantled shall not exceed 7 m. (6) A new waterproof layer is laid under the waterproof layer and the protective layer (12) under the raft slab, and a secondary lining top plate (8) is constructed to be in close contact with the new waterproof layer under the raft slab. The secondary lining top plate (8) is integrally connected with the secondary lining side wall (7) and the secondary bottom plate (6) to form an integral secondary lining structure. Grouting is performed behind the secondary lining structure to finally complete the construction of the dark-excavated tunnel structure of the present invention.

2. The method for constructing a dark-excavated tunnel that passes through the bottom plate of an existing building and structure in an ultra-close fit as claimed in claim 1, characterized in that: When the L angle steel (42) is T-welded to the main reinforcement (311) of the side wall grid steel frame, the weld height should not be less than the larger value of 6 mm and 0.6d (d is the diameter of the main reinforcement of the grid steel frame); when the additional steel plate is connected to the L angle steel by three-sided welding, and the I-beam is connected to the additional steel plate by three-sided welding, the fillet weld leg size should not be less than 1.5t 1 / 2 , and shall not be greater than t-(1~2mm) (t is the smaller value of the thickness of the steel plate connected by welding, and "-" is a minus sign).

3. A dark tunnel that passes through the bottom plate of an existing building in an ultra-close manner, comprising the bottom plate of the existing building, wherein the bottom plate of the existing building comprises a raft plate (11), a waterproof layer and a protective layer (12) from top to bottom, characterized in that: Grouting is provided to reinforce the ground in the areas on both sides of the dark excavation tunnel; a closed initial support structure is provided in the dark excavation tunnel area, which is composed of an upper initial support side wall (3) and a lower initial support side wall and a bottom plate (5) of the dark excavation tunnel; a plain concrete cushion layer (13) of the bottom plate (1) of the existing building structure is also retained between the top of the upper initial support side wall (3) and the waterproof layer and the protective layer (12); the plain concrete cushion layer (13) is closely attached to the bottom of the waterproof layer and the protective layer (12); in the closed initial support structure, the waterproof layer and the protective layer (12) are closely attached to the bottom of the waterproof layer and the protective layer (12); A new waterproof layer is arranged below the water layer and the protective layer (12); a side wall waterproof layer and a bottom plate waterproof and protective layer (10) are arranged in the closed initial support structure, closely attached to the side wall waterproof layer and the bottom plate waterproof and protective layer (10) and the new waterproof layer on the top; a closed secondary lining structure is arranged, comprising a secondary lining top plate (8), a secondary lining side wall (7) and a secondary bottom plate (6); the secondary lining top plate (8) sandwiches the waterproof layer and the protective layer (12) and the new waterproof layer and closely attached to the raft slab; a grouting layer is arranged behind the secondary lining structure to form the dark excavated tunnel.

4. The ultra-closely concealed tunnel under the floor of an existing building as claimed in claim 3, characterized in that: The upper initial support side wall (3) is provided with a foot-locking anchor pipe (32) at the foot.

5. The ultra-closely concealed tunnel under the floor of an existing building as claimed in claim 3, characterized in that: The upper initial support side wall (3) and the lower initial support side wall are provided with a side wall grid steel frame (31).

6. The ultra-closely concealed tunnel under the floor of an existing building as claimed in claim 3, characterized in that: The construction joints (9) between the secondary lining top plate (8), the secondary lining side wall (7) and the secondary bottom plate (6) are all arranged on the secondary lining side wall (7).