Full-circle needle beam lining trolley and construction method thereof
Through the combination of the sliding formwork and the ring rail trolley drive mechanism, the problems of insufficient vibration and long construction time in the existing full-circle needle beam trolley are solved, and the results of vibration at the bottom of the tunnel without dead corners and high concrete density are achieved. Improved construction efficiency and saved resources.
Patent Information
- Application Number
- CN202111497922.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-12-09
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2041-12-09
AI Technical Summary
In the tunnel concrete lining construction, the existing full-circle needle beam trolley suffers from insufficient vibration due to the bottom formwork coverage, long construction time, huge waste of resources, and the cloth mechanism is cumbersome and cannot be flexibly adjusted.
The sliding formwork and ring rail trolley drive mechanism are used. The sliding formwork moves along the ring guide rail, vacating the bottom of the tunnel, and flexibly vibrates and pours concrete, reducing the formwork coverage area and improving construction efficiency and speed.
The bottom of the tunnel is vibrated without dead ends, the concrete has high density, the construction speed is doubled, steel is saved, and resource consumption is reduced.
Smart Images

Figure CN114033436B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a construction device in tunnel concrete lining construction, in particular to a full-circle needle beam lining trolley and a construction method thereof, which are used for the construction of one-time concrete lining of the entire section of a tunnel. Background Art
[0002] The full-circle needle beam trolley is a large-scale formwork equipment used for concrete lining construction of tunnels with circular or horseshoe-shaped excavation sections.
[0003] The full-circle needle beam trolley currently in use mainly consists of: top template, side template, bottom template, needle beam frame, needle beam, needle beam base, support jack, oil cylinder, traction mechanism and other components. Each template is connected to the needle beam frame. The top template, side template and bottom template can be rotated or extended and retracted with the needle beam frame through the support jack and the oil cylinder base when erecting (dismantling) the template. The needle beam frame can drive the template to slide on the needle beam. The needle beam is connected to the needle beam base through the jacking oil cylinder. The needle beam base is supported on the lined base and excavation base of the tunnel. A winch is installed at the rear end of the needle beam. When the needle beam base is used as the support point, the needle beam frame can be pulled to slide forward and backward along the needle beam. When the template is used as the support point, the needle beam can be pulled to slide forward and backward along the needle beam frame. Before the tunnel lining, the trolley is first erected in place and then the concrete pouring construction is carried out. After the pouring construction is completed, the concrete solidifies and reaches the demoulding strength requirements, and the trolley is operated to demould and move to the next construction position for the next round of construction.
[0004] However, the existing full-circle needle beam trolley has the following disadvantages: 1. Since the bottom of the tunnel is covered by the bottom formwork, the vibration of the concrete needs to be carried out from the working window opened on the formwork. Due to the limitation of the formwork structure, the number of working windows is limited and the concrete surface that needs to be vibrated cannot be fully taken into account, resulting in the bottom concrete not meeting the structural strength standard due to insufficient vibration; 2. The process of opening and closing the working window is cumbersome and the material distribution mechanism cannot be flexibly adjusted due to the limitation of the position of the working window during material distribution, resulting in a long construction time; 3. The bottom formwork uses a large amount of steel, which causes a great waste of resources. Summary of the invention
[0005] The purpose of the present invention is to overcome the above problems existing in the prior art and provide a full-circle needle beam lining trolley and a construction method thereof. With the present invention, the entire tunnel bottom is in an open state during the lining process, which is convenient for vibration operation and conducive to vibration exhaust, and there is no dead angle for vibration, and the concrete has high compaction strength.
[0006] To achieve the above purpose, the technical solution adopted by the present invention is as follows:
[0007] A full-circle needle beam lining trolley comprises a top form, a side form, a side form, a needle beam frame and a needle beam, and is characterized in that it also comprises a side beam, a longitudinal guide rail, an annular guide rail, an annular rail trolley, a sliding template, and an annular rail trolley driving mechanism; the needle beam frame is rigidly connected to the side beam, there are two side beams, and the upper plane of each side beam is rigidly connected to the side template; the longitudinal guide rail and the annular guide rail are located between the two side beams and are rigidly connected to the side beams; the annular guide rail is slidably connected to the annular rail trolley, and the annular rail trolley is rigidly connected to the sliding template; the annular rail trolley driving mechanism is rigidly connected to the needle beam frame to drive the annular rail trolley to move on the annular guide rail.
[0008] There are four circular rail trolleys, which are slidably connected to two groups of circular guide rails through trolley rollers and limiting slide grooves on the circular guide rails, and each group of circular guide rails is connected to two circular rail trolleys respectively. The circular rail trolleys are divided into two groups according to the left and right sides of the tunnel section, with two trolleys in each group. Each group of circular rail trolleys is rigidly connected to a group of sliding templates, and two connecting bolts hinged to the chain are provided in the middle of each circular rail trolley.
[0009] The ring rail trolley driving mechanism is linked to a traction chain, the traction chain passes around the ring rail, and both ends of the traction chain are respectively hinged to the ring rail trolley to form a closed transmission chain.
[0010] There are 4 ring rail trolley drive mechanisms, 2 in each group, one group on the left and one group on the right. The ring rail trolley drive mechanisms are rigidly connected to the needle beam frame respectively. Each ring rail trolley drive mechanism is provided with a driving sprocket, which is connected to a traction chain through the driving sprocket. The rotating shaft of each group of ring rail trolley drive mechanisms is hinged through a transmission shaft.
[0011] There are four traction chains, each of which is connected to a driving sprocket of the ring rail trolley driving mechanism. The traction chains pass around the chain guide wheels arranged on the ring rail and the side wall connecting beam respectively, and the two ends are respectively hinged to the two connecting bolts of the ring rail trolley to form a closed transmission chain.
[0012] There are two longitudinal guide rails, which are rigidly connected to the front and rear inner planes of the two sets of side beams respectively, and are also rigidly connected to the lower end of the needle beam frame; a chain guide wheel is respectively provided above and below the outer end of the circumferential guide rail, and a chain guide wheel is provided below the inner end.
[0013] The top mold is a group, and its two sides are respectively hinged to two groups of side molds, and the lower end is rigidly connected to the upper ends of 10 top mold cylinders, and the lower end of the top mold cylinder is rigidly connected to the needle beam frame; the side molds are two groups, one group on the left and one group on the right are respectively hinged to the two sides of the top mold, and the middle part of each group of side molds is hinged to one end of 10 supporting jacks; the side molds are two groups, one group on the left and one group on the left are rigidly connected to the side beams on both sides, and the upper part of each group of side molds is also rigidly connected to the lower part of the needle beam frame.
[0014] The needle beam frame is a group, the upper part of which is rigidly connected to the lower ends of 10 top mold cylinders, and the lower part is rigidly connected to the side molds and side beams on both sides. The needle beam frame is also slidably connected to the needle beam; the needle beam is a group, and the left and right sides of both ends are rigidly connected to the upper ends of 4 needle beam cylinders respectively. The needle beam is also provided with a needle beam traction mechanism for driving the needle beam and the needle beam frame to slide relative to each other.
[0015] The upper end of the needle beam oil cylinder is rigidly connected to the left and right sides of the front and rear ends of the needle beam respectively, and the lower end is slidably connected to the two needle beam bases at the front and rear ends of the needle beam.
[0016] A construction method for a full-circle needle beam lining trolley, characterized in that it comprises the following steps:
[0017] A. First move the trolley to the required position of the tunnel and set up the mold;
[0018] B. Tunnel bottom concrete construction:
[0019] B1 starts the driving mechanism of the circular rail trolley, and the circular rail trolley moves and drives the sliding templates on both sides to move to the left and right sides along the circular guide rail to clear the bottom of the tunnel;
[0020] B2 Pour concrete into the tunnel bottom through the concrete placing mechanism and vibrate the concrete according to the specification requirements;
[0021] B3 When the concrete is poured to the inner top surface of the tunnel bottom, the ring track trolley driving mechanism is started, the ring track trolley moves and drives the sliding template to move toward the middle along the ring guide rail, closing the bottom of the tunnel invert and scraping off the excess concrete;
[0022] B4 Pour concrete to the outside of the sliding formwork through the placing mechanism and vibrate the concrete according to the specification requirements;
[0023] B5 When the concrete fills the bottom of the sliding formwork, start the ring rail trolley driving mechanism, and the ring rail trolley drives the sliding formwork on both sides to move to the left and right along the ring rail, and continue to pour concrete to the outside of the sliding formwork through the material placing mechanism, and vibrate the concrete according to the specification requirements, and repeat this process until the sliding formwork is connected to the side beam;
[0024] B6 Pour concrete from the side form working window through the placing mechanism and vibrate the concrete according to the specifications to complete the entire bottom concrete pouring.
[0025] Concrete pouring on both sides and top:
[0026] C1 pours concrete on both sides of the tunnel through the side form working window after the bottom concrete has initially set;
[0027] C2 pours the tunnel top concrete through the top form working window and grouting port and completes the concrete pouring;
[0028] D. When the top concrete reaches the demoulding requirements, the operating trolley is used to remove the mold;
[0029] Repeat the above steps to carry out tunnel concrete lining construction.
[0030] The advantages of adopting the present invention are:
[0031] 1. In the present invention, the bottom formwork of the current full-circle needle beam lining trolley is replaced by a sliding formwork with a very small coverage area. During the entire tunnel bottom lining process, except for the sliding formwork coverage area, the rest of the tunnel bottom is in an open state, and vibration operations can be carried out on both sides of the sliding formwork in the longitudinal direction. Since the sliding formwork has a small area, the concrete covered by it is also in the effective vibration area; the side formwork, the side formwork and the top formwork are almost perpendicular to the horizontal plane, and the top of the pouring space is open, which is conducive to inserting a vibrating rod during vibration. Therefore, there is no dead angle for vibration and exhaust during the entire construction process, and the concrete has high compaction strength.
[0032] Second, in the present invention, the circular rail trolley first drives the sliding templates on both sides to move along the circular guide rail to the left and right sides of the tunnel, leaving the tunnel bottom empty, and pouring concrete through the distribution mechanism. When the concrete is poured to the inner top surface of the tunnel bottom, the circular rail trolley is started to drive the sliding template to move along the circular guide rail to the middle of the tunnel, closing the bottom of the tunnel invert and scraping off excess concrete, and then concrete is distributed from the side of the sliding template moving direction. After the sliding template is connected to the side template, the concrete is distributed from above the side template. The entire tunnel top lining process is flexible and fast in distribution, and the tedious work of opening and closing the working window of the mold-building process is not required, and the construction speed can be increased by more than double.
[0033] 3. In the present invention, the material laying and vibration operations in the entire tunnel bottom construction process are not subject to the position restrictions caused by the working windows set on the templates in the formwork construction. Workers can flexibly arrange the construction positions, which is efficient and has low labor intensity, and is conducive to construction in harsh environments.
[0034] Fourth, the sliding template of the present invention has a small area and the added component weight is relatively light, and the total weight is light; various bottom templates used in existing mold construction are made of large-area steel plates and are heavy. Therefore, the present invention can save a lot of steel, has low cost, and occupies less social resources.
[0035] 5. A plugging plate is fixedly installed on the outer side of the front longitudinal guide rail of the present invention, and it also forms a concrete pouring space with the sliding formwork; the front half of the rear longitudinal guide rail overlaps the formed bottom arch concrete of the tunnel, and the rear half is suspended in the air, so as to prevent the sliding formwork from being obstructed by the formed bottom arch concrete when moving, and it also forms a concrete pouring space with the sliding formwork. BRIEF DESCRIPTION OF THE DRAWINGS
[0036] Figure 1 It is a schematic diagram of the structure of the trolley of the present invention;
[0037] Figure 2 for Figure 1AA structural diagram in FIG.
[0038] Figure 3 for Figure 1 Schematic diagram of the BB structure;
[0039] Figure 4 for Figure 1 Schematic diagram of CC structure;
[0040] Figure 5 It is a schematic diagram of the demoulding state structure of the present invention.
[0041] Markings in the figure are: 1. top mold, 2. side mold, 3. side mold, 4. top mold cylinder, 5. needle beam frame, 6. needle beam, 7. supporting jack, 8. side beam, 9. longitudinal guide rail, 10. ring guide rail, 11. ring rail trolley, 12. sliding template, 13. ring rail trolley driving mechanism, 14. needle beam cylinder, 15. needle beam base, 16. needle beam traction mechanism, 17. traction chain, 18. chain guide wheel. DETAILED DESCRIPTION
[0042] A full-circle needle beam lining trolley comprises a top form 1, a side form 2, a side form 3, a top form oil cylinder 4, a needle beam frame 5, a needle beam 6, a supporting jack 7, a side beam 8, a longitudinal guide rail 9, an annular guide rail 10, an annular rail trolley 11, a sliding template 12, an annular rail trolley driving mechanism 13, a needle beam oil cylinder 14, a needle beam base 15 and a needle beam traction mechanism 16. The upper plane of the side beam 8 is rigidly connected to the side form 3 and the needle beam frame 5, and the inner plane is rigidly connected to the longitudinal guide rail 9, the annular guide rail 10 and the needle beam frame 5 respectively. The annular guide rail 10 is slidably connected to the annular rail trolley 11, and the annular rail trolley 11 is rigidly connected to the sliding template 12; the annular rail trolley driving mechanism 13 is rigidly connected to the needle beam frame 5, and the annular rail trolley driving mechanism 13 is linked to a traction chain 17, which passes around the annular guide rail 10, and the two ends are respectively hinged to the annular rail trolley 11 to form a closed transmission chain.
[0043] The top mold 1 is a group, and the two sides are respectively hinged with two groups of side molds 2, and the lower end is rigidly connected to the upper ends of 10 top mold cylinders 4;
[0044] The side molds 2 are divided into two groups, one on the left and one on the right, which are respectively hinged to the two sides of the top mold 1 , and the middle part of each group of side molds 2 is hinged to one end of 10 supporting jacks 7 .
[0045] The side molds 3 are divided into two groups, one group on the left and one group on the right, which are rigidly connected to the side beams 8 on both sides. The upper part of each group of side molds 3 is also rigidly connected to the lower part of the needle beam frame 5.
[0046] There are 10 top mold oil cylinders 4 , the upper ends of which are rigidly connected to the top mold 1 , and the lower ends of which are rigidly connected to the needle beam frame 5 .
[0047] The needle beam frame 5 is a group, the upper part is rigidly connected to the lower ends of 10 top mold cylinders 4, and the lower part is rigidly connected to the left and right side molds 3 and the side beam 8. The needle beam frame 5 is also slidably connected to the needle beam 6, and the needle beam frame 5 is also rigidly connected to 4 ring rail trolley driving mechanisms 13 at the corresponding positions.
[0048] The needle beam 6 is a group, and the left and right sides of both ends are rigidly connected to the upper ends of four needle beam cylinders 14 respectively, and are also slidably connected to the needle beam frame 5. The needle beam 6 is also provided with a needle beam traction mechanism 16 that drives the needle beam 6 and the needle beam frame 5 to slide relative to each other.
[0049] The supporting jacks 7 are 20 in number and are divided into two groups, one group on the left and one group on the right. One end of each jack is hinged to the side mold 2 and the other end is hinged to the needle beam frame 5.
[0050] The side beams 8 are divided into two groups, one on each side. The upper end of each group of side beams 8 is rigidly connected to a group of side molds 3, and is also rigidly connected to two longitudinal guide rails 9, two groups of annular guide rails 10 and the lower end of the needle beam frame 5.
[0051] There are two longitudinal guide rails 9 , which are rigidly connected to the front and rear inner planes of the two sets of side beams 8 and are also rigidly connected to the lower end of the needle beam frame 5 .
[0052] The circumferential guide rails 10 are divided into two groups, which are rigidly connected to the front and rear inner planes of the two groups of side beams 8, and are also rigidly connected to the lower end of the needle beam frame 5. Each group of circumferential guide rails 10 is also slidably connected to two circumferential rail trolleys 11 through guide rail limiting slide grooves. A chain guide wheel 18 is provided above and below the outer end of each group of circumferential guide rails 10, and a chain guide wheel 18 is provided below the inner end.
[0053] There are four circular rail trolleys 11, which are slidably connected to two groups of circular guide rails 10 through trolley rollers and limiting slide grooves of the circular guide rails 10, and each group of circular guide rails 10 is respectively connected to two circular rail trolleys 11. The circular rail trolleys 11 are divided into two groups according to the left and right sides of the tunnel section, with two trolleys in each group. Each group of circular rail trolleys 11 is also rigidly connected to a group of sliding templates 12. Two connecting bolts hinged to the traction chain 17 are provided in the middle of each circular rail trolley 11.
[0054] The sliding templates 12 are in two groups, which are rigidly connected to two groups of ring rail trolleys 11 respectively.
[0055] There are four ring rail trolley drive mechanisms 13, with two of them forming a group, one group on each side. The ring rail trolley drive mechanisms 13 are rigidly connected to corresponding positions of the needle beam frame 5, and each ring rail trolley drive mechanism 13 is provided with a driving sprocket, which is connected to a traction chain 17 through the driving sprocket. The rotating shaft of each group of ring rail trolley drive mechanisms 13 is also hinged through a transmission shaft.
[0056] There are four traction chains 17, each consisting of two chains, and each chain is connected to the driving sprocket of the ring rail trolley driving mechanism 13. The traction chains 17 pass around the chain guide wheels arranged on the ring rail 10 and the side wall connecting beam respectively, and the two ends are respectively hinged to the two connecting bolts of the ring rail trolley 11 to form a closed transmission chain.
[0057] There are four needle beam cylinders 14 , the upper ends of which are rigidly connected to the left and right sides of the front and rear ends of the needle beam 6 , and the lower ends of which are slidably connected to the two needle beam bases 15 at the front and rear ends of the needle beam 6 .
[0058] There are two needle beam bases 15, one for each of the front and rear ends of the needle beam 6. The upper part of each base is slidably connected to the bottom of the two needle beam cylinders 14, and the lower part of the base is placed on the ground.
[0059] A full-circle needle beam lining trolley includes the following steps:
[0060] A. First move the trolley to the required position of the tunnel and set up the mold;
[0061] B. Tunnel bottom concrete construction:
[0062] B1 starts the driving mechanism of the circular rail trolley, and the circular rail trolley moves and drives the sliding templates on both sides to move to the left and right sides along the circular guide rail to clear the bottom of the tunnel;
[0063] B2 Pour concrete into the tunnel bottom through the placing mechanism and vibrate the concrete according to the specification requirements;
[0064] B3 When the concrete is poured to the inner top surface of the tunnel bottom, the ring track trolley driving mechanism is started, the ring track trolley moves and drives the sliding template to move toward the middle along the ring guide rail, closing the bottom of the tunnel invert and scraping off the excess concrete;
[0065] B4 Pour concrete to the outside of the sliding formwork through the placing mechanism and vibrate the concrete according to the specification requirements;
[0066] B5 When the concrete fills the bottom of the sliding formwork, start the ring rail trolley driving mechanism, and the ring rail trolley drives the sliding formwork on both sides to move to the left and right along the ring rail, and continue to pour concrete to the outside of the sliding formwork through the material placing mechanism, and vibrate the concrete according to the specification requirements, and repeat this process until the sliding formwork is connected to the side beam;
[0067] B6 Pour concrete from the side form working window through the placing mechanism and vibrate the concrete according to the specifications to complete the entire bottom concrete pouring.
[0068] Concrete pouring on both sides and top:
[0069] C1 Wait for a while, and pour concrete on both sides of the tunnel through the side form working window after the bottom concrete has initially set;
[0070] C2 pours the tunnel top concrete through the top form working window and grouting port and completes the concrete pouring;
[0071] D. Wait for a while, and when the top concrete reaches the demoulding requirements, operate the trolley to remove the mold;
[0072] Repeat the above steps to carry out tunnel concrete lining construction.
Claims
1. A full-circle needle beam lining trolley, comprising a top mold (1), a side mold (2), a side mold (3), a needle beam frame (5) and a needle beam (6), characterized in that: It also includes side beams (8), longitudinal guide rails (9), annular guide rails (10), annular rail trolleys (11), a sliding template (12), and annular rail trolley driving mechanism (13); the needle beam frame (5) is rigidly connected to the side beams (8); there are two side beams (8); the upper plane of each side beam (8) is rigidly connected to the side template (3); the longitudinal guide rail (9) and the annular guide rail (10) are located between the two side beams (8) and are rigidly connected to the side beams (8); the annular guide rail (10) is slidably connected to the annular rail trolley (11); the annular rail trolley (11) is rigidly connected to the sliding template (12); the annular rail trolley driving mechanism (13) is rigidly connected to the needle beam frame (5) to drive the annular rail trolley (11) to move on the annular guide rail (10); a plugging plate is fixedly arranged on the outer side of the front longitudinal guide rail; during construction, the plugging plate and the sliding template form a concrete pouring space; the front half of the rear longitudinal guide rail is overlapped on the concrete of the tunnel bottom arch, and the rear half is suspended.
2. The full-circle needle beam lining trolley according to claim 1 is characterized in that: There are four circular rail trolleys (11), which are slidably connected to two groups of circular guide rails (10) via trolley rollers and limiting slide grooves on the circular guide rails (10), and each group of circular guide rails (10) is respectively connected to two circular rail trolleys (11). The circular rail trolleys (11) are divided into two groups according to the left and right sides of the tunnel section, with two trolleys in each group. Each group of circular rail trolleys (11) is rigidly connected to a group of sliding templates (12), and two connecting bolts hinged to the traction chain (17) are provided in the middle of each circular rail trolley (11).
3. The full-circle needle beam lining trolley according to claim 2 is characterized in that: The circular rail trolley driving mechanism (13) is linked to a traction chain (17), and the traction chain (17) passes around the circular guide rail (10), and both ends of the traction chain are respectively hinged to the circular rail trolley (11) to form a closed transmission chain.
4. The full-circle needle beam lining trolley according to claim 3 is characterized in that: The circular rail trolley driving mechanisms (13) are four in number, two in each group, one on each side. The circular rail trolley driving mechanisms (13) are rigidly connected to the needle beam frame (5), each circular rail trolley driving mechanism (13) is provided with a driving sprocket, which is connected to a traction chain (17) via the driving sprocket, and the rotary shaft of each group of circular rail trolley driving mechanisms (13) is hinged via a transmission shaft.
5. The full-circle needle beam lining trolley according to claim 4 is characterized in that: The traction chains (17) are four in number, two in a group, and each chain is connected to a driving sprocket of the ring rail trolley driving mechanism (13). The traction chains (17) respectively pass around the ring rail (10) and the chain guide wheels provided on the side wall connecting beam, and the two ends are respectively hinged to two connecting bolts of the ring rail trolley (11) to form a closed transmission chain.
6. The full-circle needle beam lining trolley according to claim 5, characterized in that: There are two longitudinal guide rails (9), which are respectively rigidly connected to the inner planes of the two sets of side beams (8) at the front and rear sides, and are also rigidly connected to the lower end of the needle beam frame (5); a chain guide wheel is respectively provided above and below the outer end of the circumferential guide rail (10), and a chain guide wheel is provided below the inner end.
7. The full-circle needle beam lining trolley according to claim 6, characterized in that: The top mold (1) is a group, and its two sides are respectively hinged to two groups of side molds (2), and its lower end is rigidly connected to the upper ends of 10 top mold oil cylinders (4), and the lower ends of the top mold oil cylinders (4) are rigidly connected to the needle beam frame (5); the side molds (2) are two groups, one group on the left and one group on the right are respectively hinged to the two sides of the top mold (1), and the middle part of each group of side molds (2) is hinged to one end of 10 supporting jacks (7); the side molds (3) are two groups, one group on the left and one group on the right are rigidly connected to the side beams (8) on both sides, and the upper part of each group of side molds (3) is also rigidly connected to the lower part of the needle beam frame (5).
8. The full-circle needle beam lining trolley according to claim 7, characterized in that: The needle beam frame (5) is a group, the upper part of which is rigidly connected to the lower ends of 10 top mold cylinders (4), and the lower part of which is rigidly connected to the side molds (3) and the side beams (8) on both sides. The needle beam frame (5) is also slidably connected to the needle beam (6); the needle beam (6) is a group, and the left and right sides of both ends are respectively rigidly connected to the upper ends of 4 needle beam cylinders (14). The needle beam (6) is also provided with a needle beam traction mechanism (16) for driving the needle beam (6) and the needle beam frame (5) to slide relative to each other.
9. The full-circle needle beam lining trolley according to claim 8, characterized in that: The upper end of the needle beam oil cylinder (14) is rigidly connected to the left and right sides of the front and rear ends of the needle beam (6), respectively, and the lower end is slidably connected to two needle beam bases (15) at the front and rear ends of the needle beam (6).
10. The construction method of a full-circle needle beam lining trolley according to claim 1, characterized in that: Including the following processes: A. First move the trolley to the required position of the tunnel and set up the mold; B. Tunnel bottom concrete construction: B1 starts the driving mechanism of the circular rail trolley, and the circular rail trolley moves and drives the sliding templates on both sides to move to the left and right sides along the circular guide rail to clear the bottom of the tunnel; B2 Pour concrete into the tunnel bottom through the placing mechanism and vibrate the concrete according to the specification requirements; B3 When the concrete is poured to the inner top surface of the tunnel bottom, the ring track trolley driving mechanism is started, the ring track trolley moves and drives the sliding template to move toward the middle along the ring guide rail, closing the bottom of the tunnel invert and scraping off the excess concrete; B4 Pour concrete to the outside of the sliding formwork through the placing mechanism and vibrate the concrete according to the specification requirements; B5 When the concrete fills the bottom of the sliding formwork, start the ring rail trolley driving mechanism, and the ring rail trolley drives the sliding formwork on both sides to move to the left and right along the ring rail, and continue to pour concrete to the outside of the sliding formwork through the material placing mechanism, and vibrate the concrete according to the specification requirements, and repeat this process until the sliding formwork is connected to the side beam; B6 Pour concrete from the side form working window through the placing mechanism and vibrate the concrete according to the specification requirements to complete the entire bottom concrete pouring; Concrete pouring on both sides and top: C1: After the bottom concrete has initially set, concrete is poured on both sides of the tunnel through the side form work window; C2 pours the tunnel top concrete through the top form working window and grouting port and completes the concrete pouring; D. When the top concrete reaches the demoulding requirements, the operator will remove the mold; Repeat the above steps to carry out tunnel concrete lining construction.