Design method for settlement control of high-speed railway subgrade engineering during insufficient observation period due to overload reinforcement

By proposing overload unloading timing and settlement standards in railway subgrade engineering, combined with foundation settlement calculations, the problem of inaccurate overload reinforcement design caused by insufficient preloading period has been solved, quantitative calculation and accurate design of overload reinforcement have been achieved, and the roadbed has been ensured Technical reliability and economy of the project.

CN114330028BActive Publication Date: 2024-10-22CHINA RAILWAY DESIGN GRP CO LTD
0 Cites 0 Cited by

Patent Information

Application Number
CN202210105133.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-01-28
Publication Date
2024-10-22
Estimated Expiration
2042-01-28

AI Technical Summary

Technical Problem

In railway subgrade engineering, insufficient preloading period leads to the lack of accurate methods for overload reinforcement design. The existing load proportion method calculation is not accurate enough to meet the settlement control requirements, and there is a lack of quantitative calculation support.

Method used

Propose overload unloading timing and unloading settlement standard recommended values. By combining the construction progress and foundation settlement calculation, the layered comprehensive method and Takagi Shunsuke method are used to calculate the settlement amount after the overload is unloaded to the equal load, and the overload preload height and bottom width are adjusted to Meet settlement control standards and achieve quantitative calculation and precise design of overload reinforcement.

Benefits of technology

The quantitative calculation and precise design of overload reinforcement are realized to ensure that the roadbed project can meet the on-schedule assessment and track laying requirements on the premise of being technically reliable and economically reasonable, and avoiding the construction delay problem caused by insufficient preloading period.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114330028B_ABST
    Figure CN114330028B_ABST
Patent Text Reader

Abstract

The present invention discloses a design method for settlement control of overload reinforcement during the insufficient observation period of a high-speed railway subgrade project, comprising the following steps: calculating the remaining preloading period and the equal-load observation period based on the current construction group, calculating the settlement of the equal-load observation period under equal-load conditions, determining the overload unloading settlement control standard, and calculating whether the settlement control of the overload preloading design meets the requirements. The technical solution disclosed in this patent is based on the concept that the current construction group calculates that the overload preloading must be unloaded to the equal-load preloading in advance, and further proposes the recommended values ​​of the overload unloading timing and unloading settlement standard, realizing the quantitative calculation and precise design of overload reinforcement, and on the premise of reliable technology and economic rationality, it guarantees to the greatest extent that the subgrade project meets the requirements of on-time assessment, unloading and track laying.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of foundation treatment in railway roadbed engineering, and in particular to a design method for secondary loading reinforcement of high-speed railway roadbed engineering when an observation period is insufficient. Background Art

[0002] In recent years, during the construction of high-speed railways, due to the constraints of land acquisition and demolition, approval or change of key and difficult projects of bridges, tunnels and stations, and transportation and erection of beams, the preloading or static period of roadbed projects is often insufficient. In order to ensure the construction period, it is often necessary to take further measures such as overload preloading and secondary reinforcement. In the case of insufficient preloading period after the roadbed filling is completed, overload preloading is often used to accelerate the foundation settlement in disguise to meet the requirements of post-construction settlement in the specification.

[0003] Some projects use the load ratio method to convert the predicted total settlement under overload conditions into the predicted total settlement under operation period load conditions, and artificially introduce weighted coefficients for further safety reserves. First, the load ratio method often uses the height ratio method for calculation. Factors such as different bottom widths and slopes on both sides cause the two to not match. Even if the load ratio is strictly followed, the additional stress of the base under different load forms is also different, resulting in the design load settlement converted by the load ratio method is still not accurate enough, and it is difficult to determine whether it is too large or too small. The artificially introduced safety reserve is also inconsistent with the concept and original intention of overload preloading.

[0004] Based on the above analysis, it is found that there is a lack of relevant theoretical support and mature design and calculation methods for overload reinforcement during the preloading period in the field of railway construction, and it is urgently needed to transform from the qualitative stage to the quantitative calculation direction. Summary of the invention

[0005] In order to overcome the deficiencies of the above-mentioned prior art, the purpose of the present invention is to provide a design method for settlement control of insufficient overload reinforcement during the observation period of high-speed railway roadbed engineering. Based on the concept that overload preload must be unloaded in advance to equal load preload, the timing of overload unloading and recommended values ​​of unloading settlement standards are further proposed, thereby realizing quantitative calculation and precise design of overload reinforcement.

[0006] To achieve the above object, the technical solution of the present invention is:

[0007] A design method for overloading reinforcement of high-speed railway roadbed engineering during observation period, comprising the following steps:

[0008] (1) Based on the current construction progress and organizational arrangements, the structural parameters and stratum parameters of the high-speed railway subgrade project are clarified, and the remaining preloading period T1 is determined. Based on the equal load observation period T2, the overload preloading period T3 = T1-T2 is further calculated;

[0009] (2) Based on the layered comprehensive method and Takagi Shunsuke method in foundation settlement calculation, the high-speed railway subgrade structural parameters and stratum parameters are substituted to calculate the total foundation settlement △H1 under the equal load condition in the remaining preloading period T1, the post-construction settlement △H2, and the foundation settlement △H3 corresponding to the equal load observation period T2 under the same equal load condition;

[0010] (3) Based on the assumption that the unloading deformation still satisfies the consolidation law, the settlement △H4 of the foundation in T2 after unloading from overload to equal load to equal load unloading is calculated;

[0011] (4) Given the initial overload preloading height H1 and bottom width B1, calculate the foundation settlement control standard when unloading to equal load under overload condition: △H1-△H4-△H0, where △H0 is the post-construction settlement control standard required by the specification;

[0012] (5) Calculate the foundation settlement △H5 under the overload condition during the overload preloading period T3, and use △H5 ≥ △H1-△H4-△H0 as the settlement control standard to determine whether the conditions for completing the overload reinforcement design are met. If so, end the design; if not, redesign the overload preloading height H1 and bottom width B1, and return to step (3) for calculation;

[0013] Furthermore, in the step (3), the settlement ΔH4 generated by the foundation during the equal load observation period T2 from overload unloading to equal load unloading is obtained by the following method:

[0014] Method 1:

[0015] Based on the assumption that unloading deformation still satisfies the consolidation law, △H4=(U1-U3)×△H6+U2×U3×(△H6-△H1),

[0016] Among them, the total settlement of the foundation under overload conditions is △H6, the foundation consolidation degree on the overload unloading day is U3, the foundation consolidation degree on the preloading deadline day is U1, and the consolidation degree during the equal load observation period T2 is U2;

[0017] Or, method 2:

[0018] Based on engineering experience and overload conditions, △H4=η×△H3, where η is the engineering experience coefficient.

[0019] Furthermore, the engineering experience coefficient η can be combined with previous engineering experience and overload conditions, and can generally be taken as 0.3-0.6.

[0020] Furthermore, the equal load observation period T2 is 1-2 months.

[0021] Furthermore, in step (1), the structural parameters and stratum parameters of the high-speed railway subgrade engineering include:

[0022] Structural parameters: roadbed width, fill height, pile diameter, pile spacing, pile length, and pile depth of each sub-area of ​​foundation reinforcement;

[0023] Stratigraphic parameters: stratigraphic stratification type, layer thickness, density, compression modulus, consolidation coefficient, and bearing capacity.

[0024] According to the above technical scheme, the beneficial effects that can be achieved by the present invention are: based on the concept that overload preloading must be unloaded in advance to equal load preloading, the timing of overload unloading and recommended values ​​of unloading settlement standards are further proposed, and the quantitative calculation and precise design of overload reinforcement are realized. Under the premise of reliable technology and economic rationality, the roadbed project is guaranteed to meet the requirements of scheduled assessment, unloading and track laying to the greatest extent. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 . Schematic diagram of the flow chart of the design method of the present invention.

[0026] Figure 2 . Calculation diagram of the design method of the present invention.

[0027] Figure 3 .DK28+250 design drawing of a typical section of an embodiment of the present invention.

[0028] Figure 4 .Longitudinal settlement distribution curve of an embodiment of the present invention.

[0029] Figure 5 . Typical cross-section settlement development and fitting curve of the embodiment of the present invention.

[0030] Figure 6 .The embodiment of the present invention predicts the longitudinal settlement curve after construction twice. DETAILED DESCRIPTION

[0031] The present invention will be further described below in conjunction with the accompanying drawings.

[0032] like Figure 1 and Figure 2 As shown, a design method for controlling the settlement of insufficient overload reinforcement during the observation period of a high-speed railway subgrade project includes the following steps:

[0033] (1) Based on the current construction progress and organizational arrangements, the remaining preloading period T1 of the high-speed railway subgrade project is clarified, and based on the equal load observation period T2, the overload preloading period T3 = T1-T2 is further calculated.

[0034] (2) Based on the layered comprehensive method and Takagi Shunsuke method in foundation settlement calculation, the high-speed railway subgrade structural parameters and stratum parameters are substituted to calculate the total foundation settlement △H1 under the equal load condition within the remaining preloading period T1, the post-construction settlement △H2, and the foundation settlement △H3 corresponding to the equal load observation period T2 under the consistent equal load condition.

[0035] (3) Based on the assumption that the unloading deformation still satisfies the consolidation law, the settlement of the foundation in T2 from overload unloading to equal load to equal load unloading is calculated as △H4 = (U1-U3)×△H6+U2×U3×(△H6-△H1), where the consolidation degrees of the foundation on the overload unloading day and the preloading deadline day are U3 and U1, respectively. The consolidation start time is calculated from the unloading. The consolidation degree during the equal load observation period T2 is assumed to be U2, and the total settlement of the foundation under overload conditions is △H6.

[0036] (4) Given the initial overload preloading height H1 and bottom width B1, the foundation settlement control standard when unloading to equal load under overload condition is calculated according to the layered comprehensive method and Takagi Shunsuke method in foundation settlement calculation: △H1-△H4-△H0, where △H0 is the post-construction settlement control standard required by the specification.

[0037] (5) Based on the layered comprehensive method and Takagi Shunsuke method in foundation settlement calculation, the high-speed railway subgrade structural parameters and stratum parameters are substituted to calculate the foundation settlement △H5 under the overload condition within the overload preloading period T3. If △H5 ≥ △H1-△H4-15, the overload reinforcement design is completed. Otherwise, H1 and bottom width B1 are further adjusted to meet the settlement control standard of △H5 ≥ △H1-△H4-15.

[0038] The equal load observation period T2 is generally between 1 and 2 months. This is mainly because if the load is unloaded too early, the overload duration will be too short and the effect of accelerated settlement will be weakened. If the load is unloaded close to the evaluation period, the accuracy of the post-construction settlement evaluation will be affected.

[0039] The settlement △H4 during the equal load observation period after overload unloading can also be approximately determined by combining previous engineering experience and overload conditions, △H4=η×△H3, and η ranges from 0.3 to 0.6.

[0040] The following is a detailed introduction to the application and verification of the above technical solution in solving the problem of insufficient preloading period at Dongguan Station of a railway project.

[0041] (1) Geological Overview

[0042] The Dongguan Station site is located in the coastal plain area, with flat and open terrain. The surface water system is well developed, with rivers and canals crisscrossing and interweaving like a network. The strata from top to bottom are mainly: fill soil, silty clay, clay and clay, round gravel soil, and underlying tuff. The water level is buried at a depth of about 0 to 2 meters, mainly receiving atmospheric precipitation recharge. Affected by seasonal changes, the groundwater level fluctuates between 0.2 and 2 meters.

[0043] (2) Design Overview

[0044] The area around the Dongguan Station platform area has two platforms and six lines, such as Figure 3As shown, the roadbed width is about 58m, and the station fill height is about H = 4.5m. The foundation (dashed line part) is treated with a pile-slab structure of pipe piles + raft slabs. The pipe piles are made of C80 reinforced concrete, with a pile diameter of Φ = 0.5m and a pile spacing of 2.5m. The main reinforcement area (four lines in the station, the middle dashed line part) has a pile length of L = 30-34m, and the secondary reinforcement area (platform and outer departure line, the dashed lines on both sides) has a pile length of L = 18m. The pile body of the main reinforcement area penetrates 3-9m of silty clay, upper clay and clay, fine round gravel soil layer, and 10-14m of clay lies underneath. The original design uses pile preloading to accelerate the settlement of the roadbed, with a pile height of 3m, a top width of 16m, and a bottom width of 22m.

[0045] Referring to the test data of the most unfavorable section drilling DZ-0495-1, the formation parameters are shown in Table 1 below.

[0046] Table 1 Main parameters of the formation

[0047]

[0048] (3) Reinforcement calculation

[0049] Considering that the crack control and foundation bearing capacity of the pile top raft under normal use must meet the requirements of the specification, it is deduced from Article 16.2.3 of the "Technical Code for Foundation Treatment of Railway Engineering" (TB 10106-2010) that the fill height above the raft in the primary and secondary reinforcement areas should not exceed 10 and 8m respectively. In the initial trial calculation, considering the phenomenon that the closer to the center of the main line ballastless track, the better the settlement acceleration effect, the primary reinforcement area loading parameters are adjusted first in the initial trial calculation. When the primary reinforcement area loading parameters are fully adjusted, the bottom width (B1) is adjusted to 22m, and the loading height (initial overload preloading height H1) is adjusted to 5.5m, the post-construction settlement still does not meet the settlement control requirements of △H5 ≥ △H1-△H4-15. When the secondary reinforcement area loading parameters are further adjusted to a bottom width of 11m and a loading of 2.5m, the calculation results are shown in Table 2.

[0050] Table 2 Overload reinforcement calculation of Dongguan Station

[0051]

[0052] Taking the last adjustment of the initial overload preload height H1 and bottom width B1 as an example, the calculation steps are described in detail as follows:

[0053] 1. Calculate the overload preload period T3

[0054] According to the current construction organization arrangement, the remaining preloading period of this section is T 1=4.7 months. According to the D.0.2 item of the Railway Engineering Foundation Treatment Technical Code (TB 10106-2010), the pile-slab structure adopts the railway bridge code method to calculate the foundation settlement. The total foundation settlement is △H1=52.2mm, the pre-construction settlement is 27.4mm, and the pre-construction settlement accounts for 52.5%. The post-construction settlement is △H2=24.8mm, which cannot meet the relevant requirements of the code. Overload reinforcement treatment is required. The overload is unloaded to equal load T2=1 month in advance. Based on the equal load observation period T2, the overload preloading period T3=T1-T2=3.7 months is further calculated.

[0055] 2. According to the layered comprehensive method and Takagi Shunsuke method in foundation settlement calculation, the various parameters confirmed in the design overview of the Dongguan Station site are substituted for calculation to obtain the total foundation settlement △H1 under the equal load condition in the remaining preloading period T1, the post-construction settlement △H2, the total foundation settlement △H6 under overload conditions, the foundation consolidation degree U3 on the overload unloading day, the foundation consolidation degree U1 on the preloading deadline day, the consolidation degree U2 in the equal load observation period T2, and the foundation settlement △H3 corresponding to the equal load observation period T2 under the condition of constant load. The calculation results are as follows:

[0056] The total settlement of the foundation under equal load is △H1=52.2mm, the settlement after construction is △H2=24.8mm, the total settlement of the foundation under overload condition is △H6=73.8mm, the settlement after preloading under overload condition is △H7=37.1mm, the foundation consolidation degree on the overload unloading day is U3=0.61, the foundation consolidation degree on the preloading deadline is U1=0.74, the consolidation degree within T2 is U2=0.68, and the foundation settlement within the equal load observation period T2 is △H3=(U1-U3)×△H1=6.79mm.

[0057] 3. Calculate the settlement △H4 of the foundation during the period from overload unloading to equal load unloading (T2)

[0058] △H4=(U1-U3)×△H6+U2×U3×(△H6-△H1)=1.3mm.

[0059] 4. Substitute the designed surcharge preloading height of 5.5m and bottom width of 22m in the main reinforcement area, the surcharge preloading height of 2.5m and bottom width of 22m in the secondary reinforcement area, and the various parameters confirmed in the design overview of the Dongguan Station site mentioned above into the layered comprehensive method and Takagi Shunsuke method in the foundation settlement calculation to obtain △H1-△H4-△H 0= 36.5mm.

[0060] 5. According to the calculation parameters of step (4), based on the layered comprehensive method and Takagi Shunsuke method in foundation settlement calculation, calculate the foundation settlement △H5=38.4mm under the overload condition during the overload preloading period T3.

[0061] It can be seen that △H5=38.4mm, △H1-△H4-△H 0= 36.5mm, △H5>△H1-△H4-△H0, which meets the requirements and completes the overload reinforcement design.

[0062] (4) On-site implementation and verification

[0063] The overload reinforcement measures were issued to the construction unit for internal confidential implementation after confidentiality verification by internal experts. During the preloading process, the reinforcement work point was calculated to be unloaded to the equal load condition one month in advance as scheduled. The settlement during unloading was calculated to be 38.4mm, and the settlement plate data was 8.1-27.1mm. Considering the influence of stratum differences and construction disturbances, it is normal that there is a certain discrepancy between the theoretical settlement calculation and the actual value. If the settlement development trend does not show abnormal conditions such as acceleration or inflection points, it can be unloaded to the equal load normally according to the design requirements. The unloading time of the equal load preloading can be determined through the final settlement development trend and evaluation.

[0064] like Figure 4 As shown in the longitudinal settlement distribution curve of Dongguan Station, during the preliminary settlement assessment on March 18, 2021, the settlement change values ​​of each section were between 8.0-27.8mm. Affected by the delay in the passenger tunnel and construction, there was a certain lag in the installation of the surrounding settlement observation equipment, resulting in a small settlement value observed in the surrounding area. During the formal settlement assessment on June 27, 2021, the settlement of each section further developed by 0.1-1.9mm, and the settlement change value was between 9.9-29.1mm.

[0065] like Figure 5 This is a typical cross-section settlement development and fitting curve. The settlement development rate during the roadbed filling and preload soil filling period is 0.2-0.3mm / d. The settlement rate gradually slows down about one month after the filling is completed. By June 27, the settlement trend has converged, indicating that its settlement has become stable. Curve fitting regression analysis and prediction are used to meet the relevant requirements of industry specifications.

[0066] Figure 6 As shown in the two predicted longitudinal settlement curves after construction, during the preliminary settlement assessment on March 18, 2021, the predicted settlement after construction was 2.7-8.3mm, and during the formal settlement assessment on June 27, 2021, the predicted settlement after construction was 3.5-8.7mm. Due to the interference of the construction process and the limitations of the curve fitting method, there were certain deviations in the two predicted settlements after construction, but the overall difference was within 5mm, which met the requirements of relevant specifications.

[0067] The overload reinforcement work site successfully passed the settlement pre-assessment and formal assessment. There was no delay in the construction period due to insufficient preloading period. All overload reinforcement work sites successfully passed the settlement pre-assessment and formal assessment, which fully proved that the technical solution disclosed in this patent realizes the quantitative calculation and precise design of overload reinforcement. Under the premise of reliable technology and economic rationality, it maximizes the guarantee that the roadbed project meets the requirements of scheduled assessment, unloading and track laying.

Claims

1. A design method for controlling the settlement of high-speed railway subgrade engineering during insufficient overload reinforcement during the observation period, comprising the following steps: (1) Based on the current construction progress and organizational arrangements, the structural parameters and stratum parameters of the high-speed railway subgrade project are clarified, and the remaining preloading period T1 is determined. Based on the equal load observation period T2, the overload preloading period T3 = T1-T2 is further calculated; (2) Based on the layered comprehensive method and Takagi Shunsuke method in foundation settlement calculation, the high-speed railway subgrade structural parameters and stratum parameters are substituted to calculate the total foundation settlement △H1 under the equal load condition in the remaining preloading period T1, the post-construction settlement △H2, and the foundation settlement △H3 corresponding to the equal load observation period T2 under the same equal load condition; (3) Based on the assumption that the unloading deformation still satisfies the consolidation law, the settlement △H4 of the foundation in T2 after unloading from overload to equal load to equal load unloading is calculated; (4) Given the initial overload preloading height H1 and bottom width B1, calculate the foundation settlement control standard when unloading to equal load under overload condition: △H1-△H4-△H0, where △H0 is the post-construction settlement control standard required by the specification; (5) Calculate the foundation settlement △H5 under the overload condition during the overload preloading period T3, and use △H5 ≥ △H1-△H4-△H0 as the settlement control standard to determine whether the conditions for completing the overload reinforcement design are met. If so, end the design. If not, redesign the overload preloading height H1 and bottom width B1, and return to step (3) for calculation.

2. The design method for controlling the insufficient overload reinforcement settlement of high-speed railway subgrade engineering during the observation period according to claim 1 is characterized in that: In the step (3), the settlement ΔH4 generated by the foundation during the equal load observation period T2 from overload unloading to equal load unloading is obtained by the following method: Method 1: Based on the assumption that unloading deformation still satisfies the consolidation law, △H4=(U1-U3)×△H6+U2×U3×(△H6-△H1), Among them, the total settlement of the foundation under overload conditions is △H6, the foundation consolidation degree on the overload unloading day is U3, the foundation consolidation degree on the preloading deadline day is U1, and the consolidation degree during the equal load observation period T2 is U2; Or, method 2: Based on engineering experience and overload conditions, △H4=η×△H3, Among them, η is the engineering experience coefficient. Combined with previous engineering experience and overload conditions, η is taken between 0.3-0.

6.

3. The method for controlling the settlement of insufficient and overload reinforcement during the observation period of high-speed railway subgrade engineering according to claim 1 is characterized in that: The equal load observation period T2 is 1-2 months.

4. The method for controlling the settlement of insufficient and overload reinforcement during the observation period of high-speed railway subgrade engineering according to claim 1 is characterized in that: In step (1), the structural parameters and stratum parameters of the high-speed railway subgrade project include: Structural parameters: roadbed width, fill height, pile diameter, pile spacing, pile length, and pile depth of each sub-area of ​​foundation reinforcement; Stratigraphic parameters: stratigraphic stratification type, layer thickness, density, compression modulus, consolidation coefficient, and bearing capacity.