A method for improving the extraction and irrigation efficiency of hydrothermal geothermal well groups

By optimizing the layout of geothermal wells, conducting core tests, studying the blockage mechanism, and adjusting the spacing between well groups, combined with a nitrogen monitoring system, the problem of improper layout of production and injection wells in the development of hydrothermal geothermal wells has been solved, thereby improving reinjection efficiency and the sustainable utilization of geothermal resources.

CN114575836BActive Publication Date: 2024-11-22SHAANXI COALFIELD GEOLOGICAL EXPLORATION RES INST CO LTD
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202210103485.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-01-27
Publication Date
2024-11-22
Estimated Expiration
2042-01-27

AI Technical Summary

Technical Problem

In the development and utilization of hydrothermal geothermal wells, there are problems such as difficulty in reinjection and thermal breakthrough caused by improper layout of extraction and injection wells, which affect the reinjection effect and the sustainable utilization of geothermal resources.

Method used

By analyzing geological characteristics and groundwater dynamics, the layout of geothermal wells was optimized, core testing and blockage mechanism research were conducted, multi-stage filtration and pressurized venting processes were used to treat geothermal water, the spacing between well groups was adjusted, magnetic nanoparticle tracers were used for tracer experiments, and numerical simulation was combined to optimize the layout of the well group. A nitrogen monitoring system was also installed in the wellhead device to prevent oxidation and corrosion.

Benefits of technology

It has improved the extraction and irrigation efficiency of hydrothermal geothermal well groups, realized the sustainable utilization of geothermal resources and the protection of equipment, and extended the service life of geothermal fields.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114575836B_ABST
    Figure CN114575836B_ABST
Patent Text Reader

Abstract

The present invention relates to the field of geothermal utilization, and discloses a method for improving the extraction and injection efficiency of a hydrothermal geothermal well group. According to the existing data such as the geophysical prospecting data of the region, the geothermal well position is determined, and the wells are arranged equidistantly according to concentric circles; the core is used for data analysis of lithology, porosity, permeability, density, thermal conductivity, etc. during drilling construction; after completion of the well, in-situ tests such as pumping tests are carried out; the blocking mechanism of geothermal water is studied through water quality analysis, and corresponding anti-blocking and unblocking measures are made to optimize the injection process; finally, the reasonable spacing of the well group is verified by empirical formulas based on tracer test research and numerical simulation, and the layout of the well group extraction and injection wells is adjusted accordingly. The present invention takes geothermal fields as the research object, optimizes the layout of hydrothermal geothermal extraction and injection wells, ensures the comprehensive and efficient utilization of high-grade geothermal resources, realizes the sustainable utilization of hydrothermal geothermal resources, and extends the service life of geothermal fields.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of geothermal utilization, and in particular to a method for improving the extraction and irrigation efficiency of a hydrothermal geothermal well group. Background Art

[0002] Geothermal resources are a green energy with huge reserves and sustainable utilization. With the continuous expansion of geothermal resource development across the country, especially for heating, the amount of geothermal water extraction has increased rapidly. The hydrothermal geothermal system must recharge the utilized geothermal tail water to the mining layer to replenish the thermal storage water source and ensure the balance of thermal storage pressure. Geothermal recharge is the most direct and effective means to achieve sustainable exploitation and utilization of medium and deep geothermal resources.

[0003] The main problems of the reinjection of medium-deep geothermal reservoirs are blockage during the reinjection process, connectivity between production and injection wells, reasonable well spacing of the production and injection system, control of reinjection water temperature, reinjection volume and reinjection rate that are both economical and can ensure water level recovery. These problems have always been the focus and difficulty of research at home and abroad. The scale mineral components in geothermal raw water and reinjection water include quartz fragments, feldspar, siliceous rock fragments, and carbonate rock fragments. The original components of the formation are transported out with mining and utilization. In the reinjection process of medium-deep geothermal tail water, the physical blockage, chemical blockage, biological blockage, gas blockage and composite blockage in the reinjection process have the greatest impact on the reinjection effect. Geothermal reinjection is related to heat reservoir pressure, water quality, spacing between production and injection wells, well structure, heat reservoir lithology, reinjection methods and reinjection methods.

[0004] Therefore, it is necessary to establish a technical support system covering the analysis of heat reservoir characteristics, spacing and layout of production and injection wells, analysis of the causes of formation blockage and solutions, and research on injection technology, so as to improve the production and injection efficiency of hydrothermal geothermal well groups and ensure the virtuous cycle and sustainable development of geothermal development. Summary of the invention

[0005] The purpose of the present invention is to propose a method for steadily improving the production and injection efficiency of a hydrothermal geothermal well group, so as to overcome the problems of difficult re-injection and thermal breakthrough caused by improper layout of production and injection wells during the development and utilization of hydrothermal geothermal wells.

[0006] In order to achieve the above object, the technical solution adopted by the present invention is:

[0007] A method for improving the extraction and irrigation efficiency of a hydrothermal geothermal well group comprises the following steps:

[0008] Step 100, based on the regional geophysical data, well logging data of completed wells, well completion data, observation data and previous reinjection data, the basic geological characteristics and groundwater dynamic characteristics of the region are analyzed to determine the location of geothermal wells, and the wells are arranged equidistantly according to concentric circles;

[0009] Step 200, during the drilling construction, ensure that the core is taken to conduct tests and analyses on lithology characteristics, porosity, permeability, density, thermal conductivity, etc.;

[0010] Step 300, after the well is completed, in-situ tests such as drilling logging and pumping test are carried out, and a comprehensive analysis of the water quality of the completed well is performed;

[0011] Step 400, a displacement test is conducted to carry out a single well reinjection system test of geothermal water, to study the blockage mechanism, and to make corresponding anti-blockage and unblocking measures, optimize the injection process, and improve the single well reinjection efficiency;

[0012] Step 500, verifying the reasonable spacing of the well group through empirical formulas based on tracer test research and numerical simulation, and adjusting the layout of the well group production and injection wells accordingly.

[0013] Furthermore, in step 200, 1 to 3 groups of cores are collected from each thermal reservoir in the heat extraction section of the exploration and production combined hole.

[0014] Preferably, in the reinjection system test in step 400, geothermal raw water is extracted from a geothermal well, and reinjected into a selected reinjection well after being processed in sequence through oil and sand removal, exhaust, heat application, multi-stage filtration, pressurization, exhaust and acidification and injection.

[0015] Preferably, the sediment blockage, suspended matter blockage and gas blockage in geothermal water are respectively prevented and resolved by means of scale inhibitors, multi-stage filtration and multi-stage exhaust; for microbial blockage, the tail water is sterilized without affecting the geothermal water quality.

[0016] Preferably, the tracer selected for the tracer test in step 500 is magnetic nanoparticles.

[0017] Preferably, the production and injection wells of the geothermal well group are evenly arranged on concentric circles. In the early stage of geothermal field development and utilization, the development boundary and scope are delineated, and the first layer of concentric circles for the geothermal well layout is set. Even geothermal well positions are set on the boundaries of the circles. As the degree of development and utilization increases, the optimized geothermal well spacing is adjusted according to geothermal simulation data and operation results, and the radius of the concentric circles is adjusted layer by layer to adjust the geothermal production and injection well spacing.

[0018] Preferably, the wellhead device of each geothermal well in the geothermal well group adopts a multifunctional wellhead device, which is provided with a water supply pipe and a reinjection pipe, and both the water supply pipe and the reinjection pipe are provided with regulating valves.

[0019] Preferably, the geothermal wellhead is provided with a nitrogen monitoring and nitrogen filling closed system, including a buffer tank and a nitrogen tank. The wellhead device of the geothermal well is connected to the buffer tank, and the buffer tank is connected to the nitrogen tank. An inflation valve is provided on the connecting pipe between the wellhead device and the buffer tank, a nitrogen deflation valve is provided on the connecting pipe between the buffer tank and the nitrogen tank, and a pressure display screen is provided on the buffer tank.

[0020] Preferably, during the shutdown and maintenance of the geothermal well, the geothermal wellhead should be closed in time and the system should be sealed.

[0021] Furthermore, the pressure in the pipeline system is ensured to be a positive pressure of 0.01-0.03Mpa.

[0022] Compared with the prior art, the method for improving the extraction and irrigation efficiency of a hydrothermal geothermal well group of the present invention takes geothermal fields as the research object, arranges geothermal extraction and irrigation wells in small concentric circles as test research objects in the early stage, scientifically and gradually carries out geothermal energy development and utilization, optimizes the layout of hydrothermal geothermal extraction and irrigation wells, adjusts the radius of the concentric circles to achieve a more scientific spacing between extraction and irrigation wells, ensures the comprehensive and efficient utilization of high-grade geothermal resources, realizes the sustainable utilization of hydrothermal geothermal resources, and extends the service life of geothermal fields. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Other features, objects and advantages of the present invention will become more apparent from the detailed description of non-limiting embodiments made with reference to the following drawings:

[0024] Figure 1 A flow chart of a method for improving the reinjection efficiency of a hydrothermal geothermal well group;

[0025] Figure 2 This is a schematic diagram of the well layout for the geothermal well group;

[0026] Figure 3 Schematic diagram of nitrogen monitoring and nitrogen filling at the geothermal wellhead;

[0027] Figure 4 This is a flow chart of the hydrothermal geothermal utilization and treatment process system.

[0028] Figure 2 Middle label number: A-1, A-2, A-3 geothermal wells are evenly arranged in concentric circles with a radius of ra, and the distance between wells is L1; B-1, B-2, B-3 geothermal wells are evenly arranged in concentric circles with a radius of rb, and the distance between them and the geothermal wells in concentric circle A is L2; ​​C-1, C-2, C-3, C-4, C-5, C-6 geothermal wells are evenly arranged in concentric circles with a radius of rc, and the distance between them and the geothermal wells in concentric circle B is L3.

[0029] Figure 3 Winning bid number: 1-geothermal well; 2-wellhead device; 3-geothermal production pipe; 4-geothermal reinjection pipe; 5-production well valve; 6-reinjection well valve; 7-pressure gauge; 8-thermometer; 9-monitoring pressure gauge; 10-nitrogen tank; 11-buffer tank; 12-nitrogen release valve; 13-inflating valve; 14-pressure display screen.

[0030] Figure 4Winning bid number: 401-production / reinjection well; 402-hydraulic desander; 403-degassing of closed water storage tank; 404-thermal energy application; 405-multi-stage filtration; 406-pressurization and exhaust; 407-acidification and injection; 408-reinjection / production well. DETAILED DESCRIPTION

[0031] The present invention is described in detail below in conjunction with specific embodiments. The following embodiments will help those skilled in the art to further understand the present invention, but are not intended to limit the present invention in any form. It should be noted that, for those of ordinary skill in the art, several variations and improvements may be made without departing from the concept of the present invention. These all belong to the protection scope of the present invention.

[0032] refer to Figure 1 A method for improving the extraction and irrigation efficiency of a hydrothermal geothermal well group comprises the following steps:

[0033] Step 100, based on the geophysical data, well logging data, well data, observation data and previous reinjection data of the region, the regional geological structure, fault distribution and reservoir characteristics of the geothermal field thermal reservoir area are studied to obtain the basic geological characteristics and groundwater dynamic characteristics of the region. The geothermal well locations are determined and arranged equidistantly according to concentric circles; the wellhead device of each geothermal well in the geothermal well group adopts a multifunctional wellhead device, which is equipped with a water supply pipe and a reinjection pipe, and both the water supply pipe and the reinjection pipe are equipped with regulating valves;

[0034] Step 200, during the drilling construction, ensure that cores are taken, and test and analyze the lithology, porosity, permeability, density, thermal conductivity, etc. to obtain the consolidation state, cementation degree, permeability, porosity, pore throat characteristics, and physical parameters of the thermal reservoir rock. By taking core tests to analyze the looseness of the thermal reservoir formation, whether fracturing construction can be carried out, or appropriate unblocking; further, in the step 200, 1 to 3 groups of cores are taken from each thermal reservoir in the heat extraction section of the exploration and production combined hole, and the location, quantity, and quality of the cores should meet the requirements of the later laboratory measurement parameters and thermal reservoir evaluation;

[0035] Step 300, after the well is completed, in-situ tests such as drilling logging and pumping test are carried out, and the water quality of the completed well is fully analyzed; in the pumping test, the influence of the temperature field is fully considered, and the well with large water yield per unit drawdown is selected as the recharging well in combination with the hydraulic gradient;

[0036] Step 400, the displacement test is used to study the blockage mechanism of geothermal water, and corresponding anti-blockage and unblocking measures are made, the injection process is optimized, and the single well reinjection efficiency is improved. The mineral composition of the precipitate is analyzed by electron microscope to determine the mineral composition of the precipitate; the blockage effect is determined through indoor experiments under different blockage types, and technical measures for unblocking and preventing blockage are formulated; through analysis and indoor experiments, a set of acid formulas suitable for injection is developed; through software simulation, the circulation heat exchange under different well spacing conditions and different reinjection time conditions is simulated, and the heat exchange effect is obtained;

[0037] Step 500, based on the tracer test research and numerical simulation, the empirical formula of the reasonable spacing of the well group is verified and the layout of the well group production and injection wells is adjusted accordingly. The tracer selected in this embodiment is magnetic nanoparticles. The magnetic nanoparticle surface modification technology and high temperature and high pressure thermal stability analysis are used to complete the selection and configuration of the magnetic nanotracer. The magnetic nanoparticle tracer has good thermal stability and low pressure stabilization sensitivity. It can reflect the migration speed of water, help to determine the wells with close hydraulic connection, and avoid thermal breakthrough during use. The optimal well spacing between the production well and the reinjection well is determined by numerical calculation, well spacing simulation, tracer test, and combined with empirical formula verification.

[0038] In step 500, the empirical formula is referenced from: Luo Tianyu. Research on water injection capacity of thermal recovery reinjection wells [J]. China and Foreign Energy, 2019, 24(06): 21-25. In the case of ring-mounted wells, assuming that there are n wells distributed in a ring shape with a radius of R (m), then:

[0039]

[0040] Determine the reservoir thickness h, permeability k, μ = 1 × 10 -3 Pa·s, s=0、r w =0.1m, re, formation pressure p e , the production pressure difference of the production well is, and the bottom hole pressure of the injection well is p w , production well bottom hole pressure p w Here, the injection volume Q of the injection well is equal to the production volume of the production well, and R can be obtained by deduction and calculation.

[0041] In addition, in the early stage of the project, the groundwater flow numerical simulation software Feflow can be used to solve the water-heat coupling model of the geothermal production and injection well system, as well as to realize the OpenGeoSys (OGS) model for optimizing the production and injection well spacing during the development of medium and deep geothermal energy, scaling simulation in high-temperature thermal field production wells and reinjection wells, and deep well heat exchange simulation verification.

[0042] refer to Figure 2In the early stage of development and utilization of geothermal fields, the development boundary and scope are delineated, and the first concentric circle of the geothermal well layout is set. The geothermal well positions are evenly arranged on the boundary of the circle. In this embodiment, geothermal production and injection wells A-1, A-2, and A-3 are arranged on a small concentric circle A with a radius of ra as test research objects, and the distance between wells is L1. As the degree of development and utilization increases, the optimized distance between geothermal wells is adjusted according to geothermal simulation data and operation results, and the radius of the concentric circle is adjusted layer by layer to adjust the distance between geothermal production and injection wells. In the medium term, B-1, B-2, and B-3 geothermal wells are evenly arranged in concentric circle B with a radius of rb, and the distance between them and the geothermal wells in concentric circle A is L2. In the later stage, C-1, C-2, C-3, C-4, C-5, and C-6 geothermal wells are arranged in concentric circle C with a radius of rc, and the distance between them and the geothermal wells in concentric circle B is L3. Scientifically and gradually develop geothermal energy and optimize the layout of hydrothermal geothermal production and injection wells, and adjust the radius of concentric circles to achieve a more scientific spacing between production and injection wells.

[0043] refer to Figure 3 , a method for improving the extraction and injection efficiency of a hydrothermal geothermal well group also includes a geothermal extraction and injection wellhead nitrogen monitoring and nitrogen filling closed system for ensuring that the well pipe above the liquid level of the geothermal well is filled with nitrogen to protect the geothermal well pump and the suspended well pipe from being corroded by oxygen in the air. The wellhead device 2 on the geothermal well 1 is generally not completely airtight. During the shutdown and maintenance of the geothermal well, after the production well valve 5 on the geothermal production pipe 3 and the reinjection well valve 6 on the geothermal reinjection pipe 4 are closed, the pressure gauge 7 and the thermometer 8 cannot display the downhole parameters. It is necessary to monitor the well pipe above the liquid level in the geothermal well with a monitoring pressure gauge 9 on site; the geothermal well wellhead device 2 is connected to a buffer tank 11, the buffer tank 11 is connected to a nitrogen tank 10, and the nitrogen tank 10 and the buffer tank 11 form a nitrogen protection device, and an air charging valve 13 is provided on the connecting pipe between the wellhead device 2 and the buffer tank 11, and a nitrogen deflation valve 12 is provided on the connecting pipe between the buffer tank 11 and the nitrogen tank 10, and a pressure display screen 14 is provided on the buffer tank. During the maintenance period of the geothermal well, the pressure monitoring device ensures that the pressure in the pipeline system is a positive pressure of 0.01-0.03Mpa.

[0044] refer to Figure 4, a method for improving the extraction and injection efficiency of a hydrothermal geothermal well group also includes a geothermal utilization and treatment process system. Comprehensively analyzing the design ideas, according to the reinjection conditions of different geological characteristics and water quality characteristics, a hydrothermal geothermal utilization and treatment process system process is adopted, including extracting geothermal raw water from a geothermal production well 401, passing through a hydraulic desander 402, a closed water storage degassing 403, and then applying heat energy 404. The geothermal tail water after use is then passed through multi-stage filtration 405, pressurization, exhaust 406, acidification and injection 407, and then enters the reinjection well 408. When the overflow flow of the production well is not enough to meet the production requirements, a submersible pump is required to be set up as a power output supply flow system. A submersible pump is also required to be set up in the reinjection well as a return power source. The extracted geothermal water is processed through hydraulic desanding, gas-water separation, cascade utilization system and physical filtration, and then all is reinjected into the corresponding reinjection well in the same layer. The pressurization and exhaust system are added to improve the single well reinjection efficiency. Before the application of thermal energy, closed water storage and degassing are used to separate gas and water to ensure the safety of subsequent projects. Multi-stage filtration uses high-precision processing equipment to solve the physical blockage problem in the reinjection process of sandstone thermal reservoir geothermal tail water.

[0045] In the initial single well reinjection test, with the change of temperature, there is a synergistic effect between suspended matter blockage and chemical blockage. The increase in temperature accelerates the Brownian motion rate of suspended matter particles and accelerates the degree of blockage. A larger reinjection speed will also increase the reinjection effect. The main anti-blocking and unblocking measures for suspended matter blockage are multi-stage filtration, and the large, medium and small particles in geothermal water are removed in turn by hydraulic desanders, water storage tanks, multi-stage filters, etc. In chemical blockage, the change of temperature is more sensitive to the precipitation of carbonates, some aluminum silicates and iron minerals, and the chemical blockage is aggravated with the increase of temperature; pH value is mainly sensitive to the precipitation of iron minerals; carbonate minerals, some aluminum silicates and iron minerals are sensitive to the change of Eh; according to the simulation of the mixing ratio, chemical blockage is prone to occur in the early stage of reinjection. In the anti-blocking and unblocking measures, if the geothermal water quality is not changed, anti-scaling agents can be added to prevent blockage. In the experiment, it was found that the main gas blockage is composed of bubbles with a diameter equivalent to the formation throat. The anti-blocking and unblocking measures mainly adopt the addition of automatic exhaust devices in the geothermal utilization and treatment process system. Generally speaking, the main microbial blockages in geothermal reservoirs are saprophytes and iron bacteria. The prevention and removal measures for microbial blockage can sterilize the tail water without affecting the quality of geothermal water.

[0046] Geothermal fields usually adopt hydraulic fracturing to increase production or conventional acid treatment for the purpose of unblocking. Sandstone is composed of sand particles and intergranular cements. Sand particles are mainly quartz and feldspar, and cements are mainly silicates (such as clay) and carbonates. The oil and gas storage space and seepage channels of sandstone formations are the pores between sand particles that are not completely filled with cements. Through acid treatment, the focus is on using acid to dissolve the mud filter cake, solid particle intrusions, and cements and some sand particles between the formations during the well formation process, remove near-well pollution, and use HF and HFB4 to dissolve mud blockages and other scaling materials in the gaps to restore and improve the permeability of the formation near the bottom of the well, and achieve the purpose of stabilizing the formation and controlling the migration of particles. Based on the results of the core component analysis of geothermal wells and the characteristics of different acid types, a soil acid formula is generally used, and the basic acid selection is hydrochloric acid, hydrofluoric acid, and fluoroboric acid. In order to increase the permeability of the target thermal reservoir formation while taking into account the stability of the sandstone formation, a formula of HCL and HF is required.

[0047] The above describes the specific embodiments of the present invention. It should be understood that the present invention is not limited to the above specific embodiments, and those skilled in the art may make various modifications or variations within the scope of the claims, which do not affect the essence of the present invention.

Claims

1. A method for improving the extraction and irrigation efficiency of a hydrothermal geothermal well group, characterized in that: The following steps are involved: Step 100, based on the regional geophysical data, well logging data of completed wells, well completion data, observation data and previous reinjection data, the basic geological characteristics and groundwater dynamic characteristics of the region are analyzed to determine the location of geothermal wells, and the wells are arranged equidistantly according to concentric circles; The production and injection wells of the geothermal well group are evenly arranged on concentric circles. In the early stage of geothermal field development and utilization, the development boundary and scope are delineated, and the first concentric circle of the geothermal well layout is set. The geothermal well positions are evenly arranged on the boundary of the circle. As the development and utilization degree increases, the optimized geothermal well spacing is adjusted according to the geothermal simulation data and operation results, and the concentric circle radius is adjusted layer by layer to adjust the geothermal production and injection well spacing; Step 200, during the drilling construction, ensure that the core is taken to test and analyze the lithology, porosity, permeability, density, and thermal conductivity; Step 300, after the well is completed, in-situ testing of well logging and pumping test is carried out, and a comprehensive analysis of the water quality of the completed well is performed; Step 400, the displacement test is to carry out a single well reinjection system test of geothermal water, conduct a study on the blockage mechanism, and make corresponding anti-blockage and unblocking measures; in the reinjection system test in step 400, geothermal raw water is extracted from the geothermal well, and reinjected into the selected reinjection well after being processed by degreasing and sand removal, exhaust, heat energy application, multi-stage filtration, pressurization, exhaust and acidification and injection in sequence; the precipitation blockage, suspended matter blockage and gas blockage in the geothermal water are comprehensively prevented and unblocked by means of scale inhibitors, multi-stage filtration and multi-stage exhaust respectively; for microbial blockage, the tail water is sterilized without affecting the water quality of the geothermal water; Step 500, verifying the reasonable spacing of the well group through empirical formulas based on tracer test research and numerical simulation, and adjusting the layout of the well group production and injection wells accordingly.

2. The method for improving the extraction and irrigation efficiency of a hydrothermal geothermal well group according to claim 1, characterized in that: In step 200, 1 to 3 groups of cores are collected from each thermal reservoir in the heat extraction section of the exploration and production combined hole.

3. The method for improving the extraction and irrigation efficiency of a hydrothermal geothermal well group according to claim 1, characterized in that: The tracer used in the tracer test in step 500 is magnetic nanoparticles.

4. The method for improving the extraction and irrigation efficiency of a hydrothermal geothermal well group according to claim 1, characterized in that: The wellhead device of each geothermal well in the geothermal well group adopts a multifunctional wellhead device, which is provided with a water supply pipe and a reinjection pipe, and both the water supply pipe and the reinjection pipe are provided with regulating valves.

5. The method for improving the extraction and irrigation efficiency of a hydrothermal geothermal well group according to claim 4, characterized in that: The geothermal wellhead is equipped with a nitrogen monitoring and nitrogen filling closed system, including a buffer tank and a nitrogen tank. The geothermal wellhead device is connected to the buffer tank, and the buffer tank is connected to the nitrogen tank. An inflation valve is provided on the connecting pipe between the wellhead device and the buffer tank, a nitrogen deflation valve is provided on the connecting pipe between the buffer tank and the nitrogen tank, and a pressure display screen is provided on the buffer tank.

6. The method for improving the extraction and irrigation efficiency of a hydrothermal geothermal well group according to claim 1, characterized in that: During the shutdown and maintenance of geothermal wells, the geothermal wellhead should be closed in time and the system should be sealed.

7. The method for improving the extraction and irrigation efficiency of a hydrothermal geothermal well group according to claim 6, characterized in that: Ensure that the pressure in the pipeline system is a positive pressure of 0.01-0.03Mpa.

Citation Information

Cited By

  • Blockage removal and irrigation increase method for sandstone reservoir of geothermal well

    CN116771306A

  • A method for sandstone reservoir plugging and increasing irrigation of geothermal well

    CN116771306B