A modular box building stacking installation method

By verifying and sorting the box on a horizontal platform, and using different tightening methods to deal with the size deviation of the modular box, the problem of uneven size after prefabricated box in the prior art is solved, and the high precision of box building is achieved. Reliable connection and stability.

CN114622654BActive Publication Date: 2024-11-19CHINA CONSTR SCI & IND CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210172574.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-02-24
Publication Date
2024-11-19
Estimated Expiration
2042-02-24

AI Technical Summary

Technical Problem

The existing modular box building may have dimensional deviations after prefabrication, resulting in uneven support, affecting the verticality of later assembly and structural stress, resulting in the problem of unsolid connections.

Method used

A modular box building stacking installation method is proposed. By pre-assembly and checking on a horizontal platform, the box type is classified, and different tightening methods are selected according to the type, including initial screwing, repeated screwing and final screwing operations, ensuring support. The fastening connection of the seat eliminates dimensional deviation and torque loss, and improves installation accuracy and reliability.

Benefits of technology

It realizes reliable connection of box buildings, improves verticality and installation accuracy, ensures the design torque of the support, eliminates the impact of construction errors, and enhances the overall stability of the building.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114622654B_ABST
    Figure CN114622654B_ABST
Patent Text Reader

Abstract

The invention discloses a stacking installation method for a modular box building, comprising: a box having 6 supports, the supports are arranged in groups of 2 and are located at both ends and the middle of the bottom of the box, and: step S1, hoisting the box onto a horizontal standard platform, performing pre-assembly verification, checking the overall deformation of the box and recording it; step S2, classifying the boxes according to their overall deformation, into standard boxes, middle seam boxes and side seam boxes; step S3, hoisting the boxes for stacking installation, the boxes are connected by bolts, tightening is performed each time a layer of boxes is hoisted, and the tightening method is selected according to the type of the boxes; step S4, when all the boxes are hoisted, final tightening is performed on all the supports from the bottom box upwards to complete the stacking installation of the box building; the stacking installation method for modular box buildings of the invention can eliminate the influence of box size deviation during installation, so that the entire box building is reliably connected, has good verticality and high installation accuracy.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a stacking installation method for modular box buildings. Background Art

[0002] Modular box building is a new type of building system, which has the characteristics of short construction period through assembly between boxes. The early technology is immature, and the prefabricated boxes have the problem of size deviation, which affects the later assembly construction. For example, after the box is prefabricated, the bottom is not in the same horizontal plane, and there are cases where the middle support or the two end supports are tilted, resulting in a large gap between the supports after the adjacent two layers of boxes are stacked. After installation, the verticality of the entire box building is affected, and the stress of the internal structure will also change. Summary of the invention

[0003] The present invention aims to solve at least one of the technical problems existing in the prior art. To this end, the present invention proposes a modular box building stacking installation method, which can eliminate the influence of box size deviation during installation, so that the entire box building is reliably connected, has good verticality, and has high installation accuracy.

[0004] The stacking installation method of modular box buildings according to an embodiment of the present invention comprises a box, wherein the box is provided with 6 supports, which are arranged in groups of 2 and are respectively located at both ends and the middle of the bottom of the box, wherein a group of supports located in the middle of the box is support B, and two groups of supports located at the ends of the box are support A and support C, respectively, and:

[0005] Step S1, hoisting the box onto a horizontal standard platform, performing pre-assembly verification, checking the overall deformation of the box and recording it;

[0006] Step S2, classifying the box body according to the overall deformation of the box body. If there is no gap between all the supports of the box body and the standard platform, it is a standard box. If there is a gap between the support B of the box body and the standard platform, it is a center-seam box. If there is a gap between only one end of the support A or support C of the box body and the standard platform, it is a side-seam box.

[0007] Step S3, hoisting the box body for stacking installation, the box bodies are fastened and connected by bolts, and tightening operation is performed for each hoisting layer of the box body, and the tightening method is selected according to the type of the box body. If a standard box is hoisted, all the supports of the standard box are synchronously tightened, and then synchronously re-tightened. If a center seam box is hoisted, all the supports of the center seam box are synchronously tightened, and then both the support A and the support C are re-tightened. If a side seam box is hoisted, a temporary pad is added under the end support of the side seam box where there is no gap to pad it up, so that all the supports of the side seam box have no gap, and then the remaining supports without the temporary pad are initially tightened, and then the temporary pad is removed, and the supports after the temporary pad is removed are initially tightened, and finally all the supports are synchronously re-tightened;

[0008] Step S4, when all the boxes are hoisted, all the supports are tightened from the bottom box upwards to complete the stacking installation of the box building.

[0009] The modular box building stacking installation method according to the embodiment of the present invention has at least the following technical effects:

[0010] 1. In step S1, the box is placed on a horizontal standard platform to determine the deformation of the box, so that in step S2, the boxes are classified according to the deformation. After classification, it is convenient to implement different methods for connection according to different types of boxes in step S3, so that the final box building meets the design requirements. The box building is reliably connected, has good verticality, and high installation accuracy.

[0011] 2. The tightening methods are divided into initial tightening operation, repeated tightening operation and final tightening operation. The initial tightening operation can preliminarily connect the two adjacent layers of the box, so that the box on the lower layer can be affected by the gravity of the upper box, offsetting the dimensional deviation caused by the deformation of the lower box itself; the repeated tightening operation applies the bolt torque of the connecting support to the design torque value to ensure reliable connection; the final tightening operation can compensate for the torque loss that may be caused by construction in the middle, ensure that all the supports of the box building, and their connecting bolts reach the design torque, eliminating the influence of errors caused by construction.

[0012] In some embodiments of the present invention, during the initial tightening operation, the tightening torque is 1 / 2 of the design torque, during the re-tightening operation, the tightening torque is the design torque, and during the final tightening operation, the tightening torque is also the design torque to compensate for the torque loss between the supports.

[0013] In some embodiments of the present invention, the interval between the re-tightening operation and the initial tightening operation does not exceed 12 hours.

[0014] In some embodiments of the present invention, step S3 also includes step S3.1, after each layer of the box is hoisted, the elevation of the box is detected. If the elevation of the box exceeds the design value, the fit of the support and the torque value of the bolts at the position where the elevation exceeds the design value are checked, and adjustments are made so that the elevation of the box meets the requirements.

[0015] In some embodiments of the present invention, in step S4, before the final tightening operation is performed, the elevation of the entire building formed by all the boxes is measured first, and after confirming that the elevation meets the requirements, the final tightening operation is performed.

[0016] In some embodiments of the present invention, in step S3, the center seam box is hoisted first, and the initial tightening operation is synchronously performed on all the supports of this layer, and then the re-tightening operation is synchronously performed on the supports except support B. Then, the standard box is hoisted, and the initial tightening operation is synchronously performed on all the supports of this layer, and the re-tightening operation is performed on the support B of the center seam box of the previous layer. Finally, the re-tightening operation is synchronously performed on the supports of this layer except support B, and the standard boxes continue to be hoisted. The above operations are repeated. After the last standard box is hoisted, all the supports are re-tightened to complete the stacking installation of the box building.

[0017] In some embodiments of the present invention, in step S3, the middle seam box is first hoisted, and the initial tightening operation is synchronously performed on all the supports of this layer, and then the remaining supports except support B are synchronously re-tightened. Then, the middle seam box continues to be hoisted, and the initial tightening operation is synchronously performed on all the supports of this layer, and then the remaining supports except support B of this layer are synchronously re-tightened. The middle seam box continues to be hoisted, and the above operations are repeated until the last layer is hoisted with a standard box, and the initial tightening operation is synchronously performed on all the supports of this layer, and then all the supports B are re-tightened from the bottom layer upwards, and finally the remaining supports of this layer are re-tightened to complete the stacking installation of the box building.

[0018] In some embodiments of the present invention, in step S3, the center seam box is first hoisted, and the initial tightening operation is synchronously performed on all the supports of this layer, and then the remaining supports except support B are synchronously re-tightened, and then the side seam box is hoisted, and temporary pads are added under the end supports of the side seam boxes of this layer without gaps to raise them so that there are no gaps in all the supports of the side seam boxes, and then the initial tightening operation is performed on the remaining supports without temporary pads, and then the temporary pads are removed, and then the initial tightening operation is performed on the supports after the temporary pads are removed, and then the re-tightening operation is performed on the support B of the center seam box of the previous layer, and at the same time, the re-tightening operation is synchronously performed on all the supports of the side seam boxes of this layer.

[0019] Additional aspects and advantages of the present invention will be given in part in the following description and in part will be obvious from the following description, or will be learned through practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] The above and / or additional aspects and advantages of the present invention will become apparent and easily understood from the description of the embodiments in conjunction with the following drawings, in which:

[0021] Figure 1 This is a schematic diagram of the box structure of an embodiment of the present invention;

[0022] Figure 2 It is a front view of a center seam box according to an embodiment of the present invention;

[0023] Figure 3 It is a front view of the side seam box according to an embodiment of the present invention.

[0024] Reference numerals:

[0025] Box body 100. DETAILED DESCRIPTION

[0026] Embodiments of the present invention are described in detail below, examples of which are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present invention, and cannot be understood as limiting the present invention.

[0027] In the description of the present invention, it should be understood that descriptions involving orientations, such as up, down, front, back, left, right, etc., and orientations or positional relationships indicated are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.

[0028] In the description of the present invention, "several" means one or more, "more" means more than two, "greater than", "less than", "exceed" etc. are understood as not including the number itself, and "above", "below", "within" etc. are understood as including the number itself. If there is a description of "first" or "second", it is only used for the purpose of distinguishing the technical features, and cannot be understood as indicating or implying the relative importance or implicitly indicating the number of the indicated technical features or implicitly indicating the order of the indicated technical features.

[0029] In the description of the present invention, unless otherwise clearly defined, terms such as setting, installing, connecting, etc. should be understood in a broad sense, and technicians in the relevant technical field can reasonably determine the specific meanings of the above terms in the present invention based on the specific content of the technical solution.

[0030] Reference Figures 1 to 3As shown, the stacking installation method of modular box buildings according to an embodiment of the present invention includes a box 100, which is provided with 6 supports, which are arranged in groups of 2 and are respectively located at the two ends and the middle of the bottom of the box 100, a group of supports located in the middle of the box 100 is support B, and the two groups of supports located at the ends of the box 100 are support A and support C, and:

[0031] Step S1, hoist the box 100 onto a horizontal standard platform, perform pre-assembly verification, check the overall deformation of the box 100 and record it;

[0032] Step S2, classifying the box body 100 according to the overall deformation condition. If there is no gap between all the supports of the box body 100 and the standard platform, it is a standard box. If there is a gap between the support B of the box body 100 and the standard platform, it is a center-seam box. If there is a gap between only one end of the support A or support C of the box body 100 and the standard platform, it is a side-seam box.

[0033] Step S3, lifting the box 100 for stacking installation, the box 100 is fastened and connected by bolts, and tightening operation is performed each time a layer of box 100 is hoisted, and the tightening method is selected according to the type of box 100. If a standard box is hoisted, all the supports of the standard box are synchronously tightened, and then synchronously re-tightened. If a center seam box is hoisted, all the supports of the center seam box are synchronously tightened, and then the support A and the support C are re-tightened. If a side seam box is hoisted, a temporary pad is added under the end support of the side seam box where there is no gap to pad it, so that all the supports of the side seam box do not have gaps, and then the remaining supports without temporary pads are initially tightened, and then the temporary pad is removed, and the supports after the temporary pad is removed are initially tightened, and finally all the supports are synchronously re-tightened;

[0034] Step S4, when all the boxes 100 are hoisted, all the supports are tightened from the bottom box 100 upwards to complete the stacking installation of the box building.

[0035] In step S1, the box 100 is placed on a horizontal standard platform to determine the deformation of the box 100, so that in step S2, the box 100 is classified according to the deformation. After classification, it is convenient to implement different methods for connection according to different types of boxes 100 in step S3, so that the final box building meets the design requirements.

[0036] In step S3 and step S4, the tightening method is divided into initial tightening operation, re-tightening operation and final tightening operation, wherein the initial tightening operation can preliminarily connect the two adjacent layers of box bodies 100, so that the box body 100 located at the lower layer can be subjected to the gravity of the upper layer of box body 100, thereby offsetting the dimensional deviation caused by the deformation of the lower layer of box body 100 itself; after the dimensional deviation of the box body 100 is eliminated, the re-tightening operation can be performed, and the bolt torque of the connecting support is applied to the design torque value to ensure reliable connection; after all the boxes 100 are hoisted, all the supports are subjected to final tightening operation to compensate for the torque loss that may be caused by the construction in the middle, to ensure that the connecting bolts of all the supports of the box body building reach the design torque, and eliminate the influence of errors caused by the construction.

[0037] In step S3, the standard box has no size error, and the initial tightening operation and the re-tightening operation can be directly performed; for the center-seam box, the connecting bolts of all supports are first tightened, and then the connecting bolts of supports A and C are re-tightened. After the next layer of box 100 is hoisted onto the center-seam box, the gravity is transferred to the center-seam box, and the support B is pressed down, and the gap disappears. Then, the connecting bolts of support B of the center-seam box can be re-tightened; for the side-seam box, assuming that there is a gap at support A under natural gravity, it can be known that the side-seam box If the weight of the box from support B to support C is heavier, a temporary pad is added under support C to raise it, so that the side seam box deflects toward support A, eliminating the gap at support A, and then the bolts at support A are initially tightened. After completion, the temporary pad is removed. Since the weight of the side seam box from support B to support C is heavier, it is deformed due to its own gravity and the gap at support C is also eliminated. Then the bolts at support C are initially tightened, and finally all the bolts of supports A, B and C are re-tightened simultaneously.

[0038] In some embodiments of the present invention, during the initial tightening operation, the tightening torque is 1 / 2 of the design torque, during the re-tightening operation, the tightening torque is the design torque, and during the final tightening operation, the tightening torque is also the design torque to compensate for the torque loss between the supports.

[0039] The tightening method is divided into initial tightening operation, re-tightening operation and final tightening operation, wherein the tightening torque of the initial tightening operation is 1 / 2 of the design torque, and this torque can preliminarily connect the two adjacent layers of the box 100, so that the box 100 located at the lower layer can be subjected to the gravity of the upper box 100, offsetting the size deviation caused by the deformation of the lower box 100 itself, and at the same time, the larger connection torque will not cause damage to the connecting bolts when the box 100 itself is deformed;

[0040] The re-tightening operation applies the bolt torque of the connection support to the designed torque value, so that the connection between the boxes 100 is reliable and the box building safety is guaranteed;

[0041] The final tightening operation can compensate for the torque loss caused by mid-construction, ensure that the connecting bolts of all supports of the box building finally reach the designed torque, and eliminate the influence of errors caused by construction.

[0042] In some embodiments of the present invention, the interval between the re-tightening operation and the initial tightening operation does not exceed 12 hours.

[0043] Since the initial tightening operation only adjusts the connection torque of the bolts to 1 / 2 of the design torque, it is not the final connection of the box body 100. If the connection bolts are not adjusted to the design torque value in time, there is a risk of the connection bolts loosening. The longer the interval time, the greater the degree of loosening of the connection bolts and the higher the danger.

[0044] Generally, the re-tightening operation is controlled to be carried out immediately after the initial tightening operation is completed. If the re-tightening operation is delayed as needed, it should be carried out within 12 hours at the latest. If it exceeds 12 hours, the bolts that have undergone the initial tightening operation may loosen due to various reasons, and their connection function has become unreliable.

[0045] In some embodiments of the present invention, step S3 also includes step S3.1, after each layer of box 100 is hoisted, the elevation of the box 100 is detected. If the elevation of the box 100 exceeds the design value, the fit of the support and the torque value of the bolts at the position where the elevation exceeds the design value are checked, and adjustments are made to ensure that the elevation of the box 100 meets the requirements.

[0046] Ideally, after the installation of the box 100 without deformation, no gap will be generated between the supports and the elevation will not exceed the theoretical value. After each layer of the box 100 is hoisted, its elevation is tested to determine whether the gap between the supports exceeds the standard range, so as to promptly correct the torque value of the connecting bolts of this layer to eliminate the gap and make the elevation meet the requirements, thereby avoiding error accumulation and causing the final elevation to fail to meet the requirements.

[0047] In some embodiments of the present invention, in step S4, before the final tightening operation is performed, the elevation of the entire building formed by all the boxes 100 is measured first, and the final tightening operation is performed after confirming that the elevation meets the requirements.

[0048] Before the final tightening operation, the overall elevation measurement is verified to ensure the quality of the building. After confirmation, the final tightening operation is performed to complete the construction.

[0049] In some embodiments of the present invention, in step S3, the center seam box is hoisted first, and the initial tightening operation is synchronously performed on all the supports of this layer, and then the re-tightening operation is synchronously performed on the supports except support B. Then, the standard box is hoisted, and the initial tightening operation is synchronously performed on all the supports of this layer, and the re-tightening operation is performed on the support B of the center seam box of the previous layer. Finally, the re-tightening operation is synchronously performed on the supports of this layer except support B, and the standard boxes continue to be hoisted. The above operations are repeated. After the last standard box is hoisted, all the supports are re-tightened to complete the stacking installation of the box building.

[0050] First, hoist the middle seam box, and perform the initial tightening operation on all the supports of this layer simultaneously to preliminarily correct the deformation of the middle seam box. Then, except for support B, all other supports are simultaneously re-tightened to ensure a stable connection. Then, hoist the standard box, and perform the initial tightening operation on all the supports of this layer simultaneously. After the initial tightening operation is completed, the gravity of the standard box is transmitted to the middle seam box of the previous layer through the support, so that the support B of the middle seam box is pressed down to resist deformation. Finally, the gap under the support B is eliminated. At this time, the support B can be re-tightened synchronously. Finally, except for the support B of the standard box, the other supports of this layer are simultaneously re-tightened to ensure a stable connection.

[0051] Continue to hoist the standard box, and perform the initial tightening operation on all the supports of this layer simultaneously. After the initial tightening operation is completed, the gravity of the standard box is transmitted to the standard box of the previous layer through the support, so that the support B of the standard box of the previous layer moves further downward. After ensuring that the gap is eliminated, the support B of the standard box of the previous layer is re-tightened, and finally return to the standard box of this layer, and re-tighten the remaining supports except the support B of the standard box of this layer simultaneously. Repeat until the connection of the last layer is completed.

[0052] In some embodiments of the present invention, in step S3, the middle seam box is first hoisted, and the initial tightening operation is synchronously performed on all the supports of this layer, and then the remaining supports except support B are synchronously re-tightened. Then, the middle seam box continues to be hoisted, and the initial tightening operation is synchronously performed on all the supports of this layer, and then the remaining supports except support B of this layer are synchronously re-tightened. The middle seam box continues to be hoisted, and the above operations are repeated until the last layer is hoisted with a standard box, and the initial tightening operation is synchronously performed on all the supports of this layer, and then all the supports B are re-tightened from the bottom layer upwards, and finally the remaining supports of this layer are re-tightened to complete the stacking installation of the box building.

[0053] First, hoist the center seam box, and perform the initial tightening operation on all the supports of this layer simultaneously to preliminarily correct the deformation of the center seam box. Then, except for support B, the remaining supports are simultaneously tightened to ensure a stable connection.

[0054] Then continue to hoist the middle seam box, and perform the initial tightening operation on all the supports of the middle seam box of this layer simultaneously. After the initial tightening operation is completed, the gravity of the middle seam box of this layer is transmitted to the middle seam box of the previous layer through the supports. Since there is a gap under the support B of the middle seam box of this layer, the support B of the middle seam box of this layer cannot press down the middle seam box of the previous layer to resist deformation. Therefore, only the support B of the middle seam box of this layer can be tightened again;

[0055] When hoisting the last layer, only standard boxes can be selected for installation. After hoisting the standard boxes, all supports of the standard boxes are simultaneously tightened. The gravity of the standard boxes of this layer is transmitted to the middle seam boxes of the previous layer through the supports, so that the supports B of the middle seam boxes of the previous layer are pressed down to resist deformation. Similar to a chain reaction, the supports B of the middle seam boxes of the previous layer are pressed down to continue to contact the middle seam boxes of the first two layers, so that the supports B of the middle seam boxes of the first two layers are also pressed down to resist deformation, until the supports B of all the middle seam boxes resist deformation and eliminate gaps, and then all the supports B can be re-tightened from the bottom layer upwards, and then the remaining supports of the standard boxes of the last layer are re-tightened to complete the stacked installation of the box building.

[0056] In some embodiments of the present invention, in step S3, the center seam box is first hoisted, and the initial tightening operation is synchronously performed on all the supports of this layer, and then the remaining supports except support B are synchronously re-tightened, and then the side seam box is hoisted, and temporary pads are added under the end supports of the side seam boxes of this layer without gaps to raise them so that there are no gaps in all the supports of the side seam boxes, and then the initial tightening operation is performed on the remaining supports without temporary pads, and then the temporary pads are removed, and then the initial tightening operation is performed on the supports after the temporary pads are removed, and then the re-tightening operation is performed on the support B of the center seam box of the previous layer, and at the same time, the re-tightening operation is synchronously performed on all the supports of the side seam boxes of this layer.

[0057] First, hoist the center seam box, and perform the initial tightening operation on all the supports of this layer simultaneously to preliminarily correct the deformation of the center seam box. Then, except for support B, the remaining supports are simultaneously tightened to ensure a stable connection.

[0058] Next, the side seam box is hoisted, and temporary pads are added under the end supports of the side seam box without gaps to raise it, so that all the supports of the side seam box have no gaps. Assuming that there is a gap under support A in this side seam box, the weight of the section from support B to support C is greater than the weight of the section from support A to support B. At this time, a temporary pad should be added under support C to eliminate the gap under support A. Then, the initial tightening operation can be performed on supports A and B simultaneously, and then the temporary pad is removed, and the initial tightening operation is performed on support C. After completion, all the supports of the side seam box can be re-tightened. After all the supports of the side seam box have been re-tightened, the side seam box can be equivalent to a "standard box", that is, the side seam box is the same as the standard box, and all the supports have no gaps and have been re-tightened. Then the remaining supports B of the previous layer of the middle seam box can be re-tightened to complete the installation of the previous layer of the middle seam box.

[0059] According to some embodiments of the present invention, structural analysis software is used to simulate and verify the installation effect, and the software used is MIDAS GEN 2021 (v1.1).

[0060] Set up the cabinet in the software and divide the cabinet into 4 groups, including cabinet group BOX1, cabinet support groups BOX1-SPPT1, BOX1-SPPT2 and BOX1-SPPT3, where BOX1 is the cabinet numbered 1, BOX1-SPPT1, BOX1-SPPT2 and BOX1-SPPT3 are the supports of the cabinet numbered 1, BOX1-SPPT1 is support C, BOX1-SPPT2 is support B, and BOX1-SPPT3 is support C. BOX2 is the cabinet numbered 2, and so on. When stacking, the cabinets are stacked from bottom to top, and the numbers increase from small to large.

[0061] Simulate the first case: Step 1, activate box BOX1 and supports BOX1-SPPT1 and BOX1-SPPT3, and passivate supports BOX1-SPPT2 and other boxes to simulate the situation where there is a gap in support B of the first layer of the seam box. Step 2, activate box BOX2 and supports BOX2-SPPT1, BOX2-SPPT2 and BOX2-SPPT3, simulate the standard box and the standard box's supports C, B and A have no gaps, and the box's gravity is smoothly transferred to the box of the previous layer. Step 3, activate box BOX3 and supports BOX3-SPPT1, BOX3-SPPT2 and BOX3-SPPT3, at this time, the gravity of BOX2 and BOX3 is smoothly transferred to BOX1. Continue the simulation according to this step until box BOX7 is stacked. The displacement values ​​of support B of box BOX1, that is, support BOX1-SPPT2, are shown in Table 1.

[0062] Table 1 Displacement change of support BOX1-SPPT2 (unit: mm)

[0063]

[0064]

[0065] According to the simulation results, in the first case, after the center seam box of the first layer is subjected to the gravity of the second layer standard box (construction to the second step), the displacement of the support B of the center seam box of the first layer can reach 21.040 mm, that is, the gap of the support B can be eliminated, and the support B can be re-tightened, and the embodiment of the present invention can produce beneficial effects.

[0066] Simulate the second situation: Step 1, activate box BOX1 and supports BOX1-SPPT1 and BOX1-SPPT3, and passivate supports BOX1-SPPT2 and other boxes to simulate the situation where there is a gap in support B of the first-layer center seam box. Step 2, activate box BOX2 and supports BOX2-SPPT1 and BOX2-SPPT3 to simulate the center seam box of the second layer. The weight of the box is only smoothly transferred to the box of the previous layer through supports BOX2-SPPT1 and BOX2-SPPT3. Step 3, activate box BOX3 and supports BOX3-SPPT1, BOX3-SPPT2 and BOX3-SPPT3. At this time, the weight of BOX3 is smoothly transferred to BOX2. Step 4, activate box BOX4 and supports BOX4-SPPT1, BOX4-SPPT2 and BOX4-SPPT3. At this time, the weight of BOX4 is smoothly transferred to BOX3. Continue the simulation in this way until the stacking of box BOX7 is completed. The displacement values ​​of support B of box BOX1, i.e. support BOX1-SPPT2, and support B of box BOX2, i.e. support BOX2-SPPT2 are shown in Table 2.

[0067] Table 2 Displacement changes of bearings BOX1-SPPT2 and BOX2-SPPT2 (unit: mm)

[0068]

[0069] According to the simulation results, in the second case, after the center seam box of the second layer is subjected to the gravity of the center seam box of the third layer (construction to the third step), the displacement of the support B of the center seam box of the second layer can reach 25.869 mm, that is, the gap of the support B of the center seam box of the second layer can be eliminated, and the support B of the center seam box of the second layer can be re-tightened. After the re-tightening operation is completed, the gravity of the center seam box of the second layer can be smoothly transferred to the center seam box of the first layer. According to the results of the first simulation case, the gap of the support B of the center seam box of the first layer can also be eliminated, that is, the support B of the center seam box of the first layer can be re-tightened, and the embodiment of the present invention can produce beneficial effects.

[0070] Simulate the third situation: The first step is to activate the box BOX1 and the supports BOX1-SPPT1 and BOX1-SPPT2, and passivate the supports BOX1-SPPT3 and other boxes to simulate the situation where there is a gap in the support A of the first layer of the side seam box. Since the box is not disturbed by external forces, in its natural state, it will use the support in the middle as the fulcrum, and the entire box will be biased to the side with a longer segment length, that is, the side with a shorter segment length, and a gap will inevitably appear under its support. Set the side seam box in the software, and its segment length from support A to support B is less than the segment length from support B to support C, then the side seam box will have a gap under support A.

[0071] The second step is to activate box BOX2 and supports BOX2-SPPT1, BOX2-SPPT2 and BOX2-SPPT3 to simulate the standard box on the second layer. The weight of the box is smoothly transferred to the box on the previous layer through supports BOX2-SPPT1, BOX2-SPPT2 and BOX2-SPPT3.

[0072] In the third step, activate box BOX3 and supports BOX3-SPPT1, BOX3-SPPT2, and BOX3-SPPT3, and smoothly transfer the gravity of BOX2 and BOX3 to BOX1. Continue the simulation in this way until box BOX7 is stacked. The displacement values ​​of support A of box BOX1, i.e. support BOX1-SPPT3, are shown in Table 3.

[0073] Table 3 Displacement change of support BOX1-SPPT3 (unit: mm)

[0074]

[0075] According to the simulation results, in the third case, there is a gap in the support A of the first layer of side seam box, that is, box BOX1, that is, there is a gap in support BOX1-SPPT3, and no temporary pad is added to support C (BOX1-SPPT1), and support B and support C are directly tightened and re-tightened. The gap in support A cannot be eliminated by the gravity of box BOX1 itself, and until the seventh step, after box BOX7 is stacked, the maximum displacement of support A of box BOX1 is only 12.920, and the effect of eliminating the gap is not ideal.

[0076] Simulate the fourth case. In the first step, activate box BOX1 and supports BOX1-SPPT2 and BOX1-SPPT3, and deactivate supports BOX1-SPPT1 and other boxes. Simulate the situation in which there is a gap in support A of the first-layer center seam box, but the gap is transferred to support C by adding a temporary pad. In addition, in this side seam box, the length from support A to support B is shorter than the length from support B to support C.

[0077] The second step is to activate box BOX2 and supports BOX2-SPPT1, BOX2-SPPT2 and BOX2-SPPT3 to simulate a standard box. There are no gaps between supports C, B and A of the standard box, and the weight of the box is smoothly transferred to the box of the previous layer.

[0078] In the third step, activate box BOX3 and supports BOX3-SPPT1, BOX3-SPPT2 and BOX3-SPPT3. At this time, the gravity of BOX2 and BOX3 is smoothly transferred to BOX1. Continue the simulation in this way until box BOX7 is stacked. The displacement value of support C of box BOX1, that is, support BOX1-SPPT1, is shown in Table 4.

[0079] Table 4 Displacement change of support BOX1-SPPT1 (unit: mm)

[0080]

[0081]

[0082] There is a gap in support A of BOX1. Since the length from support A to support B is shorter than the length from support B to support C, a temporary pad is added to support C of BOX1 to eliminate the gap in support A first. Then, support A and support B are initially tightened and the temporary pad is removed. This will cause a gap in support C. In the simulation software, this corresponds to activating box BOX1, and supports BOX1-SPPT2 (support B) and BOX1-SPPT3 (support A).

[0083] According to the simulation results, in the fourth case, only in the first step of construction, the support BOX1-SPPT1 (support C) of the box BOX1 can achieve a maximum displacement of 29.476 mm through its own gravity, that is, after the temporary pad is removed from under the support C, the support C can eliminate the gap to facilitate initial tightening and re-tightening operations, and the embodiments of the present invention can produce beneficial effects.

[0084] There is also a situation where the middle support of the box body divides the box body equally, that is, the section length from support A to support B is equal to the section length from support B to support C. In fact, under the natural state, this box body will inevitably lean to one side, so that there is a gap under the other side. According to an embodiment of the present invention, a temporary pad is added under the end support of the side seam box where there is no gap to raise it (the weight on this side is greater), so that there is no gap in all the supports of the side seam box, and then the remaining supports without temporary pads are initially tightened, and then the temporary pads are removed. Then, the supports on the side where the temporary pads are removed will be deformed due to the weight of the box body (the weight on this side is greater), eliminating the gap, and then the supports here are initially tightened. Finally, all supports can be re-tightened at the same time. The embodiments of the present invention can produce beneficial effects.

[0085] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "illustrative embodiments", "examples", "specific examples", or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner.

[0086] Although the embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the claims and their equivalents.

Claims

1. A modular box building stacking installation method, It is characterized in that The invention comprises a box (100), wherein the box (100) is provided with 6 supports, which are arranged in groups of 2 and are respectively located at the two ends and the middle of the bottom of the box (100), wherein a group of supports located in the middle of the box (100) is a support B, and two groups of supports located at the ends of the box (100) are respectively a support A and a support C, and: Step S1, hoisting the box (100) onto a horizontal standard platform, performing pre-assembly verification, checking the overall deformation of the box (100) and recording it; Step S2, classifying the box body (100) according to the overall deformation condition, if there is no gap between all supports of the box body (100) and the standard platform, it is a standard box, if there is a gap between support B of the box body (100) and the standard platform, it is a center-seam box, and if there is a gap between only one end of support A or support C of the box body (100) and the standard platform, it is a side-seam box; Step S3, hoisting the box (100) for stacking and installation, the box (100) is fastened and connected by bolts, and tightening operation is performed each time a layer of the box (100) is hoisted, and the tightening method is selected according to the type of the box (100). If a standard box is hoisted, all the supports of the standard box are synchronously tightened and then synchronously re-tightened. If a center seam box is hoisted, all the supports of the center seam box are synchronously tightened, and then both the support A and the support C are re-tightened. If a side seam box is hoisted, a temporary pad is added under the end support of the side seam box without a gap to pad it up so that all the supports of the side seam box have no gap, and then the remaining supports without the temporary pad are initially tightened, and then the temporary pad is removed, and the supports after the temporary pad is removed are initially tightened, and finally all the supports are synchronously re-tightened; Step S4, when all the boxes (100) are hoisted, all the supports are tightened from the bottom box (100) upwards to complete the stacking installation of the box building.

2. The modular box building stacking installation method according to claim 1, It is characterized in that When performing the initial tightening operation, the tightening torque is 1 / 2 of the design torque. When performing the re-tightening operation, the tightening torque is the design torque. When performing the final tightening operation, the tightening torque is also the design torque to compensate for the torque loss between the supports.

3. The modular box building stacking installation method according to claim 2, It is characterized in that The interval between the re-tightening operation and the initial tightening operation shall not exceed 12 hours.

4. The stacking installation method of modular box building according to claim 1, It is characterized in that In step S3, it also includes step S3.1, after each layer of the box (100) is hoisted, the elevation of the box (100) is detected. If the elevation of the box (100) exceeds the design value, the fit of the support and the torque value of the bolts at the position where the elevation exceeds the design value are checked, and adjustments are made so that the elevation of the box (100) meets the requirements.

5. The stacking installation method of modular box building according to claim 1, It is characterized in that In step S4, before the final tightening operation is performed, the elevation of the entire building formed by all the boxes (100) is measured, and after confirming that the elevation meets the requirements, the final tightening operation is performed.

6. The stacking installation method of modular box building according to claim 1, It is characterized in that In step S3, the middle seam box is hoisted first, and the initial tightening operation is performed on all the supports of this layer simultaneously. Then, except for support B, the remaining supports are simultaneously re-tightened. Then, the standard box is hoisted, and the initial tightening operation is performed on all the supports of this layer simultaneously. At the same time, the support B of the middle seam box of the previous layer is re-tightened. Finally, except for support B, the remaining supports of the standard box of this layer are simultaneously re-tightened. Continue to hoist the standard box and repeat the above operations. After the last standard box is hoisted, all the supports are re-tightened to complete the stacking installation of the box building.

7. The stacking installation method of modular box building according to claim 1, It is characterized in that In step S3, the middle seam box is first hoisted, and the initial tightening operation is synchronously performed on all the supports of this layer, and then the re-tightening operation is synchronously performed on the supports except support B. Then, the middle seam box is continued to be hoisted, and the initial tightening operation is synchronously performed on all the supports of this layer, and then the re-tightening operation is synchronously performed on the supports except support B of this layer. The middle seam box is continued to be hoisted, and the above operations are repeated until the standard box is hoisted on the last layer, and the initial tightening operation is synchronously performed on all the supports of this layer, and then the re-tightening operation is performed on all the supports B from the bottom layer upwards, and finally the re-tightening operation is performed on the remaining supports of this layer to complete the stacking installation of the box building.

8. The stacking installation method of modular box building according to claim 1, It is characterized in that In step S3, the center seam box is hoisted first, and the initial tightening operation is performed on all the supports of this layer simultaneously. Then, except for support B, the remaining supports are simultaneously re-tightened. Then, the side seam boxes are hoisted, and temporary pads are added under the end supports of the side seam boxes of this layer without gaps to raise them so that there are no gaps in all the supports of the side seam boxes. Then, the initial tightening operation is performed on the remaining supports without temporary pads, and then the temporary pads are removed. Then, the initial tightening operation is performed on the supports after the temporary pads are removed, and then the re-tightening operation is performed on the support B of the center seam box of the previous layer, and at the same time, the re-tightening operation is performed on all the supports of the side seam boxes of this layer simultaneously.