A construction method for a segmental prefabricated composite composite plate composite beam structure

By prefabricating and maintaining the main beam segments in the factory, combining ultra-high toughness fiber-reinforced cement matrix composite materials and steel mesh, the problem of insufficient self-weight and rigidity of the main beam structure of large-span cable-stayed bridges is solved, and efficient construction and Improve mechanical properties and meet the quality requirements of rapid prefabricated assembly construction.

CN115821772BActive Publication Date: 2024-11-15HUBEI COMM PLANNING & DESIGN INST CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202211520343.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-11-30
Publication Date
2024-11-15
Estimated Expiration
2042-11-30

AI Technical Summary

Technical Problem

During the construction process of the large span cable-stayed bridge, the main beam structure is too heavy, the constant load axial force increases, the structural static buckling stability is reduced, and the concrete bridge deck structure of the existing combined beams is insufficient, making it easy to have paved layers. Damage and fatigue cracking cannot meet the quality requirements of rapid prefabricated assembly construction.

Method used

Using segment prefabricated composite material combined plate composite beam structure, the cement matrix composite material is reinforced by processing and prefabricating the main beam segments in the factory, including the base plate, web, orthogonal opposite-sex roof plate and shear connections. The layer and steel mesh, combined with cable-stayed cable preload, improve the crack resistance of transverse wet joints, and complete standardized operations and maintenance in the factory to reduce on-site pouring operations.

Benefits of technology

The construction period is shortened, the mechanical properties and fatigue resistance of the structure are improved, the self-weight of the structure is reduced, the overall stiffness of the bridge deck is enhanced, the compressive stress reserves between different main beam segments are improved, and the construction quality and economic performance are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115821772B_ABST
    Figure CN115821772B_ABST
Patent Text Reader

Abstract

The present invention discloses a construction method of a segment prefabricated composite composite plate composite beam structure. Different components of a main beam segment are prefabricated at the same time in a factory, and the prefabricated main beam segment is easier to perform standardized operations in the factory. By pre-casting an ultra-high toughness fiber reinforced cement-based composite material layer on an orthotropic composite top plate in the factory, the casting operations at the bridge construction site are greatly reduced. The main beam segment utilizes a combined structure of an orthotropic top plate and a composite material to effectively reduce the dead weight of the structure and has good mechanical properties. The ultra-high toughness fiber reinforced cement-based composite material layer not only participates in the stress of the main beam system as a structural layer, but also greatly improves the fatigue resistance of the orthotropic top plate as a rigid pavement. The ultra-high toughness fiber reinforced cement-based composite material layer is tensioned by inclined cables to apply a pre-tightening force to the ultra-high performance concrete at the transverse wet joint, which can improve the crack resistance of the transverse wet joint and thus improve the compressive stress reserve between different main beam segments.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of bridge design and construction, and in particular to a construction method of a segment prefabricated composite material composite plate composite beam structure. Background Art

[0002] The construction period of a large-span cable-stayed bridge can be shortened through rapid prefabrication and assembly construction. At the same time, the labor input of rapid prefabrication and assembly construction is low, the quality of concrete pouring is easier to ensure, and the impact on the surrounding environment of the construction site is small. The rapid prefabrication and assembly construction method is widely used in existing bridge construction.

[0003] However, with the increase in bridge spans, the difficulty of rapid prefabrication and assembly construction is also increasing. The compressive stress reserve between different main beam segments and the overall stiffness of the bridge deck can hardly meet actual needs. At the same time, the mechanical and economic performances of the bridge structure are increasingly sensitive to the selection of the main beam. Especially for large-span cable-stayed bridges, if the deadweight of the main beam structure is too large, it will cause a sharp increase in the axial force of the main beam and cable tower and a decrease in the static buckling stability of the structure.

[0004] Orthotropic steel bridge decks or FRP bridge decks have light structures and high bearing capacity. The use of orthotropic steel bridge decks or FRP bridge decks can reduce the deadweight of the main beam structure. However, the local stiffness of orthotropic steel bridge decks or FRP bridge decks is low. In addition, due to factors such as temperature, heavy load, and overload, they are prone to damage to the pavement layer and fatigue cracking of the bridge deck structure, and cannot meet the quality requirements for the overall stiffness of the bridge deck in rapid prefabrication and assembly construction.

[0005] In the prior art, composite beams are often used to solve the problem of insufficient overall stiffness of the bridge deck. When the steel beam and the concrete bridge deck are connected together with connectors, the two cannot freely slide relative to each other and jointly bear the longitudinal bending moment of the bridge, it is called a composite beam. Due to the advantages of high bridge deck stiffness and good economic performance, composite beams are being widely used in bridge projects at home and abroad.

[0006] However, the concrete deck structure of conventional composite beams is heavy, which is not conducive to improving the mechanical properties of long-span bridges. In addition, the concrete deck of conventional composite beams is prone to cracking and water seepage, which will lead to insufficient durability of the beam structure. The existing composite bridge deck system composed of ordinary concrete and steel panels or FRP panels cannot effectively reduce the deadweight of the structure, and the wet joints connecting different beam sections have low crack resistance, which cannot improve the problem of insufficient compressive stress reserve between different main beam segments.

[0007] Therefore, a construction method is needed that can improve the above problems through segmental prefabricated composite composite plate composite beam structure and meet the quality requirements of rapid prefabrication and assembly construction. Summary of the invention

[0008] The purpose of the present invention is to provide a construction method of a segmental prefabricated composite material composite plate composite beam structure in view of the problems existing in the prior art.

[0009] To achieve the above object, the technical solution adopted by the present invention is:

[0010] A construction method of a segmental prefabricated composite composite plate composite beam structure comprises the following steps:

[0011] S1: processing the bottom plate, web plate, diaphragm, orthotropic top plate and shear connector of the main beam segment in each factory respectively, and welding the processed shear connector to the orthotropic top plate to form an orthotropic composite top plate;

[0012] S2: transporting the processed bottom plate, the web plate and the orthotropic composite top plate to a general assembly plant, and assembling them in sequence from bottom to top in the general assembly plant into the main beam segment;

[0013] S3: the main beam segment is positioned on the tire frame, and then a steel mesh is laid according to the arrangement of the shear connector, so that the steel mesh is inserted into the shear connector. After the steel mesh is laid, an ultra-high toughness fiber reinforced cement-based composite material layer is poured on the orthotropic composite top plate, and the ultra-high toughness fiber reinforced cement-based composite material layer is cured;

[0014] S4: transporting the plurality of main beam segments that have completed the maintenance work from the general assembly plant to the construction site, and completing the work of hoisting, matching, coding, welding and weld inspection of each main beam segment;

[0015] S4.1: The main steps in the hoisting process of the main beam segment are as follows: the main beam segment to be hoisted is set as beam segment No. N, and every four main beam segments are grouped and numbered in sequence from near to far according to the distance from beam segment No. N. First, the transverse wet joint between beam segment No. 3 and beam segment No. 4 far away from beam segment No. N is reinforced, cast with ultra-high toughness fiber reinforced cement-based composite materials and maintained, and then the beam segment No. N is hoisted, and ultra-high performance concrete is cast at the transverse wet joint when the transverse wet joint is in a pre-bent state. After the transverse wet joint is cured, the inclined cable is initially stretched, and the inclined cable is used to apply pre-tightening force to the ultra-high performance concrete at the transverse wet joint;

[0016] S5: The transverse wet joints between the remaining main beam segments are completed in sequence according to the distance from the Nth beam segment from far to near, including steel bar binding, pouring of ultra-high toughness fiber reinforced cement-based composite materials, maintenance, and pouring of ultra-high performance concrete.

[0017] The construction method adopted by the present invention utilizes multiple factories to prefabricate different components of the main beam segment at the same time, thus shortening the construction period. The prefabricated main beam segment is easier to perform standardized operations in the factory, and has a high degree of standardization. During the prefabrication in the factory, CNC equipment can be used for automatic welding, and the size of the weld leg is small, which reduces the adverse thermal impact on the steel bridge deck. The notches on the perforated steel plate can be punched by a punch press through a die, and the punched holes are uniform and fine, the production is convenient, the cost is low, and it is conducive to controlling the construction quality.

[0018] By pre-casting the ultra-high toughness fiber reinforced cement-based composite material layer on the orthotropic composite top plate in the factory and completing the maintenance work of the ultra-high toughness fiber reinforced cement-based composite material layer in the factory, the casting work at the bridge construction site is greatly reduced, and the casting quality of the ultra-high toughness fiber reinforced cement-based composite material layer can be better controlled;

[0019] The transverse wet joints connecting the main beam segments are cast for a second time when they are in a pre-bent state, and the ultra-high performance concrete at the transverse wet joints is pre-tightened by tensioning the inclined cables, so as to improve the crack resistance of the transverse wet joints and thus improve the compressive stress reserve between different main beam segments;

[0020] The main beam segment utilizes the orthotropic top plate to effectively reduce the deadweight of the structure while having good mechanical properties. The ultra-high toughness fiber-reinforced cement-based composite material layer not only participates in the stress of the main beam system as a structural layer, but also greatly improves the fatigue resistance of the orthotropic top plate as a rigid pavement.

[0021] Preferably, the curing method of the ultra-high toughness fiber-reinforced cement-based composite material layer is as follows: after the pouring of the ultra-high toughness fiber-reinforced cement-based composite material layer, it is first stopped for 24 hours, then heat-cured for 72 hours, and finally standard cured for not less than 7 days to complete the curing work.

[0022] Preferably, the curing method of the transverse wet joint is as follows: after pouring the ultra-high toughness fiber reinforced cement-based composite material, the transverse wet joint is first stopped for 24 hours, then heat-cured for 72 hours, and finally standard curing for not less than 14 days is performed to complete the curing work.

[0023] Preferably, the orthotropic top plate is composed of a panel, longitudinal stiffening ribs and transverse partitions, and the longitudinal stiffening ribs are in a closed U-shape, an inverted T-shape or an inverted L-shape.

[0024] Preferably, the shear connectors are arranged in a parallel array along the span direction of the main beam segment, the shear connectors are constructed of embedded reinforcement groove ribs, the shear connectors are embedded in the strength structure layer of ultra-high toughness fiber reinforced cement-based composite materials, and the thickness of the protective layer covering the shear connectors is not less than 10 mm.

[0025] Preferably, the steel mesh is a mesh welded from transverse and longitudinal steel bars or a mesh welded from transverse and longitudinal steel sheets. After the steel mesh is prefabricated, it is integrally inserted into the shear connector to complete the positioning and installation of the steel mesh.

[0026] The shear connector provides support for the steel mesh, making the positioning of the steel mesh more convenient and accurate. The centroid of the steel mesh is biased towards the top edge of the ultra-high toughness fiber reinforced cement-based composite material layer, which can improve the bending and tension performance of the orthogonal anisotropic composite top plate in the horizontal and longitudinal directions of the bridge.

[0027] Preferably, the length of the main beam segment ranges from 14m to 20m, the transverse wet joint is arranged in the middle area of ​​the adjacent transverse partitions of the orthogonal anisotropic top plates of the two main beam segments, and the area ratio of a single transverse wet joint to the ultra-high toughness fiber reinforced cement-based composite material structural layer of a single main beam segment does not exceed 10%.

[0028] Preferably, the ultra-high toughness fiber-reinforced cement-based composite material structural layer of the main beam segment and the transverse wet joint is 40 mm to 100 mm thick.

[0029] Preferably, the material of the orthotropic top plate is high-strength steel or fiber-reinforced composite material, the strength grade of the high-strength steel is not less than 345 MPa, and the strength grade of the fiber-reinforced composite material is not less than 500 MPa.

[0030] Preferably, the strength grade of the ultra-high toughness fiber-reinforced cement-based composite material used for the main beam segment, the orthotropic composite top plate and the transverse wet joint is not less than 120 MPa.

[0031] Compared with the prior art, the present invention has the following beneficial effects:

[0032] (1) The construction method adopted by the present invention utilizes multiple factories to prefabricate different components of the main beam segment at the same time, thereby shortening the construction period. The prefabricated main beam segment is easier to carry out standardized operations in the factory, and has a high degree of standardization. During prefabrication in the factory, CNC equipment can be used for automatic welding. The weld leg size is small, which reduces the adverse thermal impact on the steel bridge deck. The notches on the perforated steel plate can be punched out by a punch press through a mold. The punched holes are uniform and fine, the production is convenient, the cost is low, and it is conducive to controlling the construction quality.

[0033] (2) The construction method adopted by the present invention pre-casts the ultra-high toughness fiber reinforced cement-based composite material layer on the orthotropic composite top plate in the factory, and completes the maintenance work of the ultra-high toughness fiber reinforced cement-based composite material layer in the factory, which greatly reduces the casting work at the bridge construction site and can better control the casting quality of the ultra-high toughness fiber reinforced cement-based composite material layer.

[0034] (3) In the construction method adopted by the present invention, the transverse wet joint connecting the main beam segments is cast for a second time when it is in a pre-bent state, and the inclined cable is used to apply a pre-tightening force to the ultra-high performance concrete at the transverse wet joint, which can improve the crack resistance of the transverse wet joint and thus improve the compressive stress reserve between different main beam segments.

[0035] (4) The main beam segment manufactured by the construction method adopted in the present invention utilizes the orthotropic top plate to effectively reduce the deadweight of the structure while having good mechanical properties. The shear connector provides support for the steel mesh, making the steel mesh convenient and accurate to position. The centroid of the steel mesh is biased toward the top edge of the ultra-high toughness fiber reinforced cement-based composite material layer, which can improve the bending and tensile properties of the orthotropic composite top plate in the transverse and longitudinal directions of the bridge. BRIEF DESCRIPTION OF THE DRAWINGS

[0036] Figure 1 It is a simplified flowchart of the method of the present invention;

[0037] Figure 2 It is a structural schematic diagram of the main beam segment of the present invention;

[0038] Figure 3 It is a structural schematic diagram of the orthotropic composite top plate of the present invention;

[0039] Figure 4 Schematic diagram of the construction method of step S5 in the present invention;

[0040] In the figure: 1. Bottom plate; 2. Web plate; 3. Orthotropic top plate; 4. Ultra-high toughness fiber reinforced cement-based composite material layer; 5. Shear connector; 6. Steel mesh; 7. Transverse wet joint; 8. Lifting equipment. DETAILED DESCRIPTION

[0041] The technical solution of the present invention will be described clearly and completely below in conjunction with the accompanying drawings of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0042] In the description of the present invention, it should be noted that the directions or positional relationships indicated by terms such as "middle", "upper", "lower", "left", "right", "inside" and "outside" are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation on the present invention.

[0043] like Figures 1 to 4As shown, the specific scheme of the embodiment is as follows:

[0044] A construction method of a segmental prefabricated composite composite plate composite beam structure comprises the following steps:

[0045] S1: The bottom plate 1, the web plate 2, the partition plate, the orthotropic top plate 3 and the shear connector 5 of the main beam segment are processed in each factory respectively, and the processed shear connector 5 is welded with the orthotropic top plate 3 to form an orthotropic composite top plate;

[0046] S2: The processed bottom plate 1, web plate 2 and orthotropic composite top plate are transported to the general assembly plant, and are positioned and assembled into main beam segments in the general assembly plant in the order of the bottom plate 1, web plate 2 and orthotropic composite top plate from bottom to top;

[0047] S3: The main beam segment is positioned on the tire frame, and then the steel mesh 6 is laid according to the arrangement of the shear connector 5, so that the steel mesh 6 is inserted into the shear connector 5. After the steel mesh 6 is laid, the ultra-high toughness fiber reinforced cement-based composite material layer 4 is poured on the orthotropic composite top plate, and the ultra-high toughness fiber reinforced cement-based composite material layer 4 is cured;

[0048] S4: transport the multiple girder segments that have completed the maintenance work from the general assembly plant to the bridge site girder hoisting area at the construction site, and complete the hoisting, matching, coding, welding and weld inspection of each girder segment in turn;

[0049] S4.1: The main steps in the main beam segment hoisting process: the main beam segment to be hoisted is set as N# beam segment, and every four main beam segments are grouped and numbered in sequence from near to far according to the distance from the N# beam segment. First, the transverse wet joint 7 between the (N-3)# beam segment and the (N-4)# beam segment far away from the N# beam segment is reinforced with steel bars, poured with ultra-high toughness fiber reinforced cement-based composite materials and maintained. Then the N# beam segment is hoisted, and ultra-high performance concrete is poured at the transverse wet joint 7 when the transverse wet joint 7 is in a pre-bent state. After the transverse wet joint 7 is cured, the inclined cable is initially stretched, and the inclined cable is used to apply pre-tightening force to the ultra-high performance concrete at the transverse wet joint 7;

[0050] S5: The transverse wet joints 7 between the remaining main beam segments are completed in sequence according to the distance from the N# beam segment from far to near, including steel bar binding, pouring of ultra-high toughness fiber reinforced cement-based composite materials, maintenance, and pouring of ultra-high performance concrete.

[0051] Specifically, N# beam section refers to beam section No. N, (N-3)# beam section refers to beam section No. 3, (N-4)# beam section refers to beam section No. 4, (N-1)# beam section, (N-2)# beam section, (N-3)# beam section and (N-4)# beam section are a group. After the construction of one group of main beam sections is completed, the construction of the next group of main beam sections will be carried out until the construction of all main beam sections is completed.

[0052] Specifically, the lifting work of the main beam segments in step S4 refers to lifting each main beam segment to the designed position using the lifting equipment 8. During this process, a temporary consolidated support system and a floating system can be set up to support the lifted main beam segments through temporary supports, or the lifting equipment 8 can be used to limit the movement of the main beam segments while lifting the main beam segments until they are spliced.

[0053] Specifically, the lifting equipment 8 uses a bridge crane.

[0054] Specifically, after the main beam segments in step S4 are hoisted, it is necessary to set a cable for each main beam segment. The cable is the main load-bearing component of the cable-stayed bridge. The lifting tools and equipment used in the construction are used to lift the cable that has been manufactured in the early stage and effectively connect it with the anchor structure on the main tower and the main beam. In addition, in some cases, it is also possible to tension and anchor it after passing through the reserved holes of the main tower and the main beam. After the cable is passed through, a tensioning connecting rod and a tensioning jack should be installed on the anchor head at the cable end, and then the operation of tensioning the cable can be implemented.

[0055] Specifically, the matching work of the main beam segments in step S4 refers to matching and positioning the main beam segments that are about to be spliced ​​together, ensuring that each main beam segment is in the correct installation position, and preventing the main beam segments from being misaligned during the splicing process, which seriously affects the quality of the project.

[0056] Specifically, the welding work and weld inspection work of the main beam segments in step S4 refers to welding the steel structures of the adjacent installed main beam segments together and inspecting the welds after welding.

[0057] Specifically, the curing method of the ultra-high toughness fiber reinforced cement-based composite material layer 4 is as follows: after the pouring of the ultra-high toughness fiber reinforced cement-based composite material layer 4 is completed, it is first stopped for 24 hours, then heat-cured for 72 hours, and finally standard cured for no less than 7 days to complete the curing work.

[0058] Specifically, the curing method of the transverse wet joint 7 is as follows: after pouring the ultra-high toughness fiber-reinforced cement-based composite material, the transverse wet joint 7 is first stopped for 24 hours, then heat-cured for 72 hours, and finally standard cured for no less than 14 days to complete the curing work.

[0059] Specifically, the orthotropic top plate 3 is composed of a panel, longitudinal stiffening ribs and transverse partitions, and the longitudinal stiffening ribs are in a closed U shape, an inverted T shape or an inverted L shape.

[0060] Specifically, the shear connector 5 is connected to the orthotropic top plate 3 through double-sided fillet welds. When prefabricated in the factory, CNC equipment can be used for automatic welding, and the weld leg size is small, which reduces the adverse thermal impact on the orthotropic top plate 3. The notches on the perforated steel plate can be punched through a die by a punch press, and the punched holes are uniform and fine, the production is convenient, and the cost is low.

[0061] Specifically, the shear connectors 5 are arranged in a parallel array along the span direction of the main beam segment. The shear connectors 5 are constructed of reinforced groove ribs. The length direction of a single shear connector 5 is perpendicular to the span direction of the main beam segment. The shear connectors 5 are buried in the strength structure layer of the ultra-high toughness fiber reinforced cement-based composite material, and the thickness of the protective layer covering the shear connectors 5 is 15 mm.

[0062] Specifically, the shear connector 5 is made of the same material as the orthotropic top plate 3, and gaps are set between adjacent shear connectors 5 to ensure connectivity during casting of the ultra-high toughness fiber reinforced cement-based composite material structural layer and improve the installation deviation problem of the shear connector 5.

[0063] Specifically, the steel mesh 6 is a mesh welded by horizontal and vertical steel bars or a mesh welded by horizontal and vertical steel sheets. After the steel mesh 6 is prefabricated, it is integrally inserted into the shear connector 5 to complete the positioning and installation of the steel mesh 6.

[0064] Specifically, the shear connector 5 provides support for the steel mesh 6, making the positioning of the steel mesh 6 more convenient and accurate. The centroid of the steel mesh 6 is biased towards the top edge of the ultra-high toughness fiber reinforced cement-based composite material structure layer, which can improve the bending and tension performance of the orthogonal anisotropic composite top plate in the horizontal and longitudinal directions of the bridge.

[0065] Specifically, the length of the main beam segment is 16m, the transverse wet joint 7 is arranged in the middle area of ​​the adjacent transverse partitions of the orthogonal anisotropic top plates 3 of the two main beam segments, and the area ratio of a single transverse wet joint 7 to the ultra-high toughness fiber reinforced cement-based composite material structural layer of a single main beam segment does not exceed 10%.

[0066] Specifically, when adjacent main beam segments are spliced, the shear connector 5 embedded in the ultra-high toughness fiber reinforced cement-based composite material structural layer passes under the transverse wet joint 7 .

[0067] Specifically, the ultra-high toughness fiber reinforced cement-based composite material structure layer of the main beam segment and the transverse wet joint 7 is 80 mm thick.

[0068] Specifically, the material of the orthotropic top plate 3 is high-strength steel or fiber-reinforced composite material, the strength grade of the high-strength steel is not less than 345 MPa, and the strength grade of the fiber-reinforced composite material is not less than 500 MPa.

[0069] Specifically, the strength grade of the ultra-high toughness fiber-reinforced cement-based composite material used in the main beam segment, the orthotropic composite top plate and the transverse wet joint 7 is not less than 120 MPa.

[0070] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A construction method for a segmental prefabricated composite composite plate composite beam structure, It is characterized in that The following steps are involved: S1: processing the bottom plate, web plate, diaphragm, orthotropic top plate and shear connector of the main beam segment in each factory respectively, and welding the processed shear connector to the orthotropic top plate to form an orthotropic composite top plate; S2: transporting the processed bottom plate, the web plate and the orthotropic composite top plate to a general assembly plant, and assembling them in sequence from bottom to top in the general assembly plant into the main beam segment; S3: the main beam segment is positioned on the tire frame, and then a steel mesh is laid according to the arrangement of the shear connector, so that the steel mesh is inserted into the shear connector. After the steel mesh is laid, an ultra-high toughness fiber reinforced cement-based composite material layer is poured on the orthotropic composite top plate, and the ultra-high toughness fiber reinforced cement-based composite material layer is cured; S4: transporting the plurality of main beam segments that have completed the maintenance work from the general assembly plant to the construction site, and completing the work of hoisting, matching, coding, welding and weld inspection of each main beam segment; S4.1: The main steps in the hoisting process of the main beam segment are as follows: the main beam segment to be hoisted is set as beam segment No. N, and every four main beam segments are grouped and numbered in sequence from near to far according to the distance from beam segment No. N. First, the transverse wet joint between beam segment No. 3 and beam segment No. 4 far away from beam segment No. N is reinforced, cast with ultra-high toughness fiber reinforced cement-based composite materials and maintained, and then the beam segment No. N is hoisted, and ultra-high performance concrete is cast at the transverse wet joint when the transverse wet joint is in a pre-bent state. After the transverse wet joint is cured, the inclined cable is initially stretched, and the inclined cable is used to apply pre-tightening force to the ultra-high performance concrete at the transverse wet joint; S5: The transverse wet joints between the remaining main beam segments are sequentially completed with the work of steel bar binding, pouring ultra-high toughness fiber reinforced cement-based composite materials, curing, and pouring ultra-high performance concrete according to the distance from the Nth beam segment from far to near; The shear connectors are arranged in a parallel array along the span direction of the main beam segment, the shear connectors are constructed of embedded reinforcement notch ribs, and the shear connectors are embedded in the strength structure layer of the ultra-high toughness fiber-reinforced cement-based composite material; The steel mesh is a mesh welded from transverse and longitudinal steel bars or a mesh welded from transverse and longitudinal steel sheets. After the steel mesh is prefabricated, it is integrally inserted into the shear connector to complete the positioning and installation of the steel mesh.

2. The construction method of a segmental prefabricated composite composite plate composite beam structure according to claim 1, Features: The curing method of the ultra-high toughness fiber-reinforced cement-based composite material layer is as follows: after the pouring of the ultra-high toughness fiber-reinforced cement-based composite material layer, the ultra-high toughness fiber-reinforced cement-based composite material layer is first stopped for 24 hours, then heat-cured for 72 hours, and finally standard cured for no less than 7 days to complete the curing work.

3. The construction method of a segmental prefabricated composite composite plate composite beam structure according to claim 1, Features: The curing method of the transverse wet joint is as follows: after pouring the ultra-high toughness fiber-reinforced cement-based composite material, the transverse wet joint is first stopped for 24 hours, then heat-cured for 72 hours, and finally standard curing for not less than 14 days is performed to complete the curing work.

4. The construction method of a segmental prefabricated composite composite plate composite beam structure according to claim 1, Features: The orthotropic plate is composed of a panel, longitudinal stiffening ribs and a transverse partition, and the longitudinal stiffening ribs are in a closed U shape, an inverted T shape or an inverted L shape.

5. The construction method of a segmental prefabricated composite composite plate composite beam structure according to claim 1, Features: The thickness of the protective layer covering the shear connector is not less than 10 mm.

6. The construction method of a segmental prefabricated composite composite plate composite beam structure according to claim 1, Features: The length of the main beam segment ranges from 14m to 20m, and the transverse wet joint is arranged in the middle area of ​​the adjacent transverse partitions of the orthogonal anisotropic top plates of the two main beam segments. The area ratio of a single transverse wet joint to the ultra-high toughness fiber-reinforced cement-based composite material structural layer of a single main beam segment does not exceed 10%.

7. The construction method of a segmental prefabricated composite composite plate composite beam structure according to claim 1, Features: The thickness of the ultra-high toughness fiber-reinforced cement-based composite material structure layer of the main beam segment and the transverse wet joint is 40 mm to 100 mm.

8. The construction method of a segmental prefabricated composite composite plate composite beam structure according to claim 1, Features: The material of the orthotropic plate is high-strength steel or fiber-reinforced composite material. The strength grade of the high-strength steel is not less than 345 MPa, and the strength grade of the fiber-reinforced composite material is not less than 500 MPa.

9. The construction method of a segmental prefabricated composite composite plate composite beam structure according to claim 1, Features: The strength grade of the ultra-high toughness fiber-reinforced cement-based composite material used in the main beam segment, the orthotropic composite top plate and the transverse wet joint is not less than 120 MPa.