An ultra-heavy-load high-formwork support system

By designing support units and diagonal brace components arranged in a rectangular array in the heavy ion device area, the problems of high material consumption and low installation efficiency of the high support formwork system were solved, and efficient concrete pouring and construction efficiency were improved.

CN115839171BActive Publication Date: 2024-10-01CSCEC STRAIT CONSTR & DEV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202211308256.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-10-25
Publication Date
2024-10-01
Estimated Expiration
2042-10-25

AI Technical Summary

Technical Problem

The existing high-support formwork system in the heavy ion device area consumes a large amount of materials, has low installation and disassembly efficiency, and has low construction efficiency, which affects traffic and material transportation.

Method used

Design an ultra-heavy load high formwork support system, using support units arranged in a rectangular array, including vertically connected support standard sections, limit connectors, top wall connectors and diagonal brace components. Through the first and second transition The panels provide attachment points, reduce welding and drilling, increase structural strength and efficiency, and utilize diagonal braces and collapsible top wall connectors for enhanced stability and ease of transportation.

Benefits of technology

It reduces the amount of steel material, improves the efficiency of installation and disassembly, and enhances the stability and construction efficiency of the support system. It is suitable for tall and thick concrete pouring in the heavy ion device area to ensure smooth construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115839171B_ABST
    Figure CN115839171B_ABST
Patent Text Reader

Abstract

The present invention relates to an ultra-heavy-load high-support formwork support system, which belongs to the field of building construction technology, and includes a plurality of support units arranged in a heavy ion device area and arranged in a rectangular array, each support unit includes a plurality of support standard sections vertically connected in sequence from bottom to top, and a plurality of limit connectors are fixedly connected between any two adjacent support units, and each support unit close to the inner wall of the heavy ion device area is connected to the inner wall of the heavy ion device area by a top wall connector; the top of each support unit arranged in the longitudinal direction is connected to a top beam assembly, and each support unit is provided with a diagonal brace assembly between the topmost support standard section and the top beam assembly; a distribution beam assembly is laid on the top of each top beam assembly, and the distribution beam assembly includes a plurality of distribution beam bodies arranged horizontally and perpendicularly to the top beam body, and a formwork support assembly is installed on the top of the distribution beam body. The present invention has good stability, low material consumption, and is convenient and quick to install.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to an ultra-heavy-load high-formwork supporting system, belonging to the technical field of building construction. Background Art

[0002] The heavy ion device area has high radiation resistance requirements, a large spatial span, and strong enclosure; the heavy ion device area has a large structural plane size and a thick structure. The thickness of some inner and outer walls can reach 3.9m-4.3m, and the top plate thickness can reach 3.5m. The top plate weight reaches more than 3,000 tons, requiring large-volume concrete pouring in multiple areas; at the same time, the heavy ion device area has a strong spatial enclosure, and the maximum clearance height of the heavy ion device area is 23m, involving an ultra-high large formwork system.

[0003] At present, full-height steel pipe support scaffolding is commonly used in high-support formwork systems. If a full-height scaffolding is used in the heavy ion device area, the distance between the scaffolding poles needs to be shortened to improve the overall rigidity of the frame. However, this will also lead to labor and material consumption in the scaffolding erection, and the distance between the scaffoldings is too close during the construction process, which affects the passage. Moreover, after the construction of the heavy ion device area is completed, the only exit for materials is the hole located at a certain height from the bottom plate. Therefore, the conditions on the construction site are limited, and the conditions for the entry and exit of machinery and tools are restricted. If conventional steel pipe support scaffolding is used, it will not only be difficult to transport materials, but also inconvenient to disassemble, the construction volume is large, and the construction efficiency is low.

[0004] A large-volume raft foundation reinforcement construction support device disclosed in the Chinese utility model patent with publication number CN217204910U, a support frame, the support frame includes a combined fixing rod and a plurality of vertical and rectangularly arranged upright poles; a fixed pad block is arranged at the bottom end of the upright pole, the fixed pad block includes a fixed block, a sleeve through hole is arranged in the middle of the top of the fixed block, and rotating rods threadedly connected to the fixed block are arranged on both sides of the fixed block, the connecting end of the rotating rod passes through the fixed block and extends into the sleeve through hole and the end is rotatably connected with an arc-shaped clamping plate; hinge grooves are arranged at both ends of the sleeve through hole, L-shaped hinged rods are hinged in the two hinge grooves, the free end of the L-shaped hinged rod is upward and an arc-shaped clamping groove is arranged at the end, and at least two connecting springs are arranged between the two L-shaped hinged rods.

[0005] The above reference example has good support stability, but the supports are densely distributed horizontally and vertically in the entire construction area, which greatly affects traffic, and is difficult to install and disassemble, with low construction efficiency, so it is urgently needed to be improved. Summary of the invention

[0006] In order to overcome the shortcomings of the existing high-support formwork system, such as large amount of material consumption in erection and low efficiency in installation and disassembly, the present invention designs an ultra-heavy-load high-support formwork support system, which has good stability, low material consumption, and convenient and quick installation and disassembly.

[0007] In order to achieve the above object, the present invention adopts the following technical solution:

[0008] A super-heavy-load high-support formwork support system includes a plurality of support units arranged in a heavy ion device area and in a rectangular array, each of the support units includes a plurality of support standard sections vertically connected in sequence from bottom to top, a plurality of limit connectors are fixedly connected between any two adjacent support units, and a top wall connector is connected between each of the support units close to the inner wall of the heavy ion device area and the inner wall of the heavy ion device area; the top ends of the support units arranged in the longitudinal direction are connected to a top beam assembly, and a diagonal brace assembly is arranged between the support standard section arranged at the top end of each support unit and the top beam assembly, the top beam assembly includes at least two top beam bodies parallel to each other, and a plurality of support fixings are fixed in sequence between any two adjacent top beam bodies along the length direction of the top beam body; a distribution beam assembly is laid on the top end of each top beam assembly, the distribution beam assembly includes a plurality of distribution beam bodies arranged horizontally and perpendicularly to the top beam body, a template support assembly is installed on the top end of the distribution beam body, the template support assembly includes a disc buckle frame, a top support and a main rib connected in sequence from bottom to top, and a template body is arranged on the top end of the main rib.

[0009] Furthermore, the limiting connector and the top wall connector are both connected to the supporting standard section through a first transition plate, the first transition plate is arranged between two adjacent supporting standard sections above and below, and the first transition plate is connected to each main chord of the supporting standard section; the first transition plate includes a first bonding plate and a first L-shaped support plate, the first L-shaped support plate is vertically fixed to the bottom end of the first bonding plate and one side is bonded to the main chord of the supporting standard section, the first transition plate is provided with a matching fixing hole corresponding to the connecting sleeve on the main chord, both ends of the first L-shaped support plate are vertically fixedly connected to the first reinforcing plate on one side away from the main chord, and the top end of the first reinforcing plate is fixedly connected to the first bonding plate.

[0010] Furthermore, a second transition plate is provided at the top of the supporting standard section at the uppermost end of each supporting unit, and the second transition plate is connected to the top of each main chord of the supporting standard section, the second transition plate includes a second bonding plate and a second L-shaped support plate, the second L-shaped support plate is vertically fixed to the bottom end of the second bonding plate and one side is bonded to the main chord, a positioning screw corresponding to the connecting sleeve on the main chord is also fixed to the bottom end of the second bonding plate, the positioning screws are inserted into the connecting sleeve one by one, the second L-shaped support plate is vertically fixedly connected to the side away from the main chord at both ends of the second L-shaped support plate, and the top end of the second reinforcement plate is fixedly connected to the second bonding plate; an L-shaped pressure plate for pressing the top beam body of the top end of the supporting unit is detachably fixed to the top end of the second transition plate, a plug-in screw hole is provided at the top end of the L-shaped pressure plate, and a fixing screw hole matching the plug-in screw hole is provided on the second bonding plate.

[0011] Furthermore, one end of the diagonal brace assembly is connected to the first transition plate, and the other end is connected to the bottom end of the top beam body; the diagonal brace assembly includes a diagonal brace rod, both ends of the diagonal brace rod are provided with sliding cavities, a sliding sleeve rod is sleeved in the sliding cavity, one end of the sliding sleeve rod is fixedly connected to a connecting support plate after extending out of the sliding cavity, a return spring is connected between one end of the sliding sleeve rod located inside the sliding cavity and the inner end of the sliding cavity, and a shock-absorbing energy-absorbing block is provided inside the rod body of the sliding sleeve rod located in the sliding cavity, and travel grooves extending to the outer side wall of the sliding sleeve rod are symmetrically provided on both sides of the shock-absorbing energy-absorbing block, an energy-absorbing screw is provided on the side of the diagonal brace rod, the energy-absorbing screw penetrates the side wall of the diagonal brace rod, the travel groove and the shock-absorbing energy-absorbing block, and both ends of the energy-absorbing screw are locked with energy-absorbing nuts after extending out of the diagonal brace rod.

[0012] Furthermore, one end of the top wall connecting member is connected to the first transition plate, and the other end is arranged in contact with the inner wall of the heavy ion device area 200; the top wall connecting member includes a first folding rod and a second folding rod whose ends are opposite to each other, the second folding rod is connected to a top wall plate on a side away from the first folding rod, the first folding rod is fixedly connected to a first hinge block at the bottom near one end of the second folding rod, and the second folding rod is fixedly connected to a second hinge block at the bottom near one end of the first folding rod, the first hinge block and the second hinge block are hinged to each other, and an arc guide groove is provided on the first hinge block, a sliding hinge rod is slidably connected in the arc guide groove, the free end of the sliding hinge rod is hinged to a swing hinge rod, the free end of the swing hinge rod is hinged to the second hinge block, the middle part of the sliding hinge rod is hinged to a hinge connecting rod, and the free end of the hinge connecting rod is hinged to a side of the first hinge block close to the second hinge block.

[0013] Furthermore, a limited sleeve hole is provided at the free end of the second folding rod, and a sleeve rod is fixed on one side of the top wall plate, the sleeve rod is slidably sleeved in the limited sleeve hole, and a pair of sliding blocks are symmetrically fixed to the side of the sleeve rod, and a pair of limited sliding grooves adapted to the sliding block are symmetrically provided on the inner wall of the limited sleeve hole, and the limiting sliding groove is connected with a rotating slot at one end close to the top wall plate, and the sliding block is movably arranged in the rotating slot, and a rotating receiving groove adapted to the width of the sliding block is also provided at the top end of the free end of the second folding rod, and one end of the rotating receiving groove extends to the free end of the second folding rod, and the rotating receiving groove is connected with the limited sleeve hole.

[0014] Furthermore, a level is provided at the top of each of the first folding rod and the second folding rod.

[0015] Furthermore, a plurality of pre-embedded fixings embedded in the ground are provided at the bottom end of each support unit, and each pre-embedded fixing is detachably connected to a main chord of each support standard section in a one-to-one correspondence.

[0016] Furthermore, starting from the third support standard section from the bottom to the top, the limiting connector is arranged between each adjacent support standard section; starting from the third support standard section from the bottom to the top, a top wall connector is connected between each support unit close to the inner wall of the heavy ion device area and the inner wall of the heavy ion device area.

[0017] Furthermore, the supporting fixings, the limiting connecting pieces, the distribution beam body and the diagonal bracing rods are all channel steels, and the top beam body is an I-beam.

[0018] Compared with the prior art, the present invention has the following characteristics and beneficial effects:

[0019] 1. The present invention reduces the use of steel materials and labor installation costs while meeting the requirements of supporting tall and thick concrete formwork through the arrangement of various support units, improves installation and construction efficiency and safety of use, and ensures smooth concrete pouring construction. In addition, the support units are arranged in a rectangular array, with a certain amount of space left between the support units to facilitate the transportation or storage of materials. The present invention is suitable for the construction of the heavy ion device area 200, and installation and disassembly are more convenient.

[0020] 2. The present invention uses the first transition plate and the second transition plate as the connection points of the limit connectors between the support standard sections and the top wall connectors between the support standard sections and the wall, so that the support standard sections will not be damaged by welding or drilling and bolting, thereby improving the service turnover rate of the support standard sections, improving the structural strength and rigidity of the support standard sections in the high formwork support system, and improving the service efficiency of the support standard sections, broadening the use of the support standard sections, and ensuring the smooth progress of concrete pouring construction. In addition, through the provision of the first L-shaped support plate and the second L-shaped support plate, the main chord of the support standard section can be conveniently pressed against, and no additional positioning and installation is required. The installation is convenient, fast, time-saving and labor-saving. The provision of the first reinforcement plate and the second reinforcement plate increases the connectable points of the connector, and also enhances the structural strength of the transition plate.

[0021] 3. The present invention improves the support stability of the top beam body by setting the diagonal bracing rods and selecting channel steel or energy-absorbing structure. The diagonal bracing rods are made of I-beam materials, which are simple and easy to obtain and suitable for popularization and use. The setting of the energy-absorbing structure improves the energy-absorbing and shock-absorbing capacity of the support system and ensures the stability of the support system.

[0022] 4. The present invention utilizes the setting of the top and wall connectors, and channel steel or a foldable structure can be selected to ensure the lateral support of the support system, so that each support unit forms a whole to firmly support the wall, thereby ensuring safety and stability. The top and wall connectors are made of I-beam materials, which are simple and easy to obtain and suitable for popularization and use. The top and wall connectors are made of foldable structures for easy storage. After storage, the occupied space is reduced, which is convenient for transportation and assembly, ensuring construction efficiency. At the same time, through the setting of the top and wall panels, the contact area between the top and wall connectors and the wall is increased to prevent damage to the wall. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 is a schematic diagram of overall support of Embodiment 1 of the present invention;

[0024] Figure 2 It is a schematic diagram of the partial connection between the first embodiment of the present invention and the inner wall of the heavy ion device area;

[0025] Figure 3 It is a partial side view of the connection between the support unit and the top beam assembly in the first embodiment of the present invention;

[0026] Figure 4 It is a partial front view connection diagram of a support unit, a top beam assembly and a formwork support assembly in accordance with a first embodiment of the present invention;

[0027] Figure 5 This is a schematic diagram of the main structure of the first transition plate of the first embodiment of the present invention;

[0028] Figure 6 is a bottom view structural schematic diagram of a first transition plate in a first embodiment of the present invention;

[0029] Figure 7 This is a schematic diagram of the main structure of the second transition plate of the first embodiment of the present invention;

[0030] Figure 8 is a bottom view structural schematic diagram of the second transition plate of the first embodiment of the present invention;

[0031] Fig. 9 is a schematic diagram of the connection between the second transition plate and the top beam body in the first embodiment of the present invention;

[0032] Fig.10 yes Figure 2 A local enlarged schematic diagram of point A;

[0033] Fig.11 is a structural schematic diagram of the diagonal bracing assembly in the second embodiment of the present invention;

[0034] Fig.12 is a partial cross-sectional schematic diagram of the diagonal brace assembly in the second embodiment of the present invention;

[0035] Fig.13is a schematic diagram of the connection between the top wall connector and the inner wall of the heavy ion device area in the third embodiment of the present invention;

[0036] Fig.14 yes Fig.13 A local enlarged schematic diagram of point B.

[0037] The figures are marked as follows: 100, support unit; 200, heavy ion device area; 2001, channel opening; 1, support standard section; 101, connecting sleeve; 102, main chord; 2, limit connector; 4, diagonal support rod; 401, sliding sleeve rod; 402, connecting support plate; 403, sliding cavity; 404, travel groove; 405, shock-absorbing energy-absorbing block; 406, return spring; 407, energy-absorbing screw; 408, energy-absorbing nut; 5, top beam body; 6, first transition plate; 601, first bonding plate; 602, first reinforcement plate; 603, first L-shaped support plate; 606, matching fixing hole; 7, L-shaped pressure plate; 701, plug-in screw hole; 8, top wall connector; 801, first folding rod; 802, The second folding rod; 8021, the limiting sleeve hole; 8022, the limiting slide groove; 8023, the rotating storage groove; 8024, the rotating card slot; 803, the level; 804, the first hinge block; 805, the second hinge block; 806, the arc guide groove; 807, the swing hinge rod; 808, the sliding hinge rod; 809, the hinge connecting rod; 10, the second transition plate; 1001, the second bonding plate; 1002, the second reinforcement plate; 1003, the second L-shaped support plate; 1004, the positioning screw; 1005, the fixing screw hole; 11, the supporting fixture; 12, the distribution beam body; 13, the template supporting assembly; 14, the embedded fixture; 15, the top wall plate; 1501, the sleeve rod; 1502, the sliding card block. DETAILED DESCRIPTION

[0038] The present invention is described in more detail below with reference to the embodiments.

[0039] A super-heavy-load high-support formwork support system includes a plurality of support units 100 arranged in a heavy ion device area 200 and arranged in a rectangular array, each support unit 100 includes a plurality of support standard sections 1 vertically connected in sequence from bottom to top, a plurality of position-limiting connectors 2 are fixedly connected between any two adjacent support units 100, each support unit 100 close to the inner wall of the heavy ion device area 200 is connected to the inner wall of the heavy ion device area 200 by a top wall connector 8; the top of each support unit 100 arranged in the longitudinal direction is connected to a top beam assembly, and each support unit 100 is provided with A diagonal brace assembly is arranged between the topmost supporting standard section 1 and the top beam assembly. The top beam assembly includes at least two top beam bodies 5 parallel to each other. A number of supporting fixings 11 are fixed in sequence between any two adjacent top beam bodies 5 along the length direction of the top beam bodies 5. A distribution beam assembly is laid on the top of each top beam assembly. The distribution beam assembly includes a number of distribution beam bodies 12 arranged horizontally and perpendicularly to the top beam body 5. A formwork support assembly 13 is installed on the top of the distribution beam body 12. The formwork support assembly 13 includes a disc buckle frame, a top support and a main rib connected in sequence from bottom to top, and a formwork body is arranged on the top of the main rib.

[0040] From the above description, it can be seen that the beneficial effects of the present invention are as follows: the present invention sets a plurality of support units 100, selects a support standard section 1 as the basic support member of the entire support system, and is easy to splice and install, and the support standard section 1 can be turned over, which greatly improves the utilization rate of materials. While meeting the requirements of high and thick concrete formwork support, it reduces the amount of steel materials used, reduces the cost of manual installation and disassembly, improves the efficiency of installation and disassembly construction and safety of use, and ensures smooth concrete pouring construction. At the same time, by arranging a plurality of support units 100 in the form of a rectangular array, a certain gap is left between each support unit 100, which can facilitate the transfer and transportation of construction materials, and is more convenient to install and disassemble, and is more suitable for heavy ion device area 200 with only one channel opening 2 During the pouring construction of 001 materials entering and exiting, the stability between two adjacent support units 100 is strengthened by setting the limit connector 2 to prevent tipping over. The stability of each support unit 100 is further strengthened by setting the top wall connector 8. The inner wall of the heavy ion device area 200 is used as support to ensure support stability when the support unit 100 is at a high height. The diagonal brace assembly improves the connection stability between the top support standard section 1 and the top beam body 5, and can effectively prevent the top beam body 5 from shifting, ensuring the installation of the subsequent formwork support assembly 13 and the formwork, and ensuring stability and safety during pouring. The support fixing member 11 is connected to the top beam body 5 of the top beam assembly to prevent the top beam body 5 from shifting while increasing the stability of the structure.

[0041] Furthermore, the limiting connector 2 and the top wall connector 8 are both connected to the supporting standard section 1 through a first transition plate 6, the first transition plate 6 is arranged between two adjacent supporting standard sections 1 above and below, and each main chord 102 of the supporting standard section 1 is connected with the first transition plate 6; the first transition plate 6 includes a first bonding plate 601 and a first L-shaped support plate 603, the first L-shaped support plate 603 is vertically fixed to the bottom end of the first bonding plate 601 and one side is bonded to the main chord 102 of the supporting standard section 1, the first transition plate 6 is provided with a matching fixing hole 606 corresponding to the connecting sleeve 101 on the main chord 102, both ends of the first L-shaped support plate 603 are vertically fixedly connected to the side away from the main chord 102 with the first reinforcing plate 602, and the top end of the first reinforcing plate 602 is fixedly connected to the first bonding plate 601.

[0042] It can be seen from the above description that through the setting of the first transition plate 6, installation points are provided for the limit connector 2, the top wall connector 8 and the diagonal brace assembly. There is no need to fix the limit connector 2, the top wall connector 8 and the diagonal brace assembly to the supporting standard section 1 by welding or bolt punching, etc., so as to avoid damage to the structure of the supporting standard section 1 itself, improve the turnover rate of the supporting standard section 1, and reduce the installation cost. The setting of the fixing hole 606 is convenient for detachable installation with the installation hole on the main chord 102 of the supporting standard section 1 itself. The setting of the first L-shaped support plate 603 is convenient for abutting against the main chord 102 during installation, which is convenient for positioning and improving installation efficiency. The setting of the first reinforcing plate 602 strengthens the supporting structure of the first transition plate 6, and at the same time provides additional connection points, which is convenient for the connection of the limit connector 2, the top wall connector 8 and the diagonal brace assembly.

[0043] Furthermore, the top of the supporting standard section 1 at the uppermost end of each supporting unit 100 is provided with a second transition plate 10, and the top of each main chord 102 of the supporting standard section 1 is connected with the second transition plate 10, the second transition plate 10 includes a second bonding plate 1001 and a second L-shaped support plate 1003, the second L-shaped support plate 1003 is vertically fixed to the bottom end of the second bonding plate 1001 and one side thereof is bonded to the main chord 102, and the bottom end of the second bonding plate 1001 is also fixed with a positioning screw 1004 corresponding to the connecting sleeve 101 on the main chord 102, and the positioning screw 1004 is fixed to the bottom end of the second bonding plate 1001. The screw rods 1004 are inserted into the connecting sleeve 101 in a one-to-one correspondence, and the second reinforcing plates 1002 are vertically fixedly connected to the sides of the second L-shaped support plates 1003 away from the main chord 102 at both ends, and the top of the second reinforcing plate 1002 is fixedly connected to the second bonding plate 1001; the top of the second transition plate 10 is detachably fixed with an L-shaped pressing plate 7 for pressing the top beam body 5 at the top of the supporting unit 100, and the top of the L-shaped pressing plate 7 is provided with a plug-in screw hole 701, and the second bonding plate 1001 is provided with a fixing screw hole 1005 matching the plug-in screw hole 701.

[0044] From the above description, it can be known that the second transition plate 10 is closely connected to the top beam body 5, which can effectively prevent the top beam body 5 from wearing the supporting standard section 1 and reduce the loss rate of the supporting standard section 1. The positioning screw 1004 is inserted into the main chord 102, which is convenient for installation and positioning. After the positioning screw 1004 passes through the main chord 102, it can be locked by a nut, which is convenient for disassembly and assembly. The setting of the second L-shaped support plate 1003 is convenient for it to be close to the main chord 102 during installation, thereby improving the positioning efficiency. The setting of the second reinforcement plate 1002 increases the strength of the second transition plate 10, and also provides an additional connection point for the connection of the upper end of the diagonal bracing assembly, which is convenient for connection. The connection position can be controlled as needed to ensure the support strength. The setting of the L-shaped pressure plate 7 facilitates the pressing and fixing of the top beam body 5, which prevents the top beam body 5 from deflecting and increases the structural connection strength.

[0045] Furthermore, one end of the diagonal brace assembly is connected to the first transition plate 6, and the other end is connected to the bottom end of the top beam body 5; the diagonal brace assembly includes a diagonal brace rod 4, both ends of the diagonal brace rod 4 are provided with a sliding cavity 403, a sliding sleeve rod 401 is sleeved in the sliding cavity 403, one end of the sliding sleeve rod 401 extends out of the sliding cavity 403 and is fixedly connected to the connecting support plate 402, and a return spring 4 is connected between one end of the sliding sleeve rod 401 located inside the sliding cavity 403 and the inner end of the sliding cavity 403 06, and a shock-absorbing energy-absorbing block 405 is arranged inside the rod body of the sliding sleeve 401 located in the sliding cavity 403, and travel grooves 404 extending to the outer wall of the sliding sleeve 401 are symmetrically arranged on both sides of the shock-absorbing energy-absorbing block 405, and an energy-absorbing screw 407 is arranged on the side of the diagonal support rod 4, and the energy-absorbing screw 407 penetrates the side wall of the diagonal support rod 4, the travel groove 404 and the shock-absorbing energy-absorbing block 405, and both ends of the energy-absorbing screw 407 are locked with energy-absorbing nuts 408 after extending out of the diagonal support rod 4.

[0046] As can be seen from the above description, during the pouring of the top layer of concrete, the top beam body 5 will be subjected to stress, which may sometimes cause relatively severe vibrations. The top beam body 5 plays the role of main support through the support unit 100, and the diagonal support assembly plays the role of auxiliary support to prevent the position between the top beam body 5 from being subjected to excessive stress and causing breakage. At the same time, through the setting of the sliding sleeve rod 401 that is slidably sleeved at both ends of the diagonal support rod 4, when the diagonal support assembly is vibrated, the sliding sleeve rod 401 can slide in the sliding cavity 403 inside the diagonal support rod 4, thereby causing relative movement between the shock-absorbing energy-absorbing block 405 and the energy-absorbing screw 407 to achieve energy consumption, thereby preventing the vibration from causing loosening of the connecting bolts and ensuring the stability of the overall supporting body. At the same time, through the setting of the return spring 406, the sliding sleeve rod 401 can be returned to its original position within a certain range, so that the connecting support plate 402 continues to press against the top beam body 5, ensuring that it can stably and continuously withstand vibration and achieve a good supporting effect.

[0047] Furthermore, one end of the top wall connector 8 is connected to the first transition plate 6, and the other end is arranged in contact with the inner wall of the heavy ion device area 200; the top wall connector 8 includes a first folding rod 801 and a second folding rod 802 whose ends are opposite to each other, and the second folding rod 802 is connected to the top wall plate 15 on the side away from the first folding rod 801, and the first folding rod 801 is fixedly connected to the bottom of the second folding rod 802 near the end of the first folding rod 801 with a first hinge block 804, and the second folding rod 802 is fixedly connected to the bottom of the first folding rod 801 near the end of the first folding rod 801 with a second hinge block 804. The connecting block 805, the first hinge block 804 and the second hinge block 805 are hinged to each other, and an arc guide groove 806 is provided on the first hinge block 804, a sliding hinge rod 808 is slidably connected in the arc guide groove 806, the free end of the sliding hinge rod 808 is hinged to a swing hinge rod 807, the free end of the swing hinge rod 807 is hinged to the second hinge block 805, a hinge connecting rod 809 is hinged to the middle part of the sliding hinge rod 808, and the free end of the hinge connecting rod 809 is hinged to a side of the first hinge block 804 close to the second hinge block 805.

[0048] As can be seen from the above description, the top wall connector 8 is used to form a supporting connection between each support unit 100 close to the inner wall of the heavy ion device area 200 and the wall, further ensuring the supporting stability of each support unit 100 and preventing it from tipping over. The top wall connector 8 is abutted against the top by the first folding rod 801 and the second folding rod 802, and the first hinge block 804 and the second hinge block 805 make the first folding rod 801 and the second folding rod 802 hinged to each other, so that the first folding rod 801 and the second folding rod 802 can be stored before installation or after disassembly, which is convenient for disassembly and transportation. It is suitable for the relatively narrow working space of the heavy ion device area 200, which improves the applicability. At the same time, the swing hinge rod 807, the sliding hinge rod 808, the hinge connecting rod 809 and the arc guide groove 806 set on the first hinge block 804 are used to realize the locking and fixation of the first folding rod 801 and the second folding rod 802. When the swing hinge rod 8 07. When the sliding hinge rod 808 and the hinge connecting rod 809 are not in a straight line, the first hinge block 804 and the second hinge block 805 cannot rotate due to the limiting effect of the connection between the swing hinge rod 807 and the sliding hinge rod 808, thereby achieving locking. When folding is required, the sliding hinge rod 808 is moved along the arc guide groove 806, so that the swing hinge rod 807, the sliding hinge rod 808 and the hinge connecting rod 809 are located in the same straight line. At this time, the connection between the swing hinge rod 807 and the sliding hinge rod 808 can be rotated, and the rotation of the first hinge block 804 and the second hinge block 805 can be achieved, thereby achieving folding and reducing the occupied space; at the same time, since the overall mass of the supporting body is large, in order to protect the wall and play a supporting role while ensuring that the wall will not be damaged, the contact area between the top wall connector 8 and the wall is increased by setting the top wall plate 15, thereby playing a role in protecting the wall.

[0049] Furthermore, a limited sleeve hole 8021 is provided at the free end of the second folding rod 802, and a sleeve rod 1501 is fixed on one side of the top wall plate 15, and the sleeve rod 1501 is slidably sleeved in the limited sleeve hole 8021. A pair of sliding blocks 1502 are also symmetrically fixed to the side of the sleeve rod 1501, and a pair of limited sliding grooves 8022 adapted to the sliding block 1502 are symmetrically provided on the inner wall of the limited sleeve hole 8021. The end of the limited sliding groove 8022 close to the top wall plate 15 is connected to a rotating groove 8024, and the sliding block 1502 is movably arranged in the rotating groove 8024. A rotating storage groove 8023 adapted to the width of the sliding block 1502 is also provided at the top of the free end of the second folding rod 802, and one end of the rotating storage groove 8023 extends to the free end of the second folding rod 802, and the rotating storage groove 8023 is connected to the limited sleeve hole 8021.

[0050] As can be seen from the above description, since the area of ​​the top wall plate 15 is large, the foldable structural design ensures that the top wall plate 15 can also be folded after disassembly or during transportation, thereby improving applicability. When the top wall is normally connected, the sliding block 1502 is stuck in the limiting slide groove 8022. At this time, the sliding block 1502 cannot rotate and can only slide along the limiting slide groove 8022. When the top wall is connected, the sliding block 1502 is stuck in the innermost end of the limiting slide groove 8022 to ensure that the sliding block 1502 does not slide out. When it needs to be stored, the sleeve rod 1501 needs to be pulled out to make The sliding block 1502 slides out of the limiting slot 8022 and enters the rotating slot 8024. The rotating slot 8024 is arranged in an arc shape, and its diameter is larger than the width of the sliding block 1502. Therefore, the sliding block 1502 can rotate in the rotating slot 8024, and then the sleeve rod 1501 is rotated so that the free end of the sleeve rod 1501 slides out from the rotating storage slot 8023, so that the top wall panel 15 is arranged parallel to the second folding rod 802, and the storage of the top wall panel 15 is completed. The storable design of the top wall panel 15 can effectively reduce the occupied space and further improve the convenience of disassembly and assembly of the device.

[0051] Furthermore, a level 803 is disposed at the top of each of the first folding rod 801 and the second folding rod 802 .

[0052] It can be seen from the above description that, by setting the level 803, it is ensured that the top-wall connector 8 can be set horizontally, and that the top-wall connector 8 can withstand a completely horizontal force and is not easily bent or deformed.

[0053] Furthermore, a plurality of pre-embedded fixing members 14 pre-embedded in the ground are disposed at the bottom of each support unit 100 , and each pre-embedded fixing member 14 is detachably connected to the main chord 102 of each support standard section 1 in a one-to-one correspondence.

[0054] From the above description, it can be seen that in order to ensure the supporting stability of the support unit 100, a pre-embedded fixing part 14 is set in the ground when pouring the ground. While determining the installation position, it can also fix the bottom of the support unit 100 and prevent deviation.

[0055] Furthermore, starting from the third supporting standard section 1 from the bottom to the top, a limiting connector 2 is arranged between each adjacent supporting standard section 1; starting from the third supporting standard section 1 from the bottom to the top, a top wall connector 8 is connected between each supporting unit 100 close to the inner wall of the heavy ion device area 200 and the inner wall of the heavy ion device area 200.

[0056] From the above description, it can be seen that the limit connector 2 and the top wall connector 8 are installed at a certain distance from the ground to ensure that the space on the ground is not disturbed, which is convenient for material transportation and storage, and the supporting standard section 1 at the bottom is relatively stable, so there is no need to add the limit connector 2 and the top wall connector 8, which saves materials and improves installation efficiency.

[0057] Furthermore, the supporting fixing member 11, the limiting connecting member 2, the distribution beam body 12 and the diagonal bracing rod 4 are all channel steels, and the top beam body 5 is an I-beam.

[0058] From the above description, it can be seen that the supporting fixings 11, the limiting connecting parts 2, the distribution beam body 12 and the diagonal bracing rods 4 can be selected according to actual needs. Channel steels and I-beams are easy to cut and weld, are resistant to aging, have a long service life and are light in weight. They can not only play the role of connection and support stability, but are also suitable for promotion and use.

[0059] Embodiment 1

[0060] In this embodiment, an ultra-heavy-load high-formwork support system is applied to the top floor construction of the heavy ion device area 200 .

[0061] like Figures 1 to 10As shown, the super-heavy-load high-formwork support system of this embodiment includes a plurality of support units 100 arranged in a heavy ion device area 200 and arranged in a rectangular array, each support unit 100 includes a plurality of support standard sections 1 vertically connected in sequence from bottom to top, a plurality of position-limiting connectors 2 are fixedly connected between any two adjacent support units 100, each support unit 100 close to the inner wall of the heavy ion device area 200 is connected to the inner wall of the heavy ion device area 200 by a top wall connector 8; the top of each support unit 100 arranged in the longitudinal direction is connected to a top beam assembly, and each support unit 100 0 A diagonal brace assembly is arranged between the supporting standard section 1 arranged at the top and the top beam assembly. The top beam assembly includes at least two top beam bodies 5 parallel to each other. A number of supporting fixing members 11 are fixed in sequence along the length direction of the top beam bodies 5 between any two adjacent top beam bodies 5; a distribution beam assembly is laid on the top of each top beam assembly. The distribution beam assembly includes a number of distribution beam bodies 12 arranged horizontally and perpendicularly to the top beam body 5. A formwork support assembly 13 is installed on the top of the distribution beam body 12. The formwork support assembly 13 includes a disc buckle frame, a top support and a main rib connected in sequence from bottom to top, and a formwork body is arranged on the top of the main rib.

[0062] Furthermore, the limiting connector 2 and the top wall connector 8 are both connected to the supporting standard section 1 through a first transition plate 6, the first transition plate 6 is arranged between two adjacent supporting standard sections 1 above and below, and each main chord 102 of the supporting standard section 1 is connected with the first transition plate 6; the first transition plate 6 includes a first bonding plate 601 and a first L-shaped support plate 603, the first L-shaped support plate 603 is vertically fixed to the bottom end of the first bonding plate 601 and one side is bonded to the main chord 102 of the supporting standard section 1, the first transition plate 6 is provided with a matching fixing hole 606 corresponding to the connecting sleeve 101 on the main chord 102, both ends of the first L-shaped support plate 603 are vertically fixedly connected to the side away from the main chord 102 with the first reinforcing plate 602, and the top end of the first reinforcing plate 602 is fixedly connected to the first bonding plate 601.

[0063] Furthermore, the top of the supporting standard section 1 at the uppermost end of each supporting unit 100 is provided with a second transition plate 10, and the top of each main chord 102 of the supporting standard section 1 is connected with the second transition plate 10, the second transition plate 10 includes a second bonding plate 1001 and a second L-shaped support plate 1003, the second L-shaped support plate 1003 is vertically fixed to the bottom end of the second bonding plate 1001 and one side thereof is bonded to the main chord 102, and the bottom end of the second bonding plate 1001 is also fixed with a positioning screw 1004 corresponding to the connecting sleeve 101 on the main chord 102, and the positioning screw 1004 is fixed to the bottom end of the second bonding plate 1001. The screw rods 1004 are inserted into the connecting sleeve 101 in a one-to-one correspondence, and the second reinforcing plates 1002 are vertically fixedly connected to the sides of the second L-shaped support plates 1003 away from the main chord 102 at both ends, and the top of the second reinforcing plate 1002 is fixedly connected to the second bonding plate 1001; the top of the second transition plate 10 is detachably fixed with an L-shaped pressing plate 7 for pressing the top beam body 5 at the top of the supporting unit 100, and the top of the L-shaped pressing plate 7 is provided with a plug-in screw hole 701, and the second bonding plate 1001 is provided with a fixing screw hole 1005 matching the plug-in screw hole 701.

[0064] Furthermore, a plurality of pre-embedded fixing members 14 pre-embedded in the ground are disposed at the bottom of each support unit 100 , and each pre-embedded fixing member 14 is detachably connected to the main chord 102 of each support standard section 1 in a one-to-one correspondence.

[0065] Furthermore, starting from the third supporting standard section 1 from the bottom to the top, a limiting connector 2 is arranged between each adjacent supporting standard section 1; starting from the third supporting standard section 1 from the bottom to the top, a top wall connector 8 is connected between each supporting unit 100 close to the inner wall of the heavy ion device area 200 and the inner wall of the heavy ion device area 200.

[0066] Furthermore, the supporting fixing member 11, the limiting connecting member 2, the distribution beam body 12 and the diagonal bracing rod 4 are all channel steels, and the top beam body 5 is an I-beam.

[0067] In this embodiment, the supporting fixing member 11, the limiting connecting member 2, the distribution beam body 12 and the diagonal bracing rod 4 are made of channel steel, and the top beam body 5 is made of I-beam. The materials are simple and easy to obtain and suitable for popularization and use.

[0068] Embodiment 2

[0069] In this embodiment, an ultra-heavy-load high-formwork support system is also applied to the top-level construction support of the heavy ion device area 200 .

[0070] An ultra-heavy-load high-formwork support system, based on the above-mentioned embodiment 1, further defines the structure and connection relationship of the diagonal support assembly as follows:

[0071] like Figure 11 to Figure 12As shown, one end of the diagonal brace assembly is connected to the first transition plate 6, and the other end is connected to the bottom end of the top beam body 5; the diagonal brace assembly includes a diagonal brace rod 4, both ends of the diagonal brace rod 4 are provided with a sliding cavity 403, a sliding sleeve rod 401 is sleeved in the sliding cavity 403, one end of the sliding sleeve rod 401 extends out of the sliding cavity 403 and is fixedly connected to the connecting support plate 402, and a return spring 40 is connected between one end of the sliding sleeve rod 401 located inside the sliding cavity 403 and the inner end of the sliding cavity 403. 6, and a damping energy-absorbing block 405 is arranged inside the rod body of the sliding sleeve 401 located in the sliding cavity 403, and a travel groove 404 extending to the outer wall of the sliding sleeve 401 is symmetrically arranged on both sides of the damping energy-absorbing block 405, and an energy-absorbing screw 407 is arranged on the side of the diagonal support rod 4, and the energy-absorbing screw 407 penetrates the side wall of the diagonal support rod 4, the travel groove 404 and the damping energy-absorbing block 405, and both ends of the energy-absorbing screw 407 are locked with energy-absorbing nuts 408 after extending out of the diagonal support rod 4.

[0072] Embodiment 3

[0073] In this embodiment, an ultra-heavy-load high-formwork support system is also applied to the top-level construction support of the heavy ion device area 200 .

[0074] An ultra-heavy-load high formwork support system, based on the above-mentioned embodiment 1 or embodiment 2, further defines the structure and connection relationship of the top wall connector 8 as follows:

[0075] like Figure 13 to Figure 14 As shown, one end of the top wall connector 8 is connected to the first transition plate 6, and the other end is arranged in contact with the inner wall of the heavy ion device area 200; the top wall connector 8 includes a first folding rod 801 and a second folding rod 802 whose ends are opposite to each other, and the second folding rod 802 is connected to the top wall plate 15 on the side away from the first folding rod 801, and the first folding rod 801 is fixedly connected to the bottom of the second folding rod 802 near one end of the first folding rod 801 with a first hinge block 804, and the second folding rod 802 is fixedly connected to the bottom of the first folding rod 801 near one end of the first folding rod 801 with a second hinge block Block 805, the first hinge block 804 and the second hinge block 805 are hinged to each other, and an arc guide groove 806 is provided on the first hinge block 804, a sliding hinge rod 808 is slidably connected in the arc guide groove 806, the free end of the sliding hinge rod 808 is hinged to a swing hinge rod 807, the free end of the swing hinge rod 807 is hinged to the second hinge block 805, a hinge connecting rod 809 is hinged to the middle part of the sliding hinge rod 808, and the free end of the hinge connecting rod 809 is hinged to a side of the first hinge block 804 close to the second hinge block 805.

[0076] Furthermore, a limited sleeve hole 8021 is provided at the free end of the second folding rod 802, and a sleeve rod 1501 is fixed on one side of the top wall plate 15, and the sleeve rod 1501 is slidably sleeved in the limited sleeve hole 8021. A pair of sliding blocks 1502 are also symmetrically fixed to the side of the sleeve rod 1501, and a pair of limited sliding grooves 8022 adapted to the sliding block 1502 are symmetrically provided on the inner wall of the limited sleeve hole 8021. The end of the limited sliding groove 8022 close to the top wall plate 15 is connected to a rotating groove 8024, and the sliding block 1502 is movably arranged in the rotating groove 8024. A rotating storage groove 8023 adapted to the width of the sliding block 1502 is also provided at the top of the free end of the second folding rod 802, and one end of the rotating storage groove 8023 extends to the free end of the second folding rod 802, and the rotating storage groove 8023 is connected to the limited sleeve hole 8021.

[0077] Furthermore, a level 803 is disposed at the top of each of the first folding rod 801 and the second folding rod 802 .

[0078] Working principle of the present invention: The present invention reduces the amount of steel materials used and the cost of manual installation and disassembly while meeting the requirements of supporting tall and thick concrete formworks through the arrangement of each support unit 100, improves the efficiency of installation and disassembly and the safety of use, and ensures the smooth progress of concrete pouring construction; at the same time, through the arrangement of the first transition plate 6 and the second transition plate 10 as the connection point of the limit connector 2 between the support standard section 1 and the top wall connector 8 between the support standard section 1 and the wall, the support standard section 1 will not be damaged by welding or drilling and bolting, thereby improving the use turnover rate of the support standard section 1, improving the structural strength and rigidity of the support standard section 1 in the high formwork support system, and improving the use efficiency of the support standard section 1, broadening the use of the support standard section 1, and ensuring The concrete pouring construction proceeds smoothly, and through the arrangement of the first L-shaped support plate 603 and the second L-shaped support plate 1003, the main chord 102 of the standard section 1 can be conveniently supported closely, without the need for additional positioning and installation, and the installation is convenient and fast, saving time and effort. The arrangement of the first reinforcing plate 602 and the second reinforcing plate 1002 increases the connectable points of the connecting parts, and also enhances the structural strength of the transition plate; the arrangement of the diagonal brace rod 4 improves the supporting stability of the top beam body 5, and at the same time, through the sliding energy-dissipating structural arrangement of the diagonal brace rod 4, the energy-dissipating and shock-absorbing capacity of the supporting system is improved, and the stability of the supporting system is ensured. The arrangement of the top wall connector 8 ensures the lateral support of the supporting system, and the top wall connector 8 is foldable for easy storage. After storage, it reduces the occupied space, facilitates transportation and assembly, and ensures construction efficiency.

[0079] In the description of the present invention, it should be noted that the terms "inside", "outside", "upper", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.

[0080] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the term "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0081] Obviously, the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

Claims

1. An ultra-heavy-load high-formwork support system, characterized by: The invention comprises a plurality of support units (100) arranged in a heavy ion device area (200) and in a rectangular array, each of the support units (100) comprising a plurality of support standard sections (1) vertically connected in sequence from bottom to top, a plurality of position limiting connectors (2) being fixedly connected between any two adjacent support units (100), a top wall connector (8) being connected between each of the support units (100) close to the inner wall of the heavy ion device area (200) and the inner wall of the heavy ion device area (200); the top of each of the support units (100) arranged in the longitudinal direction is connected to a top beam assembly, and each of the support units (100) is arranged at the top. A diagonal brace assembly is provided between the supporting standard section (1) and the top beam assembly, the top beam assembly comprises at least two top beam bodies (5) parallel to each other, and a plurality of supporting fixing members (11) are fixed in sequence along the length direction of the top beam bodies (5) between any two adjacent top beam bodies (5); a distribution beam assembly is laid on the top of each top beam assembly, the distribution beam assembly comprises a plurality of distribution beam bodies (12) arranged horizontally and perpendicularly to the top beam bodies (5), a template support assembly (13) is installed on the top of the distribution beam body (12), the template support assembly (13) comprises a buckle frame, a top support and a main rib connected in sequence from bottom to top, and a template body is provided on the top of the main rib; The position-limiting connector (2) and the top-wall connector (8) are both connected to the supporting standard section (1) via a first transition plate (6); the first transition plate (6) is arranged between two upper and lower adjacent supporting standard sections (1), and each main chord (102) of the supporting standard section (1) is connected to the first transition plate (6); the first transition plate (6) comprises a first bonding plate (601) and a first L-shaped support plate (603); the first L-shaped support plate (603) is vertically fixed to the bottom end of the first bonding plate (601) and one side thereof is bonded to the main chord (102) of the supporting standard section (1); a matching fixing hole (606) corresponding to the connecting sleeve (101) on the main chord (102) is provided on the first transition plate (6); both ends of the first L-shaped support plate (603) are vertically fixedly connected to the first reinforcing plate (602) on the side away from the main chord (102), and the top end of the first reinforcing plate (602) is fixedly connected to the first bonding plate (601); One end of the top wall connector (8) is connected to the first transition plate (6), and the other end is arranged in contact with the inner wall of the heavy ion device area (200); the top wall connector (8) comprises a first folding rod (801) and a second folding rod (802) whose ends are opposite to each other, the second folding rod (802) is connected to the top wall plate (15) on the side away from the first folding rod (801), the first folding rod (801) is fixedly connected to the bottom of the end of the second folding rod (802) with a first hinge block (804), and the second folding rod (802) is fixedly connected to the bottom of the end of the first folding rod (801) with a second hinge block (805). ), the first hinge block (804) and the second hinge block (805) are hinged to each other, and an arc-shaped guide groove (806) is provided on the first hinge block (804), a sliding hinge rod (808) is slidably connected in the arc-shaped guide groove (806), a free end of the sliding hinge rod (808) is hinged to a swing hinge rod (807), the free end of the swing hinge rod (807) is hinged to the second hinge block (805), a hinge connecting rod (809) is hinged to the middle of the sliding hinge rod (808), and the free end of the hinge connecting rod (809) is hinged to a side of the first hinge block (804) close to the second hinge block (805); A limited sleeve hole (8021) is provided at the free end of the second folding rod (802); a sleeve rod (1501) is fixed to one side of the top wall plate (15); the sleeve rod (1501) is slidably sleeved in the limited sleeve hole (8021); a pair of sliding blocks (1502) are symmetrically fixed to the side of the sleeve rod (1501); a pair of limited sliding grooves (8022) adapted to the sliding blocks (1502) are symmetrically provided on the inner wall of the limited sleeve hole (8021); the limited sliding grooves (8022) are symmetrically arranged to prevent the sliding blocks (1502) from sliding. ) is connected to one end of the top wall plate (15) with a rotating slot (8024), and the sliding block (1502) is movably arranged in the rotating slot (8024). The top end of the free end of the second folding rod (802) is also provided with a rotating receiving slot (8023) adapted to the width of the sliding block (1502), one end of the rotating receiving slot (8023) extends to the free end of the second folding rod (802), and the rotating receiving slot (8023) is connected to the limiting sleeve hole (8021).

2. The super heavy load high formwork support system according to claim 1, characterized in that: The top of the uppermost support standard section (1) of each support unit (100) is provided with a second transition plate (10), and the top of each main chord (102) of the support standard section (1) is connected to the second transition plate (10), the second transition plate (10) comprises a second bonding plate (1001) and a second L-shaped support plate (1003), the second L-shaped support plate (1003) is vertically fixed to the bottom end of the second bonding plate (1001) and one side thereof is bonded to the main chord (102), the bottom end of the second bonding plate (1001) is also fixed with a positioning screw (1004) corresponding to the connecting sleeve (101) on the main chord (102), and the positioning screw (1004) is fixed to the bottom end of the second bonding plate (1001). The positioning screw rods (1004) are plugged into the connecting sleeve (101) in a one-to-one correspondence; the second reinforcing plates (1002) are vertically fixedly connected to the sides of both ends of the second L-shaped support plate (1003) away from the main chord (102), and the top end of the second reinforcing plate (1002) is fixedly connected to the second bonding plate (1001); the top end of the second transition plate (10) is detachably fixed with an L-shaped pressing plate (7) for pressing the top beam body (5) at the top end of the support unit (100); the top end of the L-shaped pressing plate (7) is provided with a plug-in screw hole (701); and the second bonding plate (1001) is provided with a fixing screw hole (1005) that matches the plug-in screw hole (701).

3. The super heavy load high formwork support system according to claim 1, characterized in that: One end of the diagonal brace assembly is connected to the first transition plate (6), and the other end is connected to the bottom end of the top beam body (5); the diagonal brace assembly comprises a diagonal brace rod (4), both ends of the diagonal brace rod (4) are provided with a sliding cavity (403), a sliding sleeve rod (401) is sleeved in the sliding cavity (403), one end of the sliding sleeve rod (401) extends out of the sliding cavity (403) and is fixedly connected to a connecting support plate (402), and a return spring (406) is connected between one end of the sliding sleeve rod (401) located inside the sliding cavity (403) and the inner end of the sliding cavity (403). , and a damping energy-absorbing block (405) is arranged inside the rod body of the sliding sleeve rod (401) located in the sliding cavity (403), and travel grooves (404) extending to the outer wall of the sliding sleeve rod (401) are symmetrically arranged on both sides of the damping energy-absorbing block (405), and an energy-absorbing screw rod (407) is arranged on the side of the diagonal support rod (4), and the energy-absorbing screw rod (407) passes through the side wall of the diagonal support rod (4), the travel groove (404) and the damping energy-absorbing block (405), and both ends of the energy-absorbing screw rod (407) are locked with energy-absorbing nuts (408) after extending out of the diagonal support rod (4).

4. The super heavy load high formwork support system according to claim 1, characterized in that: A level (803) is provided at the top of each of the first folding rod (801) and the second folding rod (802).

5. The super heavy load high formwork support system according to claim 1, characterized in that: The bottom end of each support unit (100) is provided with a plurality of pre-embedded fixing members (14) pre-embedded in the ground, and each pre-embedded fixing member (14) is detachably connected to a main chord rod (102) of each support standard section (1) in a one-to-one correspondence.

6. The super heavy load high formwork support system according to claim 1, characterized in that: Starting from the third support standard section (1) from the bottom to the top, the limiting connector (2) is arranged between each adjacent support standard section (1); starting from the third support standard section (1) from the bottom to the top, a top wall connector (8) is connected between each support unit (100) close to the inner wall of the heavy ion device area (200) and the inner wall of the heavy ion device area (200).

7. The super heavy load high formwork support system according to claim 1, characterized in that: The supporting fixing member (11), the limiting connecting member (2), the distribution beam body (12) and the diagonal bracing rod (4) are all channel steels, and the top beam body (5) is an I-beam.