A construction control method for fan-shaped cantilever structure
Through the combination of finite element analysis and vertical adjustable support devices, prefabricated beams are installed and poured one by one, which solves the problem of difficult deformation during the construction period of the folding fan-type cantilever structure, and achieves precise control of structural deformation and improvement of construction quality.
Patent Information
- Application Number
- CN202311391401.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-10-25
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2043-10-25
AI Technical Summary
The deformation of the folding fan-type large cantilever structure is difficult to accurately control during the construction period, resulting in the failure of the building structure to meet the design requirements and affecting the construction quality.
By establishing a three-dimensional finite element analysis model of the fan-shaped spatial structure, vertical adjustable support devices are set up, prefabricated beams are installed and poured section by section, and deformation is adjusted by tensioning prestressed ribs and real-time monitoring of deformation, the construction plan is adjusted to control deformation.
Effectively control the deformation of the fan-shaped cantilever structure during the construction period, improve the quality of construction, reduce the risk of later deformation, and reduce construction costs.
Smart Images

Figure CN117432072B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of building construction, and in particular relates to a construction control method for a fan-shaped cantilever structure. Background Art
[0002] Modern buildings are becoming increasingly complex in shape and function, which poses great challenges to design and construction. Figure 2 As shown in the figure, the cantilever structure has attracted the attention of architects with its special shape and has gradually been applied to architectural works. The entire construction process of the folding fan type large cantilever structure mainly includes: the construction of the middle cylinder, the construction of the rotating thick shell connected to the cylinder, and the construction of the outermost folding fan structure. Among them, the folding fan structure is difficult to accurately control the deformation during the construction period due to its large cantilever and complex overall shape, and it is difficult to meet the design requirements. Summary of the invention
[0003] In view of this, the purpose of the present invention is to provide a fan-shaped cantilever structure construction control method for controlling the deformation of the building structure during the construction period. After the vertical support is removed, the line shape of the upper cantilever structure can be ensured to be consistent with the design state, thereby improving the construction quality of the building.
[0004] In order to achieve the above object, the present invention provides the following technical solutions:
[0005] The invention discloses a method for controlling the construction of a fan-shaped cantilever structure, comprising the following steps:
[0006] S1, establish a three-dimensional finite element analysis model of the fan-shaped space structure, and control the theoretical deformation value through finite element analysis;
[0007] S2, erecting a vertically adjustable support device under the folding fan structure;
[0008] S3, according to the construction pre-adjustment value, install the precast beams section by section from bottom to top, cast the connection between the precast beams and the thick plate shell, and tension the prestressed tendons in the precast beams;
[0009] S4, pouring concrete between precast beams one by one from bottom to top;
[0010] S5, curing concrete and removing formwork;
[0011] S6, remove the vertical adjustable support device under the folding fan structure from bottom to top to complete the construction.
[0012] Further, step S1 specifically includes:
[0013] S1.1, establish the finite element analysis model of the fan-shaped structure according to the design drawings and the in-depth construction plan;
[0014] S1.2, input the force boundary conditions and loads; perform numerical analysis of the construction process to obtain the deformation values D2 of the ends and key parts of N beams;
[0015] S1.3, correct the initial values of each precast beam, re-enter the relevant parameters, analyze the construction process, and obtain a new D2;
[0016] S1.4, analyze the initial value of each precast beam and the D2 of the design state, and judge whether the requirements are met based on the error analysis; if not, continue to adjust the parts with large deformation and re-analyze until the initial value of each precast beam and the D2 of the design state meet the requirements; obtain the construction pre-adjustment value of each key point of the beam;
[0017] S1.5, analyze the sensitivity and adjustable range of the adjustable values at each construction stage to prepare for subsequent adjustments.
[0018] Furthermore, the construction pre-adjustment value includes a processing pre-adjustment value and an on-site installation pre-adjustment value; when the processing pre-adjustment value is too small or too large, the corresponding on-site installation pre-adjustment value is adjusted.
[0019] Furthermore, in step S2, a vertically adjustable support device is arranged under the corresponding prefabricated beam to accurately control the pre-adjustment value of the on-site installation.
[0020] Further, in step S3, the deformation of the prestressed beam end is adjusted through the prestressing process.
[0021] Furthermore, before step S4, the closing time is determined according to the vertical differential deformation of each precast beam caused by the measured temperature and other factors, so as to ensure that the concrete is poured when the relative vertical deviation of the connected beams is minimal, and to carry out thermal insulation and moisture maintenance.
[0022] Furthermore, the actual deformation of key parts at each stage of structural construction is accurately measured in real time and compared with the theoretical calculated values to prepare for further adjustments to the installation plan and adjustments.
[0023] Furthermore, the vertically adjustable support device includes two groups of supporting telescopic steel frames, support plates fixed on the supporting telescopic steel frames, and a base plate spanning the two support plates, one end of the base plate is fixed with a pin shaft, and the pin shaft is rotatably connected to one end of the longitudinal hollow beam, and the longitudinal hollow beam is arranged on the lower side of the prefabricated beam along the longitudinal direction of the prefabricated beam, and a mounting seat is fixed on the side of the support plate, and the mounting seat is connected to the longitudinal hollow beam through a telescopic device; an adjusting rod is threadedly connected to the lower surface of the longitudinal hollow beam, and several groups of the adjusting rods are evenly spaced along the longitudinal direction, and the adjusting rod is rotatably connected to a pull rod after penetrating into the longitudinal hollow beam, and the pull rod extends from a through hole opened on the upper surface of the longitudinal hollow beam and is connected to a limit frame, and the limit frame is sleeved on the outer side of the prefabricated beam.
[0024] Further, the limit frame includes a square frame body, a notch is provided on the upper side of the frame body, a first connecting handle and a second connecting handle are provided at two opposite ends of the notch, a first opening groove and a second opening groove are respectively provided on the first connecting handle and the second connecting handle, a rotating shaft is rotatably provided in the first opening groove, the rotating shaft is fixedly connected to one end of the screw, a nut is connected to the other end of the screw, and the middle limit of the screw is installed in the second opening groove.
[0025] Furthermore, a groove is provided on the upper side of the base plate, and a fan-shaped support block is connected to the bottom of the groove through a spring. The outer side of the fan-shaped support block is conical, and a plurality of fan-shaped support blocks are distributed circumferentially in the groove. A circular hole matching the fan-shaped support block is also provided at the bottom of the longitudinal hollow beam, and a hot air ventilation pipe is provided on the inner side of the fan-shaped support block. The upper end of the hot air ventilation pipe passes through the upper surface of the longitudinal hollow beam and extends to the lower side of the prefabricated beam, and the lower end of the hot air ventilation pipe passes through the base plate and is connected to the hot air supply device.
[0026] Furthermore, an arc-shaped plate is provided on one side of the base plate, a through groove is provided on the arc-shaped plate, a rotating shaft is rotatably provided in the through groove, a friction wheel and a coil spring are coaxially connected to the rotating shaft, one end of the coil spring is fixedly connected to the rotating shaft, and the other end of the coil spring is connected to the arc-shaped plate, an annular groove is provided on the friction wheel, a pull rope is wound on the annular groove, the pull rope is connected to a pressure plate after being guided by a guide mechanism, the pressure plate is slidably provided on the upper side of the longitudinal hollow beam, and the pressure plate is used to provide axial inward pre-pressure for the precast beam.
[0027] The beneficial effects of the present invention are:
[0028] The present invention controls the theoretical deformation value through finite element analysis, compares the construction process monitoring with the theoretical value, fine-tunes the deformation in multiple ways, and controls the deformation and structural line type at each stage through real-time monitoring by the deformation monitoring system. The deformation of the fan-shaped cantilever structure during the construction period can be effectively controlled, thereby improving the construction quality of the building.
[0029] In the technical solution of the present invention, by establishing a deformation monitoring system for the entire construction process, the actual deformation of key parts of each stage of structural construction is accurately measured in real time and compared with the theoretical calculated value, so as to prepare for further adjustment of the installation plan and adjustment. It effectively reduces the possibility of structural deformation during the later pouring of beams, thereby reducing construction costs and providing strong data support for later construction.
[0030] Other advantages, objectives and features of the present invention will be described in the following description and will be apparent to those skilled in the art to some extent, or those skilled in the art may be taught from the practice of the present invention. The objectives and other advantages of the present invention may be realized and obtained through the following description. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] In order to make the purpose, technical solution and beneficial effects of the present invention clearer, the present invention provides the following drawings for illustration:
[0032] Figure 1 It is a construction flow chart of the construction method of the present invention;
[0033] Figure 2 It is a structural schematic diagram of the fan-shaped cantilever structure;
[0034] Figure 3 It is a structural schematic diagram of the vertically adjustable support device in Example 1;
[0035] Figure 4 It is a schematic diagram of the arrangement of the limit frame of the present invention;
[0036] Figure 5 It is a schematic diagram of the deflection of the longitudinal hollow beam;
[0037] Figure 6 It is a structural schematic diagram of a fan-shaped support block;
[0038] Figure 7 It is a structural schematic diagram of the limit frame;
[0039] Figure 8 It is a schematic diagram of the matching of the fan-shaped support block;
[0040] Fig. 9 is a schematic structural diagram of the curved plate in Example 2;
[0041] Fig.10 for Fig. 9 Enlarged view at A.
[0042] The markings in the accompanying drawings are as follows: supporting telescopic steel frame 1, supporting plate 2, bottom plate 3, pin shaft 4, longitudinal hollow beam 5, mounting seat 6, telescopic device 7, adjusting rod 8, pull rod 9, limit frame 10, prefabricated beam 11, frame body 12, notch 13, first connecting handle 14, second connecting handle 15, first opening groove 16, second opening groove 17, rotating shaft 18, screw 19, nut 20, groove 21, spring 22, fan-shaped support block 23, circular hole 24, hot air ventilation pipe 25, arc plate 26, through groove 27, rotating shaft 28, friction wheel 29, coil spring 30, annular groove 31, pull rope 32, guide mechanism 33, pressure plate 34. DETAILED DESCRIPTION
[0043] like Figure 1 As shown, a fan-shaped cantilever structure construction control method disclosed in the present invention comprises the following steps:
[0044] S1, establish a three-dimensional finite element analysis model of the fan-shaped space structure, and control the theoretical deformation value through finite element analysis; specifically include:
[0045] S1.1, establish the finite element analysis model of the fan-shaped structure according to the design drawings and the in-depth construction plan;
[0046] S1.2, input the stress boundary conditions and loads; perform numerical analysis of the construction process to obtain the deformation values D2 of the ends and key parts of N beams; arrange vertical adjustable support devices under the corresponding prefabricated beams 11 to accurately control the pre-adjustment values for on-site installation.
[0047] S1.3, correct the initial values of each precast beam 11, re-enter the relevant parameters, analyze the construction process, and obtain a new D2;
[0048] S1.4, analyze the initial value of each precast beam 11 and the D2 of the design state, and judge whether the requirements are met based on the error analysis; if not, continue to adjust the parts with large deformation and re-analyze until the initial value of each precast beam 11 and the D2 of the design state meet the requirements; obtain the construction pre-adjustment value of each key point of the beam;
[0049] S1.5, analyze the sensitivity and adjustable range of the adjustable values at each construction stage to prepare for subsequent adjustments.
[0050] S2, erecting a vertically adjustable support device under the folding fan structure;
[0051] S3, according to the construction pre-adjustment value, install the precast beam 11 from bottom to top in sections, the thick plate shell is set on the outside of the central column at the connection part of the cast-in-place precast beam 11 and the thick plate shell, and the prestressed tendons in the precast beam 11 are tensioned; the deformation of the prestressed beam end is adjusted through the tensioning prestressing process. The construction pre-adjustment value includes the processing pre-adjustment value and the on-site installation pre-adjustment value; when the processing pre-adjustment value is too small or too large, the corresponding on-site installation pre-adjustment value is adjusted.
[0052] S4, pouring concrete between 11 precast beams one by one from bottom to top;
[0053] S5, curing concrete and removing formwork;
[0054] S6, remove the vertical adjustable support device under the folding fan structure from bottom to top to complete the construction.
[0055] In this embodiment, before step S4, the closing time is determined according to the vertical differential deformation of each precast beam 11 caused by the measured temperature and other factors, to ensure that the concrete is poured when the relative vertical deviation of the connected beams is minimal, and to carry out thermal insulation and moisture maintenance.
[0056] In this embodiment, the actual deformation of key parts at each stage of structural construction is accurately measured in real time and compared with the theoretical calculated values to prepare for further adjustments to the installation plan and adjustments.
[0057] Embodiment 1, in this embodiment, as Figures 3 to 8 As shown, the vertically adjustable support device includes two sets of supporting telescopic steel frames 1, supporting plates 2 fixed on the supporting telescopic steel frames 1, and a bottom plate 3 spanning the two supporting plates 2. The supporting telescopic steel frames 1 adopt the existing structure and can be used to independently support the supporting plates 2. At the same time, the two sets of supporting telescopic steel frames 1 can be moved on the ground to adapt to the support on the prefabricated beams 11 of different heights.
[0058] Specifically, a pin shaft 4 is fixed at one end of the bottom plate 3, and the axial direction of the pin shaft 4 is along the vertical direction. The pin shaft 4 is rotatably connected to one end of the longitudinal hollow beam 5, and the longitudinal hollow beam 5 can rotate in a plane around the pin shaft 4. A boss that rotates with the longitudinal hollow beam 5 is provided at the upper end of the pin shaft 4 to prevent the longitudinal hollow beam 5 from falling out. The longitudinal hollow beam 5 is arranged on the lower side of the precast beam 11 along the longitudinal direction of the precast beam 11, and a mounting seat 6 is fixed on the side of the support plate 2, and the mounting seat 6 is connected to the longitudinal hollow beam 5 through a telescopic device 7; through the action of the telescopic device 7, the longitudinal hollow beam 5 can be driven to deflect in the horizontal plane to adjust the gap between two adjacent precast beams 11.
[0059] Among them, the lower surface of the longitudinal hollow beam 5 is threadedly connected with an adjusting rod 8, and the adjusting rod 8 is evenly spaced in the longitudinal direction. After the adjusting rod 8 penetrates into the longitudinal hollow beam 5, it is rotated and connected with a pull rod 9. The pull rod 9 extends from the through hole opened on the upper surface of the longitudinal hollow beam 5 and is connected to a limit frame 10. The limit frame 10 is sleeved on the outer side of the prefabricated beam 11. Through the limiting effect of each limit frame 10, the prefabricated beam 11 can be tightly pressed on the upper surface of the longitudinal hollow beam 5. When the longitudinal hollow beam 5 deflects in the horizontal plane, the position deformation between the beams of the prefabricated beam 11 can be adjusted. When the vertical adjustable support device located on the outside is extended and retracted, the deformation of the vertical suspension position of the prefabricated beam 11 can also be adjusted. At the same time, the limit frame 10 is arranged in several groups along the longitudinal direction, and the prefabricated beam 11 can be pressed on the upper side surface of the longitudinal hollow beam 5 in sequence along the longitudinal direction. Through the segmented limiting effect of the limit frame 10, the processing deformation of the prefabricated beam 11 itself can also be controlled to a certain extent.
[0060] In this embodiment, the limiting frame 10 includes a square frame body 12, the frame body 12 corresponds to the shape of the prefabricated beam 11, a notch 13 is provided on the upper side of the frame body 12, the notch 13 is basically located at the upper center of the frame body 12, and a first connecting handle 14 and a second connecting handle 15 are relatively provided at both ends of the notch 13, the first connecting handle 14 and the second connecting handle 15 are arranged at intervals and extend toward each other, and a first opening groove 16 and a second opening groove 17 are respectively provided on the first connecting handle 14 and the second connecting handle 15, and a rotating shaft 18 is rotatably provided in the first opening groove 16, and the rotating shaft 18 is fixedly connected to one end of a screw rod 19, and a nut 20 is connected to the other end of the screw rod 19, and the middle part of the screw rod 19 is limitedly installed in the second opening groove 17. When specifically connected, the rotating shaft 18 is inserted downward into the second opening groove 17, and the nut 20 is tightened, so that the distance between the first connecting handle 14 and the second connecting handle 15 can be shortened, so that the frame body 12 is clamped on the outer side of the prefabricated beam 11, which is convenient for disassembly and connection.
[0061] In this embodiment, a groove 21 is provided on the upper side of the bottom plate 3. The groove 21 is circular and extends downward from the upper side of the bottom plate 3. The bottom of the groove 21 is connected to a fan-shaped support block 23 through a spring 22. The outer side of the fan-shaped support block 23 is conical. A plurality of fan-shaped support blocks 23 are circumferentially distributed in the groove 21. A circular hole 24 cooperating with the fan-shaped support block 23 is provided at the bottom of the longitudinal hollow beam 5. A hot air ventilation pipe 25 is provided on the inner side of the fan-shaped support block 23. The upper end of the hot air ventilation pipe 25 passes through the upper surface of the longitudinal hollow beam 5 and extends to the lower side of the prefabricated beam 11. The lower end of the hot air ventilation pipe 25 passes through the bottom plate 3 and is connected to the hot air supply device. When the circular hole 24 of the longitudinal hollow beam 5 is aligned with the fan-shaped support block 23 on the bottom plate 3, the fan-shaped support block 23 extends toward the groove 21 under the action of the spring 22, and clamps the hot air ventilation pipe 25 inward under the guidance of the conical surface, thereby avoiding energy waste caused by air leakage. When the longitudinal hollow beam 5 is deflected, the circular hole 24 moves away from the fan-shaped support block 23. At this time, the hot air ventilation pipe 25 normally allows hot air to enter, which can keep the precast beam 11 warm and prevent the cast-in-place concrete from cracking due to uneven temperature when the precast beam 11 is connected to the thick plate shell to a certain extent.
[0062] Embodiment 2: This embodiment is different from Embodiment 1 in that, in this embodiment, an arc plate 26 is provided on one side of the bottom plate 3, a through slot 27 is provided on the arc plate 26, a rotating shaft 28 is rotatably provided in the through slot 27, a friction wheel 29 and a coil spring 30 are coaxially connected to the rotating shaft 28, one end of the coil spring 30 is fixedly connected to the rotating shaft 28, and the other end of the coil spring 30 is connected to the arc plate 26, an annular groove 31 is provided on the friction wheel 29, a pull rope 32 is wound around the annular groove 31, the pull rope 32 is connected to a pressure plate 34 after being guided by a guide mechanism 33, the pressure plate 34 is slidably provided on the upper side of the longitudinal hollow beam 5, and the pressure plate 34 is used to provide an axial inward preload for the precast beam 11. By providing the pressure plate 34, a certain preload force can be provided when the precast beam 11 is connected to the thick plate shell cast-in-place, so that the connection is tighter. When the longitudinal hollow beam 5 is deflected, the longitudinal hollow beam 5 passes through the friction wheel 29, and the friction wheel 29 is driven to rotate by the friction force. The rotation of the friction wheel 29 can pull the pull rope 32, so that the pull rope 32 pulls the pressure plate 34 axially toward the longitudinal hollow beam 5. The elastic pull rope 32 can provide axial clamping force for the precast beam 11, prevent the precast beam 11 from moving during rotation, and increase the stability of the structure.
[0063] Finally, it should be noted that the above preferred embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail through the above preferred embodiments, those skilled in the art should understand that various changes can be made in form and details without departing from the scope defined by the claims of the present invention.
Claims
1. A method for controlling the construction of a fan-shaped cantilever structure, characterized in that: The following steps are involved: S1, establish a three-dimensional finite element analysis model of the fan-shaped space structure, and control the theoretical deformation value through finite element analysis; S2, erecting a vertically adjustable support device under the folding fan structure; S3, according to the construction pre-adjustment value, install the precast beams section by section from bottom to top, cast the connection between the precast beams and the thick plate shell, and tension the prestressed tendons in the precast beams; S4, pouring concrete between precast beams one by one from bottom to top; S5, curing concrete and removing formwork; S6, dismantle the vertical adjustable support device set up under the folding fan structure from bottom to top to complete the construction; Step S1 specifically includes: S1.1, establish the finite element analysis model of the fan-shaped structure according to the design drawings and the in-depth construction plan; S1.2, input the force boundary conditions and loads; perform numerical analysis of the construction process to obtain the deformation values D2 of the ends and key parts of N beams; S1.3, correct the initial values of each precast beam, re-enter the relevant parameters, analyze the construction process, and obtain a new D2; S1.4, analyze the initial value of each precast beam and the D2 of the design state, and judge whether the requirements are met based on the error analysis; if not, continue to adjust the parts with large deformation and re-analyze until the initial value of each precast beam and the D2 of the design state meet the requirements; obtain the construction pre-adjustment value of each key point of the beam; S1.5, analyze the sensitivity and adjustable range of the adjustable value at each construction stage to prepare for subsequent adjustments; The construction pre-adjustment value includes a processing pre-adjustment value and an on-site installation pre-adjustment value; when the processing pre-adjustment value is too small or too large, the corresponding on-site installation pre-adjustment value is adjusted; In step S2, a vertically adjustable support device is arranged under the corresponding prefabricated beam, so as to accurately control the pre-adjustment value of the on-site installation; The vertically adjustable support device comprises two groups of supporting telescopic steel frames, a support plate fixed on the supporting telescopic steel frames, and a bottom plate spanning the two supporting plates. A pin is fixed at one end of the bottom plate, and the pin is rotatably connected to one end of a longitudinal hollow beam. The longitudinal hollow beam is arranged at the lower side of the prefabricated beam along the longitudinal direction of the prefabricated beam. A mounting seat is fixed on the side of the support plate, and the mounting seat is connected to the longitudinal hollow beam through a telescopic device. Through the action of the telescopic device, the longitudinal hollow beam can be driven to deflect in the horizontal plane to adjust the position of two adjacent prefabricated beams. The gap between the prefabricated beams; the lower surface of the longitudinal hollow beam is threadedly connected with an adjusting rod, and the adjusting rod is arranged in several groups at uniform intervals along the longitudinal direction. After the adjusting rod penetrates into the longitudinal hollow beam, it is rotatably connected with a pull rod, and the pull rod extends from a through hole opened on the upper surface of the longitudinal hollow beam and is connected to a limit frame. The limit frame is sleeved on the outside of the prefabricated beam, and the prefabricated beam is tightly pressed against the upper surface of the longitudinal hollow beam through the limiting effect of the limit frame, so that the position deformation between the prefabricated beams can be adjusted, thereby realizing the control of the pre-adjustment value installed on site.
2. A fan-shaped cantilever structure construction control method according to claim 1, characterized in that: In step S3, the deformation of the prestressed beam end is adjusted through the prestressing process.
3. A fan-shaped cantilever structure construction control method according to claim 2, characterized in that: Before step S4, the closing time is determined according to the vertical differential deformation of each precast beam caused by the measured temperature and other factors, to ensure that the concrete is poured when the relative vertical deviation of the connected beams is the smallest, and to carry out thermal insulation and moisture maintenance; the actual deformation of key parts at each stage of the structural construction is accurately measured in real time and compared with the theoretical calculated value to prepare for further adjustment of the installation plan and adjustments.
4. A fan-shaped cantilever structure construction control method according to any one of claims 1 to 3, characterized in that: The limit frame includes a square frame body, a notch is provided on the upper side of the frame body, a first connecting handle and a second connecting handle are provided at two opposite ends of the notch, a first opening groove and a second opening groove are respectively provided on the first connecting handle and the second connecting handle, a rotating shaft is rotatably provided in the first opening groove, the rotating shaft is fixedly connected to one end of the screw rod, a nut is connected to the other end of the screw rod, and the middle limit position of the screw rod is installed in the second opening groove.
5. A fan-shaped cantilever structure construction control method according to claim 4, characterized in that: A groove is provided on the upper side of the base plate, and a fan-shaped support block is connected to the bottom of the groove through a spring. The outer side of the fan-shaped support block is conical, and a plurality of fan-shaped support blocks are distributed circumferentially in the groove. A circular hole matching the fan-shaped support block is also provided at the bottom of the longitudinal hollow beam, and a hot air ventilation pipe is provided on the inner side of the fan-shaped support block. The upper end of the hot air ventilation pipe passes through the upper surface of the longitudinal hollow beam and extends to the lower side of the prefabricated beam. The lower end of the hot air ventilation pipe passes through the base plate and is connected to the hot air supply device.
6. A fan-shaped cantilever structure construction control method according to claim 5, characterized in that: An arc-shaped plate is provided on one side of the bottom plate, a through groove is provided on the arc-shaped plate, a rotating shaft is rotatably provided in the through groove, a friction wheel and a coil spring are coaxially connected to the rotating shaft, one end of the coil spring is fixedly connected to the rotating shaft, and the other end of the coil spring is connected to the arc-shaped plate, an annular groove is provided on the friction wheel, a pull rope is wound on the annular groove, and the pull rope is connected to a pressure plate after being guided by a guide mechanism, and the pressure plate is slidably provided on the upper side of the longitudinal hollow beam, and the pressure plate is used to provide axial inward pre-pressure for the precast beam.