A construction method for installing steel structure bracket and pipeline in air-conditioning main machine room
By using steel structure brackets and anchor bolts in the air-conditioned main room to fix and BIM forward design, combined with lifting system and mobile joists, the uneven column arrangement and poor construction environment during pipeline installation in the prior art are solved. The various problems of lifting points are set up, which achieves the beautiful and reliable fixing of the bracket, fast installation progress and good construction environment.
Patent Information
- Application Number
- CN202311614774.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-11-29
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2043-11-29
AI Technical Summary
When installing pipes and brackets in the existing air-conditioned main room, there are problems such as untidy column arrangement, complex installation process, poor construction environment, numerous lifting points and major safety hazards.
The steel structure bracket is fixed with anchor bolts, the equipment and brackets are arranged in advance through BIM forward design, a small number of lifting points are set up, and the pipes are vertically lifted using lifting systems and mobile joists to reduce construction strength and safety risks.
The bracket is beautiful and reliable in fixing, fast installation progress, good construction environment and high lifting stability, reduce the number of lifting points and construction strength, and improve safety and efficiency.
Smart Images

Figure CN117645228B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of air-conditioning main machine room, and in particular to a construction method for installing a steel structure bracket of an air-conditioning main machine room and an air-conditioning water pipe and bracket of a pipeline main machine room. Background Art
[0002] Most civil buildings are equipped with air-conditioning main machine room, which is equipped with chillers, water pumps, cooling chilled water pipes and their accessories. Some main machine rooms are also equipped with plate exchangers. There are many pipes in the machine room, including chilled water pipes, cooling water pipes, etc. In order to reduce the transmission of equipment vibrations by pipes to the upper floor, pipe brackets are mainly installed on the ground.
[0003] The existing air-conditioning main machine room has the following problems when installing pipes and brackets in the machine room:
[0004] 1) After the civil construction of the computer room was completed, the electromechanical professionals entered the construction site. The positions of the floor-standing bracket columns were set according to the civil construction structure of the computer room, equipment foundation, and ditch. The columns were not arranged neatly and the appearance was poor;
[0005] 2) When the support column is installed with the floor structure of the machine room, it is usually fixed with embedded steel bars or expansion bolts. Vertical supports are also required between the columns to ensure the stability of the columns, which affects the maintenance channel in the machine room and also affects the appearance;
[0006] 3) The bracket is constructed by welding, and the machine room is generally located in the basement, where the space is narrow and the ventilation is poor, making it difficult for smoke and dust to dissipate, affecting the health and safety of the operators.
[0007] 4) Usually, the bracket is installed first, and then the pipe is installed by installing the bracket; a large number of lifting points are set by driving expansion bolts on the top structural layer of the machine room, two lifting points are set on the top of each pipe, and then a large lifting crane is used to lift the pipe into place on the pipe bracket. A large number of lifting points need to be set on the top structural layer of the machine room, and the workload of setting the lifting points is large. When lifting the pipe, the pipe needs to be obliquely penetrated and pulled into place. The labor intensity required for lifting the pipe by obliquely passing through the bracket is high, and there are safety hazards such as pipe slipping and tilted lifting during the installation process. Summary of the invention
[0008] In view of this, in order to solve the technical problems existing in the prior art, the present invention provides a steel structure bracket with overall ground layout, the steel structure bracket is fixed with anchor bolts, it is beautiful and reliably fixed, all the steel structure brackets are connected with bolts, the installation progress is fast, the construction environment is good, only two lifting points need to be set on the floor slab, the lifting points are few and firm and reliable, only two lifting points and two groups of lifting structures need to be set on the floor slab to complete the pipeline installation of each group of steel structure brackets, and the problem of high construction intensity caused by the need to set a large number of lifting points on the top floor of the machine room in the traditional installation scheme is solved, the pipeline can be lifted onto the steel structure bracket by cooperating with the lifting assembly and the movable support beam, the pipeline can be lifted vertically into place, the oblique lifting of the pipeline can be avoided, and the lifting stability of the construction method is improved.
[0009] The present invention solves the above technical problems through the following technical solutions:
[0010] A construction method for installing steel structure brackets and pipelines in an air-conditioning main machine room, including a construction method for installing a plurality of groups of steel structure brackets and pipelines in the air-conditioning main machine room, the construction method comprising the following steps:
[0011] Step 1) BIM forward design of the computer room: The equipment installation process of the air-conditioning main room is involved in advance. Before the concrete construction stage of the computer room, BIM forward design is fully applied to arrange the equipment, drainage ditches, pipes, and steel structure brackets in the air-conditioning main room. The pipes are arranged against the wall and not directly above the air-conditioning chiller;
[0012] Step 2) Pre-embedded anchor bolts: During the construction of the base plate of the air-conditioning main room, 6 to 8 sets of anchor bolts are installed at the installation position of each single-layer bracket to firmly fix the single-layer bracket to the floor of the air-conditioning main room;
[0013] Step 3) Installation of steel structure support: The steel structure support can be set as a single-layer support or a double-layer support according to the number of pipelines and the spatial position. The single-layer support is assembled from two support columns and a support beam. The double-layer support is composed of a single-layer support and a ∏-shaped component. The ∏-shaped component is assembled from a short beam and two short columns.
[0014] Step 4) Setting of hoisting points: Each set of steel structure brackets is provided with two hoisting points fixed to the top floor of the air-conditioning main machine room;
[0015] Step 5) Installation of the hoisting system: Install two sets of hoisting systems on both sides of each set of steel structure supports, and the upper ends of the two hoisting systems pass through the two hoisting points of the floor slab respectively;
[0016] Step 6) Pipeline hoisting: Use the hoisting system to hoist the pipelines from far to near the hoisting point onto the steel structure support in sequence.
[0017] As a further improvement to the above technical solution, the anchor bolts described in step 2) are arranged at the bracket columns of the single-layer bracket, and the bracket columns are fixed to the floor of the air-conditioning main room through the anchor bolts, so that the single-layer bracket is fixed to the floor of the air-conditioning main room, and a shock-absorbing rubber pad is installed under the bottom plate of the bracket column.
[0018] As a further improvement to the above technical solution, the two support columns of the single-layer support in step 3) are distributed at both ends of the support beam and connected by bolts, and the two short columns of the ∏-shaped component are distributed at both ends of the short beam, and the short columns and the short beam are connected by bolts.
[0019] As a further improvement to the above technical solution, the lifting system described in step 5) consists of a movable supporting beam and a lifting structure, the movable supporting beam is movably installed on one side of the steel structure support, the lifting structure consists of a lifting beam, a lifting ring, and a fall chain, the lifting ring is set between the lifting beam and the fall chain, one end of the lifting ring is connected to the lifting beam, the other end of the lifting ring is connected to one end of the fall chain, a steel pipe sling is installed at the other end of the fall chain, and a barb is fixed at the lower end of the steel pipe sling.
[0020] As a further improvement to the above technical solution, the movable joist is composed of a joist connecting plate and a pipe clamp, the pipe clamp is installed on the upper end of the joist connecting plate, a lifting ear is installed on one side of the joist connecting plate, and a mounting hole is opened on the other side of the joist connecting plate. The movable joist fixes the pipeline through the pipe clamp on the joist connecting plate, and a lifting part is installed above the pipe clamp.
[0021] As a further improvement to the above technical solution, a sling is provided between the movable joist and the lifting ring of the lifting structure, one end of the sling is connected to the lifting ear of the movable joist, and the other end of the sling is connected to the lifting ring.
[0022] As a further improvement to the above technical solution, positioning holes matching with the mounting holes of the movable support beam are respectively opened on the support column and the short column, and mounting bolts matching with the positioning holes and the mounting holes are provided at the positioning holes. The movable support beam matches with the mounting bolts and the positioning holes through the mounting holes, so that the movable support beam can be movably installed on one side of the support column or the short column.
[0023] As a further improvement to the above technical solution, the pipe hoisting to the steel structure support in step 6) includes the following two hoisting stages:
[0024] Step 61) First hoisting stage: hoist the pipeline onto the single-layer support;
[0025] Step 62) Second lifting stage: Lift the pipeline onto the ∏-shaped component of the double-layer support.
[0026] Compared with the prior art, the technical solution of the present invention has at least the following beneficial effects:
[0027] (1) The construction method of the present invention includes forward design of the machine room BIM, pre-embedding of anchor bolts, installation of steel structure brackets, setting of lifting points, installation of lifting systems, installation of two sets of lifting systems on both sides of each set of steel structure brackets, and the upper ends of the two sets of lifting systems pass through the two lifting points of the floor slab and pipeline lifting respectively. In the construction method of the present invention, the steel structure brackets are fixed with anchor bolts, which are beautiful and reliably fixed. All steel structure brackets are connected with bolts, and the installation progress is fast. The construction environment is good, safe, efficient, convenient and fast. Through the construction method of the present invention, only two lifting points need to be set on the floor slab, the lifting points are few and firm and reliable, and only two lifting points and two sets of lifting structures need to be set on the floor slab to complete the pipeline installation of each set of steel structure brackets, which solves the problem of high construction intensity caused by the need to set a large number of lifting points on the top floor of the machine room in the traditional installation scheme.
[0028] (2) The construction method of the present invention can hook the lifting part of the pipe clamp through the barb of the steel pipe sling, so as to lift the pipe clamp. The present invention only needs to set two lifting points on the floor, and the two sets of lifting structures are set through the floor. Since there is no water in the pipe, the pipe is relatively light, which can improve the reliability of the lifting point, and the number of lifting points required is small. Only two lifting points and two sets of lifting structures need to be set on the floor to complete the pipe installation of each set of steel structure brackets, which solves the problem of setting a large number of lifting points on the top floor of the machine room and the high construction intensity in the traditional installation scheme. The pipe can be lifted onto the steel structure bracket by cooperating with the lifting structure and the movable support beam. The present invention can lift the pipe vertically into place through the lifting structure, avoid the oblique lifting of the pipe, and improve the stability of the pipe lifting.
[0029] The above description is only an overview of the technical solution of the present invention. In order to more clearly understand the technical means of the present invention, it can be implemented in accordance with the contents of the specification. In order to make the above and other purposes, features and advantages of the present invention more obvious and easy to understand, the following is a detailed description in combination with the preferred embodiments and the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] Figure 1 It is a schematic diagram of the process of the construction method of the present invention;
[0031] Figure 2 The structure of the lifting system of the present invention is schematically shown in FIG. Figure 1 ;
[0032] Figure 3 The structure of the lifting system of the present invention is schematically shown in FIG. Figure 2 ;
[0033] Figure 4It is a structural schematic diagram of the hoisting structure of the present invention;
[0034] Figure 5 The structure diagram of the movable support beam of the present invention is shown in FIG. Figure 1 ;
[0035] Figure 6 The structure diagram of the movable support beam of the present invention is shown in FIG. Figure 2 ;
[0036] Figure 7 This is a schematic diagram of the relationship between the support column of the present invention and the ground fixation;
[0037] Figure 8 This is an elevation view of the first pipeline of the present invention ready to be hoisted onto the support beam;
[0038] Fig. 9 It is an elevation view of the first pipeline of the present invention hoisted onto the support beam;
[0039] Fig.10 This is an elevation view of the second pipeline of the present invention ready to be hoisted onto the support beam;
[0040] Fig.11 It is an elevation view of the second pipeline of the present invention hoisted onto the support beam;
[0041] Fig.12 The elevation view of the third pipe of the present invention ready to be hoisted onto the short beam;
[0042] Fig.13 It is an elevation view of the third pipe of the present invention being hoisted onto the short crossbeam;
[0043] Fig.14 An elevation view of the fourth pipe of the present invention ready to be hoisted onto the short beam;
[0044] Fig.15 It is an elevation view of the fourth pipe of the present invention hoisted onto the short beam;
[0045] Fig.16 It is a schematic diagram of dismantling the hoisting system after the pipeline of the present invention is installed on the steel structure support.
[0046] In the figure: steel structure support 1, single-layer support 11, support column 111, support beam 112, anchor bolt 113, bottom plate 114, shock-absorbing rubber pad 115, ∏-shaped component 12, short beam 121, short column 122, lifting system 2, movable joist 21, joist connecting plate 211, round hole 2111, pipe clamp 212, lifting part 2121, lifting ear 213, lifting structure 22, lifting beam 221, lifting ring 222, fall chain 223, steel pipe sling 224, barb 225, sling 23, mounting bolt 24, floor 3, lifting point 31, pipeline 4, first pipeline 41, second pipeline 42, third pipeline 43, fourth pipeline 44, ground 5. DETAILED DESCRIPTION
[0047] The present invention is described in detail below in conjunction with the accompanying drawings, which are part of this specification and illustrate the principles of the present invention through embodiments. Other aspects, features and advantages of the present invention will become clear from the detailed description. In the drawings referred to, the same or similar parts in different figures are represented by the same reference numerals.
[0048] like Figure 1-16 As shown, the first embodiment of the present invention provides a construction method for installing a steel structure support 1 and a pipeline 4 in an air-conditioning main room, including a construction method for installing a plurality of groups of steel structure supports 1 and pipelines 4 in the air-conditioning main room, wherein the steel structure support 1 includes a single-layer support 11 and a ∏-shaped support, and the ∏-shaped support is installed above the single-layer support 11. The construction method includes the following steps:
[0049] Step 1) BIM forward design of the computer room: The equipment installation process of the air-conditioning main room is involved in advance. Before the concrete construction stage of the computer room, BIM forward design is fully applied to arrange the equipment, drainage ditch, pipe 4, and steel structure support 1 in the air-conditioning main room. Pipe 4 is arranged against the wall and not directly above the air-conditioning chiller;
[0050] Step 2) Pre-embed the anchor bolts 113: During the civil construction of the base plate 114 of the air-conditioning main room, 6 to 8 sets of anchor bolts 113 are arranged at the installation position of each single-layer bracket 11, so that the single-layer bracket 11 is firmly fixed to the floor 5 of the air-conditioning main room;
[0051] Step 3) Installation of the steel structure support 1: The steel structure support 1 can be set as a single-layer support 11 or a double-layer support according to the number and spatial position of the pipelines 4. The single-layer support 11 is assembled from two support columns 111 and a support beam 112. The double-layer support is composed of a single-layer support 11 and a ∏-shaped component 12. The ∏-shaped component 12 is assembled from a short beam 121 and two short columns 122. The steel structure support 1 can be installed quickly by using factory-prefabricated columns and beams, solving the problems of on-site welding of the support, slow installation progress, difficult ventilation in the basement, and poor construction environment caused by smoke and dust in the traditional installation method.
[0052] Step 4) Setting of hoisting points 31: Each set of steel structure brackets 1 is provided with two hoisting points 31 fixed to the top floor 3 of the air-conditioning main machine room, so that all pipes 4 of the set of steel structure brackets 1 can be installed;
[0053] Step 5) Installation of the hoisting system 2: Two sets of hoisting systems 2 are installed on both sides of each set of steel structure brackets 1, and the upper ends of the two sets of hoisting systems 2 pass through the two hoisting points 31 of the floor slab 3 respectively;
[0054] Step 6) Hoisting of the pipeline 4: The pipelines 4 from far to near the hoisting point 31 are hoisted onto the steel structure support 1 in sequence through the hoisting system 2.
[0055] The anchor bolts 113 described in step 2) of the present invention are arranged at the support column 111 of the single-layer support 11, and the support column 111 is fixed to the floor 5 of the air-conditioning main room through the anchor bolts 113, so that the single-layer support 11 is fixed to the floor 5 of the air-conditioning main room, and a shock-absorbing rubber pad 115 is installed under the bottom plate 114 of the support column 111. By arranging the shock-absorbing rubber pad 115, not only the support column 111 is tightly fixed to the floor 5, but also a shock-absorbing effect can be achieved.
[0056] The two support columns 111 of the single-layer support 11 in step 3) of the present invention are distributed at both ends of the support beam 112 and connected by bolts, and the two short columns 122 of the ∏-shaped component 12 are distributed at both ends of the short beam 121, and the short columns 122 and the short beam 121 are connected by bolts.
[0057] When the present invention is specifically implemented, the hoisting system 2 in step 5) is composed of a mobile joist 21 and a hoisting structure 22. The mobile joist 21 is movably installed on one side of the steel structure support 1. The hoisting structure 22 is composed of a hoisting beam 221, a lifting ring 222, and a fall chain 223. The lifting ring 222 is arranged between the hoisting beam 221 and the fall chain 223, one end of the lifting ring 222 is connected to the hoisting beam 221, and the other end of the lifting ring 222 is connected to one end of the fall chain 223. The movable joist 21 is connected to the other end of the fall chain 223, a steel pipe sling 224 is installed at the other end, and a barb 225 is fixed at the lower end of the steel pipe sling 224, wherein the movable joist 21 is composed of a joist connecting plate 211 and a pipe hoop 212, the pipe hoop 212 is installed at the upper end of the joist connecting plate 211, a plurality of round holes 2111 are opened on the joist connecting plate 211, and the plurality of round holes 2111 are spaced apart from each other, and pipe hoops matching the round holes 2111 are provided at both ends of the pipe hoop 212 The pipe clamp 212 is fixed to the two circular holes 2111 of the joist connecting plate 211 by the pipe clamp bolts at both ends, thereby realizing the fixation of the pipe clamp 212. The pipe clamp 212 is used to fix the pipe 4, and it is also convenient for the pipe 4 to be lifted up simultaneously with the joist connecting plate 211. The reason for setting multiple circular holes 2111 is mainly to meet the installation needs of pipe clamps 212 of different pipe diameters, thereby meeting the fixation of different pipes 4. The present invention also has a lifting ear 213 installed on one side of the joist connecting plate 211, and a mounting hole is opened on the other side of the joist connecting plate 211. The mobile joist 21 fixes the pipe 4 through the pipe clamp 212 on the joist connecting plate 211, and a lifting part 2121 is installed above the pipe clamp 212, and a sling 23 is provided between the mobile joist 21 and the lifting ring 222 of the lifting structure 22, and one end of the sling 23 is connected to the lifting ear 213 of the mobile joist 21, and the other end of the sling 23 is connected to the lifting ring 222. The barb 225 at the lower end of the steel pipe sling 224 can hook the lifting part 2121 of the pipe clamp 212, so as to facilitate the lifting of the pipe clamp 212. The present invention cooperates with the movable support beam 21 and the lifting structure 22, so that the pipe 4 can be lifted to the elevation position where the pipe 4 is required to be installed on the steel structure support 1, thereby improving the safety and convenience of steel pipe lifting. The lifting structure 22 of the present invention can realize the vertical lifting of the pipe 4, so that the pipe 4 can be lifted vertically into place, avoiding oblique penetration, and improving the stability and safety of the lifting of the pipe 4.
[0058] The present invention also provides positioning holes that match the mounting holes of the movable joist 21 on the support column 111 and the short column 122, respectively, and mounting bolts 24 that match the positioning holes and the mounting holes are provided at the positioning holes. The movable joist 21 matches the mounting bolts 24 and the positioning holes through the mounting holes, and the movable joist 21 is movably installed on one side of the support column 111 or the short column 122, so that the pipe 4 on the movable joist 21 can be hoisted to the support beam 112 above the support column 111 or the short beam 121 above the short column 122.
[0059] The hoisting of the pipeline 4 to the steel structure support 1 in step 6) includes the following two hoisting stages:
[0060] Step 61) First hoisting stage: hoist the pipeline 4 onto the single-layer support 11;
[0061] Step 62) Second hoisting stage: hoist the pipeline 4 onto the ∏-shaped component 12 of the double-layer support.
[0062] The first stage of lifting includes the following lifting steps:
[0063] Step 611), first install the two support columns 111 and the support beam 112 of the single-layer support 11;
[0064] Step 612), first install the lifting components such as the lifting ring 222, the fall chain 223, the steel pipe sling 224, and the barb 225 of the two sets of lifting structures 22, and then fix them through one end of the lifting ring 222 through the floor 3;
[0065] Step 613), fix the first pipe 41 farthest from the hanging point to the pipe clamp 212 of the movable joist 21;
[0066] Step 614), hoist the first pipe 41 farthest from the hoisting point together with the movable joist 21 to the height of the support beam 112 of the single-layer support 11 through the hoisting structure 22;
[0067] Step 615), connect the mobile joist 21 to the support column 111 with the mounting bolts 24, and tighten the mobile joist 21 and the lifting ring 222 with the sling 23;
[0068] Step 616), remove the steel pipe sling 224, remove the pipe clamp 212 between the first pipe 41 and the movable joist 21, let the first pipe 41 roll from the movable joist 21 to the installation position of the support beam 112, and then lower the movable joist 21 and the barb 225 to the ground 5;
[0069] Step 617), fix the second pipe 42 which is second farthest from the hanging point to the pipe clamp 212 of the movable joist 21;
[0070] Step 618), hoist the second pipe 42 which is the second farthest from the hoisting point together with the movable joist 21 to the height of the support beam 112 of the single-layer support 11 through the hoisting structure 22;
[0071] Step 619), connect the movable joist 21 to the support column 111 with the mounting bolts 24, and tighten the movable joist 21 and the lifting ring 222 with the sling 23;
[0072] Step 6110), remove the steel pipe sling 224, remove the pipe clamp 212 between the second pipe 42 and the movable joist 21, let the second pipe 42 roll from the movable joist 21 to the installation position of the support beam 112, and then lower the movable joist 21 and the barb 225 to the ground 5;
[0073] Repeat the above steps to install all the pipes 4 on the support beams 112 of the single-layer support 11, so that all the pipes 4 on the support beams 112 of the single-layer support 11 are installed in place.
[0074] The second lifting stage includes the following lifting steps:
[0075] Step 621), assemble the short crossbeam 121 and the two short columns 122 into a ∏-shaped component 12, and install the ∏-shaped component 12 above the support crossbeam 112 of the steel structure support 1 with fixing bolts;
[0076] Step 622), fix the third pipe 43 farthest from the hanging point to the pipe clamp 212 of the movable joist 21;
[0077] Step 623), hoist the third pipe 43 farthest from the lifting point together with the movable joist 21 to the height of the short crossbeam 121 of the ∏-shaped component 12 through the hoisting structure 22;
[0078] Step 624), connect the mobile joist 21 with the short column 122 of the ∏-shaped component 12 with the mounting bolt 24, and tighten the mobile joist 21 and the lifting ring 222 with the sling 23;
[0079] Step 625), remove the steel pipe sling 224, remove the pipe clamp 212 between the third pipe 43 and the movable joist 21, let the third pipe 43 roll from the movable joist 21 to the installation position of the support beam 112, and then lower the movable joist 21 and the barb 225 to the ground 5;
[0080] Step 626), put the fourth pipe 44 which is the second farthest from the hanging point on the pipe clamp 212 of the movable joist 21;
[0081] Step 627), hoist the fourth pipe 44 which is the second farthest from the lifting point together with the movable joist 21 to the height of the short crossbeam 121 of the ∏-shaped component 12 through the hoisting structure 22;
[0082] Step 628), connect the movable joist 21 with the short column 122 of the ∏-shaped component 12 with the mounting bolts 24, and tighten the movable joist 21 and the lifting ring 222 with the sling 23;
[0083] Step 629), remove the steel pipe sling 224, remove the pipe clamp 212 between the fourth pipe 44 and the movable joist 21, let the fourth pipe 44 roll from the movable joist 21 to the installation position of the short crossbeam 121, and then lower the movable joist 21 and the barb 225 to the ground 5;
[0084] The above steps are repeated to hoist the pipe 4 onto the ∏-shaped component 12 of the double-layer support, so that all the pipes 4 on the short crossbeam 121 of the ∏-shaped component 12 are installed in place.
[0085] Compared with the prior art, the technical solution disclosed in the above embodiment has the following beneficial effects:
[0086] In the above embodiment, the construction method of the present invention only needs to set two lifting points 31 on the floor 3, the lifting points are few and firm and reliable, and only needs to set two lifting points 31 on the floor 3 and set two sets of lifting structures 22 to complete the installation of the pipes 4 of each set of steel structure brackets 1, which solves the problem of high construction intensity of setting a large number of lifting points 31 on the top floor of the machine room in the traditional installation scheme. The barb 225 of the steel pipe sling 224 can hook the lifting part 2121 of the pipe hoop 212, and the pipe hoop 212 can be hung. The present invention only needs to set two lifting points 31 on the floor 3 and two sets of lifting structures 22 The use of the through-floor 3 setting can improve the reliability of the lifting point, and the number of lifting points required is small. Only two lifting points 31 and two groups of lifting structures 22 need to be set on the floor 3 to complete the installation of the pipes 4 of each group of steel structure supports 1, which solves the problem of high construction intensity caused by the need to set a large number of lifting points 31 on the top floor of the machine room in the traditional installation scheme. The pipe 4 can be lifted onto the steel structure support 1 by cooperating with the lifting structure 22 and the movable support beam 21. The present invention can lift the pipe 4 vertically into place through the lifting structure 22, avoids oblique lifting of the pipe 4, and improves the stability of the lifting of the pipe 4.
[0087] The above is a preferred embodiment of the present invention. It should be pointed out that a person skilled in the art can make several improvements and modifications without departing from the principle of the present invention. These improvements and modifications are also considered to be within the scope of protection of the present invention.
Claims
1. A construction method for installing steel structure brackets and pipelines in an air-conditioning main room, characterized in that: The invention relates to a construction method for installing a plurality of sets of steel structure brackets and pipelines in an air-conditioning main machine room, and the construction method comprises the following steps: Step 1) BIM forward design of the computer room: The equipment installation process of the air-conditioning main room is involved in advance. Before the concrete construction stage of the computer room, BIM forward design is fully applied to arrange the equipment, drainage ditches, pipes, and steel structure brackets in the air-conditioning main room. The pipes are arranged against the wall and not directly above the air-conditioning chiller; Step 2) Pre-embedded anchor bolts: During the civil construction of the base plate of the air-conditioning main machine room, 6 to 8 sets of anchor bolts are set at the installation position of each single-layer bracket to firmly fix the single-layer bracket to the ground of the air-conditioning main machine room. The anchor bolts are set at the bracket columns of the single-layer bracket, and the bracket columns are fixed to the ground of the air-conditioning main machine room through the anchor bolts, so that the single-layer bracket is fixed to the ground of the air-conditioning main machine room, and a shock-absorbing rubber pad is installed under the base plate of the bracket columns; Step 3) Installation of steel structure support: The steel structure support is set as a single-layer support or a double-layer support according to the number of pipelines and the spatial position. The single-layer support is assembled from two support columns and a support beam. The double-layer support is composed of a single-layer support and a ∏-shaped component. The ∏-shaped component is assembled from a short beam and two short columns. Step 4) Setting of hoisting points: Each set of steel structure brackets is provided with two hoisting points fixed to the top floor of the air-conditioning main machine room; Step 5) Installation of the hoisting system: Two sets of hoisting systems are installed on both sides of each set of steel structure supports. The upper ends of the two hoisting systems pass through the two hoisting points of the floor slab respectively. The hoisting system consists of a movable joist and a hoisting structure. The movable joist is movably installed on one side of the steel structure support. The movable joist consists of a joist connecting plate and a pipe clamp. The pipe clamp is installed on the upper end of the joist connecting plate. A lifting ear is installed on one side of the joist connecting plate, and a mounting hole is opened on the other side of the joist connecting plate. The movable joist is connected to the joist connecting plate through the joist connecting plate. The pipe clamp on the pipe is used to fix the pipeline. A lifting part is installed above the pipe clamp. The lifting structure consists of a lifting beam, a lifting ring, and a fall chain. The lifting ring is set between the lifting beam and the fall chain. One end of the lifting ring is connected to the lifting beam, and the other end of the lifting ring is connected to one end of the fall chain. A steel pipe sling is installed at the other end of the fall chain. A barb is fixed at the lower end of the steel pipe sling. A sling is set between the movable joist and the lifting ring of the lifting structure. One end of the sling is connected to the lifting ear of the movable joist, and the other end of the sling is connected to the lifting ring. Step 6) Pipeline hoisting: Use the hoisting system to hoist the pipelines from far to near the hoisting point onto the steel structure support in sequence.
2. The construction method for installing steel structure brackets and pipelines in the main room of an air conditioner according to claim 1, characterized in that: The two support columns of the single-layer support described in step 3) are distributed at both ends of the support beam and connected by bolts, and the two short columns of the ∏-shaped component are distributed at both ends of the short beam, and the short columns and the short beam are connected by bolts.
3. The construction method for installing steel structure brackets and pipelines in the main room of an air conditioner according to claim 1, characterized in that: Positioning holes matching with the mounting holes of the movable joist are respectively provided on the support column and the short column, and mounting bolts matching with the positioning holes and the mounting holes are provided at the positioning holes. The movable joist matches with the mounting bolts and the positioning holes through the mounting holes, so that the movable joist can be movably installed on one side of the support column or the short column.
4. The construction method for installing steel structure brackets and pipelines in an air-conditioning main room according to claim 1, characterized in that: The lifting of the pipeline to the steel structure support described in step 6) includes the following two lifting stages: Step 61) First hoisting stage: hoist the pipeline onto the single-layer support; Step 62) Second lifting stage: Lift the pipe onto the ∏-shaped part of the double-layer support.