A method for scheduling and planning aircraft offshore platform operations
Through an integrated aircraft offshore platform operation scheduling method, time efficiency, resource utilization and energy consumption are optimized, solving the problems of low efficiency and resource waste in the existing technology, and achieving more efficient offshore platform operations and resource management.
Patent Information
- Application Number
- CN202411016767.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-29
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2044-07-29
Smart Images

Figure CN118552010B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to a method for scheduling operations on an aircraft offshore platform, specifically a method for scheduling operations on an integrated aircraft offshore platform, belonging to the technical field of operation scheduling methods. Background Technology
[0002] In existing maritime aircraft platform operation scheduling, there are widespread problems of low overall support efficiency and low resource utilization. These problems mainly stem from the following aspects:
[0003] ① Isolated operational phases: Traditional aircraft offshore platform operation scheduling often isolates phases such as outbound and inbound operations, offshore platform transfer, aircraft maintenance support, and deployment and departure, lacking effective coordination and integration, resulting in low overall operational efficiency.
[0004] ② Inaccurate resource matching: In the process of matching aircraft with support resources, the lack of precise scheduling strategies often leads to resource waste or shortage, making it impossible to maximize the use of limited support resources.
[0005] ③ Insufficient scheduling optimization: Existing scheduling methods often lack consideration for the comprehensive effectiveness of multiple objectives and fail to effectively balance the optimization needs of time efficiency, personnel resources, equipment resources and energy consumption, resulting in low comprehensive support efficiency.
[0006] ④ Outdated technology: Traditional scheduling methods rely on human experience and lack advanced technical support, making it impossible to achieve refined management and real-time optimization, which increases operating costs and time. Summary of the Invention
[0007] The purpose of this invention is to solve the problems in the prior art and propose an aircraft offshore platform operation scheduling method. This method is oriented towards integrated and multi-objective comprehensive efficiency, aiming to improve the comprehensive support efficiency and resource utilization of aircraft offshore platform operations, reduce operating costs, and improve support efficiency.
[0008] To solve the above problems, this application provides the following technical solution:
[0009] A method for scheduling and planning operations of aircraft on offshore platforms, characterized by the following steps:
[0010] S1. Set the scheduling model and its initialization parameters: Select the simulation object, set the number of simulation objects, and equip it with the corresponding settings to establish the scheduling model. This scheduling model can complete the integrated support of the ship's deck, including inbound and outbound storage and deck transfer, maintenance support, and deployment and departure.
[0011] S2. Establish scheduling model constraints: Apply conditional constraints to the scheduling model established in step S1, including path library constraints, scheduling timing constraints, and guarantee unit constraints.
[0012] S3. Determine the objective function: Based on the constraints in step S2, set the corresponding objective function, which includes the time efficiency, personnel resources, equipment resources, and energy consumption of each sub-process.
[0013] S4. Process the objective function of step S3 to obtain the final objective function: First, normalize the objective function obtained in step S3, and then determine the weights to obtain the final objective function.
[0014] S5. Solve for the objective function.
[0015] Further, step S1 specifically involves: using a fleet of aircraft on a maritime platform as the simulation object, setting the fleet type to be fixed-wing aircraft of the same model, setting the combat objective to perform an air-to-surface combat mission, and setting the sortie scale to n aircraft, requiring n aircraft to be transferred from the hangar to the deck parking position to complete the integrated shipboard support including hangar entry and exit and deck transfer, aircraft maintenance support, and sortie and departure; the supporting setup includes aircraft maintenance procedures, aircraft maintenance personnel, and support equipment; regarding the aircraft maintenance procedures: since the aircraft are of the same model for air-to-surface combat... The missile loadout consists of two air-to-air missiles and two surface-to-surface missiles. Regarding the maintenance personnel, the transfer speed is 5 km / h, and based on the requirements of n-aircraft combat sorties, four specialties are established, totaling 40 maintenance personnel. The service support equipment is divided into seven categories: refueling stations / vehicles, power supply stations / vehicles, oxygen filling stations / vehicles, nitrogen filling stations / vehicles, hydraulic filling stations / vehicles, power stations / vehicles, and missile loading vehicles. The power stations / vehicles are shared service support equipment, while the others are dedicated equipment. The missile loading vehicles are mobile support equipment.
[0016] The gas station / vehicle, power supply station / vehicle, oxygen filling station / vehicle, nitrogen filling station / vehicle, and hydraulic filling station / vehicle are numbered sequentially as follows: The transfer speed is 3 km / h, and the supply resources corresponding to each service equipment are: The original parking positions A2~A13 and B1~B4 will be renumbered as 1-16; regarding the takeoff and departure settings, considering the impact of warm-up on the island superstructure, parking positions A3-A6 cannot be used for warm-up tasks; regarding takeoff position interference, since runway 1# and runway 3# overlap, takeoff position C1 will interfere with runway 3# when performing takeoff or holding position preparation, parking position A12 and holding position C3 will interfere with each other, and the aircraft configuration for performing takeoff missions meets the takeoff position requirements.
[0017] Furthermore, the path library constraint in step S2 is as follows: when an aircraft is moved between different parking positions, it needs to be transferred on the ship deck according to the established transfer path library;
[0018] The initiation of a transport operation first requires the constraint of having a feasible transport route, meaning that there are no other aircraft deployed along the transport route: Road t ( ( P ih , P ij , Ap Sz ij ) ) ≠∅ , t ∈ [ Sz ij , Ez ij ] ,
[0019] In the formula, Let the start and end times be the times for transporting the i-th aircraft to the j-th process. Assemble the planes. Let t0 represent the path taken by an aircraft from parking position p to parking position q, starting from any time t0. The aircraft's deployment status;
[0020] Secondly, if there are parking space conflicts when different aircraft are being moved, they must be moved in order of priority, that is: ,
[0021] In the formula, This refers to the start time of the transfer of the i-th aircraft to the j-th process. Let BM be the start time for the g-th process of transporting the e-th aircraft, where BM is a sufficiently large real number, taken as 10000 here.
[0022] Furthermore, the scheduling timing constraints in step S2 include aircraft scheduling timing constraints and resource transfer support timing constraints;
[0023] The aircraft scheduling timing constraints take the aircraft as the research object and include timing constraints for the aircraft transfer phase, timing constraints for the support phase, timing constraints for the two-phase coupling, and timing constraints for the connection between the two phases.
[0024] The timing constraints for the transit phase are expressed as follows: In the formula, Let the start and end times be the times for transporting the i-th aircraft to the j-th process. The relocation time interval is determined by calling the offshore platform path library and considering the relationship between the parking positions before and after the aircraft relocation.
[0025] ;
[0026] The timing constraints for the guarantee phase are expressed as follows: In the formula, Let be the completion time of the j-th process for the i-th aircraft. Let j be the start time of the operation for the i-th aircraft. The time used for the j-th phase of support operations for the i-th aircraft;
[0027] The timing constraints of the coupling between the transfer phase and the support phase are expressed as follows: , , Let j be the start time of the operation for the i-th aircraft. The end time for transporting the i-th aircraft through the j-th process. This refers to the start time of the transfer of the i-th aircraft to the j-th process. Let h be the completion time of the h-th operation for the i-th aircraft, and for the i-th aircraft, the h-th operation is the preceding operation of the j-th operation.
[0028] The constraints governing the transition between the transit phase and the support phase are expressed as follows: ,in, This refers to the start time of the transfer of the i-th aircraft to the j-th process. U represents the completion time of the j-th process for the i-th aircraft. d U represents the set of procedures for aircraft takeoff and departure. s This represents the set of procedures for supporting aircraft fleet operations.
[0029] Furthermore, the resource transfer timing constraints in step S2 include personnel transfer support timing constraints and aircraft departure takeoff support constraints.
[0030] The timing constraint for personnel transfer support is expressed as follows: In the formula, and These represent the transfer times for support personnel and support resources and equipment, respectively.
[0031] The transfer time for maintenance personnel is The transfer time of service equipment is expressed as This includes equipment startup preparation time. Transfer time of equipment between workstations and equipment placement time ;
[0032] Among them, the takeoff support constraints for aircraft departure are affected by the aircraft wake field; two consecutively departing aircraft must meet the wake time interval requirement, that is: , ,
[0033] In the formula, For the first The start time of the j-th process for building an aircraft. Let be the completion time of the j-th process for the i-th aircraft. This refers to the wake interval time.
[0034] Furthermore, the constraints of the support unit in step S2 include resource support capacity constraints and support station constraints. Specifically, these refer to various support resource constraints involved in the integrated support plan, including equipment and personnel constraints, work space constraints, instantaneous supply constraints of supply resources, and constraints between the allocation and demand of various resources.
[0035] The resource support capacity constraints are affected by the number of maintenance personnel required for the process, the number of service support equipment, and the resource supply capacity.
[0036] Because there are upper limits on the number of maintenance personnel in different specialties, for any given time t, the number of maintenance personnel required for any single specialty in a set of maintenance procedures performed simultaneously must not exceed the total number of personnel in that specialty. ,
[0037] In the formula, Matching state variables to the aircraft crew, if ; For process Demand for professional support personnel in category k; The number of personnel in the k-th category of support ;
[0038] For exclusive protection equipment, at any time t, the demand of a set of operations simultaneously performing protection for any resource type of protection equipment must not exceed the total number of protection equipment of that type, that is: ,
[0039] In the formula, For 0-1 parameter variables, process The demand for the kth type of support equipment; For the kth type of protection equipment ;
[0040] For shared equipment, since it can simultaneously support multiple aircraft operations, the demand for support equipment at any given time can be determined by the 0-1 variable sgn function: ,
[0041] in, For 0-1 parameter variables, process The demand for the kth type of support equipment, For the kth type of protection equipment ;
[0042] The specific constraints on the protection station positions are as follows:
[0043] When support personnel from different specialties perform the same process, the number of support personnel required cannot exceed the number of support personnel that the workstation can accommodate at the same time due to space constraints. That is, for any aircraft i and its k-th type of workstation, we have: ,
[0044] in, For 0-1 parameter variables, process Demand for the kth type of support station; This represents the upper limit of the number of personnel responsible for the k-th type of workstation on aircraft i.
[0045] Furthermore, the time efficiency in step S3 includes the offshore platform operation cycle C. max And the cumulative time of deployment delay (SD);
[0046] Among them, the offshore platform operation cycle C max It is a combination of the transfer and support operation cycle and the deployment and departure cycle, specifically referring to the operation time to complete the entire support process, that is: ,
[0047] In the formula, the time for the machine group to complete the final process is... As part of the offshore platform's operational cycle. This represents the time it takes for the i-th aircraft to complete the final process.
[0048] The cumulative sortie delay time SD refers to the sortie and departure phase. Based on the time reserve requirements for the combat mission, the sortie time of aircraft formation b should be earlier than or equal to the ideal departure time. Therefore, the minimum cumulative delay time for aircraft sortie is: .
[0049] Furthermore, the personnel efficiency in step S3 includes the comprehensive transfer time TW of the offshore platform, the comprehensive resource load variance LB, and the peak fatigue level Sf;
[0050] The comprehensive transfer time (TW) for offshore platforms is divided into the transfer phase, the maintenance and support phase, and the deployment and departure phase. ,
[0051] In the formula, Defined as a 0-1 decision variable: representing the first... Class of protection category After a worker completes process Oij, they move on to the next process Oeg to ensure its smooth operation. ,otherwise ; Indicates workstation and workstation The distance between them;
[0052] The comprehensive resource load variance LB is oriented towards the transfer phase, the maintenance support phase, and the deployment / departure phase: ,
[0053] In the formula, Indicates the first The first type of protection work The ratio of an employee's free time to their working time. Indicates the first The average idle-to-busy ratio for this type of support staff;
[0054] in: , C max For deck operation cycle, The time used for the support operation of the i-th aircraft in the j-th phase. For the introduced 0-1 decision variables,
[0055] ,
[0056] The fatigue peak level Sf is oriented towards the maintenance support phase: For personnel in a concentrated and continuous support work state, based on the fatigue accumulation law and referring to the normal distribution function, the fatigue increase model is as follows: ,
[0057] In the formula, Represents the normal distribution function. and Let be the mean and variance of the normal distribution function, respectively, and let be the fatigue rate. ;
[0058] For support personnel who are idle, their fatigue level decreases accordingly. In contrast to the fatigue increase model, the fatigue decrease model is as follows: In the formula, and These are the mean and variance of a fatigue-decreasing normal distribution, respectively.
[0059] The fatigue deceleration rate is: ;
[0060] Assume the first Category 1 The set of NWkl work time segments assigned to the support personnel Δ Tw kl = { [ sw i kl , ew i kl ] } 1 × NW kl ,correspond A set of idle time slots Δ Tq kl = { [ sq i kl , eq i kl ] } 1 × NW kl − 1 The peak fatigue level of the support personnel is then expressed as:
[0061] The peak fatigue levels of all support personnel are accumulated to obtain the peak fatigue level. .
[0062] Furthermore, the equipment resources in step S3 include the equipment resource vacancy rate Ru and the peak resource supply level Rp. The equipment resource vacancy rate Ru is geared towards the aircraft transfer and maintenance support phases. ,in, For the number of Class k security equipment, For the introduced 0-1 decision variables, ;
[0063] The peak resource supply level Rp is geared towards the maintenance and support phase.
[0064] The average number of instantaneous occurrences when various resources reach their limits is used as an indicator to measure the peak level of average resource supply. R p = ∑ t ∈ [ 1 , C max ] ∑ k ∈ Kw ( 1 − sgn ( Lw k − ∑ i ∈ I sgn ( ∑ j ∈ A t rw ijk ) ) ) / C max ⋅ | Kw | ,in, The number of aircraft that can be simultaneously supported by the k-th type of support resources. For process For the demand for the k-th type of guaranteed resources, For deck operation cycle, To ensure sufficient resources.
[0065] Furthermore, the energy consumption in step S3 includes resource transfer energy consumption We and fleet transfer energy consumption Wf. The resource transfer energy consumption We is geared towards the aircraft transfer and maintenance support phases, and is divided into human-driven and electric-driven modes. A resource transfer energy consumption index is constructed based on the weighted sum of equipment transfer distances. With energy consumption coefficient we kl To distinguish between human-powered and electric-powered, in the formula, For 0-1 intermediate decision variables, if the first... Class 1 After each support device completes process Oij, it is transferred to process Oeg for support. Otherwise, it is 0.
[0066] The peak resource supply level Rp is oriented towards the transfer and departure phases, and a fleet transport / taxiing energy consumption index is constructed using the weighted sum of fleet transfer distances as a metric: In the formula, Let be an intermediate decision variable of 0-1. If the i-th aircraft is directly transferred from the j-th process to the g-th process for support, then... Otherwise, it is 0, and the energy consumption coefficient wn is 0. ij This distinguishes between self-powered gliding and tractor-mounted transport.
[0067] Furthermore, the normalization process in step S4 is specifically calculated as follows: to form an effective mapping for performance of the nine objectives, the indicators should first be normalized. The smaller the mapping of the above indicators, the better, thereby forming a normalization process between different optimization indicators and between optimization indicators and performance objectives.
[0068] Using standard 0-1 transformation, any objective function Let its boundary range be The normalized index value is: To narrow the search range, improve search speed, and find the optimal solution more quickly, the deterministic boundary index of offshore platform operation cycle is... and cumulative time of deployment delay By employing deterministic boundary values, the search range for solutions is limited, and the upper limit of the offshore platform operation cycle is determined. The timeframes are 1+00h, 1+20h, 1+30h, 1+40h, etc., with the lower limit appropriately reduced by 45 minutes based on the task scale from the upper limit; the cumulative delay time for formation deployment. The lower limit is 0, and the upper limit can be the product of the number of mobile aircraft and the maximum average delay time.
[0069] When the value exceeds the upper limit, a penalty term based on an exponential function is introduced, thereby reducing the overall performance evaluation of the objective function. For boundary update indicators, except and The remaining indicators are all boundary update indicators, meaning that the boundary is updated in real time according to the scheduling solution during the optimization search process.
[0070] Furthermore, the determination of the index weights in step S4 is as follows: the order relation method based on the double Kendall test is used to determine the weights of the objective function, and the results are fused to form an efficiency optimization objective. By weighting the indicators, the multi-objective optimization problem is transformed into a single-objective problem of finding the optimal feasible solution.
[0071] objective function The weight is The performance indicators are: Regarding the weighting of performance indicators, the weight values of each indicator were obtained by merging the calculation results of the ordinal relation method based on the double Kendall test. The weight values are as follows: offshore platform operation cycle Cmax 0.212, deployment delay cumulative time SD 0.146, offshore platform comprehensive transfer time TW 0.097, comprehensive resource load variance LB 0.11, fatigue peak level Sf 0.053, equipment resource vacancy rate Ru 0.199, resource supply peak level Rp 0.081, resource transfer energy consumption We 0.035, and fleet transfer energy consumption Wf 0.067.
[0072] Furthermore, in step S5, the MATLAB function Optimization is used to solve the constructed scheduling model.
[0073] Compared with existing technologies, this invention has the following positive effects: simulation time shows that it is faster than manual experience scheduling; from the perspective of resource utilization, it improves the overall support efficiency and resource utilization of aircraft and reduces operating costs; and simulation data provides more comprehensive performance indicators and more detailed time-series scheduling schemes. Attached Figure Description
[0074] Figure 1 This is a flowchart of the present invention;
[0075] Figure 2 For the deck operation completion time convergence curve;
[0076] Figure 3 For the convergence curve of cumulative time for deployment delay;
[0077] Figure 4 The convergence curve of equipment resource vacancy rate;
[0078] Figure 5 The convergence curve of the comprehensive resource load variance;
[0079] Figure 6 The fatigue peak level convergence curve;
[0080] Figure 7 The convergence curve of equipment resource vacancy rate;
[0081] Figure 8 For the peak level convergence curve of resource supply;
[0082] Figure 9 The energy consumption convergence curve for resource transfer;
[0083] Figure 10 The energy consumption convergence curve for fleet transfer;
[0084] Figure 11 AON diagram for single-machine support operation procedures;
[0085] Figure 12 Gantt chart to ensure personnel movement;
[0086] Figure 13 To ensure the smooth operation of equipment scheduling using Gantt charts;
[0087] Figure 14 Gantt chart for takeoff position scheduling;
[0088] Figure 15 A Gantt diagram for equipment and personnel scheduling. Detailed Implementation
[0089] The following detailed embodiments of the present invention are given with reference to the accompanying drawings, which are used to further illustrate the structure of the present invention.
[0090] Example 1. A method for scheduling and planning aircraft operations on offshore platforms, the specific process of which is as follows: Figure 1 As shown, it includes the following steps:
[0091] S1. Set the scheduling model and its initialization parameters: Select the simulation object, set the number of simulation objects, and equip it with the corresponding settings to establish the scheduling model. This scheduling model can complete the integrated support of the ship's deck, including inbound and outbound storage and deck transfer, maintenance support, and deployment and departure.
[0092] S2. Establish scheduling model constraints: Apply conditional constraints to the scheduling model established in step S1, including path library constraints, scheduling timing constraints, and guarantee unit constraints.
[0093] S3. Determine the objective function: Based on the constraints in step S2, set the corresponding objective function, which includes the time efficiency, personnel resources, equipment resources, and energy consumption of each sub-process.
[0094] S4. Process the objective function of step S3 to obtain the final objective function: First, normalize the objective function obtained in step S3, and then determine the weights to obtain the final objective function.
[0095] S5. Solve for the objective function.
[0096] Further, step S1 specifically involves: using a fleet of aircraft on a maritime platform as the simulation object, setting the fleet type to be fixed-wing aircraft of the same model, setting the combat objective to perform an enemy combat mission, and setting the fleet size to n aircraft sorties, requiring n aircraft to be transferred from the hangar to the deck parking positions to complete integrated shipboard support including hangar entry and exit, deck transfer, maintenance support, and sortie and departure; in this embodiment, the fleet size is 12 aircraft sorties, and 12 aircraft are transferred from the hangar to the deck parking positions. The aircraft assigned to the sortie missions and the initial parking positions are shown in Table 1.
[0097] Table 1: Initial parking positions for aircraft on offshore platforms
[0098] ,
[0099] The supporting setup includes aircraft maintenance procedures, maintenance personnel, and support equipment. Regarding the aircraft maintenance procedures: since these are air-to-surface combat aircraft of the same model, the armament configuration includes two air-to-air missiles and two surface-to-surface missiles; a single-aircraft maintenance procedure AON diagram is constructed, as follows... Figure 11As shown in the figure, the required configuration quantity for each process marked in the figure is 1.
[0100] Regarding the personnel setup for aircraft maintenance, the transfer speed is 5km / h. Based on the requirements of a 12-aircraft combat sortie mission, four specialties are set up, totaling 40 aircraft maintenance personnel. The work content of each process and the required aircraft maintenance personnel specialties and service support equipment are shown in Table 2.
[0101] Table 2: Work Contents for Ensuring Successful Processes
[0102] ,
[0103] The aforementioned service support equipment is categorized into seven types: refueling stations / vehicles, power supply stations / vehicles, oxygen filling stations / vehicles, nitrogen filling stations / vehicles, hydraulic filling stations / vehicles, power supply stations / vehicles, and ammunition loading vehicles. Among these, power supply stations / vehicles are shared service support equipment, while the rest are exclusive equipment; ammunition loading vehicles are mobile support equipment.
[0104] The gas station / vehicle, power supply station / vehicle, oxygen filling station / vehicle, nitrogen filling station / vehicle, and hydraulic filling station / vehicle are numbered sequentially as follows: The transfer speed is 3 km / h, and the supply resources corresponding to each service equipment are: The original parking positions A2~A13 and B1~B4 were renumbered as 1-16, and the service support equipment coverage of the parking positions is shown in Table 3.
[0105] Table 3: Coverage of parking positions for support equipment
[0106] ,
[0107] Regarding the takeoff and departure setup, considering the impact of warm-up on the island superstructure, parking positions A3-A6 cannot be used for warm-up tasks. As for takeoff position interference, since runway #1 and runway #3 overlap, takeoff position C1 will interfere with runway #3 when preparing for takeoff or holding position. Parking position A12 and holding position C3 interfere with each other. The aircraft configuration for the sortie mission meets the takeoff position requirements.
[0108] Furthermore, the path library constraint in step S2 is as follows: when an aircraft is moved between different parking positions, it needs to be transferred on the ship deck according to the established transfer path library;
[0109] The initiation of a transport operation first requires the constraint of having a feasible transport route, meaning that there are no other aircraft deployed along the transport route: Road t ( ( P ih , P ij , Ap Sz ij ) ) ≠∅ , t ∈ [ Sz ij , Ez ij ] In the formula, Let the start and end times be the times for transporting the i-th aircraft to the j-th process. Assemble the planes. Let t0 represent the path taken by an aircraft from parking position p to parking position q, starting from any time t0. The aircraft's deployment status;
[0110] Secondly, if there are parking space conflicts when different aircraft are being moved, they must be moved in order of priority, that is: , ,
[0111] In the formula, This refers to the start time of the transfer of the i-th aircraft to the j-th process. Let BM be the start time for the g-th process of transporting the e-th aircraft, where BM is a sufficiently large real number, taken as 10000 here.
[0112] Further, the scheduling timing constraints in step S2 include aircraft scheduling timing constraints and resource transfer support timing constraints; wherein, the aircraft scheduling timing constraints take the aircraft as the research object, and the aircraft scheduling timing constraints include aircraft transfer phase timing constraints, support phase timing constraints, two-phase coupling timing constraints, and two-phase connection constraints; wherein, the transfer phase timing constraints are expressed as: In the formula, Let the start and end times be the times for transporting the i-th aircraft to the j-th process. The relocation time interval is determined by calling the offshore platform path library and considering the relationship between the parking positions before and after the aircraft relocation.
[0113] ;
[0114] The timing constraints for the guarantee phase are expressed as follows: In the formula, Let be the completion time of the j-th process for the i-th aircraft. Let j be the start time of the operation for the i-th aircraft. The time used for the j-th phase of support operations for the i-th aircraft;
[0115] Considering the two-stage coupling timing constraints, there are two main factors: First, the aircraft transfer operation must be completed before the maintenance support can be carried out in the same stage; second, the aircraft transfer operation in the next stage can only be carried out after the support operation in the previous stage is completed.
[0116] The timing constraints of the coupling between the transfer phase and the support phase are expressed as follows: , , Let j be the start time of the operation for the i-th aircraft. The end time for transporting the i-th aircraft through the j-th process. This refers to the start time of the transfer of the i-th aircraft to the j-th process. Let h be the completion time of the h-th operation for the i-th aircraft, and for the i-th aircraft, the h-th operation is the preceding operation of the j-th operation.
[0117] The coordination between aircraft maintenance support and sortie / departure requires that support operations be completed before the aircraft fleet can be sorted / departed; the constraints on the coordination between the transfer phase and the support phase are expressed as follows: ,
[0118] in, This refers to the start time of the transfer of the i-th aircraft to the j-th process. U represents the completion time of the j-th process for the i-th aircraft. d U represents the set of procedures for aircraft takeoff and departure. s This represents the set of procedures for supporting aircraft fleet operations.
[0119] Furthermore, the resource transfer timing constraints in step S2 include personnel transfer support timing constraints and aircraft departure takeoff support constraints.
[0120] The timing constraints of resource transfer support are mainly influenced by two factors: first, different priority processes must be carried out within the same resource support entity; second, provided the preceding process is completed, the next process can only proceed after the resource has been transferred from the support entity to the designated workstation. Figure 15 A Gantt diagram for equipment and personnel scheduling.
[0121] From process O in the diagram eg It can be seen that in the preceding process O pq O ij O bd After all procedures are completed, the next support process can only proceed after the transfer of support personnel and equipment from different specialties is completed; as shown in the diagram. Indicates the first Class 1 One resource guarantee device, Indicates belonging to the first The first of the security profession Security personnel, These represent different support procedures;
[0122] The timing constraint for personnel transfer support is expressed as follows: In the formula, and These represent the transfer times for support personnel and support resources and equipment, respectively.
[0123] The transfer time for maintenance personnel is The transfer time of service equipment is expressed as This includes equipment startup preparation time. Transfer time of equipment between workstations and equipment placement time ;
[0124] Among them, the takeoff support constraints for aircraft departure are affected by the aircraft wake field; two consecutively departing aircraft must meet the wake time interval requirement, that is: , ,
[0125] In the formula, For the first The start time of the j-th process for building an aircraft. Let be the completion time of the j-th process for the i-th aircraft. This refers to the wake interval time.
[0126] Furthermore, the constraints of the support unit in step S2 include resource support capacity constraints and support station constraints. Specifically, these refer to various support resource constraints involved in the integrated support plan, including equipment and personnel constraints, work space constraints, instantaneous supply constraints of supply resources, and constraints between the allocation and demand of various resources. Among these, the resource support capacity constraints are affected by the number of maintenance personnel required for the process, the number of service support equipment, and the resource supply capacity.
[0127] Because there are upper limits on the number of maintenance personnel in different specialties, for any given time t, the number of maintenance personnel required for any single specialty in a set of maintenance procedures performed simultaneously must not exceed the total number of personnel in that specialty. ,
[0128] In the formula, Matching state variables to the aircraft crew, if ; For process Demand for professional support personnel in category k; The number of personnel in the k-th category of support ;
[0129] Similar to the timing constraints of resource support, the support capacity constraints also differ because service support equipment is divided into exclusive and shared types.
[0130] For exclusive protection equipment, at any time t, the demand of a set of operations simultaneously performing protection for any resource type of protection equipment must not exceed the total number of protection equipment of that type, that is: ,
[0131] In the formula, For 0-1 parameter variables, process The demand for the kth type of support equipment; For the kth type of protection equipment ;
[0132] For shared equipment, since it can simultaneously support multiple aircraft operations, the demand for support equipment at any given time can be determined by the 0-1 variable sgn function: ,
[0133] in, For 0-1 parameter variables, process The demand for the kth type of support equipment, For the kth type of protection equipment ;
[0134] The specific constraints on the protection station positions are as follows:
[0135] When support personnel from different specialties perform the same process, the number of support personnel required cannot exceed the number of support personnel that the workstation can accommodate at the same time due to space constraints. That is, for any aircraft i and its k-th type of workstation, we have: ,
[0136] in, For 0-1 parameter variables, process Demand for the kth type of support station; This represents the upper limit of the number of personnel responsible for the k-th type of workstation on aircraft i.
[0137] To construct a holistic constraint model for shipboard support and formulate a systematic optimization objective, it is necessary to comprehensively consider the time efficiency, personnel resources, equipment resources, and energy consumption of each sub-process. Simultaneously, it is necessary to consider the coupling of performance indicators among the various sub-processes, which can be achieved by merging relevant indicators into a unified performance index. For example, in the time efficiency category, the transfer support operation cycle and the deployment / deployment cycle are merged to obtain the offshore platform operation cycle; in the equipment usage category, the transfer equipment vacancy rate and the support equipment vacancy rate are merged to obtain the resource equipment vacancy rate; and the aircraft group taxiing energy consumption and the tractor transfer energy consumption are merged to obtain the aircraft group transfer energy consumption. In this way, the original indicator structure is transformed into an objective function oriented towards integrated scheduling through merging.
[0138] Furthermore, the time efficiency in step S3 includes the offshore platform operation cycle C. max And the cumulative time of deployment delay (SD);
[0139] Among them, the offshore platform operation cycle C max It is a combination of the transfer and support operation cycle and the deployment and departure cycle, specifically referring to the operation time to complete the entire support process, that is: ,
[0140] In the formula, the time for the machine group to complete the final process is... As part of the offshore platform's operational cycle. This represents the time it takes for the i-th aircraft to complete the final process.
[0141] The cumulative sortie delay time SD refers to the sortie and departure phase. Based on the time reserve requirements for the combat mission, the sortie time of aircraft formation b should be earlier than or equal to the ideal departure time. Therefore, the minimum cumulative delay time for aircraft sortie is: .
[0142] Furthermore, the personnel efficiency in step S3 includes the comprehensive transfer time TW of the offshore platform, the comprehensive resource load variance LB, and the peak fatigue level Sf;
[0143] The aforementioned comprehensive transfer time (TW) for offshore platforms encompasses the transfer phase, maintenance support phase, and deployment / departure phase. Due to the complex and variable environment of the offshore platform deck and the numerous hazards, such as the exhaust plumes generated during aircraft transfer and deck taxiing, and route conflicts between personnel transfer and equipment / resource transfer, it is necessary to reduce the comprehensive cumulative transfer time for deck support personnel. Reducing transfer time thereby lowers the safety risks associated with personnel transfer and the degree of interference with support procedures. ,
[0144] In the formula, Defined as a 0-1 decision variable: representing the first... Class of protection category After a worker completes process Oij, they move on to the next process Oeg to ensure its smooth operation. ,otherwise ; Indicates workstation and workstation The distance between them;
[0145] The comprehensive resource load variance LB is oriented towards the transfer phase, maintenance support phase, and deployment / departure phase. The peak workload of support personnel determines their performance. If too much support work is concentrated on a few personnel, it directly affects their work status and efficiency, causing an imbalance in workload. Therefore, it is necessary to evenly distribute support work under given support task requirements to minimize the variance of the idle-to-busy ratio of support personnel. In the formula, Indicates the first The first type of protection work The ratio of an employee's free time to their working time. Indicates the first The average idle-to-busy ratio for this type of support staff;
[0146] in: , Cmax For deck operation cycle, The time used for the support operation of the i-th aircraft in the j-th phase. For the introduced 0-1 decision variables,
[0147] ,
[0148] The fatigue peak level Sf is oriented towards the maintenance and support phase:
[0149] For personnel engaged in continuous, intensive support work, maintaining a good working condition is fundamental to the efficient operation of aircraft maintenance support. As support procedures continue for extended periods, fatigue gradually accumulates among personnel, and high fatigue levels directly impact the efficiency and safety of support work. The peak fatigue level assessment considers how to manage fatigue without affecting support mission requirements. This involves rationally allocating and adjusting the working hours of support personnel, providing reasonable rest periods for those in continuous, intensive support work, thereby achieving a fatigue "peak reduction" effect. Based on the accumulation pattern of fatigue and referencing the normal distribution function, the fatigue progression model is as follows:
[0150] In the formula, Represents the normal distribution function. and These represent the mean and variance of the normal distribution function, respectively. Based on the working cycle of offshore platforms and actual surveys of the fatigue levels of support personnel, it is assumed that 90 minutes of continuous support work represents the peak fatigue level. The criterion is to take the interval (0, 90) as the corresponding value. The cumulative distribution function For the interval, then we have , The rate of increase in fatigue level is: ;
[0151] For support personnel who are idle, their fatigue level decreases accordingly. In contrast to the fatigue increase model, the fatigue decrease model is as follows: In the formula, and Let be the mean and variance of a normally distributed fatigue level, respectively. Assuming fatigue disappears after 60 minutes of continuous rest, then... , The fatigue deceleration rate is: ;
[0152] Assume the first Category 1 The set of NWkl work time segments assigned to the support personnel Δ Tw kl = { [ sw i kl , ew i kl ] } 1 × NW kl ,correspond A set of idle time slots Δ Tq kl = { [ sq i kl , eq i kl ] } 1 × NW kl − 1 The peak fatigue level of the support personnel is then expressed as:
[0153] The peak fatigue levels of all support personnel are accumulated to obtain the peak fatigue level. .
[0154] Furthermore, the equipment resources in step S3 include the equipment resource vacancy rate Ru and the peak resource supply level Rp.
[0155] The equipment resource vacancy rate Ru is geared towards the aircraft transfer and maintenance support phases. Concentrated use of support equipment will accelerate equipment performance degradation. To avoid an uneven distribution of usage where some equipment is used too frequently during support work, resulting in idle equipment on other devices, all available equipment should be utilized as much as possible during support procedures. Therefore, the equipment resource vacancy rate Ru is: ,in, For the number of Class k security equipment, For the introduced 0-1 decision variables, ;
[0156] The aforementioned peak resource supply level Rp is geared towards the aircraft maintenance support phase. Due to limitations in aircraft aviation support technology, the instantaneous supply of resources such as oil, electricity, gas, and hydraulics is subject to upper limits. To ensure the safe operation of aviation support work, full-load supply of resources should be avoided. The average number of instantaneous times when various resources reach their upper limits is used as an indicator to measure the average peak resource supply level. R p = ∑ t ∈ [ 1 , C max ] ∑ k ∈ Kw ( 1 − sgn ( Lw k − ∑ i ∈ I sgn ( ∑ j ∈ A t rw ijk ) ) ) / C max ⋅ | Kw | ,in, The number of aircraft that can be simultaneously supported by the k-th type of support resources. For process For the demand for the k-th type of guaranteed resources, For deck operation cycle, To ensure sufficient resources.
[0157] Furthermore, the energy consumption in step S3 includes resource transfer energy consumption We and fleet transfer energy consumption Wf. The resource transfer energy consumption We is geared towards the aircraft transfer and maintenance support phase. When mobile support equipment is transferred between different workstations, energy resources are consumed. Based on the power attributes of the equipment transfer, it is divided into manual drive and electric drive. A resource transfer energy consumption index is constructed using the weighted sum of equipment transfer distances as a metric. ,
[0158] With energy consumption coefficient we kl To distinguish between human-powered and electric-powered, in the formula, For 0-1 intermediate decision variables, if the first... Class 1 After each support device completes process Oij, it is transferred to process Oeg for support. Otherwise, it is 0.
[0159] The peak resource supply level Rp is geared towards the transfer and departure phases. Since the transfer of aircraft fleets on offshore platforms also consumes resources and energy, it can be categorized into two methods based on aircraft transport attributes: self-powered taxiing and towing vehicle transport. Self-powered taxiing is used for temporary aircraft landings and transfers to takeoff positions, while towing vehicles are primarily used for other phases. An energy consumption index for aircraft fleet transport / taxiing, measured by the weighted sum of aircraft fleet transfer distances, is constructed. In the formula, Let be an intermediate decision variable of 0-1. If the i-th aircraft is directly transferred from the j-th process to the g-th process for support, then... Otherwise, it is 0, and the energy consumption coefficient wn is 0. ij This distinguishes between self-powered gliding and tractor-mounted transport.
[0160] Furthermore, the normalization process in step S4 is specifically calculated as follows: to form an effective mapping for performance of the nine objectives, the indicators should first be normalized. The smaller the mapping of the above indicators, the better, thereby forming a normalization process between different optimization indicators and between optimization indicators and performance objectives.
[0161] Using standard 0-1 transformation, any objective function Let its boundary range be The normalized index value is: To narrow the search range, improve search speed, and find the optimal solution more quickly, the deterministic boundary index of offshore platform operation cycle is... and cumulative time of deployment delay By employing deterministic boundary values, the search range for solutions is limited, and the upper limit of the offshore platform operation cycle is determined. The lower limit is set at 1+00h, 1+20h, 1+30h, 1+40h, etc., with the lower limit appropriately reduced from the upper limit based on the scale of the task.
[0162] Cumulative delay time for formation deployment The lower limit is 0, and the upper limit can be the product of the number of mobile aircraft and the maximum average delay time.
[0163] When the value exceeds the upper limit, a penalty term based on an exponential function is introduced, thereby reducing the overall performance evaluation of the objective function. For boundary update indicators, except and The remaining indicators are all boundary update indicators, meaning that the boundary is updated in real time according to the scheduling solution during the optimization search process.
[0164] Furthermore, the determination of the indicator weights in step S4 is as follows:
[0165] The order relation method based on the double Kendall test is used to determine the weights of the objective function and integrate them to form an efficiency optimization objective. By weighting the indicators, the multi-objective optimization problem is transformed into a single-objective problem of finding the optimal feasible solution.
[0166] objective function The weight is The performance indicators are: Regarding the weighting of performance indicators, the weight values of each indicator were obtained by merging the calculation results of the ordinal relation method based on the double Kendall test. The weight values are as follows: offshore platform operation cycle Cmax 0.212, deployment delay cumulative time SD 0.146, offshore platform comprehensive transfer time TW 0.097, comprehensive resource load variance LB 0.11, fatigue peak level Sf 0.053, equipment resource vacancy rate Ru 0.199, resource supply peak level Rp 0.081, resource transfer energy consumption We 0.035, and fleet transfer energy consumption Wf 0.067.
[0167] Furthermore, in step S5, the MATLAB function Optimization is used to solve the constructed scheduling model.
[0168] Example 2. This example uses simulation experiments to solve the objective function.
[0169] The constructed scheduling model was solved using the MATLAB function `Optimization`, yielding the following result: Figures 1-10 The efficiency convergence curves of the nine sub-objectives shown represent the iterative trends of the efficiency sub-objectives, which are the changes in the corresponding sub-objective values during the iterative optimization of the main efficiency objective.
[0170] The graph shows the cumulative time of deployment delay. Equipment resource vacancy rate Ru, equipment resource peak level The target optimization value converges relatively quickly, stabilizing after 200 iterations. This is due to the comprehensive guarantee efficiency. The result is the fusion of weights for multiple performance sub-objectives, and it tends to stabilize after 600 iterations. During the optimization process, the values of each performance sub-objective may "jump". This is because the extreme boundary of the indicator is updated and recorded in real time during the optimization process. As the boundary value of the indicator changes, it affects the performance optimization value of the overall objective, and may in turn affect the iterative optimization of other performance sub-objectives.
[0171] Then, the solution results can be visualized for verification, such as... Figures 12-14 The figures shown are Gantt charts for personnel scheduling, equipment scheduling, and takeoff position scheduling. These charts map various JZJ support processes onto the same timeline, enabling unified allocation of processes and timing for aircraft, personnel, resources, and equipment involved in multiple JZJ processes, thus forming an efficiency-oriented integrated JZJ scheduling system. Figure 12 , Figure 13 As can be seen, parallel processes exist in the aircraft maintenance support process, and these parallel processes are simultaneously supported by constraints such as personnel and equipment resources. Furthermore, the various sub-processes in the integrated shipboard support do not exist in isolation; different sub-processes are coupled by constraints such as time, procedures, and resource allocation, further verifying the synergy of efficiency-based integrated aircraft scheduling operations.
[0172] from Figure 14 As can be seen from the diagram, there are three takeoff positions. The Gantt chart on the schedule indicates the aircraft number and the aircraft process number. Taking C1 as an example, it went through the third and fourth processes of the third aircraft, and the third and fourth processes of the eighth aircraft.
[0173] The specific embodiments described herein are merely illustrative examples of the spirit of the invention. Those skilled in the art to which this invention pertains may make various modifications or additions to the described specific embodiments or use similar methods to substitute them, without departing from the spirit of the invention or exceeding the defined scope.
Claims
1. A method for scheduling and planning aircraft offshore platform operations, characterized in that: The following steps are involved: S1. Setting the scheduling model and initialization parameters of the scheduling model: selecting the simulation object, setting the number of simulation objects, and equipping corresponding supporting settings to establish the scheduling model; S2. Establishing scheduling model constraints: Conditionally constraining the scheduling model established in step S1, including path library constraints, scheduling timing constraints, and security unit constraints; S3, determine the objective function: according to the constraint conditions of step S2, set the corresponding objective function, which includes the time efficiency, personnel resources, equipment resources and energy consumption between each sub-process; The time efficiency includes the offshore platform operation cycle C max and the cumulative time of sortie delay SD; Wherein, the offshore platform operation cycle C max It is the combination of the transit support operation cycle and the dispatch and departure cycle, specifically referring to the operation time to complete the entire support process, namely: , In the formula, the time it takes for the cluster to complete the last process is As an offshore platform operation cycle, It indicates the time when the i-th aircraft completes the last process; The cumulative delay time SD is for the departure phase. According to the time reservation requirements for combat missions, the departure time of aircraft fleet formation b should be earlier than or equal to the ideal departure time. Therefore, the cumulative delay time of the aircraft fleet is minimized as follows: ; The personnel resources include the offshore platform comprehensive transfer time TW, comprehensive resource load variance LB and fatigue peak level Sf; The comprehensive transfer time TW of the offshore platform is for the transfer stage, the maintenance support stage and the departure stage: , In the formula, Defined as a 0-1 decision variable: Category of protection After completing process Oij, personnel will transfer to the next process Oeg for support. ,otherwise ; Indicates workstation and workstation The distance between The comprehensive resource load variance LB is oriented to the transfer stage, maintenance support stage and departure stage: , In the formula, Indicates Category 1 The ratio of idle time to working time of each employee, Indicates The average idle-busy ratio of the security personnel; in: , , C max For the deck operation cycle, is the time taken for the j-th phase of the support operation for the i-th aircraft, is the introduced 0-1 decision variable, The fatigue peak level Sf is for the maintenance support stage: For personnel in a state of centralized and continuous support work, according to the accumulation law of fatigue, with reference to the normal distribution function, the fatigue increment model is as follows: , where represents the normal distribution function, and are the mean and variance of the normal distribution function respectively; the fatigue degree increasing rate is: ; For support personnel who are in an idle state, their fatigue level decreases accordingly. Contrary to the fatigue increasing model, the fatigue decreasing model is as follows: , where and are the mean and variance of the normal distribution of fatigue decrement, respectively; The fatigue deceleration rate is: ; Assume Category A set of NWkl operation time segments assigned by the support personnel ,correspond Idle time segment set , then the peak fatigue level of the support personnel is expressed as: , the accumulated fatigue peaks of all support personnel are accumulated to obtain the fatigue peak level Sf: ; The equipment resources include the equipment resource vacancy rate Ru and the resource supply peak level Rp. The equipment resource vacancy rate Ru is for the aircraft transfer and maintenance support stage. ,in, is the number of k-th category safeguard equipment, is the introduced 0-1 decision variable, ; The resource supply peak level Rp is for the maintenance service support stage. The instantaneous average number of times each resource reaches its upper limit is used as an indicator to measure the average resource supply peak level: ,in, The number of aircraft that can be supported by the k-th type of support resources at the same time, For process The demand for the k-th type of security resources is: For the deck operation cycle, To ensure the quantity of resources; The energy consumption includes resource transfer energy consumption We and cluster transfer energy consumption Wf. The resource transfer energy consumption We is oriented to the aircraft transfer and maintenance support stage, and is divided into human-driven and electric-driven. A resource transfer energy consumption index is constructed based on the weighted sum of equipment transfer distances: , The energy consumption coefficient we kl To distinguish between human-powered and electric-powered, is a 0-1 intermediate decision variable. Class After the guarantee equipment completes process Oij, it is transferred to process Oeg for guarantee. , otherwise 0, The resource supply peak level Rp is oriented to the transfer and departure phases, and constructs a fleet transportation / taxiing energy consumption index measured by the weighted sum of fleet transfer distances: , In the formula, is a 0-1 intermediate decision variable. If the i-th aircraft is directly transferred from the j-th process to the g-th process, then , otherwise it is 0, the energy consumption coefficient wn ij To distinguish between self-powered taxiing and tractor transportation; S4, processing the objective function of step S3 to obtain a final objective function: first normalizing the objective function obtained in step S3, and then determining the weight to obtain the final objective function; S5. Solve the objective function obtained in step S4.
2. The method for scheduling and planning aircraft offshore platform operations according to claim 1, characterized in that: The step S1 is specifically as follows: The simulation object is the offshore platform fleet, and the fleet type is set as fixed-wing aircraft of the same model. The combat goal is set to perform the opposite combat mission. The fleet dispatch scale is n aircraft dispatched, and n aircraft are transferred from the hangar to the deck parking position to complete the ship-deck integrated support including in and out of the hangar and deck transfer, maintenance service support, and dispatch and departure. The supporting facilities include maintenance support procedures, maintenance support personnel and service support equipment.
3. The method for scheduling and planning aircraft offshore platform operations according to claim 1 or 2, characterized in that: The path library constraints in step S2 are as follows: When an aircraft is transferred between different parking positions, it is transferred on the ship's surface according to the established transfer path library; The start of the transfer must first satisfy the constraint of a feasible transfer path, that is, there are no other aircraft on the transfer path: , In the formula, The start time and end time of the j-th process for the i-th aircraft, Assemble for the aircraft, It is represented as the path of the aircraft being transferred from parking position p to parking position q starting from any time t0, The aircraft's deployment status; Secondly, if there is a parking space conflict when different aircraft are transferred, they need to be transferred in order of priority, that is: , , In the formula, is the start time of the j-th process for the i-th aircraft, The start time of the g-th process for the e-th aircraft, and BM is 10000.
4. The method for scheduling and planning aircraft offshore platform operations according to claim 3, characterized in that: The scheduling timing constraints in step S2 include aircraft scheduling timing constraints and resource transfer guarantee timing constraints; The aircraft scheduling timing constraints take the aircraft as the research object, and the aircraft scheduling timing constraints include aircraft transfer phase timing constraints, support phase timing constraints, two-stage coupling timing constraints, and two-stage connection constraints; Among them, the timing constraints of the transfer stage are expressed as: , where The start time and end time of the j-th process for the i-th aircraft, To calculate the time interval for transportation, the offshore platform path library is called and the relationship between the parking positions before and after the aircraft transportation is obtained: ; The timing constraints in the guarantee phase are expressed as: , where is the completion time of the jth process of the i-th aircraft, is the start time of the jth process of the i-th aircraft, The time taken for the j-th phase of support work for the i-th aircraft; The coupled timing constraints of the transport phase and the guarantee phase are expressed as follows: , , is the start time of the jth process of the i-th aircraft, is the end time of the transportation of the jth process for the i-th aircraft, is the start time of the j-th process for the i-th aircraft, is the completion time of the h-th process of the i-th aircraft, and for the i-th aircraft, the h-th process is the predecessor process of the j-th process; The connection constraint between the transfer stage and the guarantee stage is expressed as: ,in, is the start time of the j-th process for the i-th aircraft, is the completion time of the jth process of the i-th aircraft, U d Represents the set of procedures for aircraft departure, U s Represents a set of processes for fleet support operations.
5. The method for scheduling and planning aircraft offshore platform operations according to claim 4, characterized in that: The resource transfer timing constraints in step S2 include personnel transfer guarantee timing constraints and aircraft departure guarantee constraints; The personnel transfer guarantee timing constraint is expressed as: , where and Respectively represent the transfer time of support personnel and support resource equipment; The transfer time of maintenance personnel is , The transfer time of service equipment is expressed as , including equipment startup preparation time , Equipment transfer time between workstations and equipment placement time ; Among them, the takeoff support constraints of the aircraft departure are affected by the aircraft wake flow field. The two aircraft dispatched continuously should meet the wake time interval requirements, that is: , , In the formula, For the The start time of the jth process of an aircraft, is the completion time of the jth process of the i-th aircraft, is the wake interval time.
6. The method for scheduling and planning aircraft offshore platform operations according to claim 5, characterized in that: The support unit constraints in step S2 include resource support capability constraints and support station constraints, which specifically refer to various support resource constraints involved in the integrated support planning, including equipment and personnel constraints, operating space constraints, supply resource instantaneous supply constraints, and constraints between the allocation and demand of various resources; The resource support capacity constraint is affected by the number of maintenance support personnel, the number of service support equipment, and the resource supply capacity required for the process; Since there is an upper limit on the number of maintenance personnel of different professions, at any time t, the number of maintenance personnel required for any professional set of processes that are simultaneously executed must not exceed the total number of personnel in that profession, that is: , In the formula, is the aircraft crew matching state quantity, if ; For process The demand for professional support personnel of category k; is the number of security personnel of the kth category ; For exclusive guarantee equipment, at any time t, the demand for guarantee equipment of any resource type by the set of processes that simultaneously execute guarantee shall not exceed the total number of guarantee equipment of this type, that is: , In the formula, is a 0-1 parameter variable, process The demand for the kth type of support equipment; Category K protection equipment ; For shared equipment, since multiple processes of the aircraft can be supported at the same time, the demand for service support equipment at the same time can be determined by the 0-1 variable sgn function: , in, is a 0-1 parameter variable, process The demand for the kth type of security equipment, Category K protection equipment ; The specific constraints of the guaranteed station position are as follows: When different professional support personnel perform the same process, due to the space limitation of the workstation, the number of support personnel required shall not exceed the number of support personnel that the workstation can accommodate at the same time. That is, for any aircraft i, the k-th workstation has: , in, is a 0-1 parameter variable, process The demand for the k-th type of security station; The upper limit of the number of personnel required to support the k-th workstation of aircraft i.
7. The method for scheduling and planning aircraft offshore platform operations according to claim 1 or 2, characterized in that: The normalization process in step S4 is specifically calculated as follows: Using the standard 0-1 transformation, any objective function , and its boundary range is , then the normalized index value is: , Deterministic boundary indicators of offshore platform operation cycle and cumulative time of delay in dispatching The deterministic boundary value is used to limit the search range of the solution, and the upper limit of the offshore platform operation cycle is 1+00h, 1+20h, 1+30h or 1+40h, with the lower limit reduced by 45 minutes from the upper limit according to the task size; Cumulative delay time for formation deployment The lower limit is 0, and the upper limit is the product of the number of aircraft dispatched and the maximum average delay time; When the value exceeds the upper limit, a penalty term based on an exponential function is introduced to reduce the comprehensive performance evaluation of the objective function, that is, ,For boundary update indicators, the boundary is updated in real time according to the scheduling solution during the optimization search process.
8. The method for scheduling and planning aircraft offshore platform operations according to claim 1 or 2, characterized in that: The determination of the indicator weight in step S4 is as follows: The order relationship method based on the double Kendall test is used to determine the weight of the objective function, which is then integrated to form the efficiency optimization goal. By weighting the indicators, the multi-objective optimization problem is converted into a single-objective optimal feasible solution problem. Objective Function The weight is , then the performance index is: In terms of setting the weight of performance indicators, the weight value of each indicator is obtained by combining the calculation results of the order relationship method based on the double kendall test. The operating cycle of the offshore platform Cmax is 0.212, the cumulative time of the dispatch delay SD is 0.146, the comprehensive transfer time of the offshore platform TW is 0.097, the comprehensive resource load variance LB is 0.11, the fatigue peak level Sf is 0.053, the equipment resource vacancy rate Ru is 0.199, the resource supply peak level Rp is 0.081, the resource transfer energy consumption We is 0.035, and the fleet transfer energy consumption Wf is 0.
067.
9. The method for scheduling and planning aircraft offshore platform operations according to claim 1 or 2, characterized in that: In step S5, MATLAB is used to call the Optimization function to solve the constructed scheduling model.
Citation Information
Patent Citations
Shipboard aircraft dynamic guarantee scheduling method and device based on rolling time domain optimization
CN112734223A
Aircraft in-out warehouse transfer scheduling method and device and computer equipment
CN116009524A