Method for reinforcing and lifting rail foundation in workshop

By setting up lifting layers and reinforcement layers in industrial plants, and using oblique grouting technology and monitoring point control, the problem of track settlement has been solved, precise lifting of the track and foundation reinforcement have been achieved, secondary settlement has been avoided, and equipment safety has been ensured. of normal use.

CN118727518APending Publication Date: 2024-10-01BEIJING HENGXIANG HONGYE FOUND REINFORCEMENT TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411071163.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-06
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

In industrial plants, the phenomenon of track settlement causes large equipment to be unable to slide. The existing grouting method has problems such as the track not being lifted or secondary settlement, which affects normal use.

Method used

A method of reinforcing and raising the track foundation inside the factory workshop is adopted. By setting up the lifting layer and the reinforcement layer under the track foundation, using oblique grouting technology, setting the grouting hole positions and monitoring points, controlling the grouting pressure and condensation speed, and realizing the track Precise lifting and foundation reinforcement.

Benefits of technology

It achieves precise and rapid lifting of the track foundation and reinforcement of the foundation, avoids secondary settlement, enhances the bearing capacity and anti-deformation ability of the foundation, and ensures the normal use of the equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118727518A_ABST
    Figure CN118727518A_ABST
Patent Text Reader

Abstract

The invention discloses a method for reinforcing and lifting a track foundation in a plant workshop, which comprises the following steps of: arranging a lifting layer and a reinforcing layer below a track foundation, arranging grouting hole positions, lifting holes and grouting holes, and accurately arranging each monitoring point position. According to the method, through shallow layer grouting lifting, grouting is conducted in a small range, grout is solidified, lifting force is generated, and the track foundation is accurately and rapidly lifted; after the lifting of the track foundation is completed, grouting reinforcement is continuously performed on the soft foundation below the foundation, so that the bearing capacity and the deformation resistance of the foundation are enhanced, and the secondary settlement of the track foundation is avoided. The grouting hole positions are arranged in a row shape, and inclined punching and grouting are performed, so that the grouting pipe goes deep into the middle position of the bottom of the track foundation, grout can be utilized more effectively, and the purpose of accurate lifting is achieved; by arranging monitoring points, the displacement of the track and the terrace can be monitored at any time; displacement of a track monitoring point can be used as a standard for completing track lifting.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of track foundation reinforcement and lifting, and in particular to a method for reinforcing and lifting a track foundation inside a factory workshop. Background Art

[0002] With the vigorous development of my country's manufacturing industry, the construction of industrial plants is increasing day by day. Generally, tracks are arranged inside the plants to carry large equipment. During use, track settlement occurs from time to time. After the track settles, the bottom of the large equipment will be close to the ground, making it impossible to slide, affecting normal use and causing delays in work and time. The track can be raised by grouting, but the current grouting method has many problems due to the order and location of grouting, such as the ground around the track bulging before the track is raised; or after the track is raised, secondary settlement occurs under the repeated action of the equipment load. Therefore, we invented a method for reinforcing and lifting the track foundation inside the workshop of a factory. Summary of the invention

[0003] The invention provides a method for reinforcing and lifting the track foundation inside a factory workshop, which is used to solve technical problems such as grouting layout, monitoring and lifting reinforcement layer setting of the factory workshop track.

[0004] To achieve the above object, the present invention adopts the following technical solution:

[0005] A method for reinforcing and lifting the track foundation inside a workshop, wherein a track foundation is arranged below the track, a lifting layer is arranged below the track foundation, and a reinforcement layer is arranged below the lifting layer; wherein the lifting layer and the reinforcement layer are separately arranged corresponding to each track foundation; wherein the lifting layer and the reinforcement layer are both obliquely grouted from both sides of the track, the lifting holes corresponding to the lifting layer are grouted, and the reinforcement holes corresponding to the reinforcement layer are grouted; the lifting holes and the reinforcement holes intersect at the top and share a grouting hole position;

[0006] The method of reinforcing and lifting the track foundation inside the factory workshop is as follows:

[0007] Step 1: Arrange the grouting holes. During the grouting reinforcement lifting process, arrange the grouting holes in rows on both sides of the settled track. The distance L between each row of grouting holes and the foundation edge line is determined by the following formula:

[0008]

[0009] In the formula:

[0010] h0—height of track foundation, mm; h1—thickness of lifting layer, mm; h2—depth from floor to top of foundation, mm; h3—thickness of reinforcement layer, mm; L0—1 / 2 of track foundation width, mm;

[0011] Step 2: Determine the inclination angle θ1 of the lifting hole. When the grouting pipe of the lifting hole is driven in, it should be driven in at a certain inclination angle. The grouting pipe should go deep into the middle of the bottom of the foundation and avoid the foundation. The inclination angle θ1 is:

[0012]

[0013] Step 3: Determine the inclination angle θ2 of the reinforcement hole. When the grouting pipe of the reinforcement hole is driven in, it is driven in at a certain inclination angle and penetrates into the middle of the bottom of the foundation. The inclination angle θ2 is:

[0014]

[0015] Step 4: Arrange monitoring points. Arrange track monitoring points on the center line of the track settlement section, arrange lifting monitoring points on both sides of the track, and arrange reinforcement monitoring points near the reinforcement holes. Among them, the track monitoring points are used to monitor whether the track is lifted; the lifting monitoring points are used to monitor whether the floor on both sides of the track bulges when the track foundation bottom is lifted by grouting, and its length from the track foundation edge line is L1; the reinforcement monitoring points are used to monitor whether the floor corresponding to the maximum slurry pressure position bulges when the foundation is reinforced by grouting, and its length from the track foundation edge line is L3.

[0016] L1 and L3 are calculated as follows:

[0017]

[0018] Step 5: Shallow small-scale grouting and lifting. The grouting pipe goes deep into the bottom of the lifting hole. During the grouting process, the displacement changes of the track monitoring point and the lifting monitoring point are observed at any time. The lifting displacement of the track monitoring point must be equal to the settlement value. If there is displacement at the lifting monitoring point, the grouting should be stopped immediately, and the adjacent grouting hole on the other side of the track should be selected for grouting. The grouting pressure and setting speed are the same as before.

[0019] Step six: deep grouting reinforcement. After the track foundation is lifted, the foundation under the lifted layer is reinforced by grouting. During deep grouting reinforcement, the grouting pipe goes deep into the bottom of the reinforcement hole. Observe the displacement changes of the reinforcement monitoring point at any time. If there is displacement, stop grouting immediately and select the adjacent grouting holes on the other side of the track for grouting to evenly fill the foundation soil layer, so that the track foundation will not cause secondary settlement under the load of the upper equipment. In this way, the reinforcement and lifting of the track foundation inside the factory workshop is completed.

[0020] Furthermore, the grouting pressure of the lifting layer is controlled at 2.5-3.0 MPa, and the slurry coagulation speed is controlled at 3-5 seconds, so that the slurry diffusion range is controlled in a smaller area, and shallow small-scale grouting lifting is carried out.

[0021] Furthermore, the width of the lifting layer is no more than twice that of the track foundation, and the thickness of the track foundation lifting layer is no more than 300 mm. Furthermore, a steel plate or grouting is pre-installed at the designed grouting boundary in the horizontal direction of the lifting layer to form a curtain layer, thereby constraining the lifting layer in the lateral direction, which is conducive to the lifting of the track foundation.

[0022] Furthermore, when the shallow layer is lifted, grouting is carried out from bottom to top, and the grouting below forms a bearing layer that slowly squeezes the soil above, causing the settlement of the track foundation to slowly rise.

[0023] Furthermore, the thickness of the reinforcement layer is 1 meter deep into the bottom soil bearing layer, and its width is not less than twice the width of the lifting layer.

[0024] Furthermore, the grouting pressure of the reinforcement layer is controlled at 0.3-0.6 MPa, the slurry setting speed is controlled at 10-60 seconds, and the slurry diffusion radius is about 2 meters, so as to carry out deep grouting reinforcement.

[0025] Furthermore, the top surface of the reinforcement layer is the bottom surface of the lifting layer, or the top surface of the reinforcement layer is concavely arranged on both sides of the lifting layer, and the height of the top surface of the reinforcement layer exceeding the bottom surface of the lifting layer is not more than half of the thickness of the lifting layer.

[0026] Furthermore, strain gauges are arranged at the respective monitoring points of the track monitoring points, lifting monitoring points and reinforcement monitoring points, and then connected with optical fiber sensors. When grouting, the strain displacement of each monitoring point will be transmitted to the display, reflecting the displacement changes of the floor in real time.

[0027] The beneficial effects of the present invention are embodied in:

[0028] 1) The present invention controls the grouting time and grouting pressure through shallow grouting lifting, so that the grouting is carried out in a small range, the slurry solidifies and generates lifting force, so that the track foundation is lifted accurately and quickly; after the track foundation is lifted, the present invention continues to reinforce the weak foundation under the foundation by grouting, thereby enhancing the bearing capacity and deformation resistance of the foundation and avoiding secondary settlement of the track foundation.

[0029] 2) The present invention arranges the grouting holes in a row and performs grouting at an angle, so that the grouting pipe penetrates into the middle of the bottom of the track foundation, which can more effectively utilize the slurry and achieve the purpose of precise lifting;

[0030] 3) The present invention can monitor the displacement of the track and the floor at any time by arranging the track monitoring points, the lifting monitoring points and the reinforcement monitoring points; the displacement of the track monitoring points can be used as the standard for the completion of the track lifting; according to the displacement of the lifting monitoring points and the reinforcement monitoring points, the grouting sequence and the grouting position can be adjusted in real time, thereby preventing the occurrence of bulging of the floor;

[0031] Other features and advantages of the present invention will be set forth in the following description, and in part will become apparent from the description, or may be understood by practicing the present invention; the main purpose and other advantages of the present invention may be realized and obtained through the solutions particularly pointed out in the description. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] Figure 1 It is a schematic diagram of the track foundation reinforcement and lifting profile;

[0033] Figure 2 It is a schematic diagram of the local section of the track foundation reinforcement and lifting;

[0034] Figure 3 It is a schematic diagram of the track foundation reinforcement and lifting plan.

[0035] Figure numerals: 1-equipment, 2-wheel, 3-track, 4-track foundation, 5-lifting layer, 6-reinforcement layer, 7-lifting hole, 8-reinforcement hole, 9-track centerline, 10-floor top surface, 11-foundation edge line, 12-track monitoring point, 13-lifting monitoring point, 14-reinforcement monitoring point. 15-grouting hole position. DETAILED DESCRIPTION

[0036] A workshop has four groups of eight tracks. Equipment 1 and corresponding wheels 2 are installed above track 3. The interval between the two tracks of track 3 is 4.5 meters. The total length of track 3 is 2000 meters. Currently, there are local settlement and cracking, with a settlement of 50 mm. The foundation below the foundation is plain fill, sandy silt and medium sand respectively.

[0037] like Figures 1 to 3 As shown, a track foundation 4 is arranged under the track 3, a lifting layer 5 is arranged under the track foundation 4, and a reinforcement layer 6 is arranged under the lifting layer 5; wherein the lifting layer 5 and the reinforcement layer 6 are separately arranged corresponding to each track foundation 4; wherein the lifting layer 5 and the reinforcement layer 6 are both obliquely grouted from both sides of the track 3, the lifting hole 7 corresponding to the lifting layer 5 is grouted, and the reinforcement hole 8 corresponding to the reinforcement layer 6 is grouted; the lifting hole 7 and the reinforcement hole 8 intersect at the top and share a grouting hole position 15.

[0038] Combination Figures 1 to 3 As shown, the method for reinforcing and lifting the foundation of the internal track 3 of the workshop is further described, and the specific steps are as follows:

[0039] Step 1: Arrange the grouting holes 15. During the grouting reinforcement lifting process, the grouting holes 15 are arranged in rows on both sides of the settled track 3. The distance L between each row of grouting holes 15 and the foundation edge line 11 is determined by the following formula:

[0040]

[0041] In the formula:

[0042] h0—the height of the track foundation 4 is 600mm; h1—the thickness of the lifting layer 5 is 200mm; h2—the depth from the floor to the top of the foundation is 200mm; h3—the thickness of the reinforcement layer 6 is 4300mm; L0—the width of the track foundation 4 is 250mm; through calculation, we get: 1000mm≤L≤1483mm, take L=1200mm.

[0043] Step 2: Determine the inclination angle θ1 of the lifting hole 7. When the grouting pipe of the lifting hole 7 is driven in, it is driven in at a certain inclination angle. The grouting pipe should penetrate into the middle position of the bottom of the foundation and avoid the foundation. The inclination angle θ1 is:

[0044]

[0045] Step 3: Determine the inclination angle θ2 of the reinforcement hole 8. When the grouting pipe of the reinforcement hole 8 is driven in, it is driven in along a certain inclination angle and penetrates into the middle position of the bottom of the foundation. The inclination angle θ2 is:

[0046]

[0047] Step 4, arrange monitoring points, arrange track monitoring point 12 on the center line of the settlement section of track 3, arrange lifting monitoring points 13 on both sides of track 3, and arrange reinforcement monitoring points 14 near reinforcement hole 8; wherein, track monitoring point 12 is used to monitor whether track 3 is lifted; lifting monitoring point 13 is used to monitor whether the floor on both sides of track 3 bulges when grouting and lifting at the bottom of track foundation 4, and its length from the edge line of track foundation 4 is L1; reinforcement monitoring point 14 is used to monitor whether the floor corresponding to the position of maximum slurry pressure bulges when grouting is used to reinforce the foundation, and its length from the edge line of track foundation 4 is L3.

[0048] L1 and L3 are calculated as follows:

[0049]

[0050]

[0051] Step 5: Shallow small-scale grouting and lifting. The grouting pipe goes deep into the bottom of the lifting hole 7. During the grouting process, the displacement changes of the track monitoring point 12 and the lifting monitoring point 13 are observed at any time. The upward displacement of the track monitoring point 12 must be equal to the settlement value. If there is any displacement of the lifting monitoring point 13, the grouting must be stopped immediately and the adjacent grouting hole on the other side of the track 3 must be selected for grouting. The grouting pressure and setting speed are the same as before.

[0052] In this embodiment, the grouting pressure of the lifting layer 5 is controlled at 2.5 MPa, and the slurry coagulation speed is controlled at 3 to 5 seconds, so that the slurry diffusion range is controlled in a smaller area, and shallow small-scale grouting lifting is performed. The width of the lifting layer 5 is not more than twice that of the track foundation 4, and the thickness of the lifting layer 5 of the track foundation 4 does not exceed 300 mm.

[0053] In addition, a steel plate or grouting is pre-installed at the horizontal grouting boundary of the lifting layer 5 to form a curtain layer, thereby constraining the lifting layer 5 in the lateral direction, which is conducive to the lifting of the track foundation 4. When the shallow layer is lifted, the grouting is carried out from bottom to top, and the grouting below forms a bearing layer that slowly squeezes the soil above, so that the settlement of the track foundation 4 is slowly lifted.

[0054] Step six, deep grouting reinforcement. After the track foundation 4 is lifted, the foundation under the lifting layer 5 is reinforced by grouting. During deep grouting reinforcement, the grouting pipe goes deep into the bottom of the reinforcement hole 8. Observe the displacement changes of the reinforcement monitoring point 14 at any time. If there is displacement, stop grouting immediately and select the adjacent grouting holes on the other side of the track 3 for grouting to evenly fill the foundation soil layer densely, so that the track foundation 4 will not cause secondary settlement under the load of the upper equipment. In this way, the reinforcement and lifting of the foundation of the track 3 inside the factory workshop is completed.

[0055] Among them, the top surface of the reinforcement layer 6 is the bottom surface of the lifting layer 5, or the top surface of the reinforcement layer 6 is concavely arranged on both sides of the lifting layer 5 horizontally, and the height of the top surface of the reinforcement layer 6 exceeding the bottom surface of the lifting layer 5 is not more than half of the thickness of the lifting layer 5.

[0056] In this embodiment, the thickness of the reinforcement layer 6 is 1 meter deep into the bottom soil bearing layer, and its width is not less than twice the width of the lifting layer 5. The grouting pressure of the reinforcement layer 6 is controlled at 0.3-0.6 MPa, the slurry setting speed is controlled at 10-60 seconds, and the slurry diffusion radius is about 2 meters, and deep grouting reinforcement is performed.

[0057] During the grouting process, strain gauges are arranged at the track monitoring point 12, the lifting monitoring point 13 and the reinforcement monitoring point 14 at their respective monitoring point locations, and then connected with optical fiber sensors. During grouting, the strain displacement of each monitoring point will be transmitted to the display, reflecting the displacement changes of the floor in real time.

[0058] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that a technician familiar with the technical field can think of within the technical scope disclosed in the present invention should be covered within the protection scope of the present invention.

Claims

1. A method for reinforcing and lifting the track foundation inside a workshop, characterized in that: A track foundation (4) is arranged below the track (3), a lifting layer (5) is arranged below the track foundation (4), and a reinforcement layer (6) is arranged below the lifting layer (5); wherein the lifting layer (5) and the reinforcement layer (6) are arranged separately corresponding to each track foundation (4); wherein the lifting layer (5) and the reinforcement layer (6) are both grouted obliquely from both sides of the track (3), the lifting hole (7) corresponding to the lifting layer (5) is grouted, and the reinforcement hole (8) corresponding to the reinforcement layer (6) is grouted; the tops of the lifting hole (7) and the reinforcement hole (8) intersect and share a grouting hole position (15); The method of reinforcing and lifting the track foundation inside the factory workshop is as follows: Step 1: Arrange grouting holes (15). During the grouting reinforcement lifting process, the grouting holes (15) are arranged in rows on both sides of the settled track (3). The distance L between each row of grouting holes (15) and the foundation edge line (11) is determined by the following formula: In the formula: h0—height of the track foundation (4), mm; h1—thickness of the lifting layer (5), mm; h2—depth from the floor to the top of the foundation, mm; h3—thickness of the reinforcement layer (6), mm; L0—1 / 2 of the width of the track foundation (4), mm; Step 2: Determine the inclination angle θ1 of the lifting hole (7). When the grouting pipe of the lifting hole (7) is driven in, it is driven in along a certain inclination angle. The grouting pipe should penetrate into the middle position of the bottom of the foundation and avoid the foundation. The inclination angle θ1 is: Step 3: Determine the inclination angle θ2 of the reinforcement hole (8). When the grouting pipe of the reinforcement hole (8) is driven in, it is driven in along a certain inclination angle and penetrates into the middle position of the bottom of the foundation. The inclination angle θ2 is: Step 4: Arrange monitoring points, arrange track monitoring points (12) on the center line of the settlement section of the track (3), arrange lifting monitoring points (13) on both sides of the track (3), and arrange reinforcement monitoring points (14) near the reinforcement holes (8); wherein the track monitoring points (12) are used to monitor whether the track (3) is lifted; the lifting monitoring points (13) are used to monitor whether the floor on both sides of the track (3) bulges when the track foundation (4) is lifted by grouting, and the length of the floor from the track foundation (4) is L1; the reinforcement monitoring points (14) are used to monitor whether the floor corresponding to the position with the maximum slurry pressure bulges when the foundation is reinforced by grouting, and the length of the floor from the track foundation (4) is L3; L1 and L3 are calculated as follows: Step 5: Shallow small-scale grouting and lifting. The grouting pipe is inserted into the bottom of the lifting hole (7). During the grouting process, the displacement changes of the track monitoring point (12) and the lifting monitoring point (13) are observed at any time. The lifting displacement of the track monitoring point (12) must be equal to the settlement value. If there is any displacement of the lifting monitoring point (13), the grouting should be stopped immediately and the adjacent grouting hole on the other side of the track (3) should be selected for grouting. The grouting pressure and setting speed are the same as before. Step 6: Deep grouting reinforcement. After the track foundation (4) is lifted, the foundation under the lifted layer (5) is reinforced by grouting. During deep grouting reinforcement, the grouting pipe goes deep into the bottom of the reinforcement hole (8). The displacement changes of the reinforcement monitoring point (14) are observed at any time. If displacement occurs, the grouting should be stopped immediately, and the adjacent grouting holes on the other side of the track (3) should be selected for grouting to evenly fill the foundation soil layer densely, so that the track foundation (4) will not cause secondary settlement under the load of the upper equipment. In this way, the reinforcement and lifting of the foundation of the track (3) inside the workshop is completed.

2. A method for reinforcing and lifting the track foundation inside a workshop as claimed in claim 1, characterized in that: The grouting pressure of the lifting layer (5) is controlled at 2.5-3.0 MPa, and the slurry coagulation speed is controlled at 3-5 seconds, so that the slurry diffusion range is controlled in a smaller area, and shallow small-scale grouting lifting is performed.

3. The method for reinforcing and lifting the track foundation inside a factory workshop as claimed in claim 1, characterized in that: The width of the lifting layer (5) is no more than twice that of the track foundation (4), and the thickness of the lifting layer (5) of the track foundation (4) is no more than 300 mm.

4. The method for reinforcing and lifting the track foundation inside a factory workshop as claimed in claim 1, characterized in that: Steel plates are pre-installed or grouting is performed to form a curtain layer at the designed grouting boundary in the horizontal direction of the lifting layer (5), thereby constraining the lifting layer (5) in the lateral direction, which is beneficial to the lifting of the track foundation (4).

5. The method for reinforcing and lifting the track foundation inside a factory workshop as claimed in claim 1, characterized in that: When the shallow layer is lifted, grouting is carried out from bottom to top, and the lower grouting forms a bearing layer which slowly squeezes the upper soil, causing the settled part of the track foundation (4) to slowly lift.

6. The method for reinforcing and lifting the track foundation inside a factory workshop as claimed in claim 1, characterized in that: The thickness of the reinforcement layer (6) is 1 meter deep into the bottom soil bearing layer, and its width is not less than twice the width of the lifting layer (5).

7. The method for reinforcing and lifting the track foundation inside a workshop as claimed in claim 1, characterized in that: The grouting pressure of the reinforcement layer (6) is controlled at 0.3-0.6 MPa, the slurry coagulation speed is controlled at 10-60 seconds, and the slurry diffusion radius is about 2 meters, so as to carry out deep grouting reinforcement.

8. The method for reinforcing and lifting the track foundation inside a workshop as claimed in claim 1, characterized in that: The top surface of the reinforcement layer (6) is the bottom surface of the lifting layer (5), or the top surface of the reinforcement layer (6) is arranged in a concave shape on both sides of the lifting layer (5), and the height of the top surface of the reinforcement layer (6) exceeding the bottom surface of the lifting layer (5) is not greater than half the thickness of the lifting layer (5).

9. The method for reinforcing and lifting the track foundation inside a workshop as claimed in claim 1, characterized in that: Strain gauges are arranged at the track monitoring point (12), the lifting monitoring point (13) and the reinforcement monitoring point (14) at their respective monitoring point locations, and then connected with optical fiber sensors. When grouting is performed, the strain displacement of each monitoring point will be transmitted to the display, reflecting the displacement change of the floor in real time.