Foundation construction device and working method thereof
By using a grid mechanism to drive the movement of the grid to form an accommodation cavity in the post-grouting technology of the pile bottom, the problem of concrete blocking the grouting port is solved, and the effective solidification of the pile bottom and the improvement of the bearing capacity are achieved.
Patent Information
- Application Number
- CN202410588716.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-13
- Publication Date
- 2024-10-01
AI Technical Summary
In the existing post-grouting technology at the pile bottom, concrete easily falls into the grouting tube and blocks the grouting port, affecting the construction efficiency and effect.
A foundation construction device is designed, including a grid mechanism, a fixing mechanism and a grouting mechanism. The driving part of the grid mechanism drives the movement of the grid mechanism to form a containment cavity that is connected or closed to the outside to prevent concrete from entering the containment cavity. inside to ensure that the grouting port is unobstructed.
It effectively prevents concrete from clogging the grouting port, improves construction efficiency and the solidification effect of the pile bottom, and ensures the increase in the bearing capacity and settlement of the pile.
Smart Images

Figure CN118727722A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of foundation construction, and in particular to a foundation construction device and a working method thereof. Background Art
[0002] At present, in the construction industry, pile bottom post-grouting technology is widely used in actual projects. Its main advantage is that it can effectively solidify the sediment and mud skin at the bottom of the pile, significantly improve the bearing capacity of the pile and reduce the settlement. This technology is particularly suitable for large-diameter and extra-long piles, can be used under a variety of geological conditions, and the construction process is relatively simple and easy to operate.
[0003] The existing post-grouting technology at the pile bottom mainly relies on the use of grouting tubes. The grouting tubes significantly improve the bearing capacity of the soil at the bottom of the pile by reinforcing the sediment, scum and disturbed soil at the bottom of the pile, thereby greatly improving the bearing capacity of the entire pile and reducing the settlement of the pile.
[0004] In the related art, a through channel is provided on the grouting pipe, so that foreign matter can be discharged from the bottom of the hole through the channel when cleaning the hole. However, the channel also causes the concrete poured above the grouting pipe to fall into the grouting pipe through the channel and cover the grouting port, affecting the normal grouting of the grouting port. Summary of the invention
[0005] The purpose of the present invention is to provide a foundation construction device and a working method thereof, so as to solve the technical problem in the prior art that concrete falls into a grouting pipe and blocks a grouting port.
[0006] In order to solve the above technical problems, the present invention provides a foundation construction device, including a grid mechanism, a fixing mechanism and a grouting mechanism;
[0007] The fixing mechanism is provided with a containing cavity, the grouting mechanism extends into the containing cavity and is connected with the fixing mechanism, the grid mechanism is provided on the fixing mechanism, a driving member is provided on the grid mechanism, and the driving member drives the grid mechanism to move relative to the fixing mechanism so that the containing cavity is connected with or closed to the outside through the grid mechanism.
[0008] In an optional embodiment, the grid mechanism includes a first grid and a second grid;
[0009] The first grid and the second grid are arranged at intervals along the axial direction of the fixing mechanism, and the first grid is connected to the driving member.
[0010] In an optional embodiment, a through hole corresponding to the first grille is provided on the fixing mechanism, and the driving member is connected to the fixing mechanism, and the driving member drives the first grille to move relative to the through hole.
[0011] In an optional embodiment, the fixing mechanism includes a pulp bundle pipe, a top plate and a bottom plate;
[0012] The top plate and the bottom plate are arranged in parallel, two ends of the pulp bundle pipe are connected to the top plate and the bottom plate respectively, and the pulp bundle pipe, the top plate and the bottom plate surround the accommodating cavity.
[0013] In an optional embodiment, the diameter of the top plate is greater than the diameter of the bottom plate.
[0014] In an optional embodiment, a steel plate strip is provided on both the top plate and the bottom plate;
[0015] The height direction of the steel strip is arranged parallel to the axis of the top plate, the steel strip on the top plate is extended toward the bottom plate, and the steel strip on the bottom plate is extended toward the top plate. The two steel strips are respectively connected to the two ends of the pulp bundle pipe.
[0016] In an optional embodiment, the grouting mechanism includes a grouting pipe and a one-way valve;
[0017] The grouting pipe is passed through the top plate, the one-way valve is arranged in the accommodating cavity, and the grouting pipe is connected to the one-way valve.
[0018] In an optional embodiment, it also includes a control mechanism and a detection mechanism;
[0019] The control mechanism is connected to the detection mechanism by electrical signals, the control mechanism is connected to the grouting mechanism by electrical signals, and the detection mechanism is arranged at the bottom of the pile.
[0020] The present invention also provides a working method based on the foundation construction device, comprising the following steps:
[0021] Weld the steel cage and the top plate, and extend the fixing mechanism into the pile hole through the steel cage;
[0022] After the fixing mechanism reaches the bottom of the pile, the first grid is opened and the pile hole is cleaned with mud;
[0023] After the hole is cleaned, the mud is pumped away;
[0024] After the slurry is pumped away, the first grid is closed, and then cement slurry is poured into the steel cage to form the upper pile body;
[0025] After the upper pile body is completed, the pile bottom is detected in real time by the detection mechanism, and the grouting parameters are configured according to the detection results of the detection mechanism;
[0026] Inject cement slurry into the accommodation cavity through the grouting pipe and the one-way valve according to the grouting parameters, so that the grouting pipe expands and presses the pile bottom, and the second grid is close to the pile bottom;
[0027] After the grout pipe expands to a certain extent, the cement slurry flows out through the gap between the second grid and the pile bottom and is poured into the pile bottom to form the pile body below.
[0028] In an optional embodiment, the configuration of grouting parameters comprises the following steps:
[0029] After the data of multiple pile bottoms are detected by the detection mechanism, the differences between the multiple data are determined;
[0030] The obtained difference is compared with the difference threshold. When the difference is less than the difference threshold, the grouting parameters of multiple pile bottoms are configured by proportional, integral and differential methods. When the difference is greater than or equal to the difference threshold, the neural network model is used to configure the grouting parameters of multiple pile bottoms according to the grouting parameters and results of each pile bottom in historical cases.
[0031] The present invention provides a foundation construction device, including a grid mechanism, a fixing mechanism and a grouting mechanism; a containing cavity is arranged in the fixing mechanism, the grouting mechanism extends into the containing cavity and is connected to the fixing mechanism, the grid mechanism is arranged on the fixing mechanism, and a driving member drives the grid mechanism to move relative to the fixing mechanism, so that the containing cavity is connected to or closed with the outside through the grid mechanism, and when injecting cement slurry to cast the upper pile, the grid mechanism can be closed, and the grid can be opened when the hole needs to be cleaned. The technical problem of concrete falling into the grouting pipe and blocking the grouting port in the prior art is solved, and the technical effect of preventing cement slurry from blocking the grouting port is achieved. BRIEF DESCRIPTION OF THE DRAWINGS
[0032] Figure 1 is a cross-sectional view of the foundation construction device mentioned in an embodiment of the present invention;
[0033] Figure 2 A top view of the foundation construction device mentioned in an embodiment of the present invention;
[0034] Figure 3 This is another cross-sectional view of the foundation construction device mentioned in the embodiment of the present invention. In the figure, 1-accommodating chamber; 2-first grid; 3-second grid; 4-slurry bundle pipe; 5-top plate; 6-bottom plate; 7-steel plate belt; 8-grouting pipe; 9-check valve; 10-handle. DETAILED DESCRIPTION
[0035] The specific implementation of the present invention is further described in detail below in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.
[0036] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0037] The existing post-grouting technology of pile bottom mainly relies on the use of grouting tubes. The grouting tubes significantly improve the bearing capacity of the soil at the bottom of the pile by reinforcing the sediment, scum and disturbed soil at the bottom of the pile, thereby greatly improving the bearing capacity of the entire pile and reducing the settlement of the pile. In the related technology, a through channel is provided on the grouting tube, which facilitates the discharge of foreign matter from the bottom of the hole through the channel when cleaning the hole. However, the channel also causes the concrete poured above the grouting tube to fall into the grouting tube through the channel and cover the grouting port, affecting the normal grouting of the grouting port.
[0038] In view of this, if Figure 1-Figure 3 As shown, some embodiments of the present invention provide a foundation construction device, including a grid mechanism, a fixing mechanism and a grouting mechanism; a accommodating chamber 1 is provided in the fixing mechanism, the grouting mechanism extends into the accommodating chamber 1 and is connected to the fixing mechanism, the grid mechanism is provided on the fixing mechanism, a driving member is provided on the grid mechanism, and the driving member drives the grid mechanism to move relative to the fixing mechanism so that the accommodating chamber 1 is connected to or closed with the outside through the grid mechanism.
[0039] In the above embodiment, a accommodating chamber 1 is provided in the fixing mechanism, and the grouting mechanism extends into the accommodating chamber 1 after passing through the fixing mechanism. The grouting mechanism can transport materials such as cement slurry, concrete slurry or natural soil slurry into the accommodating chamber 1. Furthermore, a grid mechanism is provided on the surface of the fixing mechanism, and the grid mechanism is connected to the fixing mechanism so that the accommodating chamber 1 can be connected with the outside world through the grid mechanism, and the driving member fixed on the fixing mechanism can be a motor or a cylinder, and the driving member is connected to the grid mechanism. The driving member can drive the grid mechanism to move relative to the fixing mechanism, and the movement mode includes but is not limited to rotation and translation. The grid mechanism realizes the connection or closure of the accommodating chamber 1 to the outside world by cooperating with the fixing mechanism. The grid mechanism can be opened when cleaning the hole, and when the pile body is cast on one side of the fixing mechanism, the grid mechanism can be driven by the driving member to move relative to the fixed mechanism so that the accommodating chamber 1 is closed, thereby preventing the poured cement slurry from entering the accommodating chamber 1 through the grid mechanism, causing the grouting port of the grouting mechanism to be blocked, affecting the normal casting work.
[0040] Some embodiments of the present invention provide a foundation construction device, including a grid mechanism, a fixing mechanism and a grouting mechanism; a containing chamber 1 is provided in the fixing mechanism, the grouting mechanism extends into the containing chamber 1 and is connected to the fixing mechanism, the grid mechanism is provided on the fixing mechanism, and the driving member drives the grid mechanism to move relative to the fixing mechanism, so that the containing chamber 1 is connected to or closed with the outside through the grid mechanism, and the grid mechanism can be closed when injecting cement slurry to cast the upper pile, and the grid can be opened when the hole needs to be cleaned. The technical problem of concrete falling into the grouting pipe 4 and blocking the grouting port in the prior art is solved, and the technical effect of preventing cement slurry from blocking the grouting port is achieved.
[0041] In an optional embodiment, the grid mechanism includes a first grid 2 and a second grid 3; the first grid 2 and the second grid 3 are arranged at intervals along the axial direction of the fixing mechanism, and the first grid 2 is connected to the driving member.
[0042] In the above embodiment, the first grid 2 and the second grid 3 are arranged parallel to each other, the first grid 2 and the second grid 3 can both be circular, and the first grid 2 and the second grid 3 are arranged at intervals on both sides of the fixing mechanism along the length direction of the pile hole, the first grid 2 and the second grid 3 can both be mesh-shaped, and the mesh is square, wherein the first grid 2 is arranged near the opening of the pile hole, and the second grid 3 is arranged near the bottom of the pile, the first grid 2 and the second grid 3 can both be made of metal, and the axes of the first grid 2 and the second grid 3 can be arranged to coincide with the axis of the pile hole, wherein the first grid 2 has an opening and closing function, and the second grid 3 may or may not have an opening and closing function, the first grid 2 can prevent cement slurry from entering the accommodating chamber 1 to block the grouting port when pouring the pile, and the second grid 3 is used for after the grouting mechanism grouts into the accommodating chamber 1, the second grid 3 first abuts firmly against the bottom of the pile, and after a certain pressure is reached in the accommodating chamber 1, the cement slurry in the accommodating chamber 1 flows out through the gap between the second grid 3 and the bottom of the pile and is poured on the bottom of the pile and around it to complete the pouring of the pile foundation.
[0043] Optionally, the first grille 2 and the second grille 3 also have the function of adjusting the aperture, wherein the first grille 2 and the second grille 3 can respectively adopt two meshes of the same size, and the area of the covered hole can be controlled by the mutual rotation of the two meshes, so as to complete the opening and closing of the first grille 2 or the second grille 3. When cleaning the hole, the first grille 2 and the second grille 3 can be opened to allow the mud, sand and gravel and other impurities at the bottom of the pile to be cleared away after passing through the first grille 2 and the second grille 3. The aperture of the first grille 2 and the second grille 3 can also be adjusted to avoid the larger-sized stones at the bottom of the pile from being cleared away, resulting in holes formed at the bottom of the pile. The adjustment of the aperture of the second grille 3 can control the pouring pressure and pouring speed of the cement slurry.
[0044] In an optional embodiment, a through hole corresponding to the first grille 2 is provided on the fixing mechanism, and a driving member is connected to the fixing mechanism, and the driving member drives the first grille 2 to move relative to the through hole.
[0045] In the above embodiment, the first grid 2 and the second grid 3 can be set as a single-piece partition made by laser drilling of steel bars, flat steel or round steel plates, and the aperture is adjusted according to the soil quality, wherein a through hole corresponding to the hole on the first grid 2 is provided at the opening of the fixing mechanism near the pile hole, so that during the movement of the first grid 2, the holes on the first grid 2 can completely correspond to the through holes on the fixing mechanism, so that the first grid 2 can be opened to the maximum extent, and the driving member can drive the first grid 2 to rotate relative to the through holes on the fixing mechanism, so that the area of the overlapping part between the holes and the through holes can be adjusted, thereby adjusting the diameter of the sand and gravel passing through.
[0046] In an optional embodiment, the fixing mechanism includes a pulp bundle pipe 4, a top plate 5 and a bottom plate 6; the top plate 5 and the bottom plate 6 are arranged in parallel, and the two ends of the pulp bundle pipe 4 are respectively connected to the top plate 5 and the bottom plate 6, and the pulp bundle pipe 4, the top plate 5 and the bottom plate 6 form a accommodating cavity 1.
[0047] In the above embodiment, the slurry bundle pipe 4 can be made of elastic materials, such as rubber or silicone, and the slurry bundle pipe 4 can be annular. The two ends of the slurry bundle pipe 4 are respectively connected to the top plate 5 and the bottom plate 6, so that the slurry bundle pipe 4 can form a accommodating chamber 1 together with the top plate 5 and the bottom plate 6 on both sides. A first grid 2 is provided on the top plate 5. The diameter of the first grid 2 is smaller than the diameter of the top plate 5. The center of the first grid 2 coincides with the center of the top plate 5. A through hole is provided on the top plate 5. The center of the second grid 3 coincides with the center of the bottom plate 6. The driving member can be fixed to the top plate 5 by bolts. The top plate 5 and the bottom plate 6 are arranged in parallel and at intervals. By pressurizing the accommodating chamber 1, the flexible slurry bundle pipe 4 can be expanded, so that the slurry bundle pipe 4 squeezes the pile bottom to complete the compaction of the pile bottom.
[0048] In an optional embodiment, the diameter of the top plate 5 is greater than the diameter of the bottom plate 6 .
[0049] In the above embodiment, both the top plate 5 and the bottom plate 6 can be made of metal. The top plate 5 and the bottom plate 6 can be made of stainless steel according to the environment of the pile hole. The top plate 5 is arranged on the side close to the pile body poured for the first time, and the bottom plate 6 is arranged on the side close to the pile bottom. Therefore, when the size of the top plate 5 is larger than the bottom plate 6, the diameter of the slurry bundle pipe 4 connected between the top plate 5 and the bottom plate 6 on the side close to the top plate 5 is larger than the diameter on the side close to the bottom plate 6. When the slurry bundle pipe 4 expands, the expansion direction of the slurry bundle pipe 4 is toward the pile bottom, so that the slurry bundle pipe 4 can press the pile bottom, and the fixing effect is better. At the same time, the slurry bundle pipe 4 also constrains the injection direction of the cement slurry in the accommodating chamber 1, because the slurry bundle pipe 4 presses the second grid 3 at the pile bottom position. At this time, after the internal pressure of the slurry bundle pipe 4 is too large, the gap between the second grid 3 and the pile bottom will flow out of the cement slurry, thereby completing the limitation of the injection direction of the cement slurry.
[0050] In an optional embodiment, a steel plate belt 7 is provided on both the top plate 5 and the bottom plate 6; the height direction of the steel plate belt 7 is arranged parallel to the axis of the top plate 5, the steel plate belt 7 on the top plate 5 is extended in a direction close to the bottom plate 6, and the steel plate belt 7 on the bottom plate 6 is extended in a direction close to the top plate 5, and the two steel plate belts 7 are respectively connected to the two ends of the pulp bundle pipe 4.
[0051] In the above embodiment, two steel plate belts 7 are provided, the two steel plate belts 7 are close to each other and are respectively arranged on the top plate 5 and the bottom plate 6, the two steel plate belts 7 are both made of metal material, the material is consistent with the top plate 5 and the bottom plate 6, the two steel plate belts 7 are both ring-shaped, the height directions of the two steel plate belts 7 are parallel and arranged parallel to the axis of the pile hole, the two steel plate belts 7 can be connected to the top plate 5 and the bottom plate 6 respectively by welding, the height of the steel plate belt 7 can be set to 3 cm, the two ends of the slurry bundle pipe 4 can be respectively connected to a steel plate belt 7, the slurry bundle pipe 4 can be covered on the steel plate belt 7, and then fixed by means of cable ties, throat hoops, etc., so as to tighten the two ends of the slurry bundle pipe 4 on the two steel plate belts 7, so that the slurry bundle pipe 4 is firmly fixed to prevent the two ends of the slurry bundle pipe 4 from detaching from the top plate 5 and the bottom plate 6 during the pressurization process in the accommodating chamber 1.
[0052] In an optional embodiment, the grouting mechanism includes a grouting pipe 8 and a one-way valve 9; the grouting pipe 8 is passed through the top plate 5, the one-way valve 9 is arranged in the accommodating cavity 1, and the grouting pipe 8 is connected to the one-way valve 9.
[0053] In the above embodiment, the grouting pipe 8 can be made of metal material. The grouting pipe 8 passes through the top rod and then enters the accommodating chamber 1. Two grouting pipes 8 can be provided. The two grouting pipes 8 are arranged at intervals along the diameter direction of the top plate 5. The two grouting pipes 8 are respectively arranged on both sides of the first grid 2. After the two grouting pipes 8 extend into the accommodating chamber 1, they are respectively connected to the two sides of the one-way valve 9 in the accommodating chamber 1. The one-way valve 9 can be set as a three-way. The one-way valve 9 can be connected to the grouting pipes 8 on both sides by two inlets arranged on the same straight line. A grouting port is provided in the middle of the one-way valve 9. The one-way valve 9 can ensure that the flow direction of the cement slurry flows from the grouting pipe 8 into the accommodating chamber 1, while avoiding the reverse flow into the grouting pipe 8 due to excessive pressure of the cement slurry in the accommodating chamber 1. The one-way valve 9 is arranged at intervals from the top plate 5 and the bottom plate 6, respectively, so that the grouting port on the one-way valve 9 can transport cement slurry into the accommodating chamber 1.
[0054] In an optional embodiment, it further includes a control mechanism and a detection mechanism; the control mechanism and the detection mechanism are connected by electrical signals, the control mechanism and the grouting mechanism are connected by electrical signals, and the detection mechanism is arranged at the bottom of the pile.
[0055] In the above embodiment, the detection mechanism includes a pressure sensor, a displacement sensor, a flow sensor and an acoustic wave detection sensor, etc. The pressure in the accommodating chamber 1, the pressure in the grouting pipe 8 and the pressure on the surrounding rock and soil layers can be measured by the pressure sensor, the deformation of the surrounding rock and soil layers and the deformation of the grouting pipe 4 can be measured by the displacement sensor, the size of the stone at the bottom of the pile can be measured by the acoustic wave sensor, and the flow sensor can measure the flow in the grouting pipe 8. Further, the control mechanism can include a valve. The control mechanism can be set at the output end of the grouting pump on the ground and connected to each grouting pipe 8 so that the cement slurry output by the grouting pump can change the flow rate after being controlled by the control mechanism. At the same time, it can also be set that the single-chip microcomputer controller is connected to the grouting pump to control the output power of the grouting pump, thereby controlling the grouting amount, grouting pressure, the pressure in the accommodating chamber 1, and the volume of the accommodating chamber 1. At the same time, the control mechanism can also be connected to the driving member electrical signal. The control mechanism can drive the first grid 2 to rotate relative to the top plate 5 by controlling the driving member to control the pass rate and the size of the opening at the first grid 2, thereby determining the optimal cement slurry injection parameters and the opening timing of the first grid 2.
[0056] Optionally, a computer is also included, and the control mechanism may include a software in the computer. The computer is electrically connected to the detection mechanism. The computer can collect the electrical signals detected by the detection mechanism, organize and analyze them, and can also control the control mechanism through electrical signals.
[0057] The present invention also provides a working method of a foundation construction device based on, comprising the following steps: welding a steel cage and a top plate 5 away from a side of a bottom plate 6, and extending a fixing mechanism into the pile hole through the steel cage; after the fixing mechanism reaches the bottom of the pile, the steel cage and a top plate 5 with a larger diameter are placed in, which will cause contact with the side wall of the pile hole and cause foreign matter to fall, and the hole needs to be cleaned again, and the first grid 2 is opened by a computer-controlled driving member, and the pile hole is cleaned with mud, wherein the opening degree of the first grid 2 can be controlled by a computer during hole cleaning, so as to prevent larger gravel from being washed away; after the hole cleaning is completed, the first grid 2 is opened by a computer-controlled driving member, and the pile hole is cleaned with mud. The mud is pumped away through the pipeline; after the mud is pumped away, the first grid 2 is closed, and then cement slurry is poured into the steel cage to form the upper pile body, and then maintenance is carried out until the upper pile body is completed, and then the pile bottom is detected in real time by the detection mechanism, and the grouting parameters are configured according to the detection results of the detection mechanism; according to the grouting parameters, cement slurry is injected into the accommodating chamber 1 through the grouting pipe 8 and the one-way valve 9, so that the grouting pipe 4 expands and presses the pile bottom, so that the pile bottom is squeezed and compacted, and the second grid 3 is close to the pile bottom at this time; after the grouting pipe 4 expands to a certain extent, the cement slurry flows out through the gap between the second grid 3 and the pile bottom and pours the pile bottom to form the lower pile body.
[0058] Among them, a handle 10 can be set above the top plate 5, and a plurality of handles 10 are set. Each handle 10 is used to connect the steel cage to make the connection between the handle 10 and the steel cage more convenient and firm. At the same time, during transportation, the staff can directly grasp the handle 10, which is convenient for transportation.
[0059] In an optional embodiment, configuring the grouting parameters includes the following steps: after detecting the data of multiple pile bottoms through a detection mechanism, using a computer to determine the difference between the multiple data; setting a difference threshold of the overall data, comparing the difference obtained from multiple ten sentences with the difference threshold, when the difference is less than the difference threshold, it means that the situations between the multiple pile bottoms are similar, then the multiple pile bottoms are configured with grouting parameters in a proportional, integral, and differential manner. Among them, PID is a proportional, integral, and derivative control method, which takes the surrounding rock and soil layer pressure, rock and soil layer displacement, the size of the gravel passing through the first grid 2, and the mud flow through the first grid 2 as the target value of control, and uses the proportional, integral, and differential methods to adjust the detected data in real time through the control mechanism to achieve the target value.
[0060] The proportional part is to calculate the control amount of the proportional part by comparing the deviation between the current monitoring data and the target value. The integral part is to calculate the cumulative value of the deviation to adjust the long-term deviation. The differential part is to predict the trend of future deviations by monitoring the rate of change of the deviation. In order to achieve the target value, the calculation formula of the adjustment parameter is:
[0061] H=Kp*error+Ki*integral+Kd*derivative;
[0062] Where error is the error between theoretical data and actual data, integral is the integral of error, and derivative is the differential of error. Kp, Ki and Kd are proportional, integral and differential parameters respectively, which can be adjusted according to experience and on-site conditions. H is used to adjust the grouting volume, grouting pressure, pressure of the containing chamber 1, volume of the containing chamber 1 and the size of the through hole of the first grid 2, so as to realize the automatic optimization of grouting parameters.
[0063] Furthermore, when the difference is greater than or equal to the difference threshold, the neural network model is used to configure the grouting parameters of multiple pile bottoms according to the grouting parameters and results of each pile bottom in the historical case. Among them, the neural network model first removes noise and normalizes the monitored data to ensure the accuracy and consistency of the data, and takes the rock layer pressure, rock layer displacement, the size of the gravel passing through the first grid 2, and the mud flow through the first grid 2 as the target values to be adjusted. The data and pouring results during the pouring in the historical project are input into the neural network model as cases, and the model is optimized to make its measurement more accurate. During the grouting process, the monitoring data is input into the neural network model in real time, and the neural network model generates prediction results to predict the grouting effect of the pile hole.
[0064] Optionally, the grouting parameters can be set by combining PID and neural network models. First, the PID control algorithm quickly responds to changes in the current monitoring data, and uses real-time errors to perform proportional, integral and differential calculations to generate preliminary control outputs. This step can ensure that the system responds quickly to sudden changes and maintains basic stability. Subsequently, the results of the PID control output are combined with the predictions and suggestions of the artificial neural network. The neural network provides predictions of long-term effects and potential changes by analyzing accumulated historical data and current trends. This can help the system foresee possible future situations and make pre-adjustments for these situations. Finally, the outputs of the two algorithms are considered together to form a more comprehensive and accurate control strategy. This strategy can utilize both the immediate response capability of the PID algorithm and the prediction and adaptive capabilities of the neural network, thereby achieving optimization in the control of the grouting volume, grouting pressure, the pressure of the accommodating chamber 1, the volume of the accommodating chamber 1, and the opening size of the first grid 2.
[0065] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A foundation construction device, It is characterized in that It includes a grid mechanism, a fixing mechanism and a grouting mechanism; The fixing mechanism is provided with a containing cavity, the grouting mechanism extends into the containing cavity and is connected with the fixing mechanism, the grid mechanism is provided on the fixing mechanism, a driving member is provided on the grid mechanism, and the driving member drives the grid mechanism to move relative to the fixing mechanism so that the containing cavity is connected with or closed to the outside through the grid mechanism.
2. The foundation construction device according to claim 1, It is characterized in that The grid mechanism comprises a first grid and a second grid; The first grid and the second grid are arranged at intervals along the axial direction of the fixing mechanism, and the first grid is connected to the driving member.
3. The foundation construction device according to claim 2, It is characterized in that The fixing mechanism is provided with a through hole corresponding to the first grille, the driving member is connected to the fixing mechanism, and the driving member drives the first grille to move relative to the through hole.
4. The foundation construction device according to claim 1, It is characterized in that The fixing mechanism comprises a pulp bundle pipe, a top plate and a bottom plate; The top plate and the bottom plate are arranged in parallel, two ends of the pulp bundle pipe are connected to the top plate and the bottom plate respectively, and the pulp bundle pipe, the top plate and the bottom plate surround the accommodating cavity.
5. The foundation construction device according to claim 4, It is characterized in that The diameter of the top plate is greater than the diameter of the bottom plate.
6. The foundation construction device according to claim 4, It is characterized in that The top plate and the bottom plate are both provided with steel strips; The height direction of the steel strip is arranged parallel to the axis of the top plate, the steel strip on the top plate is extended toward the bottom plate, and the steel strip on the bottom plate is extended toward the top plate. The two steel strips are respectively connected to the two ends of the pulp bundle pipe.
7. The foundation construction device according to claim 4, It is characterized in that The grouting mechanism comprises a grouting pipe and a one-way valve; The grouting pipe is passed through the top plate, the one-way valve is arranged in the accommodating cavity, and the grouting pipe is connected to the one-way valve.
8. The foundation construction device according to claim 1, It is characterized in that It also includes control agencies and testing agencies; The control mechanism is connected to the detection mechanism by electrical signals, the control mechanism is connected to the grouting mechanism by electrical signals, and the detection mechanism is arranged at the bottom of the pile.
9. A working method based on the foundation construction device according to any one of claims 1 to 8, It is characterized in that The steps include: Weld the steel cage and the top plate, and extend the fixing mechanism into the pile hole through the steel cage; After the fixing mechanism reaches the bottom of the pile, the first grid is opened and the pile hole is cleaned with mud; After the hole is cleaned, the mud is pumped away; After the slurry is pumped away, the first grid is closed, and then cement slurry is poured into the steel cage to form the upper pile body; After the upper pile body is completed, the pile bottom is detected in real time by the detection mechanism, and the grouting parameters are configured according to the detection results of the detection mechanism; According to the grouting parameters, cement slurry is injected into the accommodation cavity through the grouting pipe and the one-way valve, so that the grouting pipe expands and presses the pile bottom. At this time, the second grid is close to the pile bottom; After the grout pipe expands to a certain extent, the cement slurry flows out through the gap between the second grid and the pile bottom and is poured into the pile bottom to form the pile body below.
10. The working method according to claim 9, It is characterized in that The configuration of grouting parameters comprises the following steps: After the data of multiple pile bottoms are detected by the detection mechanism, the differences between the multiple data are determined; The obtained difference is compared with the difference threshold. When the difference is less than the difference threshold, the grouting parameters of multiple pile bottoms are configured by proportional, integral and differential methods. When the difference is greater than or equal to the difference threshold, the neural network model is used to configure the grouting parameters of multiple pile bottoms according to the grouting parameters and results of each pile bottom in historical cases.