Hole entering method for large-section railway tunnel to penetrate through accumulated soil

By adopting the temporary vertical support method and radial grouting for the partial excavation of the four-step upper guide pit in the construction of the railway tunnel, combined with advanced support and the setting of shed holes, the problems of deformation and collapse when the tunnel enters the hole and passes through the accumulated soil are solved. Effective control of construction safety and quality was achieved.

CN118728401APending Publication Date: 2024-10-01NO 3 ENG COMPANY LTD OF CCCC FIRST HARBOR ENG COMPANY +1
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202410904911.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-08
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

In the construction of railway tunnels, when the tunnel enters the hole and passes through the piled soil, due to the loose rock pile, the tunnel entrance is prone to deformation and collapse, which poses a great potential safety and quality hazard in construction. Moreover, it is difficult for the existing technology to effectively solve the collapse of large-section tunnels when passing through the piled soil. and loose ring deformation problems.

Method used

Temporary vertical support method and radial grouting are adopted for the partial excavation of the four-step upper guide pit. Construction safety is ensured through advanced support and shed hole settings. It is gradually carried out in combination with steel flower tube grouting, anchor shotcrete support and shotcrete structure. Enter the hole for construction and adjust the construction plan through monitoring and measurement.

Benefits of technology

It effectively reduces the safety risks of tunnel construction through rock piles and ensures the stability of the initial support structure. The maximum cumulative deformation is controlled at 8cm, and the maximum deformation in a single day is controlled at 4.8mm, ensuring construction safety and quality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118728401A_ABST
    Figure CN118728401A_ABST
Patent Text Reader

Abstract

The invention relates to the field of building construction, in particular to a hole entering method for a large-section railway tunnel to penetrate through accumulated soil. A large-section railway tunnel penetrating accumulated soil entering method comprises the following steps that firstly, a tunnel portal accumulated soil edge upward slope face is reinforced, and water interception and drainage construction is conducted; step 2, constructing a guide wall at a light and shade boundary position and a tunnel opening advanced pipe shed support, wherein a pipe shed adopts a calandria; step 3, constructing a shed tunnel at the position of the open cut tunnel section, wherein the shed tunnel is mainly constructed by adopting a profile steel arch frame and sprayed concrete; step 4, mechanically excavating a hidden hole section of the hole by adopting a four-step upper pilot tunnel partial excavation temporary vertical support method, and completing corresponding works such as primary support and radial grouting; and 5, an inverted arch and a second lining are followed up in time, and tunnel entering construction penetrating through the accumulated soil tunnel is completed. The method effectively solves the problem of tunnel entering construction when the large-section railway tunnel penetrates through the accumulated soil, the construction quality is improved, and the construction safety risk is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of building construction, and in particular to a method for entering a tunnel of a large-section railway tunnel through piled soil. Background Art

[0002] During the construction of railway tunnels, there are often situations where the tunnel enters the cave through rock piles. Since the rock piles are loose and have poor self-stabilization ability, especially when the tunnel section is large, it is often easy for the tunnel entrance to deform and collapse, which cannot meet the needs of on-site construction. There are major safety and quality risks in the construction, and it is easy to cause serious economic losses.

[0003] Chinese patent CN 113202501 A proposes a four-step excavation construction method for a displacement active fault zone. This method has the following shortcomings: first, for a large-section tunnel passing through accumulated soil, landslides are prone to occur when excavating the upper steps due to the large cross-section; second, the use of advanced φ42mm small pipe grouting cannot solve the problem of easy collapse of accumulated soil.

[0004] Chinese patent CN 116044418 A proposes a construction method for controlling deformation of soft rock tunnel excavation reinforcement. This method has the following shortcomings: first, the initial support adopts double-layer support, which is complicated in process and difficult to control in quality, and has great limitations for entering the tunnel and passing through the accumulated soil; second, there are only system anchor rods for the radial reinforcement of the tunnel, which has no positive effect on the deformation control of the loose circle of the accumulated soil. Summary of the invention

[0005] In order to solve the above-mentioned problem of tunnel entry through rock pile construction, the present invention provides a tunnel entry method for a large-section railway tunnel through piled soil, adopts a temporary vertical support method for partial excavation of a four-step upper pilot pit, and the upper pilot pit is divided into left and right side excavations, which can effectively reduce the safety risks of tunnel entry through rock pile construction.

[0006] The technical solution adopted by the present invention to achieve the above-mentioned purpose is: a method for entering a tunnel through a large-section railway tunnel through piled soil, which is characterized in that the problem of piled soil sliding and collapsing during excavation is solved by setting up advance support, and then the safety of entering the tunnel is further ensured by setting up a shed tunnel in the open tunnel section, and at the same time, a temporary vertical support method for partial excavation of a four-step upper pilot pit and radial grouting are used to cross the rock pile soil construction. Specifically, the following steps are included: Step 1: Slope reinforcement and drainage construction at the side of the tunnel entrance. The slope reinforcement adopts the method of steel pipe grouting; Step 2: After the slope reinforcement is completed, anchor spraying support is used at the light and dark boundary of the tunnel to provide a working surface for the advanced support construction, and the advanced support is constructed by pipe laying; Step 3: After the advanced support is completed, a shed tunnel is constructed at the open hole position to intercept the unstable soil above the hole entrance to ensure safe construction of the hole entrance; Step 4, start the construction of the blind tunnel. The blind tunnel adopts the method of partial excavation and temporary vertical support of the four-step upper pilot pit. That is, according to the size of the excavation section, it is divided into four steps for excavation. The upper step is divided into left and right parts for excavation according to the length of the arch frame unit. The joint position is greater than 1.5m from the center line. The left side of the upper step is mechanically excavated by a long-arm excavator, and temporary vertical support is set. After the excavation is completed, the initial support is completed in time; Step 5: After 3m of excavation on the left side of the upper step, continue to excavate the right side of the upper step. Mechanical excavation is used and initial support is completed in time. Step 6: After the construction reaches 8m on the left and right sides of the upper step, including 3m on the left and 5m on the right, the first middle step will be excavated. Mechanical excavation will be adopted, and initial support and temporary cross bracing will be completed in time. Step 7, repeat the above steps, follow up the second middle step and the lower step simultaneously, and remove the temporary cross brace of the first middle step during the follow-up process; Step 8, during the construction of the first middle step, the second middle step and the lower step, radial grouting is completed in a timely manner; Step 9: After the lower step is constructed for 5m, start the invert excavation construction, and carry out the initial support in time to close the ring; Step 10: During the construction process, strengthen monitoring and measurement to ensure that the cumulative deformation of the initial support is not greater than the threshold, that is, the maximum value that does not invade the secondary lining, and the deformation rate after the ring is closed is not greater than the threshold, that is, the horizontal convergence is less than 0.2mm / d and the arch sinking speed is less than 0.15mm / d. Then, carry out waterproof structure construction and follow up the subsequent lining construction in time.

[0007] The initial support includes: steel arch frame, longitudinal connecting steel bars, locking anchor pipes, steel mesh and shotcrete.

[0008] The excavation cycle advance of each step is the distance of a steel frame, and the length of each step is 3 to 5 meters.

[0009] In step 2, the advance support is a row of pipes, each of which is welded from two steel pipes, and the row of pipes are connected by locking buckles.

[0010] In step 3, the shed hole is a steel-supported shotcrete structure, and the steel support is composed of a steel arch frame, longitudinal connecting steel bars, and a steel mesh.

[0011] In step 3, the shed tunnel is a permanent structure, which serves as an outer formwork during the construction of the open tunnel lining and as the bottom layer of the open tunnel waterproofing layer.

[0012] In step 6, the temporary cross brace is a temporary structure, and is connected to the steel arch frame of the initial support 3 by bolts.

[0013] In step 8, when the radial grouting is abnormal according to the monitoring measurement data, that is, the deformation is greater than 5 mm / d, secondary grouting is performed, that is, the radial grouting step is repeated.

[0014] In step 9, the invert excavation is no more than 3 m at a time and the distance between the invert and the tunnel face is no more than 30 m.

[0015] The present invention has the following beneficial effects: for the tunnel construction of a large-section railway tunnel passing through accumulated soil, the problem of stability of the tunnel support structure is solved by adopting measures such as tunnel shed protection, advanced pipe shed support, temporary vertical support method for partial excavation of the four-step guide pit, radial grouting, etc. According to the monitoring and measurement results, the maximum cumulative deformation of the initial support is 8 cm, and the maximum deformation in a single day is 4.8 mm, which fully ensures the structural safety and reduces the construction safety risk. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a schematic diagram of the process of the present invention; Figure 2 It is a longitudinal section schematic diagram of the tunnel support structure of a large-section railway tunnel passing through piled soil according to the present invention; Figure 3 It is a cross-sectional schematic diagram of the tunnel support structure of a large-section railway tunnel passing through piled soil according to the present invention; Figure 4 It is a schematic diagram of the advanced support structure of the present invention; In the figure: 1-advance support, 2-shed tunnel, 3-initial support, 4-lining, 5-left side of upper step, 6-temporary vertical support, 7-right side of upper step, 8-first middle step, 9-second middle step, 10-lower step, 11-inverted arch; 12-radial grouting. DETAILED DESCRIPTION

[0017] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0018] To facilitate understanding of the embodiments of the present invention, several specific embodiments will be further explained below with reference to the accompanying drawings, and each embodiment does not constitute a limitation on the embodiments of the present invention. Example

[0019] Figure 1 FIG. 1 is a flow chart of a method for entering a tunnel through piled soil in a large-section railway tunnel according to an embodiment, comprising the following steps: A method for entering a tunnel through a large-section railway tunnel through piled soil. The problem of piled soil sliding and collapsing during excavation is solved by setting up advance support. Then, a shed tunnel is set up in the open tunnel section to further ensure the safety of entering the tunnel. At the same time, a temporary vertical support method for partial excavation of a four-step upper pilot pit and radial grouting are used to cross the rock pile soil construction. Specifically, the following steps are included: Step 1: Slope reinforcement and drainage construction at the side of the tunnel entrance. The slope reinforcement adopts the method of steel pipe grouting; Step 2: After the slope reinforcement is completed, anchor spraying support is used at the light and dark boundary of the tunnel to provide a working surface for the construction of advance support 1, and the advance support 1 is constructed by pipe laying; Step 3: After the advanced support 1 is completed, a shed tunnel 2 is constructed at the open tunnel position. The shed tunnel 2 intercepts the unstable soil above the tunnel entrance to ensure safe construction of the tunnel entrance. Step 4, start the construction of the blind tunnel. The blind tunnel adopts the method of temporary vertical support by partial excavation of the four-step upper pilot pit. That is, according to the size of the excavation section, it is divided into four steps for excavation. The upper step is divided into left and right parts for excavation according to the length of the arch frame unit. The joint position is greater than 1.5m from the center line. The left side 5 of the upper step is mechanically excavated by a long-arm excavator, and a temporary vertical support 6 is set. After the excavation is completed, the initial support 3 is completed in time; Step 5: Excavate 3m on the left side 5 of the upper step and continue to excavate the right side 7 of the upper step. Both are done by mechanical excavation, and the initial support 3 is completed in time; Step 6: After the construction of the left side 5 and the right side 7 of the upper step reaches 8m, including 3m on the left and 5m on the right, the first middle step 8 is excavated. Mechanical excavation is adopted, and the initial support 3 and temporary cross bracing are completed in time; Step 7, repeat the above steps, follow up the second middle step 9 and the lower step 10 simultaneously, follow up During the process, the temporary cross brace of the first middle step 8 is removed simultaneously; Step 8, during the construction of the first middle step 8, the second middle step 9 and the lower step 10, radial grouting 12 is completed in a timely manner; Step 9, after the lower step 10 is constructed for 5m, start the excavation of the invert 11, and promptly implement the initial support 3 to close the ring; Step 10, strengthen monitoring and measurement during construction to ensure that the cumulative deformation of the initial support is not greater than the threshold, that is, it does not invade the maximum value of the secondary lining, and the deformation rate after closing into a ring is not greater than the threshold, that is, the horizontal convergence is less than 0.2mm / d and the arch sinking speed is less than 0.15mm / d, that is, the waterproof structure construction is carried out, and the subsequent lining 4 construction is followed up in time.

[0020] The initial support 3 includes: a steel arch frame, longitudinal connecting steel bars, a locking anchor pipe, a steel mesh and shotcrete.

[0021] The excavation cycle advance of each step is the distance of one steel frame, and the length of each step is 3 to 5 meters.

[0022] In the step 2, the advance support 1 is a row of pipes, each of which is welded from two steel flower pipes, and the row of pipes are connected by locks.

[0023] In step 3, the shed hole 2 is a steel-supported shotcrete structure, and the steel support is composed of a steel arch frame, longitudinal connecting steel bars, and a steel mesh.

[0024] In step 3, the shed tunnel 2 is a permanent structure, which serves as an outer template during the construction of the open tunnel lining and as the bottom layer of the open tunnel waterproof layer.

[0025] In step 6, the temporary cross brace is a temporary structure, and is connected to the steel arch frame of the initial support 3 by bolts.

[0026] In step 8, when the radial grouting 12 is abnormal according to the monitoring measurement data, that is, the deformation is greater than 5 mm / d, secondary grouting is performed, that is, the radial grouting step is repeated.

[0027] In step 9, the excavation depth of the invert 11 is no more than 3 m at a time and the distance between the invert 10 and the tunnel face is no more than 30 m.

[0028] The specific application of the present invention is described below. Figure 2-Figure 4 As shown, the specific steps are as follows: Step 1: Slope reinforcement and drainage construction at the side of the accumulated soil at the tunnel entrance. The slope reinforcement mainly adopts the method of grouting with steel flower pipes. The steel flower pipes are φ60mm steel flower pipes, 6m long / root, arranged in plum blossom shape, with a spacing of 2m×2m; Step 2: After the slope reinforcement is completed, C25 anchor spraying support is used for the light and dark boundary of the tunnel. The thickness is 15cm, the length of the anchor rod is 3m / root, the plum blossom type is arranged, and the spacing is 1.2m×1.2m. A vertical surface is formed to provide a working surface for the construction of the advanced support 1. The length of the advanced support 1 is 30m. Pipe construction is adopted. Each pipe is welded by 2 φ300mm steel pipes. The pipes are connected with lock buckles. The lock buckles are made of Q235 steel plates. The pipes are constructed by jacking. The angle with the outside of the tunnel is 1 degree. After the pipe construction is completed, M20 mortar is used for filling. Finally, a high-strength retaining structure is formed to prevent the loose accumulated soil from sliding and causing landslides. Step 3: After the advanced support 1 is completed, a shed hole 2 is constructed at the open hole position. The shed hole 2 is mainly used to intercept the unstable soil above the hole. The shed hole is reinforced with I20 steel arch frames, with an arch frame spacing of 1m / frame, φ22mm threaded steel bars are set longitudinally, with a spacing of 1m / root, φ8mm steel mesh, mesh size of 20cm×20cm, and shotcrete thickness of 30cm. In order to facilitate the formation of shed hole 2 by shotcrete, the outer side of the steel support structure is wrapped and closed with a waterproof board; Step 4, start the construction of the blind hole. The blind hole adopts the temporary vertical support method of partial excavation of the four-step upper pilot pit. The length of the left side 5 of the upper step is 3m, the length of the right side 7 of the upper step is 5m, the length of the first middle step 8 is 3m, and the length of the second middle step 9 is 3m. The left side 5 of the upper step and the right side 7 of the upper step are mechanically excavated, and HW175 temporary vertical support 6 is set at the same time. After the excavation is completed, the initial support 3 is completed in time. The initial support 3 adopts HW175 steel arch frame, the steel frame spacing is 0.6m / frame, φ22mm threaded steel bars are set longitudinally, the spacing is 1m / root, the steel mesh adopts φ8mm steel mesh, the mesh size is 20cm×20cm, and the thickness of the shotcrete is 27cm; Step 5, after a certain distance of excavation on the left side 5 of the upper step, continue to start excavating the right side 7 of the upper step, all using mechanical excavation, and complete the initial support 3 in time, and after the excavation of the left side 5 of the upper step, a temporary vertical support 6 must be set; Step 6, after a certain distance between the left side 5 of the upper step and the right side 7 of the upper step, the first middle step 8 is excavated, all by mechanical excavation, and the initial support 3 and temporary cross bracing are completed in time. The temporary support adopts I18 steel, and one temporary support is set for every two steel frames; Step 7, repeat the above steps, synchronously follow up the second middle step 9 and the lower step 0, and synchronously remove the temporary cross brace of the first middle step 8 during the follow-up process; Step 8, during the construction of the first middle step 8, the second middle step 9 and the lower step 10, radial grouting 12 is completed in time, and the radial grouting adopts φ42 steel flower pipes, 4m / piece, plum blossom arrangement, spacing 1.5m×1.5m, and the grouting material is M20 cement slurry; Step 9, after a certain distance of construction of the next step 10, start excavation construction of the invert 11, timely implementation of the initial support 3, closed into a ring, the invert 11 excavation once not more than 3m and the invert 11 from the face distance is not more than 30m; Step 10: Strengthen monitoring and measurement during the construction process to ensure that the cumulative deformation of the initial support is not greater than the threshold, and the deformation rate after the ring is closed is not greater than the threshold, that is, to carry out waterproof structure construction and follow up the subsequent lining 4 construction in a timely manner.

[0029] The above disclosure is only the preferred embodiment of the present invention, which certainly cannot be used to limit the scope of the present invention. Therefore, equivalent changes made according to the claims of the present invention are still within the scope of the present invention.

Claims

1. A method for entering a tunnel through a piled soil for a large-section railway tunnel, characterized in that: By setting up advance support, the problem of soil accumulation sliding and collapsing during excavation is solved. Then, by setting up a shed tunnel in the open tunnel section, the safety of entering the tunnel is further guaranteed. At the same time, the temporary vertical support method of partial excavation of the four-step upper guide pit and radial grouting are used to cross the rock pile construction.

2. A method for entering a tunnel through piled soil for a large-section railway tunnel according to claim 1, characterized in that: The specific steps include: Step 1: Slope reinforcement and drainage construction at the side of the accumulated soil at the tunnel entrance. The slope reinforcement adopts the method of grouting with steel flower pipes. The steel flower pipes are φ60mm steel flower pipes, 6m / piece in length, arranged in plum blossom shape, with a spacing of 2m×2m; Step 2: After the slope reinforcement is completed, anchor spraying support is used at the boundary between the light and dark parts of the tunnel to provide a working surface for the construction of the advance support (1). The advance support (1) is constructed by pipe laying. Each pipe laying is welded by two φ300mm steel pipes. The pipe layings are connected by lock buckles made of Q235 steel plates. The pipe laying is constructed by jacking. Step 3, after the advanced support (1) is completed, a shed tunnel (2) is constructed at the open hole position. The shed tunnel is a steel-supported shotcrete structure. The steel support is composed of a steel arch frame, longitudinal connecting steel bars, and a steel mesh. The shed tunnel (2) intercepts the unstable soil above the hole opening to ensure safe construction of the hole opening. Step 4, start the construction of the blind tunnel. The blind tunnel is constructed by the temporary vertical support method of partial excavation of the four-step upper pilot pit. That is, according to the size of the excavation section, it is divided into four steps for excavation. The upper step is divided into left and right parts for excavation according to the length of the arch frame unit. The joint position is greater than 1.5m from the center line. The left side of the upper step (5) is mechanically excavated by a long-arm excavator, and a temporary vertical support is set (6). After the excavation is completed, the initial support (3) is completed in time; Step 5: After a certain distance of excavation on the left side of the upper step (5), continue to excavate the right side of the upper step (7), all using mechanical excavation, and complete the initial support (3) in time; Step 6: After the left side (5) and the right side (7) of the upper step have been constructed to 8 m, including 3 m on the left side and 5 m on the right side, the first middle step (8) is excavated. Long-arm excavators are used for mechanical excavation, and initial support (3) and temporary cross bracing are completed in a timely manner. Step 7, repeat the above steps, follow the second middle step (9) and the lower step (10) simultaneously, follow During the process, the temporary cross brace of the first middle step (8) is removed simultaneously; Step 8, during the construction of the first middle step (8), the second middle step (9) and the lower step (10), radial grouting (12) is completed in a timely manner, and the radial grouting adopts φ42mm steel flower pipes, 4m / piece, plum blossom arrangement, spacing 1.5m×1.5m, and the grouting material is M20 cement slurry; Step 9, after the lower step (10) is constructed for 5 m, start the excavation of the invert (11), and promptly carry out the initial support (3) to close the ring; Step 10: During the construction process, strengthen monitoring and measurement to ensure that the cumulative deformation of the initial support is not greater than the threshold, that is, the maximum value of the secondary lining is not invaded, and the deformation rate after the ring is closed is not greater than the threshold, that is, the horizontal convergence is less than 0.2mm / d and the arch sinking speed is less than 0.15mm / d. Then, carry out the waterproof structure construction and follow up the subsequent lining (4) construction in time.

3. The method for entering a tunnel through piled soil for a large-section railway tunnel according to claim 2, characterized in that: The initial support (3) comprises: a steel arch frame, longitudinal connecting steel bars, a locking anchor pipe, a steel mesh and shotcrete.

4. The method for entering a tunnel through piled soil for a large-section railway tunnel according to claim 2, characterized in that: The excavation cycle advance of each step is the distance of one steel frame, and the length of each step is 3 to 5 meters.

5. The method for entering a tunnel through piled soil for a large-section railway tunnel according to claim 2, characterized in that: In step 2, the advance support (1) is a row of pipes, each of which is welded from two steel pipes, and the row of pipes are connected by locks.

6. The method for entering a tunnel through piled soil for a large-section railway tunnel according to claim 2, characterized in that: In step 3, the shed hole (2) is a steel-supported shotcrete structure, and the steel support is composed of a steel arch frame, longitudinal connecting steel bars, and a steel mesh.

7. The method for entering a tunnel through piled soil for a large-section railway tunnel according to claim 2, characterized in that: In step 3, the shed hole (2) is a permanent structure, which serves as an outer template during the construction of the open hole lining and as the bottom layer of the open hole waterproof layer.

8. The method for entering a tunnel through piled soil for a large-section railway tunnel according to claim 2, characterized in that: In step 6, the temporary cross brace is a temporary structure, and is connected to the steel arch frame of the initial support (3) by bolt connection.

9. The method for entering a tunnel through piled soil for a large-section railway tunnel according to claim 2, characterized in that: In step 8, when the radial grouting (12) is abnormal according to the monitoring measurement data, that is, the deformation is greater than 5 mm / d, secondary grouting is performed, that is, the radial grouting step is repeated.

10. The method for entering a tunnel through piled soil for a large-section railway tunnel according to claim 2, characterized in that: In step 9, the excavation of the invert (11) is no more than 3 m at a time and the distance between the invert (10) and the tunnel face is no more than 30 m.