Incremental launching construction method for steel beam in tunnel

By setting up tracks and beam transport vehicles in the tunnel, and using jacks and winches for efficient steel beam assembly, the problem of poor steel beam assembly alignment is solved, a fast and economical construction process is achieved, construction efficiency and safety are improved, and construction costs are reduced. environmental impact.

CN118774946APending Publication Date: 2024-10-15CHINA RAILWAY NO 2 ENG GROUP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410989763.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-23
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

In the existing technology, it is difficult to ensure the assembly alignment of the steel beams during the push construction process of the steel beams in the tunnel, which results in a long construction time and affects the construction of other teams and the normal operation of passing vehicles.

Method used

Tracks and beam transport vehicles are set up in the tunnel, and steel beams are efficiently transported and assembled through jacks and winches. Software simulation is used to determine the spatial layout that meets the assembly requirements of channel beams, simplifying the construction site layout and pushing process.

Benefits of technology

It achieves rapid and reliable assembly of steel beams, shortens the construction period, reduces costs and personnel investment, improves construction efficiency and safety, and reduces the impact on the environment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118774946A_ABST
    Figure CN118774946A_ABST
Patent Text Reader

Abstract

The invention provides an incremental launching construction method for a steel beam in a tunnel. The method comprises the following steps that a tunnel internal space meeting the assembling requirement of a channel beam is determined; based on the determined internal space of the tunnel, a construction site is arranged; transporting the steel beams on the arranged construction site, and assembling the steel beams and the guide beams; and after the steel beam and the guide beam are assembled, incremental launching construction is carried out. According to the incremental launching construction method for the steel beams in the tunnel, the economic benefit is good, the splicing period of the steel beams is greatly shortened, construction is not affected by rainy seasons, the situation that workers are lost is reduced, and the construction cost is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of bridge engineering, and in particular to a method for jacking a steel beam in a tunnel. Background Art

[0002] During the jacking construction process, the beam is often in a complex stress state, which not only increases the difficulty of construction, but also affects the overall structural performance of the bridge. Due to the jacking force, the beam is prone to stress concentration and local deformation, and may even cause structural damage. Therefore, during the jacking construction process, the jacking speed and force need to be strictly controlled to avoid adverse effects on the beam.

[0003] The bridge jacking construction needs to ensure that the surrounding environment of the site is clean and the flatness of the construction site is maintained. In addition, preliminary preparations such as ground engineering and auxiliary construction pouring need to be completed before construction.

[0004] When the beam is erected by the jacking method, the front end of the beam is in a cantilever state, and the cross-sectional force is greater than that of the rear part. In order to reduce the cross-sectional force of the temporary erection of the front end of the beam, a guide beam can be installed at the front end of the beam. According to the site conditions, temporary piers can be set between the bridges to reduce the cross-sectional force of the beam during erection. When the middle span is large and temporary piers cannot be set, the guide beam can also be used to push from both sides and connect in the middle of the span. The jacking method is mainly divided into single-point jacking and multi-point jacking. Single-point jacking is to set the jacking equipment such as jacks in one place, that is, on the abutment or pier, and arrange slideways on other piers to push and slide the beam. This method has two methods: using two horizontal and vertical jacks and using through-type horizontal jacks with pull rods. Multi-point jacking is a jacking method in which jacks and other jacking equipment are set on each pier. This method can disperse the horizontal force on each pier, which is particularly beneficial for long bridges. At present, most people use this method.

[0005] A major problem with the current top-pushing construction method is how to ensure the assembly line of the steel beam when the cantilever section is long, and the long site occupancy time affects the construction of other teams and passing vehicles. Therefore, it is of great significance for this application to provide a top-pushing construction method for steel beams in tunnels that can ensure the assembly line of steel beams and is more efficient, faster and more reliable. Summary of the invention

[0006] In view of the shortcomings of the prior art, the present invention aims to solve one or more problems in the prior art. For example, one of the purposes of the present invention is to solve the problem that the assembly line of the steel beam cannot be guaranteed, the time is long, and the pushing effect is poor during the pushing construction.

[0007] In order to achieve the above-mentioned purpose, the present invention provides a method for jacking construction of steel beams in a tunnel, and the method may include the following steps: determining the internal space of the tunnel that meets the requirements for assembling trough beams; arranging the construction site based on the determined internal space of the tunnel; transporting steel beams on the arranged construction site, and assembling steel beams and guide beams; after the assembly of the steel beams and guide beams is completed, carrying out jacking construction.

[0008] According to one or more exemplary embodiments of the present invention, determining the internal space of the tunnel that meets the requirements for assembling trough beams may include: using software to simulate the process of assembling trough beam segments in the internal space of the tunnel to determine the internal space of the tunnel that meets the requirements for assembling trough beams.

[0009] According to one or more exemplary embodiments of the present invention, the arranging of the construction site may include: setting tracks on the road surface inside the tunnel, and assembling tire frames and jacking equipment.

[0010] According to one or more exemplary embodiments of the present invention, the track may include two groups of tracks arranged parallel to each other, each group of tracks includes two tracks parallel to each other and arranged below the trough beam, and the jacking equipment includes a plurality of jacks, and the plurality of jacks are evenly spaced and arranged below the trough beam.

[0011] According to one or more exemplary embodiments of the present invention, each set of tracks may be configured with a beam transport vehicle, and the beam transport vehicle is driven by a power mechanism.

[0012] According to one or more exemplary embodiments of the present invention, the beam transporter can be used to transport steel beams.

[0013] According to one or more exemplary embodiments of the present invention, the power mechanism may include a winch, the winch is connected to the beam transport vehicle via a steel wire rope, and the winch is installed at the rear of the construction site.

[0014] According to one or more exemplary embodiments of the present invention, the direction of the steel wire rope may be controlled by a diverting fixed pulley installed in front of the abutment.

[0015] According to one or more exemplary embodiments of the present invention, the beam transport vehicle may be provided with a jack, and when the beam transport vehicle transports the box body formed after assembling the steel beams to a predetermined installation location, the box body is placed on the tire frame by the jack.

[0016] According to one or more exemplary embodiments of the present invention, a transverse connection system may be provided between the boxes, and the transverse connection system may be transported to a predetermined installation position by an excavator.

[0017] Compared with the prior art, the beneficial effects of the present invention include at least one of the following:

[0018] (1) The device involved in the tunnel steel beam jacking construction method provided by the present invention has a simple structure and is easy to operate, and is easy for workers to master.

[0019] (2) The method for pushing steel beams in tunnels provided by the present invention has good economic benefits, greatly shortens the steel beam assembly period, and the construction is not affected by the rainy season, which reduces the situation of idle workers and reduces construction costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] The above and other objects and / or features of the present invention will become more apparent through the following description in conjunction with the accompanying drawings, in which:

[0021] Figure 1 A schematic diagram of the layout of a construction site in an exemplary embodiment of the present invention is shown;

[0022] Figure 2 A schematic diagram of the arrangement of a beam transport vehicle in an exemplary embodiment of the present invention is shown;

[0023] Figure 3 A schematic diagram of the position of a beam in an exemplary embodiment of the present invention is shown;

[0024] Figure 4 A schematic diagram of pushing in an exemplary embodiment of the present invention is shown.

[0025] Description of reference numerals:

[0026] 1-track, 2-jack, 3-beam transporter, 4-winch, 5-crawler crane, 6-portal, 7-steering pulley, 8-tunnel, 9-assembly frame, 10-steel beam, 11-abutment pier, 12-transverse connection system, 13-guide beam. DETAILED DESCRIPTION

[0027] Hereinafter, a method for pushing a steel beam in a tunnel according to the present invention will be described in detail with reference to the accompanying drawings and exemplary embodiments.

[0028] In the description of the present application, it should be understood that the terms "center", "upper", "lower", "front", "back", "left", "right", "top", "inside", etc., indicating the orientation or positional relationship are based on the orientation or positional relationship shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present application. The term "first" is used for descriptive purposes only and cannot be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" may explicitly or implicitly include one or more of the features. In the description of the present invention, unless otherwise specified, "multiple" means two or more.

[0029] In the description of this application, it should be noted that, unless otherwise clearly specified and limited, the terms "installation" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0030] Due to the problem of on-site construction site, the assembly site of the trough beam of the approach bridge is only 24m. The small site will affect the construction of other construction teams, so it is necessary to borrow the tunnel space. First, assemble 5 sections of trough beam segments in sequence at the assembly site, totaling 47.5m. Every time two segments are connected, they are pushed into the Green Valley Tunnel once, and the assembly site is given up to assemble the next segment. After the 5 sections are assembled, the guide beam is assembled. Similarly, the guide beam segments are assembled in sequence, and one section is pushed into the tunnel for installation. The present invention utilizes the space inside the tunnel, sets tracks on the road surface in the tunnel, transports the steel beam to the tire frame position by a beam transporter, assembles the steel beam and guide beam, and then pushes them into place at one time. The trough beam falls into place after being pushed into place. The assembly and pushing of the trough beam are carried out according to the designed linear shape, and there is no overall rotation. The present invention simplifies the construction process and reduces the investment in materials and equipment by providing a method for pushing steel beams in a tunnel. During the transportation of the steel beams, linear adjustment and welding of other steel beams can be performed, which greatly improves the work efficiency and shortens the construction period.

[0031] Exemplary Embodiment 1

[0032] Figure 1 A schematic diagram of the layout of a construction site in an exemplary embodiment of the present invention is shown; Figure 2 A schematic diagram of the arrangement of a beam transport vehicle in an exemplary embodiment of the present invention is shown; Figure 3 A schematic diagram of the position of a beam in an exemplary embodiment of the present invention is shown; Figure 4 A schematic diagram of pushing in an exemplary embodiment of the present invention is shown.

[0033] This exemplary embodiment provides a method for jacking construction of steel beams in a tunnel.

[0034] The method may include the following steps: determining the internal space of the tunnel that meets the requirements for assembling the trough beams, arranging the construction site based on the determined internal space of the tunnel, transporting steel beams on the arranged construction site, assembling the steel beams and guide beams, and performing jacking construction after the assembly of the steel beams and guide beams is completed.

[0035] In this exemplary embodiment, determining the tunnel interior space that meets the trough beam assembly requirements may include: using software to simulate the process of assembling trough beam segments in the tunnel interior space to determine the tunnel interior space that meets the trough beam assembly requirements. Here, the tunnel interior space and the specific dimensions of the trough beam are combined in the CAD drawing, the process of assembling trough beam segments in the tunnel interior space is simulated, and it is confirmed that the tunnel interior space meets the trough beam assembly requirements.

[0036] In this exemplary embodiment, Figures 1 to 4 As shown in , the construction site layout may include: setting tracks on the road surface inside the tunnel, assembling tire frames and jacking equipment. The track 1 may include two sets of tracks 1 arranged in parallel with each other, each set of tracks 1 includes two tracks 1 arranged in parallel with each other and arranged below the trough beam, and the jacking equipment includes a plurality of jacks 2, and the plurality of jacks 2 are evenly spaced and arranged below the trough beam. Here, after the trough beam is assembled in the tunnel, the jacks 2 are arranged equidistantly below the trough beam. After jacking for a certain distance, the first set of jacks in the tunnel can be transferred to the pier, connecting the subsequent jacking construction, and completing the entire jacking construction in this cycle. Each set of tracks 1 can be equipped with a beam transporter 3, which is driven by a power mechanism, and the beam transporter 3 can be used to transport steel beams 10. The power mechanism may include a winch 4, which is connected to the beam transporter 3 through a wire rope, and the winch 4 is installed at the rear of the construction site. The wire rope can control the direction through a steering fixed pulley installed in front of the abutment. Here, the elevation of the tire frame is determined according to the linear control data of the trough beam assembly. The tire frame is distributed in the left and right sections. The beam transport vehicle is composed of Ⅰ56#a I-beam and 4 steel wheels with a bearing capacity of 10 tons. A 130t crawler crane 5 (crawler crane) is arranged at the tunnel entrance. The crawler crane 5 is installed on the abutment pier 11 and is used for lifting the steel beam 10. The 130t crawler crane 5 leaves the right abutment of the tunnel entrance and moves to the front of the left tunnel entrance to install the guide beam 13 segment.

[0037] In this exemplary embodiment, the beam transporter 3 is used to transport the trough beam segments from the tunnel portal 6 to the inside of the tunnel 8 for installation. During installation, the installation is carried out sequentially from the tunnel 8 to the tunnel portal 6. Two winches 4 in the tunnel respectively lead out the steel wire rope to the front of the beam transporter 3. The two beam transporters 3 are connected by two steering pulleys 7 at the tunnel entrance and a single steel wire rope. One winch 4 collects the rope and the other winch 4 releases the rope to achieve the overall circulation. The trough beam box is longitudinally positioned by the beam transporter 3, and then placed on the assembly frame 9 by the vertical jack on the beam transporter 3. The transverse connection system 12 between the trough beam boxes is transported to the installation position by a wheeled excavator, and a "door"-shaped frame is processed on site and placed on the top plate of the steel beam, and then temporarily fixed by a chain hoist or steel wire rope. After the trough beam segment is assembled, the top push construction is carried out, and the center line of the trough beam structure coincides with the center line of the tunnel structure. During the entire construction process, the staff use walkie-talkies to communicate to improve efficiency.

[0038] In summary, the advantages of the present invention include at least one of the following:

[0039] (1) The steel beam jacking construction method provided by the present invention has good safety and benefits. The winch is simple to operate and easy to master. By using a walkie-talkie to communicate, the reliability is strong, the signal is stable, and the communication is convenient and fast, which greatly improves the safety quality of the site.

[0040] (2) The method for pushing steel beams in tunnels provided by the present invention has good environmental benefits, reduces the investment in other equipment, saves electricity and fuel resources, and greatly protects the ecological environment of remote mountainous areas.

[0041] Although the above description of a method for jacking steel beams in a tunnel of the present invention has been described in conjunction with exemplary embodiments, it should be clear to those skilled in the art that various modifications and changes may be made to the exemplary embodiments of the present invention without departing from the spirit and scope defined by the claims.

Claims

1. A method for pushing a steel beam in a tunnel, characterized in that: The method comprises the following steps: Determine the internal space of the tunnel that meets the requirements for the assembly of the trough beams; Arrange the construction site based on the determined internal space of the tunnel; Transport steel beams and assemble steel beams and guide beams on the arranged construction site; After the steel beams and guide beams are assembled, top pushing construction is carried out.

2. The method for pushing steel beams in tunnels according to claim 1, characterized in that: The method of determining the tunnel internal space that meets the requirements for assembling the grooved beams comprises: using software to simulate the process of assembling the grooved beam segments in the tunnel internal space to determine the tunnel internal space that meets the requirements for assembling the grooved beams.

3. The method for pushing steel beams in tunnels according to claim 1, characterized in that: The construction site layout includes: setting tracks on the road surface inside the tunnel, assembling tire frames and jacking equipment.

4. The method for pushing steel beams in tunnels according to claim 3, characterized in that: The track comprises two sets of tracks arranged in parallel with each other, each set of tracks comprises two tracks which are parallel with each other and arranged below the trough beam, and the jacking equipment comprises a plurality of jacks which are evenly spaced and arranged below the trough beam.

5. The method for pushing steel beams in tunnels according to claim 4, characterized in that: Each set of tracks is equipped with a beam transport vehicle, which is driven by a power mechanism.

6. The method for pushing steel beams in tunnels according to claim 5, characterized in that: The beam transporter can be used to transport steel beams.

7. The method for pushing steel beams in tunnels according to claim 5, characterized in that: The power mechanism comprises a winch, which is connected to the beam transport vehicle via a steel wire rope and is installed at the rear of the construction site.

8. The method for pushing steel beams in tunnels according to claim 7, characterized in that: The direction of the steel wire rope is controlled by a steering fixed pulley installed in front of the abutment.

9. The method for pushing steel beams in tunnels according to claim 1, characterized in that: The beam transport vehicle is provided with a jack. When the beam transport vehicle transports the box body formed after assembling the steel beams to a predetermined installation position, the box body is placed on the tire frame through the jack.

10. The method for pushing steel beams in tunnels according to claim 9, characterized in that: A transverse connection system is arranged between the boxes, and the transverse connection system is transported to a predetermined installation position by an excavator.