Hoisting equipment capable of simultaneously hoisting multiple frame culverts and use method of hoisting equipment
By designing hoisting equipment with slide rails and hydraulic lifting systems, we have solved the problems of high construction conditions and slow hoisting speeds of existing equipment, achieved the simultaneous hoisting of multiple frame culverts, reduced costs and construction risks, and ensured the safety of railway lines. security and stability.
Patent Information
- Application Number
- CN202410884660.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-03
- Publication Date
- 2024-10-29
AI Technical Summary
Existing hoisting equipment has high requirements on construction roads and construction conditions during use, requires the cooperation of large-scale mechanical equipment, and is difficult to hoist multiple frame culverts at the same time, resulting in a reduction in hoisting speed, especially in construction sites for tunnels under railway business lines Due to poor geographical conditions, large machinery and equipment cannot be transported.
A hoisting equipment including two slide rails, tripod bracket, traveling steel wheel, support base, adjustment plate, lifting beam, drive motor, electric hoist and hydraulic lifting mechanism is designed. The sliding and hydraulic system realizes the lifting of multiple frame culverts. Hoist simultaneously and adjust the hoisting height and speed.
It reduces the requirements for construction roads and conditions, increases the hoisting speed, reduces cost investment, ensures construction safety, and the equipment structure is stable, easy to disassemble and reuse, and avoids damage to existing railway lines.
Smart Images

Figure CN118850993A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of hoisting, and in particular to a hoisting device for hoisting a plurality of frame culverts at the same time and a use method thereof. Background Art
[0002] Hoisting is a general term for the installation and positioning of equipment by a lifting mechanism. Hoisting refers to the installation and positioning of equipment by a crane or a lifting mechanism. Hoisting is a special term for the positioning of equipment. We often encounter equipment loading, transportation, installation and other work. Hoisting engineering is one of the important equipment in the rapid construction of railway operating lines. Its content is to use lifting equipment to lift components and place and fix them in the designed position. However, the existing hoisting equipment still has the following problems during use:
[0003] 1. The existing hoisting equipment has high requirements for construction roads and construction conditions during use. Large-scale machinery and equipment are needed to complete the installation of the frame culvert. In addition, the construction site of the railway underpass under the operating line often has poor geographical conditions, incomplete road supporting facilities, and large-scale machinery and equipment cannot be transported to the site.
[0004] 2. It is difficult to hoist multiple frame culverts at the same time with the existing hoisting equipment during use. Multiple frame culverts need to be hoisted in batches, which reduces the hoisting speed of the frame culvert. To this end, the invention provides a hoisting device for hoisting multiple frame culverts at the same time and a method of using the device. Summary of the invention
[0005] The present invention provides a lifting device for lifting a plurality of frame culverts at the same time and a use method thereof, which solves the problems that the existing lifting equipment has high requirements on construction roads and construction conditions during use, and requires the cooperation of large-scale mechanical equipment to complete the installation of the frame culvert, and the construction site of the railway operating line underpass is often poor in geographical conditions, the road supporting facilities are not perfect, and large-scale mechanical equipment cannot be transported, and the existing lifting equipment is difficult to lift a plurality of frame culverts at the same time during use, and the plurality of frame culverts need to be lifted in batches, which reduces the lifting speed of the frame culvert.
[0006] The invention provides the following technical scheme: a hoisting device for hoisting multiple frame culverts at the same time and a use method thereof, comprising two slide rails, two triangular brackets are provided above the two slide rails, walking steel wheels are fixedly installed at the bottom ends of the two triangular brackets, the bottom ends of the two groups of walking steel wheels are respectively in contact with the outer surfaces of the two slide rails, the top ends of the two triangular brackets are fixedly inlaid with support seats, the inner walls of the two support seats are slidably connected with adjustment plates, the bottom surfaces of the two adjustment plates are provided with threaded grooves, the inner bottom walls of the two support seats are fixedly inlaid with bearing rings, the inner rings of the two bearing rings are threadedly connected with screws, the outer surfaces of the two screws are respectively threadedly connected with the inner walls of the two threaded grooves, a lifting beam is fixedly installed on the upper surfaces of the two adjustment plates, a cavity is provided inside the lifting beam, and two driving motors are fixedly installed on the inner wall of the cavity, and transmission screws are fixedly installed on the output ends of the two driving motors, and the outer surfaces of the two transmission screws are threadedly connected There is a sliding block, the bottom surfaces of the two sliding blocks are fixedly connected with sliding support plates, the bottom surfaces of the two sliding support plates are fixedly installed with two electric hoists, the output ends of the two groups of electric hoists are fixedly connected with a first steel rope, the bottom ends of the two groups of the first steel ropes are fixedly connected with a hook, a hydraulic lifting mechanism is provided on the outside of the slide rail, the output end of the hydraulic lifting mechanism is fixedly connected with a hydraulic oil pipe, the end of the hydraulic oil pipe away from the hydraulic lifting mechanism is fixedly connected with a hydraulic cylinder, the outer surface of the triangular bracket is fixedly connected with a hydraulic fixed support, the upper surface of the hydraulic fixed support is fixedly connected with the bottom end of the hydraulic cylinder, the outer surface of the triangular bracket is fixedly connected with a maintenance ladder, two pulleys are installed on the upper surface of the lifting beam, the outer surfaces of the two pulleys are slidably connected with a second steel rope, the bottom ends of the two second steel ropes are fixedly connected with a lifting tripod, the telescopic end of the hydraulic cylinder is fixedly connected with a connecting clamp, and the outer surface of the triangular bracket is fixedly connected with two component positioning adjusters.
[0007] As a preferred technical solution of the present invention, the inner wall of the cavity is fixedly connected with a bearing seat, the ends of the two transmission screws close to each other are respectively fixedly connected to the inner rings of the two bearing seats, the outer surfaces of the two transmission screws are fixedly connected with bearing plates, and the bottom surfaces of the two bearing plates are fixedly connected to the inner bottom wall of the cavity.
[0008] As a preferred technical solution of the present invention, two sliding holes are provided on the outer surface of the lifting beam, and the inner walls of the two sliding holes are slidably connected with two slide plates, and the bottom surfaces of the two groups of slide plates are fixedly connected to the upper surfaces of the two sliding support plates respectively.
[0009] As a preferred technical solution of the present invention, the side surfaces of the two support seats that are away from each other are fixedly connected to the limiting slides, the inner walls of the two limiting slides are slidably connected to the limiting plates, and the side surfaces of the two limiting plates that are close to each other are respectively fixedly connected to the side surfaces of the two adjustment plates that are away from each other.
[0010] As a preferred technical solution of the present invention, the side surfaces of the two limit plates that are away from each other are fixedly connected with reinforcement plates, and the upper surfaces of the two reinforcement plates are fixedly mounted to the bottom surface of the lifting beam.
[0011] As a preferred technical solution of the present invention, a fixing plate is fixedly installed on the bottom surfaces of the two slide rails, two traction members are fixedly connected to the front side of the fixing plate, and two universal wheels are fixedly installed on the bottom surfaces of the two slide rails.
[0012] As a preferred technical solution of the present invention, two sliding plates are fixedly installed on the outer surfaces of the two groups of walking steel wheels, and the side surfaces of the two groups of sliding plates close to each other are slidably connected to the outer surfaces of the two slide rails respectively.
[0013] As a preferred technical solution of the present invention, anti-derailment baffles are fixedly installed at the front and rear ends of the two slide rails, and two wooden wedge positioning blocks are placed on the upper surfaces of the two slide rails.
[0014] As a preferred technical solution of the present invention, a controller is fixedly installed on the side surfaces of the two triangular brackets that are away from each other, and a horizontal plate is fixedly connected to the inner walls of the two triangular brackets.
[0015] As a preferred technical solution of the present invention, S1, first put the frame culvert in place and install the slide rail; S2, then connect and install the lifting beam and the adjustment plate, so that the lifting beam can be installed and fixed above the triangular bracket, and the assembly of the door frame will be completed; S3, the door frame is hoisted to the top of the predetermined slide rail by the lifting equipment, and the installation is debugged; S4, the door frame is slid on the top of the slide rail for trial operation; S5, multiple electric hoists are operated to drive the first steel rope and the hook to hoist the components.
[0016] The present invention has the following beneficial effects:
[0017] 1. The hoisting equipment for hoisting multiple frame culverts at the same time and the use method thereof can reduce the requirements for construction roads and construction conditions through the use of a gantry, and can complete the installation of the frame culvert without the cooperation of large-scale mechanical equipment, thereby solving the problem that large-scale mechanical equipment cannot be transported, and reducing the cost investment of railway operating line underpass construction projects. The equipment structure has the characteristics of fast installation and disassembly, stable performance, and high reuse. In addition, the application of the gantry equipment does not need to cause damage to the existing railway operating lines, thereby improving the safety of the operating line construction, and no longer needs to cut or weld the rails, which provides a strong guarantee for the restoration of the line and reduces the professional requirements for line construction.
[0018] 2. The hoisting equipment for hoisting multiple frame culverts at the same time and the use method thereof, through the adjustment plate provided on the support seat, and in cooperation with the screw rod, can drive the overall height of the lifting beam to be adjusted, and then facilitate the adjustment of the lifting height of the lifting beam and the electric hoist, and through the adjustment component provided inside the lifting beam, it can drive the two sliding support plates and two groups of electric hoists to perform adjustment movements, and through the setting of the two groups of electric hoists, multiple frame culverts can be hoisted at the same time, solving the current problem of needing to hoist multiple frame culverts in batches, and improving the hoisting speed of the frame culvert. There is no need for personnel to concentrate on the operation in the foundation pit, and only one person is needed to operate the elevator in the prefabricated frame culvert, which greatly reduces the safety hazards caused by foundation pit collapse and mechanical damage, and the comprehensive utilization of the equipment's lifting system and the track puller effectively reduces the economic cost of special equipment. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a three-dimensional structural schematic diagram of the front view of the present invention;
[0020] Figure 2 is a side view of the present invention;
[0021] Figure 3 It is a front view of the present invention;
[0022] Figure 4 It is a schematic diagram of the three-dimensional structure of the bottom view of the present invention;
[0023] Figure 5 A sectional view of the front view of the present invention;
[0024] Figure 6 A sectional view of a side view of the present invention;
[0025] Figure 7 It is a cross-sectional view of the side view of the support seat in the present invention;
[0026] Figure 8 It is a schematic diagram of the three-dimensional structure of the bottom view of the support seat in the present invention.
[0027] In the figure: 1, slide rail; 2, walking steel wheel; 3, triangular bracket; 4, support seat; 5, adjustment plate; 6, thread groove; 7, screw; 8, bearing seat; 9, bearing ring; 10, lifting beam; 11, cavity; 12, driving motor; 13, transmission screw; 14, sliding block; 15, sliding support plate; 16, electric hoist; 17, first steel rope; 18, hook; 19, sliding hole; 20, slide plate; 21, sliding plate; 22, bearing plate; 23, fixed Plate; 24, traction part; 25, limit slide; 26, limit plate; 27, reinforcement plate; 28, universal wheel; 29, wooden wedge positioning block; 30, cross plate; 31, controller; 32, anti-derailment baffle; 33, hydraulic lifting mechanism; 34, hydraulic oil pipe; 35, component positioning adjuster; 36, maintenance ladder; 37, pulley; 38, hydraulic cylinder; 39, second steel rope; 40, connecting clamp; 41, hydraulic fixed support; 42, lifting tripod. DETAILED DESCRIPTION
[0028] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0029] See also Figure 1-8A hoisting device for hoisting multiple frame culverts at the same time and a method of using the hoisting device, comprising two slide rails 1, triangular brackets 3 are arranged above the two slide rails 1, walking steel wheels 2 are fixedly installed at the bottom ends of the two triangular brackets 3, the bottom ends of the two groups of walking steel wheels 2 are respectively in contact with the outer surfaces of the two slide rails 1, the top ends of the two triangular brackets 3 are fixedly inlaid with support seats 4, the inner walls of the two support seats 4 are slidably connected with adjustment plates 5, the bottom surfaces of the two adjustment plates 5 are provided with threaded grooves 6, the inner bottom walls of the two support seats 4 are fixedly inlaid with bearing rings 9, the inner rings of the two bearing rings 9 are threadedly connected with screws 7, the outer surfaces of the two screws 7 are respectively threadedly connected with the inner walls of the two threaded grooves 6, and the upper surfaces of the two adjustment plates 5 are jointly fixedly installed with a lifting beam 10, A cavity 11 is provided inside the lifting beam 10, and two driving motors 12 are fixedly installed on the inner wall of the cavity 11. Transmission screws 13 are fixedly installed on the output ends of the two driving motors 12, and sliding blocks 14 are threadedly connected to the outer surfaces of the two transmission screws 13. The bottom surfaces of the two sliding blocks 14 are fixedly connected with sliding support plates 15, and the bottom surfaces of the two sliding support plates 15 are fixedly installed with two electric hoists 16. The output ends of the two groups of electric hoists 16 are fixedly connected with first steel ropes 17, and the bottom ends of the two groups of first steel ropes 17 are fixedly connected with hooks 18. Through the cooperation of the driving motor 12, the transmission screw 13 and the sliding block 14, the sliding support plate 15 and the electric hoist 16 can be driven to move, so as to facilitate the adjustment of the position of the two groups of electric hoists 16.
[0030] A hydraulic lifting mechanism 33 is provided on the outside of the slide rail 1, and the output end of the hydraulic lifting mechanism 33 is fixedly connected to a hydraulic oil pipe 34, and the end of the hydraulic oil pipe 34 away from the hydraulic lifting mechanism 33 is fixedly connected to a hydraulic cylinder 38, the outer surface of the triangular bracket 3 is fixedly connected to a hydraulic fixed support 41, and the upper surface of the hydraulic fixed support 41 is fixedly connected to the bottom end of the hydraulic cylinder 38, and the outer surface of the triangular bracket 3 is fixedly connected to a maintenance ladder 36, and two pulleys 37 are installed on the upper surface of the lifting beam 10, and the outer surfaces of the two pulleys 37 are slidably connected to the second steel ropes 39, and the bottom ends of the two second steel ropes 39 are fixedly connected to a lifting tripod 42, the telescopic end of the hydraulic cylinder 38 is fixedly connected to a connecting clamp 40, and the outer surface of the triangular bracket 3 is fixedly connected to two component positioning adjusters 35.
[0031] In a preferred embodiment, the inner wall of the cavity 11 is fixedly connected to a bearing seat 8, and the ends of the two transmission screws 13 that are close to each other are fixedly connected to the inner rings of the two bearing seats 8 respectively. The outer surfaces of the two transmission screws 13 are fixedly connected to bearing plates 22, and the bottom surfaces of the two bearing plates 22 are fixedly connected to the inner bottom wall of the cavity 11. The outer surface of the lifting beam 10 is provided with two sliding holes 19, and the inner walls of the two sliding holes 19 are slidably connected to two slide plates 20, and the bottom surfaces of the two groups of slide plates 20 are fixedly connected to the upper surfaces of the two sliding support plates 15 respectively. Through the cooperation of the bearing seat 8 and the bearing plate 22, the transmission screw 13 can be supported during operation, which will make the transmission screw 13 more stable during operation. By using the cooperation of the sliding hole 19 and the slide plate 20, the sliding support plate 15 will be more stable when sliding, and the sliding support plate 15 and the sliding block 14 will be prevented from rotating.
[0032] In a preferred embodiment, the side surfaces of the two support seats 4 that are away from each other are fixedly connected to the limiting slides 25, the inner walls of the two limiting slides 25 are slidably connected to the limiting plates 26, the side surfaces of the two limiting plates 26 that are close to each other are respectively fixedly connected to the side surfaces of the two adjustment plates 5 that are away from each other, and the side surfaces of the two limiting plates 26 that are away from each other are fixedly connected to the reinforcing plates 27, the upper surfaces of the two reinforcing plates 27 are fixedly installed on the bottom surface of the lifting beam 10, and through the cooperation of the limiting slides 25 and the limiting plates 26, the adjusting plates 5 can be limited when adjusting the height to avoid the problem of slipping, and the connection between the lifting beam 10 and the triangular bracket 3 as a whole is deepened by the reinforcing plates 27.
[0033] In a preferred embodiment, a fixing plate 23 is fixedly installed on the bottom surfaces of the two slide rails 1, two traction members 24 are fixedly connected to the front of the fixing plate 23, two universal wheels 28 are fixedly installed on the bottom surfaces of the two slide rails 1, two sliding plates 21 are fixedly installed on the outer surfaces of the two sets of walking steel wheels 2, and the side surfaces of the two sets of sliding plates 21 close to each other are respectively slidably connected to the outer surfaces of the two slide rails 1, and anti-derailment baffles 32 are fixedly installed on the front and rear ends of the two slide rails 1, two wooden wedge positioning blocks 29 are placed on the upper surfaces of the two slide rails 1, and control The inner walls of the two triangular brackets 3 are fixedly connected with a cross plate 30. The fixing plate 23 and the traction member 24 can make the two slide rails 1 more stable. The cooperation of the traction member 24 and the universal wheel 28 can be used for traction with the help of other power equipment. In the absence of other power equipment, human power can be used for pushing, which reduces the requirements for the use environment and improves the applicability of the equipment. The cooperation of the anti-derailing baffle 32 and the sliding plate 21 can prevent the walking steel wheel 2 from sliding above the slide rail 1. The cross plate 30 can be used to support the controller 31, which will make the controller 31 more stable when working.
[0034] In a preferred embodiment, S1, first put the frame culvert in place and install the slide rail 1; S2, then connect and install the lifting beam 10 and the adjustment plate 5, so that the lifting beam 10 can be installed and fixed above the triangular bracket 3, and the assembly of the portal frame will be completed; S3, the portal frame is hoisted to the top of the predetermined slide rail 1 by the lifting equipment, and the installation is debugged; S4, the portal frame is slid on the top of the slide rail 1 for trial operation; S5, multiple electric hoists 16 are operated to drive the first steel rope 17 and the hook 18 to hoist the components.
[0035] Working principle, first put the frame culvert in place, then install the slide rail 1, then connect and install the lifting beam 10 and the adjusting plate 5, and then the lifting beam 10 can be installed and fixed above the triangular bracket 3, and then the assembly of the door frame is completed, and then the door frame is hoisted to the top of the predetermined slide rail 1, and the installation size is debugged and checked, and then the walking steel wheel 2 at the bottom of the triangular bracket 3 is slid on the top of the slide rail 1, and it can be tested, and then the anti-derailment baffles 32 are installed at the front and rear ends of the slide rail 1, and the wooden wedge positioning block 29 is taken to position the walking steel wheel 2 to prevent it from slipping. After everything is ready, during hoisting, the operator is equipped with a lifting hoist and a pushing door frame at four lifting points according to the weight of the component. Then after the frame culvert is installed in place, the first operation process is repeated until the frame culvert is installed.
[0036] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0037] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A hoisting device for hoisting multiple frame culverts at the same time and a method for using the same, comprising two slide rails (1), characterized in that: A triangular bracket (3) is provided above the two slide rails (1), and a walking steel wheel (2) is fixedly installed at the bottom end of the two triangular brackets (3). The bottom ends of the two groups of walking steel wheels (2) are respectively in contact with the outer surfaces of the two slide rails (1). The top ends of the two triangular brackets (3) are fixedly inlaid with a support seat (4), and the inner walls of the two support seats (4) are slidably connected with an adjustment plate (5). The bottom surfaces of the two adjustment plates (5) are provided with a threaded groove (6). The inner bottom walls of the two support seats (4) are fixedly inlaid with a bearing ring (9), and the inner rings of the two bearing rings (9) are threadedly connected with The screw rod (7) is provided with a screw rod (7), the outer surfaces of the two screw rods (7) are respectively threadedly connected to the inner walls of the two thread grooves (6), a lifting beam (10) is fixedly installed on the upper surfaces of the two adjustment plates (5), a cavity (11) is provided inside the lifting beam (10), two driving motors (12) are fixedly installed on the inner wall of the cavity (11), the output ends of the two driving motors (12) are fixedly installed with transmission screws (13), the outer surfaces of the two transmission screws (13) are threadedly connected to sliding blocks (14), and the bottom surfaces of the two sliding blocks (14) are fixedly connected to sliding support plates (15), Two electric hoists (16) are fixedly installed on the bottom surfaces of the two sliding support plates (15), the output ends of the two groups of electric hoists (16) are fixedly connected to the first steel rope (17), and the bottom ends of the two groups of the first steel rope (17) are fixedly connected to the hook (18). The outside of the slide rail (1) is provided with a hydraulic lifting mechanism (33), the output end of the hydraulic lifting mechanism (33) is fixedly connected to a hydraulic oil pipe (34), and one end of the hydraulic oil pipe (34) away from the hydraulic lifting mechanism (33) is fixedly connected to a hydraulic cylinder (38), and the outer surface of the triangular bracket (3) is fixedly connected to a hydraulic fixed support (4 1), the upper surface of the hydraulic fixed support (41) is fixedly connected to the bottom end of the hydraulic cylinder (38), the outer surface of the triangular bracket (3) is fixedly connected to the maintenance ladder (36), the upper surface of the lifting beam (10) is installed with two pulleys (37), the outer surfaces of the two pulleys (37) are slidably connected to the second steel rope (39), the bottom ends of the two second steel ropes (39) are fixedly connected to the lifting tripod (42), the telescopic end of the hydraulic cylinder (38) is fixedly connected to the connecting clamp (40), and the outer surface of the triangular bracket (3) is fixedly connected to two component positioning adjusters (35).
2. The hoisting device for hoisting multiple frame culverts at the same time and the method for using the hoisting device according to claim 1 are characterized in that: The inner wall of the cavity (11) is fixedly connected to a bearing seat (8); the ends of the two transmission screws (13) that are close to each other are respectively fixedly connected to the inner rings of the two bearing seats (8); the outer surfaces of the two transmission screws (13) are fixedly connected to bearing plates (22); and the bottom surfaces of the two bearing plates (22) are fixedly connected to the inner bottom wall of the cavity (11).
3. The hoisting device for hoisting multiple frame culverts at the same time and the method for using the hoisting device according to claim 1, characterized in that: The outer surface of the lifting beam (10) is provided with two sliding holes (19), the inner walls of the two sliding holes (19) are slidably connected with two slide plates (20), and the bottom surfaces of the two groups of slide plates (20) are respectively fixedly connected to the upper surfaces of the two sliding support plates (15).
4. The hoisting device for hoisting multiple frame culverts at the same time and the method for using the hoisting device according to claim 1, characterized in that: The side surfaces of the two support seats (4) that are away from each other are fixedly connected to the limit slide seats (25), the inner walls of the two limit slide seats (25) are slidably connected to the limit plates (26), and the side surfaces of the two limit plates (26) that are close to each other are fixedly connected to the side surfaces of the two adjustment plates (5) that are away from each other.
5. The hoisting device for hoisting multiple frame culverts at the same time and the method for using the hoisting device according to claim 4, characterized in that: The side surfaces of the two limit plates (26) that are away from each other are fixedly connected with a reinforcing plate (27), and the upper surfaces of the two reinforcing plates (27) are fixedly mounted to the bottom surface of the lifting beam (10).
6. The hoisting device for hoisting multiple frame culverts at the same time and the method for using the hoisting device according to claim 1, characterized in that: A fixing plate (23) is fixedly mounted on the bottom surfaces of the two slide rails (1), two traction members (24) are fixedly connected to the front surface of the fixing plate (23), and two universal wheels (28) are fixedly mounted on the bottom surfaces of the two slide rails (1).
7. The hoisting device for hoisting multiple frame culverts at the same time and the method for using the hoisting device according to claim 1, characterized in that: Two sliding plates (21) are fixedly mounted on the outer surfaces of the two groups of traveling steel wheels (2), and the side surfaces of the two groups of sliding plates (21) close to each other are respectively slidably connected to the outer surfaces of the two slide rails (1).
8. The hoisting device for hoisting multiple frame culverts at the same time and the method for using the hoisting device according to claim 1, characterized in that: Anti-derailment baffles (32) are fixedly installed at both front and rear ends of the two slide rails (1), and two wooden wedge positioning blocks (29) are placed on the upper surfaces of the two slide rails (1).
9. The hoisting device for hoisting multiple frame culverts at the same time and the method for using the hoisting device according to claim 1, characterized in that: A controller (31) is fixedly mounted on the side surfaces of the two triangular brackets (3) that are away from each other, and a transverse plate (30) is fixedly connected to the inner walls of the two triangular brackets (3).
10. The method for simultaneously hoisting multiple frame culverts according to claim 1, characterized in that: S1, first put the frame culvert in place and install the slide rail (1); S2, then connect and install the lifting beam (10) and the adjustment plate (5), so that the lifting beam (10) can be installed and fixed above the triangular bracket (3), and the assembly of the portal frame will be completed; S3, the portal frame is hoisted to the top of the predetermined slide rail (1) by the lifting equipment, and the installation is debugged; S4, the portal frame is slid on the top of the slide rail (1) for trial operation; S5, multiple electric hoists (16) are operated to drive the first steel rope (17) and the hook (18) to hoist the components.