Hole guiding device and method for driving drainage plate in surface rock-filled field
By using a drilling device combining steel rods and steel pipes, and utilizing a vibratory hammer and switch support, the problem of difficulty in installing drainage boards on soft soil surfaces with surface rock or hard soil crust was solved. This enabled efficient and low-disturbance drainage board construction, expanding the scope of application and reducing costs.
Patent Information
- Application Number
- CN202411106038.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-13
- Publication Date
- 2024-11-05
AI Technical Summary
Existing technologies make it difficult to install drainage boards when filling soft soil sites with rocks or hard soil crusts on the surface, and traditional methods suffer from problems such as hole collapse, low construction efficiency, and high cost.
A drilling device combining steel rods and steel pipes is used. The high-frequency vibration of the vibratory hammer and the quick connection of the switch support are utilized. The steel rods break and squeeze the soil first, and the steel pipes form holes to protect the wall, so as to realize the vertical installation of the drainage board.
It has expanded the scope of application for drainage board installation, improved construction quality and efficiency, reduced costs, minimized environmental disturbance, and promoted sustainable development.
Smart Images

Figure CN118895756A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of geotechnical engineering, and relates to the construction of reinforced foundation in soft soil sites, in particular to a hole-guiding device and method for reinforcing the foundation by installing drainage boards. Background Art
[0002] It is an economical and effective method to install drainage boards to drain and consolidate the foundation in soft soil sites. On the other hand, when there is a hard crust layer such as stone or soil filling on the surface of the soft soil site, it is often very difficult to install the drainage board. To solve this problem, although the method of excavating the surface hard crust layer such as stone or soil filling can be adopted, this method is not very suitable when the hard crust layer is thick, because the excavation is difficult, the backfill material requirements are high, and the cost is high. At present, most of them use the method of leading holes, first make a hole in the hard crust layer of the stone or soil filling on the surface of the foundation, and then install the drainage board from the hole to the soft soil layer. The disadvantage of this method is that since the hard crust layer of the stone or soil filling is easy to collapse, the drainage board often cannot be driven down, affecting the construction. Summary of the invention
[0003] In view of the problems and defects of the prior art, the purpose of the present invention is to provide a hole-guiding device and method for installing drainage boards in surface stone-filled sites, so as to solve the problem of difficulty in installing drainage boards when the surface of a soft soil foundation is filled with stones or soil.
[0004] The present invention adopts the following technical solution:
[0005] A hole-drilling device for drilling a drainage board in a surface stone-filled site comprises a vibrating hammer, a steel pipe, a steel chisel, a steel chisel tooth cutter, and a steel pipe bending plate; the steel pipe and the vibrating hammer are connected by a switch support, the steel pipe is sleeved outside the steel chisel and extends out from the head of the steel pipe, the tail of the steel chisel is flush with the tail of the steel pipe, and the vibrating hammer is vertically connected to the steel pipe and the tail of the steel chisel to apply vibration impact to them.
[0006] Preferably, the switch support includes a support body fixed on the top of the steel pipe and a connecting piece detachably connected to the support body, the connecting piece is used to connect with the vibrating hammer, and a locking mechanism for quick locking or release is provided between the connecting piece and the support body, and the locking mechanism is bolt locking, snap locking or hydraulic locking to achieve quick connection and disassembly of the steel pipe and the vibrating hammer.
[0007] Preferably, the steel chisel is made of high-strength, high-toughness alloy steel material; preferably, the head of the steel chisel is conical; preferably, the cone angle range of the cone is 60° to 90°; preferably, the cone angle of the head of the steel chisel is 75°.
[0008] Preferably, the diameter of the steel drill is 12 to 15 cm to provide sufficient rigidity and strength while facilitating driving; the diameter of the steel pipe is 15 to 18 cm to form a protective layer on the outside of the steel drill and reduce driving resistance.
[0009] Preferably, the steel drill head is evenly provided with a plurality of tooth cutters along the radial direction to increase the contact area between the steel drill and the stone.
[0010] Preferably, the radial angle between two adjacent tooth cutters is 60°; preferably, the top width of the tooth cutter is 5 mm and the height is 5 mm.
[0011] Preferably, the steel pipe is made of seamless steel pipe or spiral welded pipe to maintain sufficient straightness and stability during the construction process to avoid bending or deformation.
[0012] Preferably, the wall thickness of the steel pipe is 4-6 mm; preferably, the outer surface of the steel pipe is evenly distributed with a plurality of grooves along the circumference to reduce the contact area between the steel pipe and the stone; preferably, the circumferential angle between two adjacent grooves is 30°, the depth of each groove is 0.5 mm, and the bottom width is 3-5 mm; preferably, the cross-sectional shape of the groove is rectangular, trapezoidal or semicircular; preferably, the bottom end of the steel pipe is bent inwardly so that the bottom end of the steel pipe is tapered to prevent stones from entering and reduce the resistance to driving; preferably, the angle between the lower end of the steel pipe and the vertical direction is 30°, and the bending length is 1 cm.
[0013] The method for installing a drainage board using the above-mentioned hole-drawing device comprises the following steps:
[0014] 1) Use steel drill and steel pipe to penetrate the hard crust layer including stone filling or soil filling;
[0015] 2) Disconnect the steel pipe from the vibrating hammer;
[0016] 3) Lift the vibrating hammer, pull out the steel chisel, and leave the steel pipe in the foundation;
[0017] 4) Install plastic drainage board from the center of the steel pipe;
[0018] 5) Pull out the steel pipe.
[0019] Preferably, in step 1), the impact force of a high-frequency vibration hammer is used to penetrate the hard shell layer with the steel drill and the steel pipe.
[0020] Optionally, the steel drill and the vibratory hammer are fixed, a steel pipe slightly larger than the diameter of the steel drill is put on the steel drill, the vibratory hammer and the steel pipe are connected through a switch support, and the vibratory hammer is connected to equipment including an excavator or a crane and is driven by the equipment to vibrate and move up and down; the high-frequency vibration of the vibratory hammer is used to penetrate the surface stone filling layer of the site, so that the heads of the steel drill and the steel pipe enter the soft soil layer, and at the same time, the tails of the steel drill and the steel pipe have a section protruding outside the surface stone filling layer of the site; the constraints of the vibratory hammer and the steel pipe are released, the vibratory hammer is lifted, the steel drill is pulled out, the steel pipe is buried in the site, and the drainage board is driven into the soft soil layer through the holes in the steel pipe, and finally the steel pipe is pulled out, thereby realizing the installation of the drainage board in the surface stone filling site.
[0021] Optionally, the steel drill and the vibratory hammer are fixed, a steel pipe slightly larger than the diameter of the steel drill is put on the steel drill, the vibratory hammer and the steel pipe are connected through a switch support, and the vibratory hammer is connected to equipment including an excavator or a crane and is driven by the equipment to vibrate and move up and down; the high-frequency vibration of the vibratory hammer is used to penetrate the surface stone filling layer of the site, so that the heads of the steel drill and the steel pipe enter the soft soil layer, and at the same time, the tails of the steel drill and the steel pipe have a section protruding outside the surface stone filling layer of the site; the constraints of the vibratory hammer and the steel pipe are released, the vibratory hammer is lifted, the steel drill is pulled out, and the steel pipe is buried in the site; sand and soil materials are filled in the holes of the steel pipe, and a drainage board is installed after the steel pipe is pulled out.
[0022] The hole-guiding device and construction method for installing the drainage board on the surface stone-filled site provided by the present invention have significant advantages and beneficial effects compared with the prior art, specifically including the following aspects:
[0023] 1) Solve the problem of drainage board installation and expand the scope of application
[0024] Traditional drainage board installation equipment and processes are mainly suitable for natural soft soil foundations or sites with plain fill on the surface. When encountering hard interlayers such as fill stone and gravel on the surface, it is difficult for the drainage board to penetrate the hard shell layer, which seriously affects the installation effect and efficiency. The present invention adopts a hole-guiding device composed of a steel chisel and a steel pipe. The conical head of the steel chisel is used to break the soil first, and a hole is formed under the protective wall effect of the steel pipe. It can effectively penetrate several meters or even thicker hard surface layers, creating conditions for subsequent drainage board installation. Therefore, the present invention greatly expands the scope of application of drainage board installation, allowing it to adapt to more complex and changeable formation conditions;
[0025] 2) Improve the quality of drainage board installation and ensure drainage effect
[0026] Whether the drain board can be driven vertically into the designed depth and fit tightly with the soil is a key factor in determining the drainage consolidation effect. The hole-guiding device and construction method of the present invention utilize the advance guiding effect of the steel chisel and the wall support effect of the steel pipe to ensure the verticality and stability of the hole, providing a good driving channel for the drain board. At the same time, prefabricated holes are also conducive to the close contact between the drain board and the soil, avoiding quality defects such as bending, breaking, and clogging of the drain board during the driving process, thereby maximizing the drainage efficiency of the drain board and ensuring the quality of foundation consolidation.
[0027] 3) Significantly improve construction efficiency and shorten construction period
[0028] When installing a drainage board on a hard surface foundation, conventional processes usually require pre-drilling of pilot holes and then manual insertion of the drainage board, which results in very low construction efficiency and seriously restricts the progress of the project. The hole-guiding device and construction method of the present invention can quickly guide the steel drill and steel pipe to form a hole by utilizing the powerful impact force of the vibrating hammer; the quick connection and separation function of the switch support can achieve seamless switching between pulling out the steel drill and inserting the drainage board, and the entire installation process can be mechanized and automated, which can increase construction efficiency by several times or even dozens of times, greatly shortening the construction period;
[0029] 4) Save construction costs and improve economic benefits
[0030] The installation of drainage board is an important process for soft foundation treatment, which directly affects the cost of the entire project. The use of the hole-guiding device and construction method of the present invention can save the cost of manpower, materials, equipment, etc. to the maximum extent through reasonable structural design and process optimization. For example, the steel chisel and steel pipe can be reused many times, which significantly reduces material consumption; the switch support ensures the rapid turnover of equipment and improves the utilization rate of machine hours; mechanized and automated operations reduce the configuration of on-site personnel and save labor costs.
[0031] 5) Protect the environment and promote sustainable development
[0032] The traditional construction of hard surface drainage boards often requires large-scale earth excavation and backfilling, which generates a large amount of waste soil and dust, and has an adverse impact on the environment. The use of the hole-guiding device and construction method of the present invention, through the guided hole-making of the steel drill and steel pipe, minimizes the amount of earth excavation, and realizes environmentally friendly construction with low disturbance and less waste soil; at the same time, mechanized construction also reduces the generation of dust and noise on site, and improves the construction environment. Therefore, the promotion and application of the present invention is conducive to the coordinated development of engineering construction and the ecological environment, and promotes the realization of sustainable development goals. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following drawings are provided for display:
[0034] Figure 1 The present invention is a schematic cross-sectional view of an embodiment of a hole-guiding device for constructing a drainage board in a surface stone-filled site.
[0035] Figure 2 It is a schematic diagram of the arrangement of the tooth cutters on the steel drill bit of the hole-guiding device of the present invention.
[0036] Figure 3 This is a schematic diagram of using the hole-guiding device of the present invention to construct in a soft soil site. Figure 1 .
[0037] Figure 4 This is a schematic diagram of using the hole-guiding device of the present invention to construct in a soft soil site. Figure 2 .
[0038] Numbers in the figure are as follows: 1. Vibratory hammer; 2. Steel pipe; 3. Steel chisel; 4. Toothed knife; 5. Steel pipe bending plate.
[0039] It should be noted that the above-mentioned drawings only show some embodiments of the present invention. For ordinary technicians in this field, they can also obtain drawings of other embodiments based on these drawings without paying any creative work. DETAILED DESCRIPTION
[0040] In order to make the purpose, technical solution and beneficial effects of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention.
[0041] For ease of description, spatially relative terms, such as "under", "below", "down", "above", "upper", etc., will be used when necessary to describe the relationship of one element or feature relative to another element or feature shown in the drawings. The spatially relative terms are intended to include different orientations of the device in use or operation other than the orientation shown in the drawings. For example, if the device in the figure is turned over, elements described as being "under" or "beneath" other elements or features will be oriented as being "above" the other elements or features.
[0042] Unless otherwise defined, the terms used herein have the same meaning as commonly understood by ordinary technicians in the field to which the invention belongs, and the terms should be understood to have the same meaning as in the context of the relevant technology and should not be understood in an idealized or overly formal way, except where explicitly defined in the present invention.
[0043] A hole-drilling device for drilling drainage boards in surface stone-filled sites comprises a vibrating hammer, a steel pipe and a steel chisel; the steel pipe and the vibrating hammer are connected by a switch support, the steel pipe is sleeved outside the steel chisel and extends out from the head of the steel pipe, the tail of the steel chisel is flush with the tail of the steel pipe, and the vibrating hammer is vertically connected to the tails of the steel pipe and the steel chisel to apply vibration impact to them.
[0044] The switch support includes a support body fixed on the top of the steel pipe and a connecting piece detachably connected to the support body, the connecting piece is used to connect with the vibratory hammer, and a locking mechanism for quick locking or release is provided between the connecting piece and the support body. The locking mechanism can be selected from bolt locking, snap locking or hydraulic locking, etc., which can realize quick connection and disassembly of the steel pipe and the vibratory hammer and improve construction efficiency.
[0045] The steel chisel is made of high-strength and high-toughness alloy steel material. The head of the steel chisel is conical, and the cone angle range is 60° to 90°. For a rock-filling layer containing a large amount of stones and gravel, a larger cone angle can more effectively disperse stress when encountering large particles, thereby reducing the risk of damage to the steel chisel head. The cone angle of the head of the steel chisel is 75°, which can achieve a good balance between penetration resistance and wear resistance, and can effectively crush and push away gravel particles without excessively increasing the wear of the steel chisel head.
[0046] The diameter of the steel drill is 12 to 15 cm, which can provide sufficient rigidity and strength, while the diameter is not too large, so it is easy to drive in; the diameter of the steel pipe is 15 to 18 cm, which can form a protective layer on the outside of the steel drill to reduce the driving resistance.
[0047] The steel drill head is evenly provided with multiple tooth cutters along the axial direction, and the angle between two adjacent tooth cutters is 60°. By evenly arranging the tooth cutters on the steel drill head, the contact area between the steel drill and the stone is increased, the crushing and cutting effects are enhanced, and the construction efficiency is improved; the tooth cutter top width is 5mm and the height is 5mm. In addition, the design can be optimized according to the size and strength of the stone to adapt to different formation conditions.
[0048] The steel pipe is made of seamless steel pipe or spiral welded pipe with a wall thickness of 4 to 6 mm, ensuring that the steel casing maintains sufficient straightness and stability during construction to avoid bending or deformation.
[0049] The outer surface of the steel pipe is evenly distributed with a plurality of grooves along the circumferential direction; the angle between two adjacent grooves along the circumferential direction is 30°, the depth of each groove is 0.5 mm, and the bottom width is 3 to 5 mm; the cross-sectional shape of the grooves can be rectangular, trapezoidal or semicircular; the provision of the grooves reduces the contact area between the steel pipe and the stone, reduces the driving resistance, and improves the construction efficiency.
[0050] The bottom end of the steel pipe is bent inward by 30° (angle with the vertical direction) and the bending length is 1 cm, so that the bottom end of the steel pipe is tapered, which can effectively prevent stones and the like from entering and significantly reduce the resistance to driving, taking into account the construction quality and efficiency.
[0051] The method for installing a drainage board using the above-mentioned hole-drawing device comprises the following steps:
[0052] 1) Use steel drill and steel pipe to penetrate the hard crust layer including stone filling or soil filling;
[0053] 2) Disconnect the steel pipe from the vibrating hammer;
[0054] 3) Lift the vibrating hammer, pull out the steel chisel, and leave the steel pipe in the foundation;
[0055] 4) Install plastic drainage board from the center of the steel pipe;
[0056] 5) Pull out the steel pipe.
[0057] In step 1), the impact force of a high-frequency vibration hammer is used to penetrate the hard shell layer with the steel drill and the steel pipe.
[0058] Fix the steel chisel and the vibrating hammer, put a steel pipe with a diameter slightly larger than that of the steel chisel on the steel chisel, connect the vibrating hammer and the steel pipe through a switch support, and connect the vibrating hammer to the equipment including an excavator or a crane, so that the vibrating hammer is driven by the equipment to vibrate and move up and down; utilize the high-frequency vibration of the vibrating hammer to penetrate the surface stone filling layer of the site, so that the heads of the steel chisel and the steel pipe enter the soft soil layer, and at the same time, the tails of the steel chisel and the steel pipe have a section protruding outside the surface stone filling layer of the site; release the constraints of the vibrating hammer and the steel pipe, lift the vibrating hammer, pull out the steel chisel, bury the steel pipe in the site, and drive the drainage board into the soft soil layer through the holes of the steel pipe, and finally pull out the steel pipe, so as to realize the installation of the drainage board in the surface stone filling site; alternatively, fill the holes of the steel pipe with sand and soil materials, and install the drainage board after pulling out the steel pipe.
[0059] like Figure 1 As shown, a hole-drilling device for drilling a drainage board in a surface stone-filled site comprises a vibrating hammer 1, a steel pipe 2 and a steel chisel 3; the steel pipe 2 and the vibrating hammer 1 are connected by a switch support, the steel pipe 2 is sleeved on the outside of the steel chisel 3, the head of the steel chisel 3 is conical, and a toothed knife 4 is arranged on the upper part, extending from the head of the steel pipe 2, and the tail of the steel chisel 3 is flush with the tail of the steel pipe 2, and the vibrating hammer 1 is vertically connected to the tail of the steel pipe 2 and the steel chisel 3 to apply vibration impact to them.
[0060] In one embodiment, the diameter of the steel drill 3 is about 12-15 cm, and the diameter of the steel pipe 2 is about 15-18 cm.
[0061] The method for installing a drainage board using the hole-guiding device of the present invention comprises: fixing a steel drill 3 and a vibrating hammer 1, sleeve a steel pipe 2 slightly larger than the diameter of the steel drill 3 on the steel drill 3, connecting the vibrating hammer 1 and the steel pipe 2, and connecting the vibrating hammer 1 to an excavator or a crane and other equipment, and being driven by the equipment to vibrate and move up and down; utilizing the high-frequency vibration of the vibrating hammer 1 to penetrate the surface stone-filling layer of the site, so that the heads of the steel drill 3 and the steel pipe 2 enter the soft soil layer, and at the same time, a section of the tail of the steel drill 3 and the tail of the steel pipe 2 protrudes outside the surface stone-filling layer of the site; releasing the constraints of the vibrating hammer 1 and the steel pipe 2, lifting the vibrating hammer 1, pulling out the steel drill 3, burying the steel pipe 2 in the site, driving the drainage board into the soft soil layer through the holes of the steel pipe 2, and finally pulling out the steel pipe 2, thereby realizing the installation of the drainage board in the surface stone-filling site.
[0062] In another embodiment, the holes of the steel pipe 2 may be filled with sand material, which can prevent the holes from collapsing and does not hinder the installation of the drainage board. The drainage board can be installed after the steel pipe is pulled out.
[0063] In summary, the hole-guiding device and construction method for installing drainage boards in surface stone-filled sites provided by the present invention give full play to the role of key components such as steel chisels, steel pipes, and switch supports through innovative design concepts and optimized construction processes, forming a set of comprehensive solutions that are technologically advanced, economically efficient, and environmentally friendly. Compared with the prior art, the present invention can effectively solve the problem of difficulty in installing drainage boards when filling stones or soil on the surface of soft soil foundations, improve construction quality and efficiency, and reduce construction costs.
[0064] The above description of the embodiments is to facilitate the understanding and use of the present invention by those skilled in the art. It is obvious that those skilled in the art can easily make various modifications to these embodiments and apply the general principles described herein to other embodiments without creative work. Therefore, the present invention is not limited to the above embodiments, and improvements and modifications made by those skilled in the art based on the disclosure of the present invention without departing from the scope of the present invention should be within the protection scope of the present invention.
Claims
1. A hole-guiding device for constructing a drainage board in a surface rockfill site, characterized in that: It includes a vibrating hammer, a steel pipe, a steel chisel, a steel chisel tooth cutter, and a steel pipe bending plate; the steel pipe and the vibrating hammer are connected by a switch support, the steel pipe is sleeved outside the steel chisel and extends out from the head of the steel pipe, the tail of the steel chisel is flush with the tail of the steel pipe, and the vibrating hammer is vertically connected to the steel pipe and the tail of the steel chisel to apply vibration impact to them.
2. The hole-guiding device for installing drainage board in surface rockfill site according to claim 1, characterized in that: The switch support includes a support body fixed on the top of the steel pipe and a connecting piece detachably connected to the support body, the connecting piece is used to connect with the vibration hammer, and a locking mechanism for quick locking or release is provided between the connecting piece and the support body, and the locking mechanism is bolt locking, snap locking or hydraulic locking to achieve quick connection and disassembly of the steel pipe and the vibration hammer.
3. The hole-guiding device for installing drainage board in surface rockfill site according to claim 1, characterized in that: The steel chisel is made of high-strength and high-toughness alloy steel material; preferably, the head of the steel chisel is conical; preferably, the cone angle range of the cone is 60° to 90°; preferably, the cone angle of the head of the steel chisel is 75°.
4. The hole-guiding device for installing drainage board in surface rockfill site according to claim 1, characterized in that: The diameter of the steel drill is 12-15 cm to provide sufficient rigidity and strength and facilitate driving; the diameter of the steel pipe is 15-18 cm to form a protective layer on the outside of the steel drill and reduce driving resistance.
5. The hole-guiding device for installing drainage board in surface rockfill site according to claim 1, characterized in that: The steel drill head is evenly provided with a plurality of tooth cutters along the radial direction to increase the contact area between the steel drill and the stone.
6. The hole-guiding device for installing drainage board in surface rockfill site according to claim 5, characterized in that: The radial angle between two adjacent tooth cutters is 60°; preferably, the tooth cutter top width is 5mm and the height is 5mm.
7. The hole-guiding device for installing drainage board in surface rockfill site according to claim 1, characterized in that: The steel pipe is made of seamless steel pipe or spiral welded pipe, and maintains sufficient straightness and stability during the construction process to avoid bending or deformation; preferably, the wall thickness of the steel pipe is 4 to 6 mm.
8. The hole-guiding device for installing drainage board in surface rockfill site according to claim 1, characterized in that: The outer surface of the steel pipe is evenly distributed with a plurality of grooves along the circumference to reduce the contact area between the steel pipe and the stone blocks; preferably, the angle between two adjacent grooves along the circumference is 30°, the depth of each groove is 0.5 mm, and the bottom width is 3 to 5 mm; preferably, the cross-sectional shape of the groove is rectangular, trapezoidal or semicircular; preferably, the bottom end of the steel pipe is bent inwardly so that the bottom end of the steel pipe is tapered to prevent stones from entering and reduce the resistance to driving; preferably, the angle between the lower end of the steel pipe and the vertical direction is 30°, and the bending length is 1 cm.
9. A method for constructing a drainage board using the hole-drawing device according to claim 1, characterized in that: The following steps are involved: 1) Use steel drill and steel pipe to penetrate the hard crust layer including stone filling or soil filling; 2) Disconnect the steel pipe from the vibrating hammer; 3) Lift the vibrating hammer, pull out the steel chisel, and leave the steel pipe in the foundation; 4) Install plastic drainage board from the center of the steel pipe; 5) Pull out the steel pipe.
10. The method for installing a drainage board according to claim 9, characterized in that: In step 1), the impact force of a high-frequency vibration hammer is used to penetrate the hard shell layer with the steel drill and the steel pipe.
11. The method for installing a drainage board according to claim 9, characterized in that: Fix the steel chisel and the vibrating hammer, put a steel pipe slightly larger than the diameter of the steel chisel on the steel chisel, connect the vibrating hammer and the steel pipe through a switch support, and connect the vibrating hammer to the equipment including an excavator or a crane, so that the vibrating hammer is driven by the equipment to vibrate and move up and down; utilize the high-frequency vibration of the vibrating hammer to penetrate the surface stone filling layer of the site, so that the heads of the steel chisel and the steel pipe enter the soft soil layer, and at the same time, the tails of the steel chisel and the steel pipe have a section protruding outside the surface stone filling layer of the site; release the constraints of the vibrating hammer and the steel pipe, lift the vibrating hammer, pull out the steel chisel, bury the steel pipe in the site, and drive the drainage board into the soft soil layer through the holes of the steel pipe. Finally, pull out the steel pipe, thereby realizing the installation of the drainage board in the surface stone filling site.
12. The method for installing a drainage board according to claim 9, characterized in that: Fix the steel drill and the vibrating hammer, put a steel pipe slightly larger than the diameter of the steel drill on the steel drill, connect the vibrating hammer and the steel pipe through a switch support, and connect the vibrating hammer to the equipment including an excavator or a crane, so that the vibrating hammer is driven by the equipment to vibrate and move up and down; utilize the high-frequency vibration of the vibrating hammer to penetrate the surface stone filling layer of the site, so that the heads of the steel drill and the steel pipe enter the soft soil layer, and at the same time, the tails of the steel drill and the steel pipe have a section protruding outside the surface stone filling layer of the site; release the constraints of the vibrating hammer and the steel pipe, lift the vibrating hammer, pull out the steel drill, and bury the steel pipe in the site; fill the holes of the steel pipe with sand and soil materials, and install a drainage board after the steel pipe is pulled out.