Wellhead groove structure of real drilling test base and construction method of wellhead groove structure

The crane track beams and prefabricated formwork of the modular structure are prefabricated when pouring concrete, combined with micro-expanded concrete and embedded bolts to fix it, and the problems of long construction time and high cost of wellhead grooves in the existing technology are solved, and rapid construction and Reuse meets the stability requirements of drilling rig movement.

CN118895947APending Publication Date: 2024-11-05SHAANXI YANCHANG PETROLEUM GRP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411104496.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-13
Publication Date
2024-11-05

AI Technical Summary

Technical Problem

The wellhead trough of the existing drilling test base is completely poured with concrete, resulting in a long construction time and needs to be demolished after the test, which is time-consuming and labor-intensive, affecting efficiency and cost.

Method used

The crane track beams and prefabricated formwork are adopted with modular structures, and prefabricated forms are prefabricated when pouring the concrete of the drilling rig track beams, shortening the construction time, and fixed connections through micro-expanded concrete and embedded bolts to ensure stable structure and rapid installation and disassembly.

Benefits of technology

The construction time of the wellhead groove is shortened, and the crane track beams and prefabricated formwork can be reused after the drilling is completed, saving construction costs and ensuring the structural stability of the drilling rig's moving tracks.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118895947A_ABST
    Figure CN118895947A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of well drilling, and particularly relates to a well mouth groove structure of a real drilling test base and a construction method thereof. The well mouth structure comprises a ground pouring plate and a plurality of well mouths arranged on the ground pouring plate, and the well mouths are linearly arranged; the crane track beams and the drilling machine track beams are adjacent to each other and are symmetrically arranged on the two sides of the wellhead which is linearly arranged, and the crane track beams are close to the wellhead; a crane track is arranged on the upper surface of the crane track beam; a drilling machine moving track is arranged on the drilling machine track beam, the concrete pile foundations are arranged in the drilling machine track beam, and the concrete pile foundations extend to the lower portion of the ground to be fixed; the crane track beam and the prefabricated formwork are of a modular structure, prefabrication is carried out while concrete pouring is carried out on the drilling machine track beam, the construction time of a wellhead groove is shortened, and the construction cost is saved; the drilling machine moving track is fixedly connected through the embedded bolts, the structural stability of the drilling machine moving track is guaranteed, and the moving requirement of the drilling machine is met.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of drilling, and in particular relates to a wellhead slot structure of a real drilling test base and a construction method thereof. Background Art

[0002] The intelligent drilling guide system is known as the "crown jewel" of oil drilling technology. It uses a rotary steering system and a geological steering system to realize real-time drilling data analysis, predict geological structures, optimize drilling paths, and effectively increase drilling speed. It is a national weapon for efficiently completing directional wells and horizontal wells, and is also a "killer" technology for improving the efficiency of exploration and development of conventional and unconventional complex oil and gas reservoirs. The intelligent drilling guide system can improve exploration efficiency, reduce exploration risks, optimize oil and gas field development strategies, realize intelligent oilfield management, and thus increase oilfield production capacity. The actual drilling test base provides a real and controllable actual drilling test environment for the intelligent drilling guide system, which can simulate and verify the performance of the intelligent drilling guide system under different geological conditions, and provide an important basis for its functional optimization and technological innovation. Through iterative tests at the actual drilling base, a large amount of real data can be collected and verified, system performance can be evaluated, problems and bottlenecks can be discovered, and improvements and optimizations can be made quickly.

[0003] In order to facilitate the movement of drilling rigs, the actual drilling test base usually lays tracks along the designed wellbore (concrete cast wellhead slot) trajectory, so that the drilling rig can move on the track to meet the needs of rapid testing. After drilling a test well, the drilling rig can be moved to the next test wellhead slot position along the track without disassembly, which greatly reduces the non-test drilling operation time and greatly improves the test drilling efficiency. However, the wellhead slot designed by the current test base is completely cast in concrete, which takes a long time to construct. After the test drilling operation is completed, other test operations need to be carried out, and the wellhead slot needs to be dismantled, which is time-consuming and labor-intensive. Summary of the invention

[0004] In order to overcome the above problems, the purpose of the present invention is to provide a wellhead slot structure and a construction method of a real drilling test base. By adopting a modular structure, the crane track beam and the prefabricated formwork are prefabricated at the same time as the concrete pouring of the drilling rig track beam, thereby shortening the construction time of the wellhead slot. After the drilling is completed, the crane track beam and the prefabricated formwork can be reused, saving construction costs.

[0005] The technical scheme of the present invention is as follows: it comprises a ground casting plate and a plurality of wellheads arranged on the ground casting plate, wherein the wellheads are arranged linearly; it also comprises two sets of adjacent crane track beams and drilling rig track beams, which are symmetrically arranged on both sides of the wellheads arranged linearly, wherein the crane track beam is close to the wellhead; a crane track is arranged on the upper surface of the crane track beam; a drilling rig moving track is arranged on the drilling rig track beam, and it also comprises a plurality of concrete pile foundations arranged in the drilling rig track beam, wherein the concrete pile foundation extends into the lower part of the ground for fixing; It also includes a prefabricated template located between two crane track beams, the prefabricated template is arranged on a ground casting plate and is sleeved on the wellhead; a fixing device is provided at the lower end of the crane track beam close to the wellhead; it also includes a drainage channel arranged on the ground casting plate, the drainage channel is located between adjacent wellheads; it also includes a plurality of drainage grooves arranged on the prefabricated template, the drainage grooves are connected to the drainage channel; the prefabricated template is composed of a plurality of unit prefabricated templates, there are joints between adjacent unit prefabricated templates, and the number of unit prefabricated templates is the same as the number of wellheads.

[0006] The crane track beam and prefabricated formwork both adopt a modular structure, that is, the crane track beam is composed of multiple unit track beams, and the prefabricated formwork is composed of multiple unit prefabricated formworks. A modular structure is adopted, and the prefabricated formwork can be selected according to the number of wellheads. The prefabricated formwork is composed of a single prefabricated formwork unit around each well, and there is a splicing seam between adjacent prefabricated formwork units. In addition, the crane track beam and the prefabricated formwork adopt a modular structure and are prefabricated at the same time as the drilling rig track beam concrete is poured, thereby shortening the construction time of the wellhead slot. After drilling is completed, the crane track beam and the prefabricated formwork can be reused, saving construction costs.

[0007] Drainage grooves are set on the ground casting plate, and all the drainage grooves are finally connected to the drainage channel, which can ensure that the accumulated water in the wellhead groove is discharged into the drainage channel through the drainage grooves, and the accumulated water inside the wellhead groove can be quickly discharged.

[0008] Furthermore, the fixing device is composed of a fixing block and a fixing anchor, the fixing block is arranged at the lower part of the crane track beam and close to the ground casting plate, and the crane track beam is fixedly connected to the ground casting plate through the fixing anchor.

[0009] The fixing device here is used to fix the crane track beam and ensure that the crane track beam can be quickly installed and disassembled.

[0010] Furthermore, a wellhead fixing ring is sleeved on the outer side of the wellhead above the ground casting plate, and a water stop is filled between the wellhead fixing ring and the prefabricated template.

[0011] The wellhead fixing ring can protect the wellhead when it is hoisted with the template, and filling the water stop between the wellhead fixing ring and the prefabricated template can effectively seal.

[0012] Furthermore, there is a track beam filler between the crane track beam and the drilling rig track beam, and the track beam filler is filled with micro-expansive concrete.

[0013] In order to ensure a tight connection between the crane track beam and the drilling rig track beam, micro-expansive concrete is filled in the track beam caulking.

[0014] Furthermore, the surface of the crane track beam close to the wellhead is a downwardly inclined surface, and the fixing block is arranged at the bottom of the inclined surface end; The crane track is located in the middle of the crane track beam and is a trapezoidal groove structure, with a steel plate laid on the bottom.

[0015] A steel plate is laid at the bottom of the trapezoidal groove to ensure that the crane can move smoothly in the crane track during construction.

[0016] Furthermore, the drilling rig moving track is located in the middle of the top of the drilling rig track beam, and the drilling rig moving track is fixedly connected to the top of the concrete pile foundation by embedded bolts.

[0017] The drilling rig mobile track is fixedly connected to the top of the concrete pile foundation by embedded bolts, which ensures the structural stability of the drilling rig mobile track and meets the movement requirements of the drilling rig.

[0018] Furthermore, the cross section of the fixing block is a right triangle, the inclined surface of which is located on the same inclined surface as the inclined surface of the crane track beam, and a plurality of fixing anchors are respectively provided on one side thereof close to the crane track beam and the ground casting plate.

[0019] The inclined surface of the fixing block has the same inclination angle as the inclined surface of the crane track and is located on the same inclined surface, and the fixing block is fixed by a plurality of fixing anchors.

[0020] Furthermore, the center distance between adjacent wellheads is 4>D≥2m, and the number of columns of linearly arranged wellheads provided in the middle of the ground casting plate is M, 6≥M≥2.

[0021] In actual operation, it is necessary to ensure that there is enough spacing between the wellheads. On the one hand, the distance between the wells can fully utilize the well slot space, and on the other hand, it is more convenient during implementation.

[0022] A construction method for a wellhead slot structure of a real drilling test base, the steps of which are: S1: Level the site, hammer the guide tube as the wellhead into the designed well slot area, and construct the concrete pile foundation at the location of the drilling rig track beam; S2: Concrete the ground slab on the ground of the wellhead and concrete pile foundation area, weave steel mesh at the concrete pile foundation, and cast the drilling rig track beam; S3: hoisting the prefabricated crane track beams one by one on the side of the ground casting plate close to the drilling rig track beam and fixing them with fixing blocks, and hoisting and laying the prefabricated template on the outside of the wellhead at the same time; S4: Fill the seam of the track beam where the crane track beam and the drilling rig track beam are connected with micro-expansive concrete. The precast formwork is composed of multiple unit precast formworks. The joints of adjacent unit precast formworks are filled with waterstops. The drilling rig mobile track is fixed to the top of the concrete pile foundation with embedded bolts. Steel plates are laid in the crane track in the middle of the top of the crane track beam to complete the overall construction.

[0023] The technical effects of the present invention are as follows: 1. The present invention adopts a modular structure through the crane track beam and the prefabricated template, and prefabricates the drill track beam while pouring concrete, thereby shortening the construction time of the wellhead slot. After the test drilling is completed, the crane track beam and the prefabricated template can be reused, saving construction costs. 2. The drilling rig mobile track of the present invention is fixedly connected to the top of the concrete pile foundation by embedded bolts, ensuring the structural stability of the drilling rig mobile track and meeting the movement requirements of the drilling rig.

[0024] The following is a further description with reference to the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 It is a schematic diagram of the wellhead slot structure of a real drilling test base of the present invention.

[0026] Figure 2 It is a top view schematic diagram of a wellhead slot structure of a real drilling test base of the present invention.

[0027] Figure numerals: 1-drilling rig mobile track; 2-drilling rig track beam; 3-concrete pile foundation; 4-track beam caulking; 5-crane track; 6-crane track beam; 7-fixed anchor; 8-fixed block; 9-prefabricated formwork; 10-wellhead; 11-wellhead fixing ring; 12-ground casting plate; 13-drainage channel; 14-drainage trough; 15-joining seam. DETAILED DESCRIPTION

[0028] Example 1 like Figure 1 , Figure 2 As shown, a wellhead slot structure of a real drilling test base includes a ground casting plate 12, and a wellhead 10 arranged linearly in 2 rows and 4 columns is provided in the middle of the ground casting plate 12, and a crane track beam 6 and a drilling rig track beam 2 are sequentially provided at both sides of the ground casting plate 12, wherein the crane track beam 6 is close to the wellhead 10, and a crane track 5 is provided on the upper surface of the crane track beam 6; A drilling rig mobile track 1 is provided in the middle of the drilling rig track beam 2, and also includes a plurality of concrete pile foundations 3 arranged in the drilling rig track beam 2, and the concrete pile foundations 3 extend into the lower part of the ground and are fixed; It also includes a prefabricated template 9 located between two crane track beams 6, which is arranged on a ground casting plate 12 and sleeved on a wellhead 10; a fixed block is provided at the lower end of the crane track beam 6 on one side close to the wellhead 10; wherein a drainage channel 13 is provided on the ground casting plate 12 between adjacent wellheads 10.

[0029] It also includes a plurality of drainage grooves 14 arranged on the prefabricated template 9, and the drainage grooves 14 are connected to the drainage channel 13; the prefabricated template 9 is composed of a plurality of unit prefabricated templates, and there are joints 15 between adjacent unit prefabricated templates, and the number of unit prefabricated templates is the same as the number of wellheads 10; the crane track beam and the prefabricated template both adopt a modular structure.

[0030] In this embodiment, the crane track beam is composed of multiple unit track beams, and the prefabricated formwork is composed of multiple unit prefabricated formworks. A modular structure is adopted. The number of wellheads is the same as the number of unit prefabricated formworks. The prefabricated formwork is composed of a single prefabricated formwork unit surrounding each well. There are joints between adjacent prefabricated formwork units. In addition, the crane track beam and the prefabricated formwork adopt a modular structure and are prefabricated at the same time as the concrete pouring of the drilling rig track beam, thereby shortening the construction time of the wellhead slot. After drilling is completed, the crane track beam and the prefabricated formwork can be reused, saving construction costs.

[0031] Example 2 On the basis of Example 1, further, the cross-section of the fixing block 8 is a right triangle, and a plurality of fixing anchors 7 are respectively provided on the side close to the crane track beam 6 and the ground casting plate 12, and the crane track beam 6 is fixedly connected to the ground casting plate 12 by the fixing anchors 7.

[0032] The cross section of the fixing block 8 in this embodiment is a right triangle, and its inclined surface is located on the same inclined surface as the inclined surface of the crane track beam 6. A plurality of fixing anchors 7 are respectively provided on the side of the fixing block 8 close to the crane track beam 6 and the ground casting plate 12. The crane track beam 6 is fixedly connected to the ground casting plate 12 by the fixing anchors 7, ensuring that the crane track beam 6 can be quickly installed and disassembled.

[0033] Example 3 On the basis of Example 2, further, the wellhead 10 is provided with a wellhead fixing ring 11 on the outer side above the ground casting plate 12, and a water stop is filled between the wellhead fixing ring 11 and the prefabricated template 9.

[0034] In this embodiment, the wellhead 10 is provided with a wellhead fixing ring 11 on the outer side above the ground casting plate 12 to protect the wellhead when the prefabricated formwork 9 is hoisted. A waterstop is filled between the wellhead fixing ring 11 and the prefabricated formwork 9 to ensure sealing.

[0035] Example 4 On the basis of Example 3, further, the track beam filling joint 4 is filled with micro-expansive concrete.

[0036] In this embodiment, the track beam caulking 4 is filled with micro-expansive concrete to ensure a tight connection between the crane track beam 6 and the drilling rig track beam 2 .

[0037] Example 5 On the basis of Example 4, further, the crane rail 5 is a trapezoidal groove structure, and a steel plate is laid on the bottom of the trapezoidal groove structure.

[0038] In this embodiment, the crane track 5 is a trapezoidal groove structure, and a steel plate is laid on the bottom of the trapezoidal groove structure to ensure that the crane can move smoothly in the crane track 5 during construction.

[0039] Example 6 On the basis of Example 5, further, the drilling rig movable track 1 is fixedly connected to the top of the concrete pile foundation 3 by embedded bolts.

[0040] In this embodiment, the drilling rig movable track 1 is fixedly connected to the top of the concrete pile foundation 3 by embedded bolts, which ensures the structural stability of the drilling rig movable track and meets the movement requirements of the drilling rig.

[0041] Example 7 On the basis of Example 6, further, the center distance D between adjacent wellheads 10 is 2m, and the number of rows of linearly arranged wellheads 10 provided in the middle position of the ground casting plate 12 is 6. Under the condition of ensuring drilling safety, this distance condition between wells can make full use of the well slot space.

[0042] Example 8 The construction method of constructing the wellhead slot structure as described in Example 7 is as follows: S1: Level the site, hammer the conduit serving as the wellhead 10 into the designed well slot area, and construct a concrete pile foundation 3 at the location of the drilling rig track beam 2; S2: pouring concrete on the ground surface of the wellhead 10 and the concrete pile foundation 3 area, weaving a steel mesh at the concrete pile foundation 3, and pouring the drilling rig track beam 2; S3: hoisting the prefabricated crane track beams 6 on the side of the ground casting plate 12 close to the drilling rig track beam 2 and fixing them with the fixing blocks 8, and hoisting and laying the prefabricated template 9 on the outside of the wellhead 10; S4: Fill the track beam caulking 4 where the crane track beam 6 and the drilling rig track beam 2 are connected with micro-expansive concrete. The precast formwork 9 is composed of multiple unit precast formworks. The joints 15 of adjacent unit precast formworks 9 are filled with waterstops. The drilling rig mobile track 1 is fixedly connected to the top of the concrete pile foundation 3 by embedded bolts. A steel plate is laid in the crane track 5 in the middle of the top of the crane track beam 6 to complete the overall construction.

Claims

1. A wellhead slot structure of a real drilling test base, comprising a ground casting plate (12) and a plurality of wellheads (10) arranged on the ground casting plate (12), Features: The wellheads are arranged linearly; It also includes two sets of adjacent crane track beams (6) and drilling rig track beams (2), which are symmetrically arranged on both sides of a wellhead (10) arranged in a linear manner, wherein the crane track beam (6) is close to the wellhead (10); a crane track (5) is provided on the upper surface of the crane track beam (6); The drilling rig track beam (2) is provided with a drilling rig moving track (1), and also comprises a plurality of concrete pile foundations (3) arranged in the drilling rig track beam (2), wherein the concrete pile foundations (3) extend into the lower part of the ground and are fixed; It also includes a prefabricated template (9) located between the two crane track beams (6), wherein the prefabricated template (9) is arranged on a ground casting plate (12) and sleeved on a wellhead (10); A fixing device is provided at the lower end of the crane track beam (6) on the side close to the wellhead (10); It also includes a drainage channel (13) arranged on the ground casting plate (12), wherein the drainage channel (13) is located between adjacent wellheads; and it also includes a plurality of drainage grooves (14) arranged on the prefabricated template (9), wherein the drainage grooves (14) are connected to the drainage channel (13); The prefabricated template (9) is composed of a plurality of unit prefabricated templates, adjacent unit prefabricated templates have joint seams (15) between them, and the number of the unit prefabricated templates is the same as the number of wellheads.

2. The wellhead slot structure of the actual drilling test base according to claim 1, Features: The fixing device is composed of a fixing block (8) and a fixing anchor (7); the fixing block (8) is arranged at the bottom of the crane track beam (6) and close to the ground casting plate (12); the crane track beam (6) is fixedly connected to the ground casting plate (12) via the fixing anchor (7).

3. The wellhead slot structure of the actual drilling test base according to claim 1, Features: The wellhead (10) is provided with a wellhead fixing ring (11) on the outer side above the ground casting plate (12), and a water stop is filled between the wellhead fixing ring (11) and the prefabricated template (9).

4. The wellhead slot structure of the actual drilling test base according to claim 1, Features: There is a track beam filler (4) between the crane track beam (6) and the drilling rig track beam (2), and the track beam filler (4) is filled with micro-expansive concrete.

5. The wellhead slot structure of the actual drilling test base according to claim 2, Features: The surface of the crane track beam (6) close to the wellhead (10) is a downwardly inclined surface, and the fixing block (8) is arranged at the bottom of the inclined surface end; The crane track (5) is located in the middle of the crane track beam (6) and is a trapezoidal groove structure, with a steel plate laid on the bottom.

6. The wellhead slot structure of the actual drilling test base according to claim 1, Features: The drilling rig movable track (1) is located at the middle position of the top of the drilling rig track beam (2), and the drilling rig movable track (1) is fixedly connected to the top of the concrete pile foundation (3) by means of embedded bolts.

7. The wellhead slot structure of the actual drilling test base according to claim 5, Features: The cross section of the fixing block (8) is a right triangle, the inclined surface of which is located on the same inclined surface as the inclined surface of the crane track beam (6), and a plurality of fixing anchors (7) are respectively provided on one side thereof close to the crane track beam (6) and the ground casting plate (12).

8. The wellhead slot structure of the actual drilling test base according to claim 7, Features: The center distance between adjacent wellheads (10) is 4>D≥2m, and the number of columns of linearly arranged wellheads (10) provided in the middle of the ground casting plate (12) is M, and 6≥M≥2.

9. A method for constructing a wellhead slot structure of a real drilling test base, comprising constructing the wellhead slot structure as claimed in claim 8, Features: The steps include: S1: Level the site, hammer the conduit serving as the wellhead (10) into the designed well slot area, and construct a concrete pile foundation (3) at the location of the drilling rig track beam (2); S2: pouring a ground pouring plate (12) with concrete on the ground in the area of ​​the wellhead (10) and the concrete pile foundation (3), weaving a steel mesh at the concrete pile foundation (3), and pouring a drilling rig track beam (2); S3: hoisting the prefabricated crane track beams (6) on the side of the ground casting plate (12) close to the drilling rig track beam (2) in sequence and fixing them with fixing blocks (8), and at the same time hoisting and laying the prefabricated template (9) on the outside of the wellhead (10); S4: The track beam caulking (4) where the crane track beam (6) and the drilling rig track beam (2) are connected is filled with micro-expansive concrete, the prefabricated formwork (9) is composed of a plurality of unit prefabricated formworks, the joints (15) of adjacent unit prefabricated formworks (9) are filled with water stop strips, the drilling rig mobile track (1) is fixedly connected to the top of the concrete pile foundation (3) by embedded bolts, and a steel plate is laid in the crane track (5) at the middle position of the top of the crane track beam (6), thereby completing the overall construction.