Fabricated steel bar structure for tunnel concrete lining and mounting method
By adopting prefabricated steel bar structure and positioning clamp system in tunnel concrete lining, the rapid and accurate connection of steel bar segments is achieved, solving the problems of complex, labor intensity and difficult to guarantee the steel bar joints of tunnel lining are complex, and the construction efficiency and Stress safety.
Patent Information
- Application Number
- CN202310497160.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-05-05
- Publication Date
- 2024-11-05
AI Technical Summary
The existing tunnel concrete lining steel bar structures are insufficient in stress safety in weak surrounding rocks or large-span tunnels. Due to limited operating space, the steel bar binding process is complex and the quality is difficult to guarantee, resulting in low construction efficiency and high cost.
Adopt the prefabricated steel bar structure, including circumferential steel bars, longitudinal steel bars and stirrups. The circumferential steel bar positioning tool can achieve rapid and accurate positioning and connection of steel bar segments, and use temporary positioning support and hydraulic system to adjust the position to reduce on-site binding operations. , improve the degree of mechanization.
It improves construction efficiency, reduces costs, ensures stress safety and concrete pouring quality, and reduces on-site labor intensity and assembly errors.
Smart Images

Figure CN118895988A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of tunnel lining, and in particular relates to an assembled steel bar structure for tunnel concrete lining and an installation method. Background Art
[0002] For tunnels or underground caverns with weak surrounding rocks or large spans, secondary lining and stress-bearing steel bars are often designed to ensure the safety of the tunnel under stress. Especially in the frost-resistant or earthquake-resistant sections, the steel bars are often denser to prevent the tunnel from cracking under external forces. However, due to the limited working space in tunnels and underground caverns, the lining steel bars are currently still manually tied, which requires a large number of workers and has high labor intensity. Many steel bars need to be lifted, positioned, and bent on site. The steel bar tying process is complicated, and the quality of the steel bar tying is difficult to guarantee.
[0003] Chinese patents "A Tunnel Concrete Lining Structural Steel Bar" (CN201921190607.5) and "An Assembled Connection Method for Tunnel Concrete Lining Structural Steel Bars" (CN201910681709.5) propose a tunnel concrete lining structural steel bar and connection method, including multiple unit steel bars, each unit is 4 main bars, wavy connecting bars and reinforcing bars are arranged between the main bars, and the units are connected by welded L-shaped angle steels and their bolts, which is very similar to the grid steel frames we commonly use. However, this scheme does not consider the connection between the longitudinal and circumferential main bars. The 4 main bars are all located in the same section, and it does not meet the requirements of the specification for the staggered arrangement of the stress-bearing bar joints. In fact, it changes the structural stress, and the stress between the units only relies on the angle steel and 4 bolts. Compared with the force transmission between the main bars, it is difficult to ensure the safety of the stress. At the same time, for conventional tunnel construction, the invert is often constructed ahead of the arch wall, and it is necessary to provide working space for the drainage system, arch wall reinforcement operation and concrete pouring. It is difficult to achieve full-ring pouring at one time, which is quite different from on-site operations. At the same time, the technical solution does not give the assembly sequence of the arch wall reinforcement units. For staged assembly, due to assembly errors and deflection of the reinforcement segments, an unreasonable assembly sequence will make it difficult to accurately install the final top reinforcement unit. Summary of the invention
[0004] In order to solve the problems of many existing tunnel lining steel bar joints, high labor intensity of manual binding work in the tunnel, complex procedures and difficult quality assurance, the present invention proposes an assembled steel bar structure and installation method for tunnel concrete lining, which can realize rapid installation and positioning of steel bar segments and rapid and accurate positioning of connecting steel bars without affecting and changing the stress mode of the structural steel bars, thereby improving construction efficiency and reducing costs.
[0005] The technical solution of the present invention is: an assembled steel bar structure for tunnel concrete lining, comprising a plurality of steel bar segments arranged along the cross section of the tunnel concrete lining, the steel bar segments comprising a plurality of circumferential steel bars, a plurality of longitudinal steel bars and stirrups, the plurality of circumferential steel bars are arranged in two rows in parallel along the extension direction of the tunnel concrete lining, the stirrups are connected between the two rows of circumferential steel bars, a plurality of longitudinal steel bars are connected between the same row of circumferential steel bars, the longitudinal steel bars are arranged perpendicularly to the circumferential steel bars, the lower ends of the circumferential steel bars of the steel bar segments at the side wall positions on both sides of the cross section of the tunnel concrete lining are connected with reserved circumferential steel bars for the invert, circumferential steel bar positioning fixtures and circumferential steel bar connectors are provided between the circumferential connecting steel bars between adjacent steel bar segments, and the circumferential steel bar connectors are positioned by the circumferential steel bar positioning fixtures.
[0006] The annular steel bar positioning fixture is a rectangular frame structure, including two longitudinal positioning components arranged parallel to each other, the longitudinal positioning components including two first positioning rods arranged parallel to each other, the two ends of the two first positioning rods are respectively connected to fixed rods, and a plurality of adjustable second positioning rods are vertically arranged between two adjacent first positioning rods in the two parallel longitudinal positioning components, and two positioning holes are provided on the second positioning rods, and the diameter of the positioning holes is larger than the outer diameter of the annular steel bar.
[0007] The first positioning rod is provided with a longitudinal positioning slot, and the second positioning rod is provided with a transverse positioning slot. A bolt is provided at the overlapping position of the longitudinal positioning slot of the first positioning rod and the transverse positioning slot of the second positioning rod. The bolt passes through the longitudinal positioning slot and the transverse positioning slot to fix the first positioning rod and the second positioning rod in connection, and the positioning hole is provided in the transverse positioning slot.
[0008] The distance between the two positioning holes on the second positioning rod is the same as the parallel spacing between two rows of parallelly arranged annular steel bars.
[0009] The longitudinal connecting steel bars between adjacent ring steel bar segments are connected by steel bar binding.
[0010] A plurality of temporary positioning supports are arranged on the side of the steel bar segment facing the tunnel, and a hydraulic system with a limiting device is arranged on the temporary positioning support so as to adjust the position of the steel bar segment.
[0011] The annular steel bars in the steel bar segments are respectively connected or welded to the longitudinal steel bars and stirrups by steel bar binding.
[0012] A method for installing a prefabricated steel structure for tunnel concrete lining, installing the prefabricated steel structure for tunnel concrete lining as described above, comprising the following steps: S1: According to the tunnel section, transportation tools and transportation line conditions, and the requirements of the in-tunnel lifting, rotation, and positioning processes, the circumferential and longitudinal lengths of the steel segments required for the tunnel lining are determined, and they are pre-processed in the factory and stored in a dedicated finished product storage area; S2: Tie up the inverted arch reinforcement in the tunnel, position the reserved annular reinforcement of the inverted arch according to the design requirements, and finally pour the inverted arch concrete; S3: The prefabricated steel bar segments are transported to the tunnel, and the steel bar segments are hoisted to the designated position of the tunnel using special hoisting and assembly equipment. The steel bar segments are positioned and fixed, and assembled and cycled. The installation of the steel bar segments is as follows: S31: First install the steel bar segments of the vault, use the total station to accurately measure and locate, and use temporary positioning supports to fix them; S32: Then install the circumferential reinforcement positioning fixtures at both ends of the reinforcement segment of the arch, and then install the reinforcement segments at the arch shoulders on both sides in sequence. By inserting the circumferential reinforcement into the reinforcement positioning holes of the circumferential reinforcement positioning fixtures, the circumferential connecting reinforcements of adjacent lining reinforcement segments can be accurately positioned. Only fine-tuning is required on site to achieve accurate connection between the reinforcements. S33: Finally, the steel bar segments at the side wall positions on both sides are connected and installed with the reserved annular steel bars of the inverted arch. According to the position of the annular steel bar positioning fixture fixed on the reserved annular steel bars of the inverted arch, forced centering is performed to ensure that the annular steel bars of the steel bar segments can be inserted into the annular steel bar positioning fixture fixed on the reserved annular steel bars of the inverted arch. The steel bar segments are fixed with temporary positioning supports, thereby achieving accurate connection between the steel bar segments at the side wall positions and the reserved annular steel bars of the inverted arch. S4: After the steel segments of the tunnel concrete lining cross section are assembled, the annular steel positioning fixture is removed, and then the stirrups at the connection of the steel segments are tied. After all the steel positioning and tying are completed, the temporary positioning support is removed, and the steel segments of the next cycle tunnel are assembled. The steel segments of the two adjacent ring tunnels are tied and connected with longitudinal connecting steel bars.
[0013] The technical effects of the present invention are: 1. The present invention processes the steel bar segments in a unified and centralized manner in a processing plant, and then transports them to the tunnel for rotation, lifting, positioning and assembly. Compared with the on-site binding of the second lining steel bars in the tunnel, the mechanization degree of segment prefabrication and assembly is greatly improved, which effectively reduces the number of construction workers and working time in the tunnel, improves the standardization degree of segment prefabrication and assembly, improves construction efficiency, and reduces construction costs; 2. The steel bars of the steel bar segments of the present invention are connected by existing commonly used connecting parts, without adding additional operating procedures, ensuring the force safety of the lining structure and the vibration quality of the concrete pouring process; 3. The present invention uses an annular steel bar positioning fixture to accurately insert two adjacent annular steel bars into the transverse positioning slots on the annular steel bar positioning fixture, and uses annular steel bar connectors to connect them, thereby achieving precise positioning and connection of the annular steel bars of adjacent segments.
[0014] The following is a further description with reference to the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 The present invention is a schematic structural diagram of an assembled steel bar structure for tunnel concrete lining according to an embodiment of the present invention.
[0016] Figure 2 It is a top cross-sectional view of a steel bar segment according to an embodiment of the present invention.
[0017] Figure 3 It is a front cross-sectional view of a steel bar segment according to an embodiment of the present invention.
[0018] Figure 4 This is a top sectional view of the annular steel bar positioning fixture according to an embodiment of the present invention.
[0019] Figure 5 For the embodiment of the present invention Figure 4 A partial enlarged view of the AA point in the middle.
[0020] Figure 6 It is a side sectional view of the annular steel bar positioning fixture according to an embodiment of the present invention.
[0021] Figure numerals: 1-rebar segment, 2-circumferential reinforcement, 3-longitudinal reinforcement, 4-circumferential reinforcement connector, 5-reserved circumferential reinforcement for the invert arch, 6-circumferential reinforcement positioning fixture, 7-hoops, 8-temporary positioning support, 611-longitudinal positioning slot, 612-transverse positioning slot, 62-positioning hole, 63-bolt, 64-fixing rod. Implementation
[0022] Example 1 Figure 1~Figure 3As shown, an assembled steel bar structure for tunnel concrete lining comprises a plurality of steel bar segments 1 arranged along the cross section of the tunnel concrete lining, the steel bar segments 1 comprising a plurality of circumferential steel bars 2, a plurality of longitudinal steel bars 3 and stirrups 7, the plurality of circumferential steel bars 2 are arranged in parallel in two rows along the extension direction of the tunnel concrete lining, the stirrups 7 are connected between the two rows of circumferential steel bars 2, a plurality of longitudinal steel bars 3 are connected between the circumferential steel bars 2 in the same row, the longitudinal steel bars 3 are arranged perpendicular to the circumferential steel bars 2, the lower ends of the circumferential steel bars 2 of the steel bar segments 1 at the side wall positions on both sides of the cross section of the tunnel concrete lining are connected with reserved circumferential steel bars 5 for the invert, a circumferential steel bar positioning fixture 6 and a circumferential steel bar connector 4 are provided between the circumferential connecting steel bars 2 between adjacent steel bar segments 1, and the circumferential steel bar connector 4 is positioned by the circumferential steel bar positioning fixture 6.
[0023] During actual use, the size of the steel bar segment 1 described in the present invention is determined according to the tunnel section size, steel bar transportation conditions and the in-tunnel assembly process, and a refined model of the steel bar segment 1 is established through BIM technology, which is then processed uniformly in a processing plant and then transported to the tunnel for rotation, lifting, positioning and assembly. Compared with the on-site binding of the second lining steel bars in the tunnel, the mechanization degree of segment prefabrication and assembly is greatly improved, which effectively reduces the number of construction workers and working time in the tunnel, improves the standardization degree of segment prefabrication and assembly, improves construction efficiency and reduces construction costs; the present invention uses the annular steel bar positioning fixture 6 to accurately position two adjacent annular steel bars, and uses the annular steel bar connector 4 to connect them, thereby realizing the precise positioning and connection of the adjacent segment annular steel bars 2.
[0024] Embodiment 2 Preferably, on the basis of Embodiment 1, in this embodiment, as Figure 4~Figure 6 As shown, the annular steel bar positioning fixture 6 is a rectangular frame structure, including two longitudinal positioning components arranged parallel to each other, the longitudinal positioning components include two first positioning rods arranged parallel to each other, and the two ends of the two first positioning rods are respectively connected to fixed rods 64. A plurality of adjustable second positioning rods are vertically arranged between two adjacent first positioning rods in the two parallel longitudinal positioning components, and two positioning holes 62 are provided on the second positioning rods, and the diameter of the positioning hole 62 is larger than the outer diameter of the annular steel bar 2.
[0025] During actual use, the annular steel bar positioning fixture 6 of the present invention is a rectangular frame structure, including two longitudinal positioning components arranged parallel to each other, the longitudinal positioning components including two first positioning rods arranged parallel to each other, and the two ends of the two first positioning rods are respectively connected to fixing rods 64, and a plurality of adjustable second positioning rods are vertically arranged between two adjacent first positioning rods in the two longitudinal positioning components arranged parallel to each other, and two positioning holes 62 are provided on the second positioning rods. When in use, by inserting the annular steel bars 2 into the steel bar positioning holes 62 of the annular steel bar positioning fixture 6, the annular connecting steel bars 2 of adjacent lining steel bar segments 1 can be accurately positioned and connected. The diameter of the positioning holes 62 is larger than the outer diameter of the annular steel bars 2, and the annular steel bars 2 can be quickly inserted.
[0026] Embodiment 3 Preferably, on the basis of Embodiment 1 or Embodiment 2, in this embodiment, a longitudinal positioning slot 611 is provided on the first positioning rod, a transverse positioning slot 612 is provided on the second positioning rod, a bolt 63 is provided at the overlapping position of the longitudinal positioning slot 611 of the first positioning rod and the transverse positioning slot 612 of the second positioning rod, the bolt 63 passes through the longitudinal positioning slot 611 and the transverse positioning slot 612 to fix the first positioning rod and the second positioning rod together, and the positioning hole 62 is arranged in the transverse positioning slot 612.
[0027] During actual use, the first positioning rod of the present invention is provided with a longitudinal positioning slot 611, and the second positioning rod is provided with a transverse positioning slot 612. A bolt 63 is provided at the overlapping position of the longitudinal positioning slot 611 of the first positioning rod and the transverse positioning slot 612 of the second positioning rod. The bolt 63 passes through the longitudinal positioning slot 611 and the transverse positioning slot 612 to fix the first positioning rod and the second positioning rod in connection. By adjusting the overlapping position of the longitudinal positioning slot 611 and the transverse positioning slot 612, accurate positioning and connection of the annular steel bar 2 can be achieved.
[0028] Embodiment 4 Preferably, based on Embodiment 1 or Embodiment 3, in this embodiment, the distance between the two positioning holes 62 on the second positioning rod is the same as the parallel spacing between two rows of parallelly arranged annular steel bars 2 .
[0029] During actual use, the distance between the two positioning holes 62 on the second positioning rod of the present invention is the same as the parallel spacing of the two rows of parallel annular steel bars 2, which is convenient for accurately inserting two adjacent annular steel bars 2 into the transverse positioning slots on the annular steel bar positioning fixture, and connecting them with the annular steel bar connector 4, thereby realizing the precise positioning connection of adjacent segment annular steel bars.
[0030] Embodiment 5 Preferably, on the basis of Embodiment 1 or Embodiment 4, in this embodiment, the longitudinal connecting steel bars 3 between adjacent ring steel bar segments 1 are connected by steel bar binding to form a lining steel bar as a whole.
[0031] During actual use, the longitudinal connecting steel bars 3 between adjacent ring steel bar segments 1 of the present invention are connected by steel bar binding to form a lining steel bar as a whole. The existing commonly used connecting piece such as steel bar binding is used for connection without adding additional operating procedures, thereby ensuring the stress safety of the lining structure and the vibration quality of the concrete pouring process.
[0032] Embodiment 6 Preferably, based on Embodiment 1 or Embodiment 5, in this embodiment, a plurality of temporary positioning supports 8 are provided on the side of the steel segment 1 facing the tunnel, and a hydraulic system with a limiting device is provided on the temporary positioning supports 8 to adjust the position of the steel segment 1.
[0033] During actual use, the steel bar segment 1 of the present invention is provided with a plurality of temporary positioning supports 8 on the side facing the tunnel, so as to facilitate accurate positioning and fixing of the steel bar segment 1 .
[0034] Embodiment 7 Preferably, on the basis of Embodiment 1 or Embodiment 6, in this embodiment, the annular steel bars 2 in the steel bar segment 1 are respectively connected or welded to the longitudinal steel bars 3 and stirrups 7 by steel bar binding.
[0035] During actual use, the annular steel bars 2 in the steel bar segment 1 of the present invention are connected or welded to the longitudinal steel bars 3 and stirrups 7 respectively by steel bar binding or welding. The existing commonly used connecting parts such as steel bar binding or welding are used without adding additional operating procedures, thereby ensuring the stress safety of the lining structure and the vibration quality of the concrete pouring process.
[0036] Embodiment 8 A method for installing a prefabricated steel bar structure for tunnel concrete lining, installing the prefabricated steel bar structure for tunnel concrete lining as described above, comprises the following steps: S1: According to the tunnel section, transportation tools and transportation line conditions, and the requirements of the in-tunnel lifting, rotation, and positioning process, the circumferential and longitudinal lengths of the steel bar segments 1 required for the tunnel lining are determined, and they are pre-processed in the factory and stored in a dedicated finished product storage area; S2: tying the inverted arch reinforcement in the tunnel, positioning the reserved annular reinforcement 5 of the inverted arch according to the design requirements, and finally pouring the inverted arch concrete; S3: The prefabricated steel segment 1 is transported to the tunnel, and the steel segment 1 is hoisted to the designated position of the tunnel by special hoisting and assembly equipment. The steel segment 1 is positioned and fixed, and the assembly and circulation operation are performed. The installation of the steel segment 1 is as follows: S31: first install the steel bar segment 1 of the arch, use a total station to perform accurate measurement and positioning, and use a temporary positioning support 8 to fix it; S32: Then, the circumferential steel bar positioning fixtures 6 are installed at both ends of the steel bar segment 1 of the arch, and then the steel bar segments 1 at the arch shoulders on both sides are installed in sequence. By inserting the circumferential steel bars 2 into the steel bar positioning holes 62 of the circumferential steel bar positioning fixtures 6, the circumferential connecting steel bars 2 of the adjacent lining steel bar segments 1 can be accurately positioned. Only fine-tuning is required on site to achieve accurate connection between the steel bars. S33: Finally, the steel bar segments 1 at the side wall positions on both sides are connected and installed with the reserved annular steel bars 5 for the inverted arch. According to the position of the annular steel bar positioning fixture 6 fixed on the reserved annular steel bar 5 for the inverted arch, forced alignment is performed to ensure that the annular steel bars 2 of the steel bar segments 1 can be inserted into the annular steel bar positioning fixture 6 fixed on the reserved annular steel bar 5 for the inverted arch. The steel bar segments 1 are fixed with temporary positioning supports 8, thereby achieving accurate connection between the steel bar segments 1 at the side wall positions and the reserved annular steel bars 5 for the inverted arch. S4: After the steel bar segments 1 of the tunnel concrete lining cross section are assembled, the annular steel bar positioning fixture 6 is removed, and then the stirrups 7 at the connection of the steel bar segments 1 are tied. After all the steel bars are positioned and tied, the temporary positioning support 8 is released, and the steel bar segments 1 of the next cycle tunnel are assembled. The steel bar segments 1 of the two adjacent ring tunnels are tied and connected using longitudinal connecting steel bars 3.
[0037] The present invention first installs the lining steel bar segment 1 of the arch, adopts the temporary positioning support 8 to accurately fix it, then installs the circumferential steel bar positioning fixtures 6 at both ends, and then sequentially installs the lining steel bar segments 1 of the spandrels on both sides, through the circumferential steel bar positioning fixtures 6 at both ends of the lining steel bar segment, the circumferential connecting steel bars 2 of the adjacent lining steel bar segments 1 can be accurately positioned and connected, and the temporary positioning support 8 is also adopted for accurate fixing, and finally the lining steel bar segments 1 of the side walls on both sides are positioned and connected with the inverted arch steel bar, and the reserved circumferential steel bar positioning fixture of the inverted arch is connected with the reserved circumferential steel bar positioning fixture 6 of the steel bar segment, so as to achieve the accurate positioning connection of the reserved circumferential steel bar 5 of the inverted arch and the circumferential steel bar 2 of the steel bar segment. Compared with the prior art, the prior art has high labor intensity, slow progress and difficult quality control in the on-site binding of the second lining steel bar in the tunnel hole, and the implementation of the present technology greatly improves the standardization degree of segment prefabrication and assembly, effectively reduces the construction workers and operation time in the tunnel, and the steel bars can be connected by the currently commonly used connectors, which can ensure the force safety and the quality of the concrete pouring process vibration.
[0038] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that can be easily conceived by any technician familiar with the technical field within the technical scope disclosed by the present invention should be covered within the protection scope of the present invention.
Claims
1. An assembled steel bar structure for tunnel concrete lining, characterized in that: The invention comprises a plurality of steel bar segments (1) arranged along a cross section of a tunnel concrete lining, wherein the steel bar segments (1) comprise a plurality of circumferential steel bars (2), a plurality of longitudinal steel bars (3) and stirrups (7), wherein the plurality of circumferential steel bars (2) are arranged in parallel in two rows along an extension direction of the tunnel concrete lining, wherein the stirrups (7) are connected between the two rows of circumferential steel bars (2), wherein a plurality of longitudinal steel bars (3) are connected between the circumferential steel bars (2) in the same row, wherein the longitudinal steel bars (3) are arranged perpendicular to the circumferential steel bars (2), wherein the lower ends of the circumferential steel bars (2) of the steel bar segments (1) at the side wall positions on both sides of the cross section of the tunnel concrete lining are connected to reserved circumferential steel bars (5) for an invert, and between the circumferential connecting steel bars (2) between adjacent steel bar segments (1) are provided circumferential steel bar positioning fixtures (6) and circumferential steel bar connectors (4), wherein the circumferential steel bar connectors (4) are positioned by the circumferential steel bar positioning fixtures (6).
2. The assembled steel bar structure for tunnel concrete lining according to claim 1, characterized in that: The annular steel bar positioning fixture (6) is a rectangular frame structure, comprising two longitudinal positioning components arranged in parallel with each other, the longitudinal positioning components comprising two first positioning rods arranged in parallel with each other, the two ends of the two first positioning rods are respectively connected to fixing rods (64), and a plurality of adjustable second positioning rods are vertically arranged between two adjacent first positioning rods in the two longitudinal positioning components arranged in parallel with each other, and two positioning holes (62) are provided on the second positioning rods, and the diameter of the positioning hole (62) is larger than the outer diameter of the annular steel bar (2).
3. The assembled steel bar structure for tunnel concrete lining according to claim 2, characterized in that: The first positioning rod is provided with a longitudinal positioning slot (611), and the second positioning rod is provided with a transverse positioning slot (612). A bolt (63) is provided at a position where the longitudinal positioning slot (611) of the first positioning rod overlaps with the transverse positioning slot (612) of the second positioning rod. The bolt (63) passes through the longitudinal positioning slot (611) and the transverse positioning slot (612) to fix the first positioning rod and the second positioning rod together. The positioning hole (62) is provided in the transverse positioning slot (612).
4. The assembled steel bar structure for tunnel concrete lining according to claim 2, characterized in that: The distance between the two positioning holes (62) on the second positioning rod is the same as the parallel spacing between two rows of parallelly arranged annular steel bars (2).
5. The assembled steel bar structure for tunnel concrete lining according to claim 1, characterized in that: The longitudinal connecting steel bars (3) between adjacent ring steel bar segments (1) are connected by steel bar binding to form a lining steel bar as a whole.
6. The assembled steel bar structure for tunnel concrete lining according to claim 1, characterized in that: A plurality of temporary positioning supports (8) are provided on the side of the steel bar segment (1) facing the tunnel, and a hydraulic system with a limiting device is provided on the temporary positioning support (8), so as to adjust the position of the steel bar segment (1).
7. The assembled steel bar structure for tunnel concrete lining according to claim 1, characterized in that: The annular steel bars (2) in the steel bar segment (1) are respectively connected or welded to the longitudinal steel bars (3) and stirrups (7) by steel bar binding.
8. A method for installing a prefabricated steel structure for tunnel concrete lining, comprising installing a prefabricated steel structure for tunnel concrete lining as claimed in claims 1 to 7, characterized in that: The following steps are involved: S1: According to the tunnel section, transportation tools and transportation line conditions, and the requirements for in-tunnel lifting, rotation, and positioning processes, the circumferential and longitudinal lengths of the steel bar segments (1) required for tunnel lining are determined, and they are pre-processed in the factory and stored in a dedicated finished product storage area; S2: tying the inverted arch reinforcement in the tunnel, positioning the reserved annular reinforcement (5) of the inverted arch according to the design requirements, and finally pouring the inverted arch concrete; S3: transport the prefabricated steel bar segment (1) into the tunnel, use special lifting and assembly equipment to lift the steel bar segment (1) to the designated position of the tunnel, position and fix the steel bar segment (1), and assemble and cycle the steel bar segment (1). The installation of the steel bar segment (1) is specifically as follows: S31: first install the steel bar segment (1) of the arch, use a total station to perform accurate measurement and positioning, and use temporary positioning supports (8) to fix it; S32: Then, the circumferential steel bar positioning fixtures (6) are installed at both ends of the steel bar segment (1) of the arch crown, and then the steel bar segments (1) at the arch spandrels on both sides are installed in sequence. By inserting the circumferential steel bars (2) into the steel bar positioning holes (62) of the circumferential steel bar positioning fixtures (6), the circumferential connecting steel bars (2) of the adjacent lining steel bar segments (1) can be accurately positioned. Only fine adjustment is required on site to achieve accurate connection between the steel bars. S33: Finally, the steel bar segments (1) at the side wall positions on both sides are connected and installed with the reserved annular steel bars (5) of the inverted arch. According to the position of the annular steel bar positioning fixture (6) fixed on the reserved annular steel bar (5) of the inverted arch, forced alignment is performed to ensure that the annular steel bars (2) of the steel bar segments (1) can be inserted into the annular steel bar positioning fixture (6) fixed on the reserved annular steel bar (5) of the inverted arch. The steel bar segments (1) are fixed with temporary positioning supports (8), thereby achieving accurate connection between the steel bar segments (1) at the side wall positions and the reserved annular steel bars (5) of the inverted arch. S4: After the steel bar segments (1) of the tunnel concrete lining cross section are assembled, the annular steel bar positioning fixture (6) is removed, and then the stirrups (7) at the connection of the steel bar segments (1) are tied. After all the steel bars are positioned and tied, the temporary positioning support (8) is removed, and the steel bar segments (1) of the next loop tunnel are assembled. The steel bar segments (1) of two adjacent loop tunnels are tied and connected using longitudinal connecting steel bars (3).