Drilling and splitting synchronous heading machine and heading process thereof
Through the design of the drilling and splitting synchronous boring machine, the hard rock layer is drilled and split by using the synchronous drilling and splitting device and memory alloy technology, which solves the problems of low efficiency and safety hazards of hard rock excavation in the existing technology, and achieves the problem of correctness and safety risks. Rapid and high-quality excavation of hard rock formations.
Patent Information
- Application Number
- CN202411005141.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-25
- Publication Date
- 2024-11-08
AI Technical Summary
The existing integrated tooth cutting machine has difficulty effectively cutting hard rock formations with hardness coefficients greater than f8, resulting in low cutting efficiency, high wear rate of tooth cutting and increased failure rate of the boring machine. The existing rock-breaking method has safety hazards. And continuous excavation cannot be achieved.
A drill-splitting synchronous boring machine is designed, using cantilever boring machine, drill-splitting control arm and synchronous boring device, and hard rock is achieved through the track frame, sprocket transmission mechanism, impact rock drilling mechanism and drill-assisted splitting mechanism. The drilling holes are synchronously split, weakening the strength of the rock mass, and combining memory alloy and heating sleeve to perform segmented splitting of the drilling wall to achieve continuous excavation.
The excavation efficiency and cutting ability are improved, the cutting wear is reduced, and the rapid and high-quality excavation of hard rock layers is achieved. The drilling efficiency and quality are improved through synchronous processes.
Smart Images

Figure CN118911696A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of tunnel boring machine equipment, and in particular to a synchronous drilling and splitting tunnel boring machine and a tunnel boring process thereof. Background Art
[0002] As an important pillar of my country's economic construction and industrial production, coal plays a vital role in the energy structure. The construction of coal mine shafts and tunnels is one of the core links of coal mining. However, there is a serious imbalance between mining and excavation in coal mining, which restricts the improvement of mine production efficiency and safety mining level in my country. Among them, one of the main reasons is the difficulty of rock tunnel excavation. The existing pick-type integrated tunneling machines are difficult to effectively and economically cut hard rock formations with a hardness coefficient greater than f8 (i.e., compressive strength greater than 80MPa), resulting in low cutting efficiency, excessive pick wear rate, and increased tunneling machine failure rate. In order to complete the excavation, it is often necessary to withdraw the tunneling machine and use drilling and blasting for rock breaking and excavation. However, this practice has potential safety hazards and cannot achieve continuous excavation. At the current stage of development, the country particularly emphasizes the construction of intelligent coal mine systems and focuses on promoting the development of intelligent and rapid excavation technology. Therefore, the study of automated tunneling machinery that efficiently crushes hard rocks is of great significance for realizing less-managed and unmanned excavation and building an intelligent energy mining system. Summary of the invention
[0003] The purpose of the present invention is to overcome the problems in the background technology and provide a drilling and splitting synchronous tunneling machine and its tunneling process. The tunneling machine has a compact structure and can perform synchronous drilling and splitting on hard rock formations with a rock formation hardness f>10, thereby weakening the strength of the rock mass to be cut, improving the tunneling efficiency, and improving the tunneling capacity while keeping the cutting power of the tunneling machine unchanged.
[0004] In order to achieve the above-mentioned invention object, the technical solution adopted by the present invention is specifically: a drilling and splitting synchronous roadheader, comprising a cantilever roadheader, a drilling and splitting control arm, and a synchronous drilling and splitting device, wherein the drilling and splitting control arm is arranged on the cantilever roadheader, and the synchronous drilling and splitting device is arranged on the drilling and splitting control arm;
[0005] The drilling and splitting control arm can adjust the rock drilling angle of the synchronous drilling and splitting device, and drive the synchronous drilling and splitting device to move forward and backward;
[0006] The synchronous drilling and splitting device includes a track frame, a sprocket transmission mechanism, an impact rock drilling mechanism, a splitting while drilling mechanism and a connecting clamping device. The track frame is installed on the drilling and splitting control arm through the connecting clamping device. The sprocket transmission mechanism, the impact rock drilling mechanism and the splitting while drilling mechanism are all arranged on the track frame. The sprocket transmission mechanism is used to provide driving force, so that the impact rock drilling mechanism and the splitting while drilling mechanism can move forward and backward along the track frame.
[0007] Furthermore, an I-shaped structure with a concave space is provided on the track frame, and the upper and lower outer edge track structures of the track frame are used to install an impact rock drilling mechanism and a splitting-while-drilling mechanism.
[0008] Furthermore, the sprocket transmission mechanism includes a sprocket drive motor, a driving sprocket, a chain and a driven sprocket arranged on a track frame, the chain is cooperatively arranged between the driving sprocket and the driven sprocket, the chain is fixedly connected to the impact rock drilling mechanism and the while-drilling splitting mechanism respectively, and can drive the impact rock drilling mechanism and the while-drilling splitting mechanism to move synchronously.
[0009] Furthermore, the impact rock drilling mechanism includes a slider-type connecting seat, a rock drilling impactor, a drill rod and an impact drill bit. The rock drilling impactor is installed on a track frame through a slider-type connecting seat, and the slider-type connecting seat is fixedly connected to a chain. One end of the drill rod is connected to the rock drilling impactor, and the other end is connected to the impact drill bit after rotating through the drilling splitting mechanism. When performing impact drilling operations, the impact drill bit can be pushed forward along the track frame through the sprocket transmission mechanism.
[0010] Further, the splitting mechanism while drilling includes a second slider-type connecting seat, a hydraulic slewing mechanism, a connecting flange, a splitting frame, a displacement loading mechanism, a heating sleeve, a memory alloy, a supporting slag discharging mechanism and a slag collecting mechanism. The hydraulic slewing mechanism is installed on the track frame through the second slider-type connecting seat and is fixedly connected to the chain through the second slider-type connecting seat. The splitting frame, the heating sleeve, the memory alloy, the displacement loading mechanism and the supporting slag discharging mechanism together constitute the main body of the splitting mechanism while drilling. The chain in the sprocket transmission mechanism can drive the splitting mechanism while drilling to move forward along the track frame when moving;
[0011] The splitting frame is multi-sectioned, and a displacement loading mechanism and a plurality of heating sleeves are arranged on each section of the splitting frame. The heating sleeve is arranged perpendicular to the chain, and the memory alloy is arranged in the heating sleeve. The length of the memory alloy increases after being heated, and after extending out of the heating sleeve, it pushes the displacement loading mechanism to move outward, so that the splitting mechanism while drilling expands and its diameter becomes larger. The multiple heating sleeves, memory alloys and displacement loading mechanisms arranged in an array in the axial direction of the splitting frame can play a role in segmented splitting of the borehole wall.
[0012] Furthermore, a through hole matching with the drill rod is provided in the splitting frame, and both ends of the splitting frame are circular sections with grooves for connecting with the connecting flange and the slag collecting mechanism;
[0013] The heating sleeve is cylindrical, composed of a metal sleeve, an adhesive and a nickel-chromium alloy wire, and is installed in the corresponding slot of the splitting frame. The memory alloy is a hollow cylinder with a spiral groove, which is installed in the heating sleeve. The displacement loading mechanism is installed on the moving track of the splitting frame, and its inner side is connected to the memory alloy.
[0014] Furthermore, the supporting slag discharge mechanism is an arc-shaped plate with a middle groove, which is arranged on the other side of the splitting frame and opposite to the installation plane of the heating sleeve, the memory alloy and the displacement loading mechanism, and plays the role of supporting the splitting and removing the rock debris;
[0015] The connecting flange is a columnar structure, and has a through hole in the middle that matches the size of the drill pipe. The connecting flange is used to connect and fix the hydraulic rotary mechanism and the splitting frame;
[0016] The slag collecting mechanism contains a through hole matched with the drill rod size and a slag outlet connected to the supporting slag discharging mechanism. One end of the slag collecting mechanism is connected to the end of the splitting frame, and the other end is close to the impact drill bit.
[0017] The present invention provides a tunneling process, comprising the following steps:
[0018] S1: According to the side and roof positions of the cross-section contour, the cross-section is divided into a middle groove area, a left cutting area, a right cutting area and a roof cutting area. The height of the middle groove area is equal to the height of the side, and the width is the width of the excavable space by the pitching and swinging of the roadheader drum. Dense drilling is performed in the groove area. The projection area of a single cutting drum is used as a reference. Within the projection area of a single cutting drum, the number and spacing of holes drilled must ensure that the drilling area reaches at least 3 / 5 of the projection area of the cutting drum. The drilling depth must reach the full insertion depth of the synchronous drilling and splitting device. After the drilling is completed, the middle groove area is cut by the roadheader, and the cutting depth must reach the drilling depth.
[0019] S2: Drilling and splitting work is performed in the left cutting area and the right cutting area to create a fracture network;
[0020] S3: Cutting work is performed in the left cutting area and the right cutting area, and the roadheader drum cuts the split area in a Z-shaped trajectory;
[0021] S4: Drilling and splitting work in the roof area;
[0022] S5: Cutting work is carried out in the roof area, and the drum of the roadheader cuts the split area in an N-shaped trajectory;
[0023] S6: Perform edge sweeping cutting along the contour of the cutting area to ensure the contour quality of the cutting area.
[0024] Furthermore, the method for performing the drilling and splitting work in the left cutting area and the right cutting area is as follows:
[0025] The drill and splitting holes are arranged in multiple rows vertically, each row of drill and splitting holes is parallel to the free surface formed in the middle groove area, and the splitting direction is perpendicular to it. The drill and splitting holes are split row by row from the inside to the outside, and the splitting order of each row of splitting holes is: the middle hole is split first, the drill and splitting holes are split from the middle to the top, and then the drill and splitting holes are split from the middle to the bottom; the distance between the splitting holes and the spacing between the splitting holes in each row are determined according to the power of the drilling and splitting device and the cross-section rock conditions, and the cross-section cracks after splitting must be larger than 5mm, and the cracks between the holes and the free surface cracks must be clearly visible.
[0026] Furthermore, the method for drilling and splitting the top plate area is as follows: after the cutting of the left cutting area and the right cutting area has been completed and connected with the middle groove area to form a cut space, the top plane of the cut space is used as a free surface for drilling and splitting, and the drilling and splitting holes are arranged in multiple columns horizontally, and the drilling and splitting holes are split one by one from bottom to top; the splitting order of each column of splitting holes is: the middle hole is split first, and the drilling and splitting holes are split one by one from the middle to the outside; the splitting hole arrangement requirements and the crack surface formation requirements are consistent with the left and right cutting area drilling and splitting requirements.
[0027] Compared with the prior art, the present invention has the following beneficial effects:
[0028] 1. By drilling and splitting the cross-section rock mass, the integrity of the rock is weakened, creating a free surface that is beneficial to drum cutting. During drum cutting, it is only necessary to overcome the rock fracture resistance between the root of the crack surface and the free surface to complete the overall cutting. The rock failure mode of a single pick cutting will be converted from grinding and crushing to fracture failure under the action of impact force, which greatly improves the strength of the rock that can be cut under fixed cutting power, reduces pick wear, and improves the cutting capacity of the tunnel boring machine.
[0029] 2. Compared with other drilling and splitting assisted tunneling machines, the present invention realizes the continuous drilling and splitting processes, and does not need to be re-drilled through other rotating devices, which greatly improves the drilling and splitting efficiency and quality. In addition, the drilling and splitting structure of the present invention is compact and has a small curb weight; it realizes the synchronous coordination of drilling and splitting and cutting work, and can adjust the hole position in time according to the formation of drilling and splitting cracks, reducing the number of invalid drilling; according to the process proposed by the present invention, combined with the equipment, the rock mass split by drilling and splitting can be completely cut at one time in a single excavation footage, thereby increasing the single-cycle footage and realizing fast and high-quality excavation of hard rock formations (hardness coefficient ≥ f10). BRIEF DESCRIPTION OF THE DRAWINGS
[0030] The accompanying drawings are used to provide further understanding of the present invention and constitute a part of the specification. They are used to explain the present invention together with the embodiments of the present invention and do not constitute a limitation of the present invention.
[0031] Figure 1This is the overall structural diagram of the drilling and splitting synchronous tunneling machine of the present invention.
[0032] Figure 2 It is a structural diagram of the drilling and splitting control arm of the present invention.
[0033] Figure 3 It is a structural diagram of the synchronous drilling and splitting device of the present invention in the recovery state.
[0034] Figure 4 It is a structural diagram of the synchronous drilling and splitting device of the present invention in the extended state.
[0035] Figure 5 It is a partial exploded view of the splitting-while-drilling mechanism 3-4 of the present invention.
[0036] Figure 6 It is a schematic diagram of the excavation process of the drilling and splitting synchronous tunnel boring machine of the present invention.
[0037] Wherein, the accompanying drawings are marked as follows:
[0038] 1. Cantilever tunnel boring machine;
[0039] 2. Drilling and splitting control arm; 2-1. Primary telescopic mechanism; 2-1-1. Rack guide rail base; 2-1-2. Primary gear moving device; 2-1-2a. Moving device housing 1; 2-1-2b. Primary hydraulic drive motor; 2-1-2c. Primary drive gear; 2-2. Secondary telescopic mechanism; 2-2-1. Lifting hydraulic cylinder; 2-2-2. Secondary rack guide rail; 2-2-3. Secondary gear moving device; 2-2-2a. Moving device housing 2; 2-2-2b. Secondary hydraulic drive motor; 2-2-2c. Secondary drive gear; 2-3. Angle control device; 2-3-1. Secondary rotary hydraulic rotary device; 2-3-2. Adjustment hydraulic cylinder; 2-3-3. Primary rotary hydraulic rotary device;
[0040] 3. Synchronous drilling and splitting device; 3-1. Track frame; 3-2. Sprocket transmission mechanism; 3-2-1. Sprocket drive motor; 3-2-2. Driving sprocket; 3-2-3. Chain; 3-2-4. Driven sprocket; 3-3. Impact rock drilling mechanism; 3-3-1. Sliding block type connecting seat 1; 3-3-2. Rock drilling impactor; 3-3-3. Drill rod; 3-3-4. Impact drill bit; 3-4. Splitting while drilling mechanism; 3-4-1. Sliding block type connecting seat 2; 3-4-2. Hydraulic rotary mechanism; 3-4-3. Connecting flange; 3-4-4. Splitting frame; 3-4-5. Displacement loading mechanism; 3-4-6. Memory alloy; 3-4-7. Heating sleeve; 3-4-8. Support and slag discharge mechanism; 3-4-9. Slag collecting mechanism; 3-5. Connecting clamping device. DETAILED DESCRIPTION
[0041] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. Of course, the specific embodiments described here are only used to explain the present invention and are not used to limit the present invention.
[0042] Example: Figure 1 As shown, the synchronous drilling and splitting roadheader proposed in the present invention comprises a cantilever roadheader 1, a drilling and splitting control arm 2, and a synchronous drilling and splitting device 3.
[0043] like Figure 2 As shown, the drilling and splitting control arm is composed of a primary telescopic mechanism 2-1, a secondary telescopic mechanism 2-2, and an angle control device 2-3.
[0044] The first-level telescopic mechanism 2-1 includes a rack guide rail base 2-1-1 and a first-level gear moving device 2-1-2 installed on the frame above the crawler tracks on both sides of the tunnel boring machine; wherein both ends of the rack guide rail base 2-1-1 are provided with a limit mechanism, which is fixedly installed on the support plate above the crawler tracks of the tunnel boring machine; the first-level gear moving device 2-1-2 includes a moving device housing 1, a first-level hydraulic drive motor 2-1-2b and a first-level drive gear 2-1-2c, the first-level drive gear 2-1-2c is arranged in the moving device housing 1 2-1-2a, and is coaxially connected with the first-level hydraulic drive motor 2-1-2b, and the first-level drive gear 2-1-2c is meshed with the gear guide rail of the rack guide rail base 2-1-1;
[0045] The secondary telescopic mechanism 2-2 includes a lifting hydraulic cylinder 2-2-1 installed on the primary gear moving device 2-1-2, a secondary rack guide 2-2-2 and a secondary gear moving device 2-2-3; wherein the secondary rack guide 2-2-2 is fixedly installed on the primary gear moving device 2-1-2; the secondary gear moving device 2-2-3 includes a moving device housing 2-2-3a, a secondary hydraulic drive motor 2-2-3b and a secondary drive gear 2-2-3c, the secondary drive gear 2-2-3c is arranged in the moving device housing 2-2-3a, and is coaxially connected with the secondary hydraulic drive motor 2-2-3b, and the secondary drive gear 2-2-3c is meshed with the gear guide of the rack guide base 2-2-2;
[0046] The angle control device 2-3 includes an auxiliary rotary hydraulic rotary device 2-3-1, an adjusting hydraulic cylinder 2-3-2 and a main rotary hydraulic rotary device 2-3-3; one end of the shell of the auxiliary rotary hydraulic rotary device 2-3-1 is hinged to one end of the shell of the main rotary hydraulic rotary device 2-3-3, and the other end of the shell of the auxiliary rotary hydraulic rotary device 2-3-1 is connected to the other end of the shell of the main rotary hydraulic rotary device 2-3-3 through the adjusting hydraulic cylinder 2-3-2; the angle control device 2-3 is integrally installed on the secondary gear moving device 2-2-3 of the secondary telescopic mechanism 2-2.
[0047] like Figure 3 As shown, the synchronous drilling and splitting device 3 includes a track frame 3-1, a sprocket transmission mechanism 3-2, an impact rock drilling mechanism 3-3, a splitting mechanism while drilling 3-4, and a connecting clamping device 3-5. The synchronous drilling and splitting device 3 is installed on the drilling and splitting control arm 2 through the connecting clamping device 3-5; the track frame 3-1 is an I-shaped structure with a concave space, and the upper and lower outer edge track structures of the frame are used to install the impact rock drilling mechanism 3-3 and the splitting mechanism while drilling 3-4; the track frame 3-1 is provided with a reserved space for installing the sprocket transmission mechanism 3-2, and the front end of the track frame 3-1 is provided with a positioning guide structure that matches the size of the splitting mechanism while drilling 3-4; the sprocket transmission mechanism 3-2 includes a sprocket drive motor 3-2-1, a driving sprocket 3-2-2, a chain 3-2-3, and a driven sprocket 3-2-4, which are installed at corresponding positions on the track frame 3-1.
[0048] like Figure 4 As shown, the impact rock drilling mechanism 3-3 includes a slider-type connecting seat 3-3-1, a rock drilling hammer 3-3-2, a drill rod 3-3-3, and an impact drill bit 3-3-4. The rock drilling hammer 3-3-2, the drill rod 3-3-3, and the impact drill bit 3-3-4 together constitute the main body of the rock drilling machine. The rock drilling hammer 3-3-2 is installed on the track frame 3-1 through a slider-type connecting seat 3-3-1 and is fixed with a chain 3-2-3. When performing impact drilling operations, it is driven forward along the track frame through the sprocket transmission mechanism 3-2.
[0049] like Figure 5As shown, the splitting mechanism while drilling 3-4 includes a slider-type connecting seat 2 3-4-1, a hydraulic rotary mechanism 3-4-2, a connecting flange 3-4-3, a splitting frame 3-4-4, a displacement loading mechanism 3-4-5, a heating sleeve 3-4-7, a memory alloy 3-4-6, a supporting slag discharge mechanism 3-4-8 and a slag collection mechanism 3-4-9; the hydraulic rotary mechanism 3-4-2 is installed on the track frame 3-1 through the slider-type connecting seat 2 3-4-1 and is fixed to the chain 3-2-3. When the impact drilling operation is performed, it is pushed forward along the track frame 3-1 by the sprocket transmission mechanism 3-2 synchronously with the impact drilling mechanism 3-3; the splitting frame 3-4-4, the heating sleeve 3-4 -7, memory alloy 3-4-6, displacement loading mechanism 3-4-5, and supporting slag discharge mechanism 3-4-8 together constitute the main body of the splitting mechanism 3-4 while drilling. The splitting frame 3-4-4 is used to install the heating sleeve 3-4-7, memory alloy 3-4-6, displacement loading mechanism 3-4-5, and supporting slag discharge mechanism 3-4-8. The splitting frame 3-4-4 is multi-sectioned and used to install multiple heating sleeves 3-4-7, memory alloy 3-4-6 and displacement loading mechanism 3-4-5. Two heating sleeve 3-4-7 fixing slots and displacement loading mechanism 3-4-5 moving tracks are arranged in each section. A concave space is reserved inside the splitting frame 3-4-4, which is matched with the drill rod size of the impact drilling mechanism to make the drilling center and the splitting center The two ends of the splitting frame 3-4-4 are circular sections with grooves, which are used to connect with the connecting flange 3-4-3 and the slag collecting mechanism 3-4-9. The heating sleeve 3-4-7 is cylindrical, composed of a metal sleeve, an adhesive and a nickel-chromium alloy wire, and is installed in the corresponding slot of the splitting frame 3-4-4; the memory alloy 3-4-6 is a hollow cylinder with a spiral groove, which is installed in the heating sleeve 3-4-7. The displacement loading mechanism 3-4-5 is installed on the displacement loading mechanism 3-4-5 moving track of the splitting frame 3-4-4 and is connected to the memory alloy 3-4,6. On the splitting frame 3-4-4, multiple heating sleeves 3-4-7, memory alloy 3-4-6 and displacement loading mechanism 3-4-5 are installed in an array along the axis. to split the borehole wall in sections; the supporting slag discharge mechanism 3-4-8 is an arc-shaped plate with a middle groove, which supports splitting and removes rock chips, and is installed on the other side of the installation plane of the heating sleeve 3-4-7, the memory alloy 3-4-6, and the displacement loading mechanism 3-4-5; the connecting flange 3-4-3 is a columnar structure, and the middle part contains a through hole matching the size of the drill rod, and the connecting flange 3-4-3 is used to connect the fixed hydraulic rotary mechanism 3-4-2 and the splitting frame 3-4-4; the slag collecting mechanism 3-4-9 contains a through hole matching the size of the drill rod and a slag outlet connected to the supporting slag discharge mechanism 3-4-9, and the slag collecting mechanism 3-4-9 is installed at the end of the splitting frame 3-4-4 and is close to the impact drill bit 3-3-4.
[0050] like Figure 4As shown, the principle that the drilling splitting device 3-4 can achieve rock splitting is: the memory alloy 3-4-6 has two stable phases, a high-temperature phase and a low-temperature phase. Under the low-temperature state, the memory alloy 3-4-6 is in the martensite phase. When the temperature is higher than the austenite temperature, the alloy phase transforms to austenite, and the alloy recovers to the shape in the austenite phase. If the deformation cannot be recovered, the memory alloy 3-4-6 releases a huge recovery stress; after the drilling splitting mechanism 3-4 is completely in contact with the rock hole wall, the rock heating system is started to heat the heating sleeve 3-4-7 to quickly increase the temperature, and the memory alloy 3-4-6 installed in the heating sleeve 3-4-7 is displaced along the axial direction, and the displacement loading mechanism 3-4-5 is pushed to squeeze the rock hole wall, causing the rock hole wall to be damaged by tensile stress to form a crack surface, thereby achieving the purpose of weakening the rock mass.
[0051] The working steps of the synchronous drilling and splitting device to achieve splitting while drilling are as follows: after the drilling and splitting control arm 2 reaches the predetermined drilling and splitting position on the wall, the impact drilling mechanism 3-3 and the sprocket transmission mechanism 3-2 are started, and the synchronous drilling and splitting device 3 performs rock drilling; after the impact drilling mechanism 3-3 drills to the specified depth, the hydraulic rotary mechanism 3-4-2 of the splitting mechanism 3-4 is adjusted, and the angle of the splitting mechanism 3-4 in the rock hole is adjusted so that the extension direction of the splitting direction of the displacement loading mechanism 3-4-5 is perpendicular to the adjacent free surface; the rock heating system is started to deform the memory alloy 3-4-6, and the displacement loading mechanism 3-4-5 is pushed to squeeze the rock hole wall to crack the rock. After completing the drilling and splitting, the tunneling machine spray device is used to cool the splitting mechanism 3-4 while drilling, so that the memory alloys 3-4, 6 are restored to the retracted state before the next hole drilling and splitting work can be carried out.
[0052] like Figure 6 As shown, the excavation process of the drilling and splitting synchronous tunneling machine includes the following steps:
[0053] Step 1: According to the side and roof positions of the cross-section contour, the cross-section is divided into the middle groove area, the left cutting area, the right cutting area, and the roof cutting area. The height of the middle groove area is equal to the height of the side, and the width is the width of the excavable space of the roadheader drum pitching and swinging; intensive drilling is performed in the groove area, with the projection area of a single cutting drum as a reference. Within the projection area of a single cutting drum, the number and spacing of holes must be such that the drilling area must reach 3 / 5 or more of the projection area of the cutting drum, and the drilling depth must reach the full insertion depth of the synchronous drilling and splitting device. After the drilling is completed, the middle groove area is cut by the roadheader, and the cutting depth must reach the drilling depth.
[0054] Step 2: Drill and split the left and right cutting areas to create a fracture network. The drill and split holes are arranged in multiple rows in the longitudinal direction. Each row of drill and split holes is parallel to the free surface formed in the middle groove area, and the splitting direction is perpendicular to it. The drill and split holes are split from the inside to the outside in rows; the splitting order of each row of split holes is: the middle hole is split first, the drill and split holes are split from the middle to the top, and then the drill and split holes are split from the middle to the bottom; the distance between the split holes and the spacing between the split holes in each row are determined according to the power of the drilling and splitting device and the rock conditions of the cross section. It is necessary to make the cross-section cracks larger than 5mm after splitting, and the cracks between the holes and the free surface cracks are clearly visible.
[0055] Step 3: Carry out cutting work in the left cutting area and the right cutting area, and the tunnel boring machine drum cuts the split area in a Z-shaped trajectory.
[0056] Step 4: Drill and split the roof area. After the left and right cutting areas are cut and connected to the middle groove area to form a cut space, the top plane of the cut space is used as a free surface for drilling and splitting. The drilling and splitting holes are arranged in multiple columns horizontally, and the drilling and splitting holes are split one by one from bottom to top. The splitting order of each column of splitting holes is: the middle hole is split first, and the drilling and splitting holes are split from the middle to the outside in sequence. The splitting hole arrangement requirements and the requirements for forming crack surfaces are consistent with the drilling and splitting requirements of the left and right cutting areas.
[0057] Step 5: Cutting work is carried out in the roof area, and the tunnel boring machine drum cuts the split area in an N-shaped trajectory.
[0058] Step 6: Perform edge sweeping and cutting along the contour of the cutting area to ensure the contour quality of the cutting area.
[0059] Therefore, by drilling and splitting the cross-section rock mass, the integrity of the rock is weakened, creating a free surface that is beneficial to roller cutting. During roller cutting, it is only necessary to overcome the rock fracture resistance between the root of the crack surface and the free surface to complete the overall cutting. The rock failure mode of a single pick cutting will be converted from grinding and crushing to fracture failure under the action of impact force, which greatly improves the strength of the rock that can be cut under a fixed cutting power, reduces pick wear, and improves the cutting capacity of the tunnel boring machine. In addition, compared with other drilling and splitting assisted tunneling machines, the drilling and splitting synchronous tunneling machine and its tunneling process proposed in the present invention have the following special advantages: the two processes of drilling and splitting are realized continuously, and there is no need to re-align the holes through other rotating devices, which greatly improves the drilling and splitting efficiency and the quality of drilling and splitting. In addition, the drilling and splitting structure of the present invention is compact and has a small curb weight; the drilling and splitting work and the cutting work are carried out synchronously, and the hole position can be adjusted in time according to the formation of the drilling and splitting cracks, thereby reducing the number of invalid drilling; the process combined with the equipment proposed in the present invention can completely cut the rock mass split by drilling and splitting at one time in a single tunneling footage, thereby increasing the single-cycle footage and realizing fast and high-quality tunneling of hard rock formations (hardness coefficient ≥ f10).
[0060] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A synchronous drilling and splitting tunnel boring machine, characterized in that: It comprises a cantilever tunneling machine (1), a drilling and splitting control arm (2), and a synchronous drilling and splitting device (3), wherein the drilling and splitting control arm (2) is arranged on the cantilever tunneling machine (1), and the synchronous drilling and splitting device (3) is arranged on the drilling and splitting control arm (2); The drilling and splitting control arm (2) can adjust the rock drilling angle of the synchronous drilling and splitting device (3) and drive the synchronous drilling and splitting device (3) to move forward and backward; The synchronous drilling and splitting device (3) comprises a track frame (3-1), a sprocket transmission mechanism (3-2), an impact rock drilling mechanism (3-3), a splitting while drilling mechanism (3-4) and a connecting clamping device (3-5); the track frame (3-1) is mounted on a drilling and splitting control arm (2) via the connecting clamping device (3-5); the sprocket transmission mechanism (3-2), the impact rock drilling mechanism (3-3) and the splitting while drilling mechanism (3-4) are all arranged on the track frame (3-1); the sprocket transmission mechanism (3-2) is used to provide a driving force to enable the impact rock drilling mechanism (3-3) and the splitting while drilling mechanism (3-4) to move forward and backward along the track frame (3-1).
2. A drilling and splitting synchronous tunneling machine according to claim 1, characterized in that: An I-shaped structure with a concave space is arranged on the track frame (3-1), and the upper and lower outer edge track structures of the track frame (3-1) are used to install an impact rock drilling mechanism (3-3) and a splitting-while-drilling mechanism (3-4).
3. The drilling and splitting synchronous tunneling machine according to claim 1, characterized in that: The sprocket transmission mechanism (3-2) comprises a sprocket drive motor (3-2-1), a driving sprocket (3-2-2), a chain (3-2-3) and a driven sprocket (3-2-4) arranged on a track frame (3-1); the chain (3-2-3) is arranged between the driving sprocket (3-2-2) and the driven sprocket (3-2-4); the chain (3-2-3) is respectively fixedly connected to the impact rock drilling mechanism (3-3) and the splitting-while-drilling mechanism (3-4), and can drive the impact rock drilling mechanism (3-3) and the splitting-while-drilling mechanism (3-4) to move synchronously.
4. A drilling and splitting synchronous tunneling machine according to claim 3, characterized in that: The impact rock drilling mechanism (3-3) comprises a slider-type connecting seat (3-3-1), a rock drilling impactor (3-3-2), a drill rod (3-3-3) and an impact drill bit (3-3-4); the rock drilling impactor (3-3-2) is installed on a track frame (3-1) via a slider-type connecting seat (3-3-1); the slider-type connecting seat (3-3-1) is fixedly connected to a chain (3-2-3); one end of the drill rod (3-3-3) is connected to the rock drilling impactor (3-3-2); the other end of the drill rod (3-3-3) is connected to the impact drill bit (3-3-4) after rotating through a splitting mechanism (3-4); when performing an impact drilling operation, the impact drill bit (3-3-4) can be pushed forward along the track frame (3-1) via a sprocket transmission mechanism (3-2).
5. The drilling and splitting synchronous tunneling machine according to claim 4, characterized in that: The splitting mechanism while drilling (3-4) comprises a second slider-type connecting seat (3-4-1), a hydraulic rotary mechanism (3-4-2), a connecting flange (3-4-3), a splitting frame (3-4-4), a displacement loading mechanism (3-4-5), a heating sleeve (3-4-7), a memory alloy (3-4-6), a supporting slag discharge mechanism (3-4-8) and a slag collection mechanism (3-4-9); the hydraulic rotary mechanism (3-4-2) is installed on the track frame (3-1) via the second slider-type connecting seat (3-4-1). The splitting frame (3-4-4), the heating sleeve (3-4-7), the memory alloy (3-4-6), the displacement loading mechanism (3-4-5) and the supporting slag discharge mechanism (3-4-8) together constitute the main body of the splitting mechanism (3-4) while drilling, and the chain (3-2-3) in the sprocket transmission mechanism (3-2) can drive the splitting mechanism (3-4) while drilling to move forward along the track frame (3-1); The splitting frame (3-4-4) is multi-sectioned, and a displacement loading mechanism (3-4-5) and a plurality of heating sleeves (3-4-7) are arranged on each section of the splitting frame (3-4-4). The heating sleeve (3-4-7) is arranged perpendicular to the chain (3-2-3). The memory alloy (3-4-6) is arranged in the heating sleeve (3-4-7). The length of the memory alloy (3-4-6) increases after being heated. After extending out of the heating sleeve (3-4-7), the displacement loading mechanism (3-4-5) is pushed to move outward, so that the splitting mechanism (3-4) is expanded and its diameter becomes larger. The plurality of heating sleeves (3-4-7), the memory alloy (3-4-6) and the displacement loading mechanism (3-4-5) arranged in an array in the axial direction of the splitting frame (3-4-4) can play a role in segmented splitting of the borehole wall.
6. The drilling and splitting synchronous tunneling machine according to claim 5, characterized in that: The splitting frame (3-4-4) is provided with a through hole matched with the drill rod (3-3-3), and both ends of the splitting frame (3-4-4) are circular sections with grooves for connecting with the connecting flange (3-4-3) and the slag collecting mechanism (3-4-9); The heating sleeve (3-4-7) is cylindrical, composed of a metal sleeve, an adhesive and a nickel-chromium alloy wire, and is installed in a corresponding slot of a splitting frame (3-4-4). The memory alloy (3-4-6) is a hollow cylinder containing a spiral groove and is installed in the heating sleeve (3-4-7). The displacement loading mechanism (3-4-5) is installed on a moving track of the splitting frame (3-4-4), and its inner side is connected to the memory alloy (3-4-6).
7. The drilling and splitting synchronous tunneling machine according to claim 6, characterized in that: The supporting slag discharge mechanism (3-4-8) is an arc-shaped plate with a middle groove, which is arranged on the other side of the splitting frame (3-4-4) and is opposite to the installation plane of the heating sleeve (3-4-7), the memory alloy (3-4-6) and the displacement loading mechanism (3-4-5), and plays the role of supporting splitting and removing rock debris; The connecting flange (3-4-3) is a columnar structure, and has a through hole in the middle thereof that matches the size of the drill rod (3-3-3). The connecting flange (3-4-3) is used to connect and fix the hydraulic rotary mechanism (3-4-2) and the splitting frame (3-4-4); The slag collecting mechanism (3-4-9) contains a through hole with a size matching that of the drill rod (3-3-3) and a slag outlet connected to the supporting slag outlet mechanism (3-4-8). One end of the slag collecting mechanism (3-4-9) is connected to the end of the splitting frame (3-4-4), and the other end is close to the impact drill bit (3-3-4).
8. A tunneling process, the tunneling process is based on a drilling and splitting synchronous tunneling machine according to any one of claims 1 to 7, characterized in that: The steps include: S1: According to the side and roof positions of the cross-section contour, the cross-section is divided into a middle groove area, a left cutting area, a right cutting area and a roof cutting area, wherein the height of the middle groove area is equal to the height of the side, and the width is the width of the excavable space by the pitching and swinging of the roadheader drum. Dense drilling is performed in the groove area. The projection area of a single cutting drum is used as a reference. Within the projection area of a single cutting drum, the number and spacing of holes drilled must ensure that the drilling area is at least 3 / 5 of the projection area of the cutting drum. The drilling depth must reach the full insertion depth of the synchronous drilling and splitting device (3). After the drilling is completed, the middle groove area is cut by the roadheader, and the cutting depth must reach the drilling depth. S2: Drilling and splitting work is performed in the left cutting area and the right cutting area to create a fracture network; S3: Cutting work is performed in the left cutting area and the right cutting area, and the roadheader drum cuts the split area in a Z-shaped trajectory; S4: Drilling and splitting work in the roof area; S5: Cutting work is carried out in the roof area, and the drum of the roadheader cuts the split area in an N-shaped trajectory; S6: Perform edge sweeping and cutting along the contour of the cutting area to ensure the contour quality of the cutting area.
9. A tunneling process according to claim 8, characterized in that: In S2, the method for performing the drilling and splitting work in the left cutting area and the right cutting area is as follows: The drill and splitting holes are arranged in multiple rows vertically, each row of drill and splitting holes is parallel to the free surface formed in the middle groove area, and the splitting direction is perpendicular to it. The drill and splitting holes are split row by row from the inside to the outside, and the splitting order of each row of splitting holes is: the middle hole is split first, the drill and splitting holes are split from the middle to the top, and then the drill and splitting holes are split from the middle to the bottom; the distance between the splitting holes and the spacing between the splitting holes in each row are determined according to the power of the drilling and splitting device and the cross-section rock conditions, and the cross-section cracks after splitting must be larger than 5mm, and the cracks between the holes and the free surface cracks must be clearly visible.
10. A tunneling process according to claim 8, characterized in that: In step S4, the method for drilling and splitting the top plate area is as follows: after the cutting of the left cutting area and the right cutting area has been completed and connected with the middle groove area to form a cut space, the top plane of the cut space is used as a free surface for drilling and splitting, and the drilling and splitting holes are arranged in multiple columns horizontally, and the drilling and splitting holes are split one by one from bottom to top; the splitting order of each column of splitting holes is: the middle hole is split first, and the drilling and splitting holes are split one by one from the middle to the outside; the splitting hole arrangement requirements and the crack surface formation requirements are consistent with the left and right cutting area drilling and splitting requirements.
Citation Information
Cited By
Five-drill-bit drilling and splitting cooperative in-situ expansion cracking rock breaking device and rock breaking process thereof
CN121138858A
Splitting machine with drilling function