Supporting structure of arch-shaped supporting foundation pit and construction method
By adopting a support structure with arched support foundation pits in the subway foundation pit construction and using a combined structure of arched support beams and steel columns, the stability of conventional steel support in the case of poor soil quality is solved, and the stability of foundation pits is achieved and significantly improved deformation.
Patent Information
- Application Number
- CN202411184781.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-27
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2044-08-27
AI Technical Summary
In subway foundation pit construction, conventional steel supports have poor stability under poor soil quality, resulting in large deformation of the foundation pit and affecting safety.
The supporting structure adopts an arched support foundation pit, including underground continuous walls, concrete straight support, steel columns, column piles, arch support beams and steel support, and is connected through embedded bolt holes and arc-shaped steel plates to form a 120° arch structure. , use expanded concrete and steel inclined support to transmit soil pressure, offset soil pressure and retain core soil.
The stability of the foundation pit is improved, deformation is reduced, and the safety of the foundation pit is ensured. The combined structure of segmented arch support beams and steel columns is effectively offset, which enhances the overall stability of the support system.
Smart Images

Figure CN118933020A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of subway foundation pits, and in particular to a supporting structure of an arch-shaped supporting foundation pit and a construction method. Background Art
[0002] In subway foundation pit construction, in order to ensure the construction of conventional steel supports, steel supports must be constructed after excavation is completed. The core soil in the middle of the foundation pit cannot be retained, and the lower load-bearing steel supports are too long, resulting in poor stability of the steel supports. When the soil conditions of the foundation pit are poor, it is easy to cause large overall deformation of the foundation pit and poor stability of the support system, thus affecting the safety of the foundation pit. Summary of the invention
[0003] In order to solve the problems existing in the background technology, the present invention provides a supporting structure for an arched supporting foundation pit.
[0004] The present invention adopts the following technical solution: A supporting structure for an arch support foundation pit, characterized in that it includes an underground continuous wall excavated downward, a concrete straight support, a steel column, a column pile, an arch support beam and a steel support, wherein one end of the steel column is arranged in the column pile, and the other end is connected to the concrete straight support; arch support beams are arranged on both sides of the steel column, and embedded bolt holes are arranged inside the arch support beam; a steel support is arranged on the back side of the arch support beam, and one end of the steel support is connected to the arch support beam, and the other end is connected to the underground continuous wall.
[0005] Furthermore, a pre-buried arc steel plate is arranged in the arched support beam connected to the steel support, and a pre-buried steel plate is arranged in the underground continuous wall connected to the steel support.
[0006] Furthermore, the arched support beam is composed of a plurality of segmented arched support beams, the plurality of segmented arched support beams are provided with bolt holes, and the plurality of segmented arched support beams are connected by bolts. The arched support beam is an arched structure of about 120°, and is formed by connecting a plurality of prefabricated arc-shaped concrete blocks by the bolt connection system.
[0007] Furthermore, the connection between the arched support beam and the steel column is filled with expansive concrete. The arched support beam and the column pile are connected and fixed by the expansive concrete. Furthermore, a diagonal brace is provided at the connection between the arched support beam and the steel support, and a steel diagonal support is provided at the connection between the steel support and the underground continuous wall. The connection between the steel support and the arched support and the underground continuous wall is connected by the embedded steel plate. The connection between the arched support beam and the underground continuous wall is fixed by the expansion concrete.
[0008] A supporting structure for an arch-supported foundation pit, in which the soil pressure exerted on an underground continuous wall, the lowest horizontal soil pressure is offset by a plurality of segmented arch-support beam assembly structures, the middle horizontal soil pressure is transmitted to a plurality of segmented arch-support beam assembly structures through steel supports to offset each other, the upward pull received by the arch-support beam is transmitted to the column piles through steel columns to offset it by soil friction. The formation of the above system ensures the stability of the foundation pit, and when the foundation pit support system is fully formed, most of the core soil in the foundation pit is retained, thereby reducing the deformation of the foundation pit. BRIEF DESCRIPTION OF THE DRAWINGS
[0009] Figure 1 A cross-sectional schematic diagram of an arch support foundation pit support system and a construction method provided by the present invention; Figure 2 A schematic diagram of excavation step 1 of an arch support foundation pit support system and construction method provided by the present invention; Figure 3 A schematic diagram of excavation step 2 of an arch support foundation pit support system and construction method provided by the present invention; Figure 4 A schematic diagram of excavation step 3 of an arch support foundation pit support system and construction method provided by the present invention; Figure 5 A schematic diagram of excavation step 4 of an arch support foundation pit support system and construction method provided by the present invention; Figure 6 A schematic diagram of excavation step 5 of an arch support foundation pit support system and construction method provided by the present invention; Figure 7 A detailed diagram of the connection between the first arch support beam 6 and the column 3 of an arch support foundation pit support system and construction method provided by the present invention.
[0010] Figure 8 A detailed diagram of the connection between arched support beams of an arched support foundation pit support system and construction method provided by the present invention.
[0011] Fig. 9 A detailed diagram of the connection between the secondary arch support beams 7, 8 and the steel support 5 of an arch support foundation pit supporting system and construction method provided by the present invention.
[0012] Fig.10 A detailed diagram of the connection between an underground continuous wall 1 and a steel support 5 of an arch support foundation pit support system and construction method provided by the present invention.
[0013] The numbers marked in the figure are as follows: 1-underground continuous wall; 2-concrete straight support; 3-steel column; 4-column pile; 5-steel support; 6-arch support beam; 7-second arch support beam; 8-third arch support beam; 9-last arch support beam; 11-embedded steel plate; 12-expansive concrete; 13-steel inclined support; 51-inclined support; 62-embedded bolt hole; 63-bolt system; 71-embedded curved steel plate DETAILED DESCRIPTION
[0014] The present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments.
[0015] With reference to the accompanying drawings, A supporting structure for an arch support foundation pit comprises an underground continuous wall 1 excavated downward, a concrete straight support 2, a steel column 3, a column pile 4, an arch support beam 6 and a steel support 5, wherein a section of the steel column 3 is arranged in the column pile 4, and the other end is connected to the concrete straight support 2; an arch support beam 6 is arranged on both sides of the steel column 3, and embedded bolt holes 62 are arranged inside the arch support beam 6; a steel support 5 is arranged on the back side of the arch support beam 6, and one end of the steel support 5 is connected to the arch support beam 6, and the other end is connected to the underground continuous wall 1.
[0016] A pre-buried arc steel plate 71 is arranged inside the arched support beam 6 connected to the steel support 5 , and a pre-buried steel plate 11 is arranged inside the underground continuous wall 1 connected to the steel support 5 .
[0017] The arched support beam 6 is composed of a plurality of segmented arched support beams, wherein embedded bolt holes 62 are arranged in the plurality of segmented arched support beams, and the plurality of segmented arched support beams are connected by a bolt system 63. The arched support beam is an arched structure of about 120°, and is formed by connecting a plurality of prefabricated arc-shaped concrete blocks by a bolt connection system.
[0018] The joint between the arched support beam 6 and the steel column 3 is filled with expansion concrete 12. The arched support beam 6 and the column pile 4 are connected and fixed by the expansion concrete 12. The connection between the arched support beam 6 and the steel support 5 is provided with a diagonal support 51, and the connection between the steel support 5 and the underground continuous wall 1 is provided with a steel diagonal support 13. The connection between the steel support 5 and the arched support beam 6 and the underground continuous wall 1 is connected by the embedded steel plate 11. The connection between the arched support beam 6 and the underground continuous wall 1 is fixed by the expansion concrete 12.
[0019] A supporting structure for an arch-supported foundation pit, in which the soil pressure exerted on an underground continuous wall, the lowest horizontal soil pressure is offset by a plurality of segmented arch-support beam assembly structures, the middle horizontal soil pressure is transmitted to a plurality of segmented arch-support beam assembly structures through steel supports to offset each other, the upward pull received by the arch-support beam is transmitted to the column piles through steel columns to offset it by soil friction. The formation of the above system ensures the stability of the foundation pit, and when the foundation pit support system is fully formed, most of the core soil in the foundation pit is retained, thereby reducing the deformation of the foundation pit.
[0020] The specific construction steps are as follows: S1: First, dig a trench for the underground continuous wall 1, lower the underground continuous wall reinforcement cage, set the embedded steel plate 11 in the underground continuous wall reinforcement cage, and cast the underground continuous wall 1 as a whole, construct the column piles 4, and put in the steel column 3; S2: constructing the prefabricated first arch support beam 6 and the second arch support beam 7 of the concrete structure according to the size specifications of the foundation pit, and reserving the connection bolt holes 62 according to the connection requirements to facilitate the installation of the connection bolt system 63; S3: Excavate the foundation pit. When the excavation reaches the elevation of the concrete support 2, pour the concrete support 2 and anchor it into the steel column 3. Figure 2 As shown; S4: After the concrete support 2 reaches the design strength, continue to excavate the foundation pit to the elevation of the first arch support beam 6, assemble the two first arch support beams 6 using the connecting bolt system 63, and fill with expansion concrete 12, such as Figure 3 As shown; S5: Continue to excavate the foundation pit to the elevation of the secondary arch support beam 7, assemble the first arch support beam 6 and the secondary arch support beam 7 using the connecting bolt system 63, and set the steel support 5 at a predetermined height. Figure 4 As shown; S6: Continue to excavate the foundation pit to the elevation of the secondary arch support beam 8, use the connecting bolt system 63 to assemble the secondary arch support beams 7 and 8 in sequence, and set the steel support 5 at a predetermined height. Figure 5 As shown; S7: Continue to excavate the foundation pit to the elevation of the last arch support beam 9, use the connecting bolt system 63 to assemble the second arch support beam 7 and the last arch support beam 9 in sequence, and fill the gap between the underground continuous wall 1 with expansion concrete 12, such as Figure 6 As shown; S8: Excavation of foundation pit is completed, such as Figure 1 As shown, as the structure is rebuilt, the support system is dismantled in sequence to complete the recovery of the support system.
[0021] Note that the above are only preferred embodiments of the present invention and the technical principles used. Those skilled in the art will understand that the present invention is not limited to the specific embodiments described herein, and that various obvious changes, readjustments and substitutions can be made by those skilled in the art without departing from the scope of protection of the present invention. Therefore, although the present invention has been described in more detail through the above embodiments, the present invention is not limited to the above embodiments, and may include more other equivalent embodiments without departing from the concept of the present invention, and the scope of the present invention is determined by the scope of the appended claims.
Claims
1. A supporting structure for an arched foundation pit, characterized in that: It includes an underground continuous wall excavated downward, concrete straight supports, steel columns, column piles, arched support beams and steel supports, wherein one end of the steel column is arranged in the column pile, and the other end is connected to the concrete straight support; arched support beams are arranged on both sides of the steel column, and embedded bolt holes are arranged inside the arched support beams; a steel support is arranged on the back side of the arched support beam, one end of the steel support is connected to the arched support beam, and the other end is connected to the underground continuous wall.
2. The arch support pit support structure according to claim 1, characterized in that: An embedded arc steel plate is arranged in the arched support beam connected to the steel support, and an embedded steel plate is arranged in the underground continuous wall connected to the steel support.
3. The supporting structure of an arched supporting foundation pit according to claim 1, characterized in that: The arched support beam is composed of a plurality of segmented arched support beams, wherein bolt holes are arranged in the plurality of segmented arched support beams, and the plurality of segmented arched support beams are connected by bolts.
4. The arch support pit support structure according to claims 1 and 3, characterized in that: The joint between the arched support beam and the steel column is filled with expansive concrete.
5. The arch support pit support structure according to claim 2, characterized in that: A diagonal brace is provided at the connection between the arch support beam and the steel support, and a steel diagonal support is provided at the connection between the steel support and the underground continuous wall.
6. A supporting structure and construction method for an arched supporting foundation pit according to any one of claims 1 to 5, characterized in that: The following steps are involved: Step 1: First, dig a continuous wall under the trench, put in a steel cage, set a pre-buried steel plate in the steel cage, cast the whole into shape, drive in construction column piles, and put in steel columns; Step 2: prefabricate the first arched support beam and the extended arched support beam according to the size of the foundation pit, and prefabricate the connecting bolt holes at the joints of the arched support beams; Step 3: When the foundation pit is excavated to the concrete support elevation, the concrete support is poured and anchored into the steel column; Step 4: After the concrete brace reaches the designed strength, continue to excavate the foundation pit to the elevation of the first arch support beam, assemble the split first arch support beam using the connecting bolt system, and fill the gap with expansion concrete; Step 5: Continue to excavate the foundation pit to the elevation of the second arch support beam, extend and splice it with the first arch support through the connecting bolt system, and set up steel supports at the predetermined height; Step 6: Continue to excavate the foundation pit and repeat step 5 according to the elevation of the arch support beam; Step 7: Continue to excavate the foundation pit to the elevation of the end of the arched support beam, connect the arched support beam at the end with connecting bolts, connect the other end to the embedded steel plate in step 1, and fill the gap with expansion concrete; Step 8: After the foundation pit is excavated, the support system will be dismantled in sequence as the structure is rebuilt to complete the recovery of the support structure system.
Citation Information
Patent Citations
Self-balancing supporting structure of tool type arch support of subway foundation pit end well
CN105350545A
Cover-excavation full-inverse construction method for assembled vault large-span column-free underground structure
CN110080295A
Arched inner support of deep foundation pit
CN211312530U
Foundation pit support supporting structure
CN217267517U
Foundation pit supporting device
CN219547812U
Cited By
Roadway supporting method and steel shed
CN121897374A