Rock-socketed lock catch steel pipe pile cofferdam with rotary excavating, drilling, hole guiding and concrete pouring functions and construction method

Through rotary drilling drilling guide hole injected concrete rock-embedded lock steel pipe pile cofferdam construction method, combined with intelligent monitoring system and suspension system, the problems of water leakage and structural instability during the insertion and construction of steel pipe pile cofferdam are solved, and the problems of water leakage and structural instability in the process of drilling steel pipe pile cofferdam are improved. The construction accuracy and efficiency are achieved, and higher quality and environmental protection are achieved.

CN118933041AInactive Publication Date: 2024-11-12HANGZHOU JIANGRUN TECH LIMITED
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202411433505.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-15
Publication Date
2024-11-12
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

During the insertion and construction process of existing steel pipe pile cofferdams, there are problems such as water leakage, unperpendicular pile body, and incorrect position, resulting in uneven structural stress, affecting construction accuracy and efficiency. In addition, traditional methods produce large noise and damage steel. Pipe piles increase construction difficulty and cycle.

Method used

The construction method of concrete rock-embedded steel pipe pile cofferdam is adopted for rotary drilling drilling lead holes. Through intelligent monitoring system, rotary drilling technology, suspension system and waterproof lubrication measures, the insertion accuracy and stability are ensured and construction is reduced. links and noise to improve construction efficiency and safety.

Benefits of technology

It improves construction accuracy and efficiency, reduces construction difficulty and cost, reduces water leakage risk, shortens construction cycle, reduces the impact on the environment, and achieves higher construction quality and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933041A_ABST
    Figure CN118933041A_ABST
Patent Text Reader

Abstract

The invention relates to a rock-socketed lock catch steel pipe pile cofferdam and a construction method, female and male lock mouths are distributed on the left side and the right side of a steel pipe and located on the horizontal line, a reinforcement cage is placed on the lower portion of the lock mouth steel pipe through a rotary drilling guide hole, surrounding purlins and inner supports are made of corrugated I-shaped steel, and the four corners of each surrounding purlin are provided with an inclined inner support. And two inner supports are distributed in the middle and are connected through welding. The cofferdam is provided with three layers of surrounding purlins, and each layer of surrounding purlin is connected with a locking steel pipe through a bracket. The construction difficulty is reduced, and the construction precision is improved; and a rotary drilling guide hole concrete pouring technology is applied, so that the construction links are reduced, the construction period is shortened, and the working efficiency is improved. In addition, noise and vibration generated in the hole guiding process are small, and the influence on the surrounding environment is low; and an intelligent monitoring system is applied, so that the construction precision is effectively improved, the measurement difficulty is reduced, the construction error is effectively reduced, and the construction intellectualization is realized.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of steel cofferdam construction, and in particular relates to a rotary drilling hole pouring concrete embedded rock locking steel pipe pile cofferdam and a construction method. Background Art

[0002] With the development of the national economy, more and more large-scale bridge projects are being built on major rivers and more and more cross-sea bridge projects are being built in coastal areas. Deepwater caps are being used more and more widely in bridge projects. In recent years, single-wall or double-wall steel plate cofferdams have been most widely used as temporary water retaining structures for the construction of deepwater foundation caps for bridges, and rich design and construction experience has been accumulated. As a type of steel cofferdam, steel pipe pile cofferdams have the advantages of light weight, high strength, reusability and relatively easy construction. However, when inserting and driving, the friction at the lock mouth is large, making it difficult to insert and drive, and water leakage is prone to occur at the lock mouth. In addition, during the insertion and driving process, the pile body will not be vertical or the position will be incorrect. Once this happens, it may cause uneven stress on the structure and even affect the stability of the entire structure, seriously affecting the construction accuracy.

[0003] The traditional construction method is difficult to penetrate into the rock layer and generates a lot of noise, which disturbs the surrounding environment and may also damage the steel pipe piles, causing the rock mass and the steel pipe piles to not match each other, resulting in water leakage, tilting, movement, etc. Subsequent waterproofing treatment is required, which increases the difficulty of construction, prolongs the construction period, and seriously affects the construction efficiency and progress.

[0004] Therefore, how to propose a locking steel pipe pile cofferdam and construction method with high construction precision, high construction efficiency, water leakage prevention, low comprehensive cost, small impact on the environment, intelligence and digitization has become a technical problem that technical personnel in this field urgently need to solve. Summary of the invention

[0005] The purpose of the present invention is to overcome the deficiencies in the prior art and to provide a rotary drilling hole pouring concrete embedded rock locking steel pipe pile cofferdam and a construction method.

[0006] The construction method of rotary drilling, hole pouring, concrete embedding, rock locking steel pipe pile cofferdam comprises the following steps: S1. Locate the design position of the cofferdam based on the steel casing, and set up the construction platform and guide device; S2. Place a total station on each steel casing and construction platform, and set sensors on the new locking steel pipe piles to form an intelligent monitoring system for measurement and positioning; S3. Intelligent monitoring system assists in driving new type of locking steel pipe piles and closing the joints; S4, drilling holes in the new type of locking steel pipe pile, pouring concrete; curtain grouting water-stopping construction; S5. Weld beams on the steel casing, and each beam is connected to a threaded rod controlled by a jack to form a suspension system; S6. Pump out water from the cofferdam, install corbels from bottom to top, and lower the purlins onto the corbels through the suspension system; and perform water blocking treatment.

[0007] Preferably, the new locking steel pipe pile is provided with a negative locking mouth and a positive locking mouth, the negative locking mouth is rectangular, and the positive locking mouth is triangular, and corner locking steel pipe piles are arranged at the four corners of the cofferdam, and the negative locking mouth and the positive locking mouth on the corner locking steel pipe pile are arranged at 90 degrees, and the negative locking mouth and the positive locking mouth of the new locking steel pipe pile are on the same horizontal line.

[0008] Preferably, in step S1, the construction platform is positioned by a steel casing, a steel pipe is used on the outside of the designed position of the cofferdam to form the foundation of the construction platform, and then a support frame is built on the steel pipe, and a platform plate is provided on the support frame to form a construction platform.

[0009] Preferably, in step S2, a total station is placed on each steel casing and construction platform, automated sensor equipment is set outside at a certain distance from both ends of the new locking steel pipe pile, and automated sensors are set at the four corners of the purlin.

[0010] Preferably, in step S3, the driving position of the first new locking steel pipe pile is determined and fixed by means of a guide device and a total station, and a crawler crane and a vibration pile hammer are used to cooperate in the construction, and the new locking steel pipe piles are driven in sequence from the upstream, and the piles are closed downstream. When driving the last few new locking steel pipe piles, the closing distance is first measured, and the spacing between the new locking steel pipe piles is calculated and adjusted.

[0011] Preferably, the intelligent monitoring system includes a pressure sensor. In step S2, a pressure sensor is installed on the inner side at a certain distance from the bottom of the new locking steel pipe pile. In step S4, a rotary drilling rig is used to drill a hole in the new locking steel pipe pile, and the bottom of the new locking steel pipe pile is embedded in the weathered rock. Then a steel cage is lowered, and the overlap length of the steel cage and the new locking steel pipe pile is greater than or equal to 1.5 meters. A concrete mixer truck is used to pour concrete into the conduit to grout the new locking steel pipe pile until a change in the pressure sensor is detected and the grouting is stopped.

[0012] Preferably, in step S5, a cross beam is welded on the steel casing, and an upper support is welded on each end of each cross beam. A jack is provided in the upper support. The threaded connecting rod is driven by operating the jack, and the threaded connecting rod is connected to the lower support. When the surrounding purlin is lowered, the surrounding purlin is placed on the lower support.

[0013] Preferably, in S6, the purlin is composed of an I-beam, the web of the I-beam is made of corrugated steel, the four corners of the purlin are connected by welding, an inclined inner support is arranged between adjacent inner walls of the purlin, two vertical inner supports are arranged between the two long sides of the purlin, the four inclined inner supports are welded to the purlin, and the two vertical inner supports are also connected to the purlin by welding. The purlin is lowered by a suspension system, and the data of the total station and the automated sensor are observed at any time during the lowering.

[0014] Preferably, in step S6, when water is pumped to below the first circle of purlins, pumping is stopped, and corbels are installed below the first circle of purlins. The corbels include I-beams, and the corbels are welded to the new locking steel pipe piles.

[0015] The rotary drilling and hole pouring concrete rock-embedded locking steel pipe pile cofferdam is obtained by any of the above methods.

[0016] The beneficial effects of the present invention are: 1) The present invention adopts a new type of lock buckle and lock buckle waterproof and lubricating measures. The male lock mouth and the female lock mouth can be well fixed to each other, reducing the offset error generated during the insertion process. Evenly applying butter on the lock mouth and filling the lock mouth with clay or the like can play a role of lubrication and waterproofing during the insertion process, reduce the difficulty of insertion caused by friction and reduce the damage to the lock mouth, reduce the construction difficulty, and improve work efficiency.

[0017] 2) The present invention adopts an intelligent monitoring system. By arranging a total station and automated sensor equipment, the displacement, depth, offset angle and other parameters of the steel pipe pile during the insertion and release of the surrounding purlin are accurately measured. The accuracy of the construction is effectively improved, the difficulty of measurement is reduced, and the size of the error is effectively controlled. The use of automated sensors can monitor the accuracy of the construction in real time, thereby realizing the intelligentization of the construction.

[0018] 3) The present invention adopts the technology of rotary drilling and pouring concrete, which improves the stability and reliability of the new type of locking steel pipe pile, not only improves the construction efficiency, but also ensures the construction safety and quality. Compared with the traditional construction method, the rotary drilling and pouring concrete eliminates the situation that the new type of locking steel pipe pile does not match the rock mass, reduces the construction links, and shortens the construction period. In addition, the noise and vibration generated during the hole-drawing process are small, and the impact on the surrounding environment is low.

[0019] 4) The purlin and inner support of the present invention are made of corrugated steel. Compared with the traditional purlin and inner support, the purlin made of corrugated steel has a certain flexibility while maintaining good rigidity. When the cofferdam is subjected to external force, the load can be reasonably distributed and it has a certain deformation capacity. Moreover, it is light in weight, easy to transport and install on site, and effectively shortens the construction period.

[0020] 5) The present invention adopts a suspension system, which can accurately control the descending speed and position of the purlin, thereby improving the accuracy and efficiency of construction. Compared with the traditional use of a crane, the use of a suspension system reduces the difficulty of construction and can reduce material waste.

[0021] 6) The present invention adopts intelligent and digital technologies in many places, which greatly improves the construction efficiency and speeds up the construction speed and accuracy through the timely transmission of information. In addition, the precision and efficiency of intelligent and digital equipment achieve higher construction quality and lower comprehensive cost, and improve construction efficiency, safety and environmental protection. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 The general diagram of the cofferdam of the present invention is shown in FIG. Figure 2 A side view of the cofferdam of the present invention; Figure 3 A top view of the cofferdam and sensor arrangement diagram of the present invention; Figure 4 This is a connection diagram of the locking steel pipe of the present invention; Figure 5 This is a diagram showing the layout of the intelligent locking steel pipe and sensors of the present invention; Figure 6 This is a diagram of the rotary drilling and hole pouring concrete construction and sensor location of the present invention; Figure 7 It is the corbel diagram of the present invention; Figure 8 This is a diagram of the suspension system of the present invention; Fig. 9 This is a detailed diagram of the rotary drilling construction of the present invention; Fig.10 This is the overall construction flow chart of this invention.

[0023] In the figure: 1. New type of locking steel pipe pile; 2. Steel cage; 3. Purlin; 4. Corbel; 5. Steel casing; 6. Inclined inner support; 7. Corrugated steel; 8. Automated sensor; 9. Male lock; 10. Female lock; 11. Corner locking steel pipe pile; 12. Pile hammer machine; 13. Automated sensor equipment; 14. Total station; 15. Concrete mixer truck; 16. Conduit; 17. Pressure sensor; 18. Construction platform pile; 19. Support frame; 20. Platform plate; 21. I-beam; 22. Crossbeam; 23. Jack; 24. Threaded connecting rod; 25. Lower support; 26 Rotary drilling rig; 27. Rock mass; 28. Vertical inner support. DETAILED DESCRIPTION

[0024] The present invention is further described below in conjunction with embodiments. The description of the following embodiments is only used to help understand the present invention. It should be noted that for ordinary persons in the art, without departing from the principle of the present invention, the present invention can also be modified in some ways, and these improvements and modifications also fall within the scope of protection of the claims of the present invention.

[0025] Embodiment 1 As an example, Fig.10 As shown, this rotary drilling and hole pouring concrete embedded rock locking steel pipe pile cofferdam and construction method includes the following steps: S1, such as Figure 4 As shown, the new type of locking steel pipe pile is processed; the female locking mouth 9 and the male locking mouth 8 should be kept on the same horizontal line, the male and female locking angles of the locking steel pipe pile 10 at the four corners should be 90 degrees, and the welds of the steel pipe pile should be full, without cracks and pores. The upper and lower sensor installation places are polished and smoothed with a cutting machine.

[0026] S2, such as Figure 4 As shown, a construction platform and a guide device are built based on a steel casing; the steel casing 5 is used for positioning so that the pile driving machine can drive the pile, a steel pipe 18 is used to form a platform foundation, and then a support frame 19 is built on the pile foundation. The structure of the frame should be stable and able to withstand the load generated during construction, and then a platform plate 20 is set on the frame 19. The guide frame is installed on the construction platform according to the pre-designed position and size. During the installation process, it is necessary to ensure that the various parts of the guide frame are firmly connected, the overall structure is stable, and the correct relative position relationship with the steel casing is maintained.

[0027] S3, such as Figure 2 , Figure 5 , Figure 6 As shown, an intelligent monitoring system is built to measure and locate; automated sensors 7 are arranged at the four corners of each layer of purlin 3, sensors 13 are installed at a certain distance from each end of the locking steel pipe pile, and total stations 14 are placed on the steel casing and the construction platform to monitor the depth and offset angle of the purlin 3 and the locking steel pipe 1 in real time. Sensors 17 are installed at a height of 1.5 inside the lower end of the locking steel pipe pile to monitor the pouring height of concrete. Before installing the sensor, the installation position should be polished and smoothed to ensure data accuracy and reduce errors.

[0028] S4, such as Figure 4As shown, the new type of locking steel pipe pile is intelligently inserted and closed; after the locking steel pipe is inspected and qualified, it is transported to the construction platform by a transport vehicle, and then a crane and a crawler crane with a shock pile hammer 12 are used to cooperate with the construction. Before the insertion, the female lock mouth 8 and the male lock mouth 9 need to be evenly coated with butter to reduce the resistance during the insertion. At the same time, in order to prevent the pile end and the pile head from being damaged during the insertion, the pile end and the pile head need to be locally strengthened. And in order to prevent water leakage from the lock mouth, clay, saw foam, etc. need to be filled in the lock mouth. The insertion position and fixation of the first locking steel pipe are determined by the guide device and the total station 14, and then the crawler crane with a shock pile hammer 12 is used to cooperate with the construction. Stop when it is slowly inserted to two-thirds, and check whether the inclination of the pile body exceeds 0.5% through the total station and the automatic sensor. If the requirements are met, continue to hammer, otherwise it will be pulled out and re-inserted.

[0029] S5, rotary drilling and hole pouring of concrete; S6, curtain grouting water stop; S7, install the lifting system; S8, processing of corrugated steel purlins, support welding and lowering; S9, pumping water from the cofferdam, installing corbels and water blocking treatment; Cofferdam construction completed Embodiment 2 As another embodiment, this embodiment 2 proposes, on the basis of the embodiment 1, a more specific rotary drilling hole pouring concrete rock embedded locking steel pipe pile cofferdam and construction method, wherein steps S5 to S9 are specifically as follows: S5, such as Fig. 9 As shown, a rotary drilling rig 26 is used to guide the hole, and the pile needs to be embedded in the weathered rock 27 for one meter. After the hole is guided, the steel cage 2 is lowered.

[0030] S6, curtain grouting water stop; ensure that all construction equipment and materials meet the design requirements and on-site safety measures are in place. Use pressure grouting method to grout, the grouting pressure is determined by experiment, and the water-cement ratio of cement slurry is 1:1.

[0031] S7, install the lifting system; first, place the support beam 2 on the steel casing 5 and weld it for reinforcement, and place a jack at each end of the support beam 2. The upper support is installed on the beam, and a jack 23 is arranged in the upper support. When lowering the purlin 3, the purlin 3 is installed on the lower support 25. When lowering, the jack 23 is operated to drive the threaded connecting rod 24 to move downward. The suspension device must be balanced and stable, and it must be able to withstand the weight of the load of the purlin and its upper structure.

[0032] S8, corrugated steel purlin processing, support welding and lowering; the purlin 3 and the inner support 6 are installed on the construction platform, and then lowered to the designated position through the lifting system. The purlin 3 and the steel pipe pile 1 should be closely attached. If not, a small steel plate can be welded between the two for connection, or fine stone concrete can be filled.

[0033] S9. Pump water from the cofferdam and install the corbels; when the water is pumped to 50cm below the first circle of purlins 3, stop pumping and install the corbels 4, and then complete the corbels 4 support of the second and third circles of purlins in sequence until the water is pumped out. When pumping water, observe whether there is any leakage. If the leakage is small, use a foam expansion meter to seal it. If the leakage is large, observe whether it is on the wall. If it is on the wall, repair or weld the wall. If it is at the connection of the lock steel pipe, the connection can be welded or blocked with expansion waterproof glue. If water gushing from the base is large, a well point dewatering plan can be adopted in advance.

[0034] It should be noted that the parts in this embodiment that are the same or similar to those in the first embodiment can be referenced to each other and will not be described in detail in this application.

[0035] Embodiment 3 As another embodiment, this embodiment 2 proposes, on the basis of the embodiment 1, a more specific rotary drilling hole pouring concrete rock embedded locking steel pipe pile cofferdam and construction method: The new locking steel pipe pile 1 is provided with a negative locking mouth 9 and a positive locking mouth 10, the negative locking mouth 9 is rectangular, and the positive locking mouth 10 is triangular. Corner locking steel pipe piles 11 are arranged at the four corners of the cofferdam 3. The negative locking mouth 9 and the positive locking mouth 10 on the corner locking steel pipe pile 11 are arranged at 90 degrees. The negative locking mouth 9 and the positive locking mouth 10 of the new locking steel pipe pile 1 are on the same horizontal line.

[0036] In step S4, the driving depth and inclination of the pile body are checked at any time through the intelligent monitoring system during the driving process. The construction sequence should start from the upstream and then carry out the jointing in the downstream. Before the jointing, the jointing distance should be accurately measured when the last few piles are driven, and the spacing of the locking steel pipes should be calculated and adjusted to reduce the position deviation of the jointing corner piles.

[0037] In step S5, the overlap length of the steel cage 2 and the locking steel pipe 1 is not less than 1.5 meters to ensure that the concrete and the steel pipe are firmly combined. Before pouring concrete, the clay and other debris on the inner wall of the steel pipe need to be cleaned, otherwise it will affect the bonding between the concrete and the locking steel pipe 1. Use a concrete mixer 15 to pour concrete into the conduit 16, and the inner wall of the conduit 16 for pouring concrete should be smooth and round without water leakage. It should be tried and tested before use. When starting to inject concrete, the distance between the conduit and the bottom of the hole should be 300mm to 500mm.

[0038] In step S6, the amount of accelerator is 2% of the amount of cement. Parameters such as grouting pressure and diffusion radius should be determined before construction. During the construction process, the cement slurry mix ratio should be strictly controlled, and the cement slurry specific gravity and fluidity related indicators should be regularly checked to ensure that the requirements of the plan are met. After the grouting is completed, core sampling is carried out to verify the grouting effect, and problems are promptly handled.

[0039] In step S8, the purlin 3 and the support 5 are both I-shaped steel, the middle web is made of corrugated steel 6, and the purlin 3 and the support 5 are connected by welding, and the welding quality should meet the requirements.

[0040] It should be noted that the parts in this embodiment that are the same or similar to those in the first embodiment can be referenced to each other and will not be described in detail in this application.

[0041] The various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the various embodiments can be referenced to each other.

Claims

1. A construction method for a rotary drilling hole pouring concrete embedded rock locking steel pipe pile cofferdam, characterized in that: The following steps are involved: S1. Locate the design position of the cofferdam based on the steel casing, and set up the construction platform and guide device; S2. Place a total station on each steel casing and construction platform, and set sensors on the new locking steel pipe piles to form an intelligent monitoring system for measurement and positioning; S3. Intelligent monitoring system assists in driving new type of locking steel pipe piles and closing the joints; S4, drilling holes in the new type of locking steel pipe pile, pouring concrete; curtain grouting water-stopping construction; S5. Weld beams on the steel casing, and each beam is connected to a threaded rod controlled by a jack to form a suspension system; S6. Pump out water from the cofferdam, install corbels from bottom to top, and lower the purlins onto the corbels through the suspension system; and perform water blocking treatment.

2. The construction method of rotary drilling and pouring concrete into rock-embedded locking steel pipe pile cofferdam as claimed in claim 1 is characterized in that: The new locking steel pipe pile is provided with a negative locking mouth and a positive locking mouth. The negative locking mouth is rectangular and the positive locking mouth is triangular. Corner locking steel pipe piles are arranged at the four corners of the cofferdam. The negative locking mouth and the positive locking mouth on the corner locking steel pipe pile are arranged at 90 degrees. The negative locking mouth and the positive locking mouth of the new locking steel pipe pile are on the same horizontal line.

3. The construction method of rotary drilling and pouring concrete into rock-embedded locking steel pipe pile cofferdam as claimed in claim 1 is characterized in that: In step S1, the construction platform is positioned by a steel casing, a steel pipe is used to form the foundation of the construction platform outside the designed position of the cofferdam, and then a support frame is built on the steel pipe, and a platform plate is set on the support frame to form a construction platform.

4. The construction method of rotary drilling and pouring concrete into rock-embedded locking steel pipe pile cofferdam as claimed in claim 1 is characterized in that: In step S2, a total station is placed on each steel casing and construction platform, an automated sensor device is set outside at a certain distance from both ends of the new locking steel pipe pile, and automated sensors are set at the four corners of the purlin.

5. The construction method of rotary drilling and pouring concrete into rock-embedded locking steel pipe pile cofferdam as claimed in claim 1, characterized in that: In step S3, the driving position of the first new locking steel pipe pile is determined and fixed by means of the guide device and the total station. During the driving process, a crawler crane and a vibration pile hammer are used to cooperate with the construction. The new locking steel pipe piles are driven in sequence from the upstream, and the piles are closed downstream. When the last few new locking steel pipe piles are driven, the closing distance is first measured, and the spacing between the new locking steel pipe piles is calculated and adjusted.

6. The construction method of rotary drilling and pouring concrete into rock-embedded locking steel pipe pile cofferdam as claimed in claim 1, characterized in that: The intelligent monitoring system includes a pressure sensor. In step S2, a pressure sensor is installed on the inner side at a certain distance from the bottom of the new locking steel pipe pile; in step S4, a rotary drilling rig is used to drill a hole in the new locking steel pipe pile, and the bottom of the new locking steel pipe pile is embedded in the weathered rock, and then a steel cage is lowered, and the overlap length of the steel cage and the new locking steel pipe pile is greater than or equal to 1.5 meters; a concrete mixer truck is used to pour concrete into the conduit to grout the new locking steel pipe pile until a change in the pressure sensor is detected and the grouting is stopped.

7. The construction method of rotary drilling and pouring concrete into rock-embedded locking steel pipe pile cofferdam as claimed in claim 1, characterized in that: In step S5, a crossbeam is welded on the steel casing, and an upper support is welded on each end of each crossbeam. A jack is provided in the upper support. The threaded connecting rod is driven by operating the jack, and the threaded connecting rod is connected to the lower support. When the surrounding purlin is lowered, the surrounding purlin is placed on the lower support.

8. The construction method of rotary drilling and pouring concrete into rock-embedded locking steel pipe pile cofferdam as claimed in claim 4, characterized in that: In S6, the purlin is composed of I-beams, the web of the I-beams is made of corrugated steel, the four corners of the purlin are connected by welding, inclined inner supports are set between adjacent inner walls of the purlin, two vertical inner supports are set between the two long sides of the purlin, the four inclined inner supports are welded to the purlin, and the two vertical inner supports are also connected to the purlin by welding. The purlin is lowered by the suspension system, and the total station and automated sensor data are observed at any time during the lowering.

9. The construction method of rotary drilling and pouring concrete into rock-embedded locking steel pipe pile cofferdam as claimed in claim 1, characterized in that: In step S6, when the water is pumped to the bottom of the first circle of purlins, the pumping is stopped, and a corbel is installed under the first circle of purlins. The corbel includes an I-beam, and the corbel is welded and connected to the new locking steel pipe pile.

10. A rotary drilling and hole pouring concrete rock-embedded locking steel pipe pile cofferdam, characterized in that: Obtained by the method according to any one of claims 1 to 9.

Citation Information

Patent Citations

  • Control device of elevation of underwater filled concrete and use method

    CN102692259A

  • Construction method of cover and excavation top-down permanent steel pipe column

    CN116145723A

  • Construction process for constructing lock catch steel pipe pile cofferdam on steep slope hard rock riverbed

    CN118273366A

  • Control concrete surpasses irritates high device

    CN204645052U

  • Concrete pouring sensor and ballastless track self-compacting concrete pouring monitoring system

    CN212670161U