Prestressed kerf-free terrace and construction method thereof

By using a combination of fiberglass SBS self-adhesive moisture-proof layer, dry sand isolation layer, and PE film in prestressed seamless flooring, combined with prestressing tensioning and grouting technology, the problems of complex processes and high costs in existing technologies have been solved, achieving high-performance flooring construction.

CN118933303APending Publication Date: 2024-11-12CHINA CONSTR FOURTH ENG DIV CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411272350.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-11
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

Existing prestressed seamless concrete floor structures are complex in process, costly, and greatly affected by concrete properties, making them difficult to promote and apply in practice.

Method used

The system combines a fiberglass SBS self-adhesive moisture-proof layer, a dry sand isolation layer, a PE film, edge templates, anchors, corrugated metal pipes, and steel strands, and uses prestressed tensioning and grouting technology to form a seamless floor structure.

Benefits of technology

It improves the load-bearing capacity and crack resistance of the floor, reduces the risk of cracking during construction, lowers maintenance costs, adapts to uneven settlement, and meets the needs of industrial buildings.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933303A_ABST
    Figure CN118933303A_ABST
Patent Text Reader

Abstract

The invention relates to a prestressed non-kerf terrace, which comprises an original ground surface (8), a concrete cushion layer (7), a glass fiber SBS (Styrene Butadiene Styrene) self-adhesion damp-proof layer (6), a dry sand isolating layer (5) and a PE (Polyethylene) film (4), wherein a side template (10) is vertically arranged on the PE film (4); the anchor bearing (9) is vertically fixed in the middle of the side edge of the side template (10); the steel strand (3) penetrates into the metal corrugated pipe (2) and is fixed with the anchor seat (9); and concrete (1) is poured on the PE film (4) and between the edge templates (10). After the concrete (1) is poured, the steel strand (3) is tensioned; after tensioning is completed, grouting and anchor sealing are conducted on the metal corrugated pipe (2); and pouring the post-cast strip. According to the prestressed non-kerf terrace and the construction method thereof, the concrete terrace is in a normal pressed state, shrinkage cracks are reduced or eliminated, and the crack resistance of the terrace is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of floor construction, and in particular to a prestressed seamless floor and a construction method thereof. Background Art

[0002] With the advancement of my country's industrial construction, industrial buildings such as industrial plants and logistics warehouses have also put forward higher requirements for floors: large loads and large areas. The appearance of cracks in the floor will greatly reduce the bearing capacity of the structure; if structural joints are set in the floor, it may cause dust and mold to seriously affect the use function of the floor structure, threatening the safe operation of products such as medicines and food and large equipment. The cracks in the base concrete of the floor structure are the main cause of cracking of the surface layer. The pre-cut seams and cracks of the base concrete are very likely to cause reflective cracks in the surface layer. Considering the structural bearing capacity and use requirements, some large-span floors must not have cracks. In the prior art, seamless floor structures are mainly realized by steel fiber concrete and prestressed concrete. The steel fiber concrete floor structure can currently achieve a one-way size of 30m without seams, but it often suffers local damage characterized by the expansion of the main cracks during use, and the crack width is large, causing cracks in the surface layer. Although the currently common prestressed concrete floor structure can achieve no cutting seams, its process is complicated, the cost is high, and it is greatly affected by the properties of the concrete itself, making it difficult to promote and apply in practice.

[0003] Therefore, a prestressed seamless floor with simple process and strong environmental adaptability is urgently needed to solve the above-mentioned problems in the prior art, and further realize the durable and safe use of the prestressed seamless floor surface.

[0004] The above information disclosed in this Background section is only for enhancement of understanding of the background of the invention and therefore it may contain information that does not form the prior art that is already known to a person of ordinary skill in the art. Summary of the invention

[0005] The purpose of the present invention is to provide a prestressed seamless floor and a construction method thereof, so as to solve the technical problems that the existing prestressed seamless concrete floor structure has complex process, high cost, and is greatly affected by the properties of concrete itself, making it difficult to promote and apply in practice.

[0006] In order to achieve the above object, the present invention provides the following technical solutions:

[0007] A prestressed seamless floor comprises:

[0008] original ground;

[0009] A concrete cushion layer supported parallel to the original ground surface;

[0010] A glass fiber SBS self-adhesive moisture-proof layer is laid on the concrete cushion layer;

[0011] A dry sand isolation layer is spread on the glass fiber SBS self-adhesive moisture-proof layer;

[0012] PE film, laid on the dry sand isolation layer;

[0013] A side template is vertically mounted on the PE film;

[0014] An anchor seat, vertically fixed to the middle of the side edge of the edge template;

[0015] Metal corrugated pipe is used to protect the steel strands in the pipe and facilitate the later tensioning;

[0016] The steel strand is inserted into the metal corrugated tube and fixed to the anchor seat;

[0017] Concrete is poured on the PE film and between the side formworks.

[0018] A construction method for a prestressed seamless floor comprises the following steps:

[0019] S1. Compact the original soil surface in layers;

[0020] S2. pouring a concrete cushion layer on the original ground;

[0021] S3. Laying the glass fiber SBS self-adhesive moisture-proof layer on the concrete cushion;

[0022] S4. The dry sand isolation layer is evenly laid on the glass fiber SBS self-adhesive moisture-proof layer;

[0023] S5. PE film is laid on the dry sand isolation layer;

[0024] S6. The side formwork is installed around the prestressed floor; the anchor is installed on the side formwork;

[0025] S7. Cut the steel strands and insert them into the metal corrugated pipe;

[0026] S8. Arrangement and installation of the metal bellows;

[0027] S9. The steel strand is inserted into the anchor seat and the anchor seat is fixed to the edge template;

[0028] S10. Set up a steel reinforcement layer;

[0029] S11. Concrete pouring;

[0030] S12. After pouring concrete, the steel strands should be tensioned twice;

[0031] S13. After the tensioning is completed, grouting and anchoring of the metal bellows are performed;

[0032] S14. Pouring of post-cast joint.

[0033] In the above-mentioned construction method of prestressed seamless floor, in step S1, if the original ground soil is of poor quality, it needs to be replaced to ensure that the bearing capacity of the foundation is ≧100KPa / mm.

[0034] In the above-mentioned construction method of the prestressed seamless floor, in step S2, the flatness of the concrete cushion layer is controlled within the specification requirements.

[0035] In the above-mentioned construction method of the prestressed seamless floor, in step S3, the glass fiber SBS self-adhesive moisture-proof layer can effectively isolate the underground water vapor and ensure the dry environment of the floor.

[0036] In the above-mentioned construction method of the prestressed seamless floor, in step S4, the thickness of the dry sand isolation layer is 2 cm, and the water content of the sand is less than 5%.

[0037] In the construction method of the above-mentioned prestressed seamless floor, in step S5, the PE film is overlapped by hot-melt automatic welding, and the overlap width shall not be less than 80 mm. It is folded up to 200 mm on the prestressed floor surface at the walls and columns. A 20 mm thick extruded board shall be set beside the walls and columns to ensure that it is disconnected from the prestressed floor; the dry sand isolation layer and the PE film separate the connection between the prestressed floor and the base layer, reducing the influence of the base layer settlement on the prestressed floor.

[0038] In the above-mentioned construction method of the prestressed seamless floor, in step S6, the side formwork is made of plywood.

[0039] In the above-mentioned construction method of the prestressed seamless floor, in step S7, the steel strands are cut according to the length of the prestressed floor; the steel strands generally must not be less than four, and the length of the tensioning section must be reserved when cutting.

[0040] In the construction method of the above-mentioned prestressed seamless floor, in step S8, the metal corrugated pipe is evenly arranged on the PE film at an interval of 1.6m to 2.0m in the vertical and horizontal directions, an exhaust pipe is inserted into the metal corrugated pipe, ф20 PE grouting pipes are arranged at both ends of the metal corrugated pipe, the metal corrugated pipe is arranged in the middle of the prestressed floor with a pad, and 250mm wide A12@50 steel bars are arranged at the ends of the metal corrugated pipe.

[0041] In the above-mentioned construction method of the prestressed seamless floor, in step S9, the exposed steel strands are wrapped with a film to protect the steel strands from damage during subsequent construction.

[0042] In the above-mentioned construction method of the prestressed seamless floor, in step S10, a steel reinforcement layer is arranged within 300 mm of the floor edge to prevent the prestressed floor from cracking due to the maximum force on the end during the tensioning process.

[0043] In the construction method of the above-mentioned prestressed seamless floor, in step S11, the concrete pouring needs to be formed in one time and the flatness and surface quality must be strictly controlled. The prestressed floor is poured with concrete of not less than C40, the water-cement ratio of the concrete shall not be greater than 0.6, and the maximum particle size of the coarse aggregate shall not be greater than 30mm. Before pouring the floor, the metal component with fine-tuned elevation is fixed with concrete on the PE film at a spacing of 3m and the designed elevation; the lower part of the metal component has a "J"-shaped steel bar base, and a "U"-shaped steel bar is welded on the upper part. A nut is welded next to the "U"-shaped steel bar, and a screw is passed under the nut, and the elevation is fine-tuned with the screw. When pouring concrete, a laser level is used in conjunction with the metal component to control the aluminum alloy scraper to level the prestressed floor, and the floor flatness can be controlled within 2mm.

[0044] In the construction method of the above-mentioned prestressed seamless floor, in step S12, within 24 hours after the concrete is poured, a prestress of about 25% is applied for the first tensioning to control the shrinkage cracks of the early concrete; the second tensioning is when the concrete strength reaches 75% of the design value, and all the prestress is tensioned. During the initial tensioning, when it reaches 25% of the design stress, the tensioning is stopped immediately and the tensioning length is recorded; during the final tensioning, when it reaches 100% of the design stress, the tensioning is stopped immediately and the final elongation of the steel strand is measured. The actual value of the elongation needs to be controlled between -5% and +10%.

[0045] In the construction method of the above-mentioned prestressed seamless floor, in step S13, after the tensioning is completed, the excess steel strands are cut off, the grouting pipe is extended, the anchor seat is sealed with non-shrinkage mortar, and the metal corrugated pipe is immediately grouted. Before grouting, the slurry needs to be processed and grouting is carried out. The solid grouting can only be carried out after the grouting molding quality and strength meet the design requirements. The anchor can be sealed after the slurry overflows from the exhaust hole. If the length of the prestressed floor exceeds 100m, a grouting pipe can be set in the middle of the floor, and grouting is carried out from the middle to both ends.

[0046] In the above-mentioned construction method of the prestressed seamless floor, in step S14, the post-casting strip is poured 14 days after the completion of step S13.

[0047] In the above technical scheme, the present invention provides a prestressed seamless floor and a construction method thereof, which has the following beneficial effects:

[0048] Compared with the prior art, the present invention has a prestressed seamless floor in which the concrete slab is placed in a normal compressive state due to the active application of prestress, thereby reducing or eliminating shrinkage cracks and improving the bearing capacity and crack resistance of the floor. Prestressing improves the bending and tensile resistance of the floor, making it more resistant to adverse soil conditions and more adaptable to uneven settlement of the foundation. The construction process of the prestressed seamless floor in the present invention can reduce steel bars, reduce the thickness of concrete, speed up the construction speed, effectively reduce the cracking of the floor during use, improve the overall stability and durability of the ground, and almost no maintenance is required, saving maintenance costs; compared with the existing prestressed seamless floor, the construction process is simple and is less affected by the performance of the concrete itself. The prestressed seamless floor of the present invention can meet the high performance requirements of industrial buildings such as industrial plants and logistics warehouses for floors, and has broad application prospects in the field of industrial buildings. BRIEF DESCRIPTION OF THE DRAWINGS

[0049] Figure 1 An embodiment of the present invention provides a cross-sectional schematic diagram of a prestressed seamless floor.

[0050] Figure 2 A side schematic diagram of a prestressed seamless floor is provided for an embodiment of the present invention.

[0051] The accompanying drawings are marked as follows:

[0052] 1-concrete, 2-metal corrugated pipe, 3-steel strand, 4-PE film, 5-dry sand isolation layer, 6-glass fiber SBS self-adhesive moisture-proof layer, 7-concrete cushion, 8-original soil surface, 9-anchor seat, 10-side formwork. DETAILED DESCRIPTION

[0053] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention. Therefore, the following detailed description of the embodiments of the present invention provided in the drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention.

[0054] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.

[0055] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.

[0056] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the present invention, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.

[0057] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be directly connected or indirectly connected through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0058] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may include that the first and second features are in direct contact, or may include that the first and second features are not in direct contact but are in contact through another feature between them. Moreover, a first feature being "above", "above" and "above" a second feature includes that the first feature is directly above and obliquely above the second feature, or simply indicates that the first feature is higher in level than the second feature. A first feature being "below", "below" and "below" a second feature includes that the first feature is directly below and obliquely below the second feature, or simply indicates that the first feature is lower in level than the second feature.

[0059] In order to enable those skilled in the art to better understand the technical solution of the present invention, the present invention will be further described in detail below with reference to the accompanying drawings.

[0060] like Figure 1-2 As shown, a prestressed seamless floor comprises:

[0061] Original land surface 8,

[0062] A concrete cushion layer 7, which is supported parallel to the original ground surface 8;

[0063] The glass fiber SBS self-adhesive moisture-proof layer 6 is laid on the concrete cushion layer 7;

[0064] A dry sand isolation layer 5 is spread on the glass fiber SBS self-adhesive moisture-proof layer 6;

[0065] PE film 4, laid on the dry sand isolation layer 5;

[0066] The side template 10 is vertically mounted on the PE film 4;

[0067] Anchor seat 9, vertically fixed to the middle of the side edge of edge template 10;

[0068] Metal corrugated tube 2, used to protect the steel strand 3 in the tube for later tensioning;

[0069] The steel strand 3 is inserted into the metal corrugated tube 2 and fixed to the anchor seat 9;

[0070] Concrete 1 is poured on the PE film 4 and between the side templates 10.

[0071] A construction method for a prestressed seamless floor comprises the following steps:

[0072] S1. Compact the original ground surface layer by layer. If the original ground surface is of poor quality, it needs to be replaced to ensure that the bearing capacity of the foundation is ≥100KPa / mm.

[0073] S2. Pour a concrete cushion layer 7 on the original ground surface 8, and control its flatness within the specification requirements.

[0074] S3. Lay the glass fiber SBS self-adhesive moisture-proof layer 6 on the concrete cushion layer 7. The glass fiber SBS self-adhesive moisture-proof layer can effectively isolate the underground water vapor and ensure the dry environment of the floor.

[0075] S4. The dry sand isolation layer 5 is evenly laid on the glass fiber SBS self-adhesive moisture-proof layer 6, with a thickness of 2 cm and a sand moisture content of less than 5%.

[0076] S5. PE film 4 is laid on the dry sand isolation layer 5. The overlap of PE film 4 is hot-melt automatic welding, and the overlap width shall not be less than 80mm. It is turned up to 200mm above the prestressed floor surface at the wall and column. A 20mm thick extruded board shall be set beside the wall and column to ensure that it is disconnected from the prestressed floor. The dry sand isolation layer 5 and PE film 4 cut off the connection between the prestressed floor and the base layer, reducing the impact of the base layer settlement on the prestressed floor.

[0077] S6. The edge formwork 10 is installed around the prestressed floor; the anchor seat 9 is installed on the edge formwork 10. The edge formwork 10 is made of plywood.

[0078] S7. Cut the steel strands 3 according to the length of the prestressed floor and insert them into the metal corrugated pipe 2. Generally, there should be no less than four steel strands 3, and the length of the tensioning section should be reserved when cutting.

[0079] S8. Laying out and installing the metal corrugated pipe 2. The metal corrugated pipe 2 is evenly arranged on the PE film 4 at a spacing of 1.6m to 2.0m in the vertical and horizontal directions. The exhaust pipe is inserted into the metal corrugated pipe 2. ф20 PE grouting pipes are arranged at both ends of the metal corrugated pipe 2. The metal corrugated pipe 2 is arranged in the middle of the prestressed floor with a pad. A 250mm wide A12@50 steel bar is arranged at the end of the metal corrugated pipe.

[0080] S9. The steel strand 3 is inserted into the anchor seat 9 and the anchor seat 9 is fixed to the side template 10. The exposed steel strand 3 is wrapped with a film to protect the steel strand 3 from damage in subsequent construction.

[0081] S10. Set up a steel reinforcement layer. Set up a steel reinforcement layer within 300mm of the floor edge to prevent the prestressed floor from cracking due to the maximum force on the end during the tensioning process.

[0082] S11. Concrete pouring. Concrete pouring needs to be formed in one step and the flatness and surface quality must be strictly controlled. Prestressed floor is poured with concrete 1 not less than C40, the water-cement ratio of concrete 1 shall not be greater than 0.6, and the maximum particle size of coarse aggregate shall not be greater than 30mm. Before pouring the floor, the metal components with fine-tuning elevation are fixed with concrete on the PE film 4 at a spacing of 3m and the designed elevation; the metal components have a "J"-shaped steel bar base at the bottom, and "U"-shaped steel bars are welded on the top. A nut is welded next to the "U"-shaped steel bar, and a screw is passed under the nut, and the elevation is fine-tuned with the screw. When pouring concrete, a laser level is used in conjunction with the metal components to control the aluminum alloy scraper to level the prestressed floor, and the floor flatness can be controlled within 2mm.

[0083] S12. After pouring concrete 1, the steel strand 3 should be tensioned twice. Within 24 hours after pouring concrete 1, apply about 25% prestress for the first tensioning to control the shrinkage cracks of early concrete; the second tensioning is when the strength of concrete 1 reaches 75% of the design value, and all prestress is tensioned. During the initial tensioning, when the design stress reaches 25%, the tensioning should be stopped immediately, and the tensioning length should be recorded; during the final tensioning, when the design stress reaches 100%, the tensioning should be stopped immediately, and the final elongation of the steel strand 3 should be measured. The actual value of the elongation should be controlled between -5% and +10%.

[0084] S13. After tensioning is completed, grouting and anchoring are performed on the metal corrugated pipe 2. After tensioning is completed, the excess steel strands are cut off, the grouting pipe is extended, the anchor seat is sealed with non-shrinkage mortar, and the metal corrugated pipe is immediately grouted. Before grouting, the slurry needs to be grouted by process. The solid grouting can only be performed after the grouting molding quality and strength meet the design requirements. The anchoring can be performed after the slurry overflows from the exhaust hole. If the length of the prestressed floor exceeds 100m, a grouting pipe can be set in the middle of the floor, and grouting can be performed from the middle to both ends.

[0085] S14. Casting of post-casting strips. 14 days after step S13 is completed, casting of post-casting strips is performed.

[0086] Finally, it should be noted that the described embodiments are only part of the embodiments of the present application, rather than all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by those skilled in the art without making any creative work are within the scope of protection of the present application.

[0087] The above description is only by way of illustration of certain exemplary embodiments of the present invention. It is undoubted that those skilled in the art can modify the described embodiments in various ways without departing from the spirit and scope of the present invention. Therefore, the above drawings and descriptions are illustrative in nature and should not be construed as limiting the scope of protection of the claims of the present invention.

Claims

1. A prestressed seamless floor, comprising: original ground(8); A concrete cushion layer (7) supported parallel to the original ground surface (8); A glass fiber SBS self-adhesive moisture-proof layer (6) is laid on the concrete cushion layer (7); A dry sand isolation layer (5) is spread on the glass fiber SBS self-adhesive moisture-proof layer (6); A PE film (4) is laid on the dry sand isolation layer (5); A side template (10) is vertically mounted on the PE film (4); An anchor seat (9) is vertically fixed to the middle of the side edge of the edge template (10); The metal corrugated tube (2) is used to protect the steel strands (3) in the tube and facilitate the subsequent tensioning; A steel strand (3) is inserted into the metal corrugated tube (2) and fixed to the anchor seat (9); Concrete (1) is poured on the PE film (4) and between the side templates (10).

2. A construction method for the prestressed seamless floor according to claim 1, comprising the following steps: S1. compacting the original soil surface (8) in layers; S2. pouring a concrete cushion layer (7) on the original soil surface (8); S3. Laying the glass fiber SBS self-adhesive moisture-proof layer (6) on the concrete cushion layer (7); S4. The dry sand isolation layer (5) is evenly laid on the glass fiber SBS self-adhesive moisture-proof layer (6); S5. The PE film (4) is laid on the dry sand isolation layer (5); S6. The side template (10) is installed around the prestressed floor; the anchor seat (9) is installed on the side template (10); S7. The steel strand (3) is cut and inserted into the metal bellows (2); S8. The metal bellows (2) is laid out and installed; S9. The steel strand (3) is inserted into the anchor seat (9) and the anchor seat (9) is fixed to the side mold plate (10); S10. Set up a steel reinforcement layer; S11. Concrete (1) pouring; S12. After pouring the concrete (1), the steel strand (3) should be tensioned twice; S13. After the tensioning is completed, the metal bellows (2) is grouted and anchored; S14. Pouring of post-cast joint.

3. The construction method of the prestressed seamless floor according to claim 2 is characterized in that: In step S1, when the original ground surface (8) has poor soil quality and needs to be replaced, the bearing capacity of the foundation should be guaranteed to be ≧100KPa / mm; In step S2, the flatness of the concrete cushion layer (7) is controlled within the specification requirements; In step S4, the thickness of the dry sand isolation layer (5) is 2 cm, and the water content of the sand is less than 5%.

4. The construction method of the prestressed seamless floor according to claim 2 or 3 is characterized in that: In step S5, the PE film (4) is overlapped by hot-melt automatic welding, and the overlap width shall not be less than 80 mm. It is folded up to 200 mm on the prestressed floor surface at the wall and column, and a 20 mm thick extruded board is required to be set beside the wall and column; the dry sand isolation layer (5) and the PE film separate the connection between the prestressed floor and the base layer.

5. The construction method of the prestressed seamless floor according to claim 4 is characterized in that: In step S7, the steel strands (3) are cut according to the length of the prestressed floor; the number of the steel strands (3) is no less than four, and the length of the tensioning section is reserved when cutting.

6. The construction method of the prestressed seamless floor according to claim 4 is characterized in that: In step S8, the metal corrugated pipe (2) is evenly arranged on the PE film (4) at intervals of 1.6m to 2.0m in the vertical and horizontal directions, an exhaust pipe is inserted into the metal corrugated pipe (2), ф20 PE grouting pipes are arranged at both ends of the metal corrugated pipe (2), the metal corrugated pipe (2) is arranged in the middle of the prestressed floor with a pad, and 250mm wide A12@50 steel bars are arranged at the ends of the metal corrugated pipe.

7. The construction method of the prestressed seamless floor according to claim 6 is characterized in that: In step S9, the exposed steel strand (3) is wrapped with a film; In step S10, a steel reinforcement layer is provided within 300 mm of the floor edge.

8. The construction method of the prestressed seamless floor according to claim 7 is characterized in that: In step S11, the concrete (1) is poured once and the flatness and surface finish are strictly controlled; the prestressed floor is poured with concrete of not less than C40, the water-cement ratio of the concrete shall not be greater than 0.6, and the maximum particle size of the coarse aggregate shall not be greater than 30 mm; before pouring the floor, a metal component with a fine-adjustable elevation is fixed with concrete on the PE film (4) at a spacing of 3 m and a designed elevation; the lower part of the metal component is a "J"-shaped steel bar base, and a "U"-shaped steel bar is welded on the upper part. A nut is welded next to the "U"-shaped steel bar, and a screw is passed under the nut, and the elevation is fine-tuned with the screw; when pouring concrete, a laser level is used in conjunction with the metal component to control the aluminum alloy scraper to level the prestressed floor, and the floor flatness is controlled within 2 mm.

9. The construction method of the prestressed seamless floor according to claim 8 is characterized in that: In step S12, within 24 hours after the concrete (1) is poured, a prestress of about 25% is applied for the first tensioning to control the shrinkage cracks of the early concrete; the second tensioning is when the concrete strength reaches 75% of the design value, and all the prestress is tensioned; during the initial tensioning, when the design stress reaches 25%, the tensioning is stopped immediately and the tensioning length is recorded; During final tensioning, when the design stress reaches 100%, the tensioning is stopped immediately and the final elongation of the steel strand is measured. The actual value of the elongation is controlled between -5% and +10%.

10. The construction method of the prestressed seamless floor according to claim 9 is characterized in that: In step S13, after the tensioning is completed, the excess steel strands (3) are cut off, the grouting pipe is extended, the anchor seat is sealed with non-shrinkage mortar, and the metal corrugated pipe (2) is immediately grouted. Before grouting, the slurry is subjected to process grouting. After the grouting molding quality and strength meet the design requirements, the solid grouting is carried out. When the slurry overflows from the exhaust hole, the anchor is sealed. When the length of the prestressed floor exceeds 100m, a grouting pipe is set in the middle of the floor, and grouting is carried out from the middle to both ends.