Shield grinding diaphragm wall construction method

Through the shield grinding ground wall construction method without thrust + in-situ rotation, combined with soft-soil cutting board and reinforcement area construction, the problem of cutting reinforced concrete enclosure piles in existing subway stations in the existing technology is solved, and the problem of cutting reinforced concrete enclosure piles in existing subway stations is realized. The safe passage of the shield machine and effective structure maintenance reduce tool wear and control structural settlement.

CN118933823APending Publication Date: 2024-11-12CHINA RAILWEY ENG SERVICE CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411006392.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-25
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

The existing technology is difficult to efficiently and safely deal with the pile foundations of underground obstacles within the subway shield under the circuit, especially the cutting of reinforced concrete enclosure piles at existing subway stations, and conventional shield machines lack the ability to cut piles. , a complete technical solution system has not been formed.

Method used

Adopt the shield grinding ground wall construction method with no thrust + in-place rotation. Through the construction of soft-soil cutting board and reinforcement area, combined with grouting control, the maintenance and repair of underground walls of existing operating lines can be achieved, and tools can be reduced. Wear to ensure that the shield machine passes through the existing wall and controls the settlement of the structure.

Benefits of technology

Effective maintenance and waterproofing of existing subway stations and surrounding buildings has been achieved, tool wear has been reduced, shield mechanisms have been ensured safely through existing walls, and settlement of structures and buildings has been effectively controlled.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933823A_ABST
    Figure CN118933823A_ABST
Patent Text Reader

Abstract

The invention relates to a shield grinding diaphragm wall construction method. The method comprises the following steps that model selection and transformation are conducted on a shield tunneling machine cutterhead, wherein the cutterhead is a soft soil type cutterhead; reinforcing area construction; wall grinding construction of the shield tunneling machine is conducted, specifically, the thrust, the rotating speed and the propelling speed are gradually reduced from the position, 1200-1300 mm away from the diaphragm wall, of the shield tunneling machine; after the cutter head of the shield tunneling machine reaches the diaphragm wall, the rotating speed of the cutter head is 0.8-1.2 r / min, and the thrust is within 3000t; the cutterhead rotates for 4-5r in situ every time the cutterhead advances by 1-2mm; grouting in the construction process comprises shield grouting, synchronous grouting and secondary grouting. According to the shield grinding diaphragm wall construction method, the hob-free soft soil type cutterhead is adopted, the rotating speed, the penetration degree and the thrust of the cutterhead are controlled in the construction process, steel bars can be better cut, cutter abrasion can be better reduced, the underground diaphragm wall of an existing operation line can be maintained, a shield tunneling machine can smoothly pass through the existing diaphragm wall, and the service life of the shield tunneling machine is prolonged. And timely and effective repair and water prevention can be realized, and settlement of the existing running station structure and the integral ballast bed and settlement of surrounding buildings are controlled.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of shield construction, in particular to a shield grinding ground-connected wall construction method. Background Art

[0002] For subway construction, its tunnel construction methods are constantly updated. Due to insufficient consideration in the early stage, some urban construction inevitably conflicts with new construction methods and processes. At present, the treatment of underground obstacle pile foundations within the scope of the subway shield underpass is generally carried out by pulling piles on the ground, drilling piles after excavating shafts, and replacing pile foundations. In related technologies, the direct cutting of existing subway station retaining piles by shields is affected by multiple factors, and conventional shield machines do not have the ability to cut piles, and a complete technical solution system has not yet been formed. Therefore, developing an efficient and safe method for shield cutting of existing reinforced concrete retaining piles of subway stations has become a construction problem that needs to be solved urgently. Summary of the invention

[0003] The present invention aims to solve at least one of the technical problems in the related art to a certain extent. To this end, the embodiment of the present invention proposes a shield grinding ground tether wall construction method, which adopts a no-thrust + in-situ rotation method to better cut the steel bars and better reduce the wear of the tool, and can realize the maintenance of the underground tether wall of the existing running line, so that the shield machine can smoothly pass through the existing tether wall, and can also repair and waterproof more timely and effectively, and combined with the grouting during the construction process, it controls the settlement of the existing running station structure and the integral roadbed and the settlement of surrounding buildings.

[0004] The shield grinding ground-connected wall construction method according to the embodiment of the present invention comprises the following steps:

[0005] S1, select and transform the shield machine cutterhead: the cutterhead adopts a soft soil cutterhead with an opening rate of 40%-50%;

[0006] S2, reinforcement area construction: reinforcement is carried out in the area adjacent to the existing ground connection wall in the tunnel path to form a reinforcement area;

[0007] S3, shield machine wall grinding construction:

[0008] S31, the shield machine starts to gradually reduce the thrust, rotation speed and propulsion speed when it is 1200-1300mm away from the ground-connected wall;

[0009] S32, after the shield machine cutterhead reaches the ground-connected wall, the cutterhead speed is 0.8-1.2r / min, and the thrust is within 3000t; for every 1-2mm forward movement, the cutterhead rotates 4-5r in place;

[0010] S4, grouting during construction:

[0011] S41, shield grouting: injecting grouting effect into the periphery of the excavated tunnel to fill the pores created by the excavation;

[0012] S42, synchronous grouting: synchronous grouting volume 6.5m 3 / ring, grouting pressure is 3-4bar;

[0013] S43, secondary grouting: secondary grouting is carried out on the fifth ring behind the current propulsion ring, with a grouting pressure of 0.3-0.4MPa and a grouting volume of 0.8-1.0m 3 / ring.

[0014] The shield grinding underground diaphragm wall construction method of the embodiment of the present invention adopts a soft soil cutterhead without a roller cutter, controls the cutterhead rotation speed, penetration and thrust during construction, and adopts a no-thrust + in-situ rotation method to better cut the steel bars and better reduce the tool wear. It can realize the maintenance of the underground diaphragm of the existing operating line, enable the shield machine to pass through the existing diaphragm smoothly, and can also repair and waterproof more timely and effectively. In addition, combined with the grouting during the construction process, it controls the settlement of the existing operating station structure and the integral roadbed and the settlement of surrounding buildings.

[0015] In some embodiments, in S1, the knife disc is equipped with a center shell knife, a high shell knife, a low shell knife, a cutting knife, a diameter protection knife, an edge cutting knife and a super digging knife. The distance between two adjacent high shell knives is 300mm or 150mm, and the distance between two adjacent low shell knives is 300mm or 150mm. Some of the high shell knives and some of the low shell knives are staggered.

[0016] In some embodiments, in S1, the opening rate of the blade disc is 46%.

[0017] In some embodiments, in S2, during the construction of the reinforcement area, MJS large-diameter high-pressure rotary jet piles are used for reinforcement at the cutterhead of the corresponding shield machine. The reinforcement range is 3m on the left and right and 3m on the top and bottom of the corresponding shield machine outer skin, and the length along the tunnel direction is 6m.

[0018] In some embodiments, in S2, the MJS large-diameter high-pressure jet grouting piles are set to have 48 Pile, 11 Pile, effective pile length 12.6m.

[0019] In some embodiments, in S31, during the period from when the shield machine is 1200 mm in front of the ground-connected wall to when the cutter head contacts the ground-connected wall, the construction parameters are as follows: soil pressure: 1.9-2.0 bar, advancement speed: 2-5 mm / min, cutter head rotation speed: 0.7-0.8 rpm, cutter head torque: 1000-1500 kN·m.

[0020] In some embodiments, in S32, high-concentration bentonite is simultaneously added to the soil bin of the shield machine to fill the bin for excavation, and the construction parameters are as follows: soil pressure: 1.9-2.0 bar, propulsion speed: 0-2 mm / min, the shield machine is started in low penetration mode, the cutter head speed: 0.8 r / min; the cutter head torque: 2000-3500 kN·m.

[0021] In some embodiments, in S32, inert mortar is added to the soil bin of the shield machine, and the slurry setting time is not less than 12 hours.

[0022] In some embodiments, in S42, the slurry parameters are as follows: cement content ≥ 120 kg / m 3 , consistency ≤11cm, 1-day strength ≥0.2MPa, 28-day strength ≥2.5MPa, consolidation shrinkage and decantation rate <5%, slurry bleeding rate <3%, initial setting time 4-6h.

[0023] In some embodiments, in S3, water and bentonite are used to lubricate and cool the cutter disc and the cutter; and / or, in S43, cement-water glass double liquid slurry is used for secondary grouting. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 is a schematic structural diagram of a cutter disc according to an embodiment of the present invention;

[0025] Figure 2 It is a schematic diagram of the trajectory of the high shell knife and the low shell knife;

[0026] Figure 3 is a schematic diagram of the tunnel path through the existing ground-connected wall.

[0027] Reference numerals:

[0028] The tunnel path is 1, the existing ground-connected wall is 2, and the jet-jet pile is 3;

[0029] The knife disc 4 includes a center shell knife 41 , a high shell knife 42 , a low shell knife 43 , a cutting knife 44 , and a side cutting knife 45 . DETAILED DESCRIPTION

[0030] Embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings. The embodiments described below with reference to the accompanying drawings are exemplary and intended to be used to explain the present invention, but should not be understood as limiting the present invention.

[0031] The shield grinding ground-connected wall construction method according to the embodiment of the present invention comprises the following steps:

[0032] S1, select and transform the shield machine cutterhead: the cutterhead adopts a soft soil cutterhead, a soft soil cutterhead house roller, and an opening rate of 40%-50%, that is, the opening area of ​​the cutterhead accounts for 40%-50% of the total area of ​​the cutterhead.

[0033] S2, reinforcement area construction: The area adjacent to the existing ground-connected wall in the tunnel path is reinforced to form a reinforcement area. The tunnel path is the path that needs to be excavated. Before the shield machine reaches the existing ground-connected wall, the area of ​​the existing ground-connected wall that needs to be crossed is reinforced.

[0034] S3, shield machine wall grinding construction:

[0035] S31, the shield machine starts to gradually reduce the thrust, cutterhead speed and propulsion speed when it is 1200-1300mm away from the ground-connected wall;

[0036] S32, after the shield machine cutterhead reaches the ground-connected wall, the cutterhead speed is 0.8-1.2r / min, and the thrust is within 3000t; for every 1-2mm forward movement, the cutterhead rotates 4-5r in place;

[0037] S4, grouting during construction:

[0038] S41, shield grouting: injecting grouting effect into the periphery of the excavated tunnel to fill the pores created by the excavation;

[0039] S42, synchronous grouting: synchronous grouting volume 6.5m 3 / ring, grouting pressure is 3-4bar;

[0040] S43, secondary grouting: secondary grouting is performed on the fifth ring behind the current propulsion ring, with a grouting pressure of 0.3-0.4MPa and a grouting volume of 0.8-1.0m 3 / ring;

[0041] S5, construction monitoring.

[0042] The shield grinding ground-connected wall construction method of the embodiment of the present invention adopts a soft soil cutterhead without a roller to grind the existing ground-connected wall and the steel bars in the ground-connected wall. During the construction, the cutterhead rotation speed, penetration and thrust are controlled. The no-thrust + in-situ rotation method can better cut the steel bars and better reduce the tool wear; the cutterhead opening rate is larger than the opening rate of a conventional earth pressure shield machine, which is convenient for the steel bars to pass through the cutterhead into the soil bin; the area adjacent to the existing ground-connected wall in the tunnel path is reinforced to form a reinforced area, which can realize the maintenance of the underground connecting wall of the existing operating line, enable the shield machine to pass through the existing connecting wall smoothly, and can also repair and waterproof more timely and effectively, and combined with the grouting during the construction process, the settlement of the existing operating station structure and the integral roadbed and the settlement of surrounding buildings are controlled.

[0043] Further, in S1, the cutter disc is equipped with a center shell cutter, a high shell cutter, a low shell cutter, a cutting cutter, a diameter protection cutter, an edge cutting cutter and an over-digging cutter. Figure 1 and Figure 2 As shown, the distance between two adjacent high shell knives is 300mm or 150mm, the distance between two adjacent low shell knives is 300mm or 150mm, and some high shell knives and some low shell knives are arranged alternately. Figure 1 As shown, a portion of high shell knives and a portion of low shell knives are arranged in the radial direction of the cutter disc. The portion of high shell knives and the portion of low shell knives are staggered, which is conducive to cutting steel bars. When cutting steel bars, it can ensure that the steel bars are subjected to multiple staggered forces in various places, thereby extending the life of the tool and cutting the steel bars into multiple small sections to avoid the steel bars being too large in volume after cutting and causing them to get stuck in the soil bin spiral machine and other parts.

[0044] Specifically, the number and parameters of the center shell cutter, high shell cutter, low shell cutter, cutter, gauge cutter, edge cutter and super digging cutter are shown in Table 1. Figure 1 As shown in the figure, the over-digging amount of the over-digging tool is 50mm.

[0045] Table 1 Tool quantity and parameters

[0046]

[0047] Furthermore, increasing the number and height of raised shell knives and low shell knives and reducing the distance between knives will help improve the cutting of steel bars by the cutter disc.

[0048] Specifically, the cutterhead opening rate is 46%. The total weight of the cutterhead is about 47t, and the support method is central support. The cutterhead diameter of the shield machine is φ6860, and the tail shield diameter is 6810. The cutterhead excavates the tunnel in full section with an excavation diameter of Φ6860mm. The cutterhead can rotate in both directions to discharge slag. The normal service life of the cutterhead is more than 10km.

[0049] In some embodiments, before the shield machine wall grinding construction, the screw conveyor supporting the shield machine is modified. The drive mode of the screw conveyor is rear center drive. During excavation, the excavated soil from the cutter head falls to the bottom of the soil compartment and is transported to the belt conveyor through the screw conveyor. The screw conveyor is provided with 5 inspection doors on the cylinder, 2 of which are hydraulic inspection doors and 3 are manual inspection doors. When necessary, the inspection doors can be opened to clean the soil stuck between the spiral blades. There are 8 injection ports arranged on the screw machine cylinder, and bentonite or foam can be injected through these holes to improve the fluidity of the soil. The normal service life of the screw conveyor is greater than 10,000 hours.

[0050] The surfaces of the first three blade sections and the shaft of the screw shaft of the screw conveyor are welded with a 5mm thick wear-resistant layer; wear-resistant alloy blocks are welded around the periphery of the first three blade sections, and the bottom sleeve, fixed section, and slag discharge door cylinder of the screw conveyor are welded with a 5mm thick wear-resistant layer.

[0051] Furthermore, in S2, during the construction of the reinforcement area, MJS large-diameter high-pressure jet grouting piles were used to reinforce the corresponding shield machine cutterhead. The reinforcement range was 3m on the left and right sides of the corresponding shield machine skin, 3m on the top and bottom, and 6m in length along the tunnel direction. The length along the tunnel direction was 6m, that is, along the forward direction of the shield machine, the front and rear distance of the reinforcement area was 6m. When the shield machine was at least 6m away from the existing ground-connected wall, the reinforcement of the reinforcement area was completed. Figure 3 , which is a schematic diagram of a tunnel path passing through an existing ground-anchored wall, wherein the tunnel path is 1, the existing ground-anchored wall is 2, and the jet-jet pile is 3.

[0052] In S2, there are 48 MJS large-diameter high-pressure jet grouting piles installed. Pile, 11 Pile, effective pile length 12.6m.

[0053] In S3, water and bentonite are used to lubricate and cool the cutter disc and the tool. Using water and bentonite not only cools the cutter disc and the tool, but also reduces the wear of the cutter disc and the tool. The cutter disc should be frequently reversed to prevent the cutter disc from rotating in the same direction for a long time, which may cause one-way friction of the steel bar and make it difficult to start in the opposite direction.

[0054] Furthermore, in S31, during the period from when the shield machine is 1200 mm in front of the ground-connected wall to when the cutterhead contacts the ground-connected wall, the construction parameters are as follows: soil pressure: 1.9-2.0 bar, advancement speed: 2-5 mm / min, cutterhead rotation speed: 0.7-0.8 rpm, and cutterhead torque: 1000-1500 kN·m.

[0055] Furthermore, in S32, high-concentration bentonite is added to the soil bin of the shield machine for tunneling. The construction parameters are as follows: soil pressure: 1.9-2.0 bar, advancement speed: 0-2 mm / min, start the shield machine low penetration mode, cutter head speed: 0.8 r / min; cutter head torque: 2000-3500 kN·m.

[0056] It is strictly forbidden to make excessive corrections while the shield machine is passing through the ground-connected wall.

[0057] In S32, inert mortar is added to the soil bin of the shield machine, and the slurry setting time is not less than 12 hours. Adding inert mortar to the soil bin increases the suspension and fluidity of the materials in the soil bin, thereby ensuring that the steel bars and concrete blocks entering the soil bin can better enter the screw machine.

[0058] Specifically, the inert mortar adopts commercial mortar.

[0059] Furthermore, high molecular polymers are added to the inert mortar to increase the suspension rate and fluidity of the slurry in the bin, preventing large-scale deposition of steel bars and concrete blocks or causing poor slag discharge, so as to facilitate subsequent soil removal and construction operations.

[0060] After the tail of the shield machine passes through the ground-connected wall, a water-stop ring is promptly constructed again in the reinforced area and the ground-connected wall to cut off the water coming from the rear.

[0061] In S41, shield grouting: injecting mud effect around the excavated tunnel to fill the pores created by the excavation, which can reduce the natural settlement of the upper covering soil. The diameter of the shield cutter head is φ6860, the diameter of the tail shield is 6810, the filling rate is controlled at 120%, and the filling volume of each ring is 0.77m 3 , grouting pressure 2.0-2.5bar, reducing the natural settlement of the upper covering soil.

[0062] In S42, the parameters of the synchronous grouting slurry are as follows: cement content ≥ 120kg / m 3 , consistency ≤11cm, 1-day strength ≥0.2MPa, 28-day strength ≥2.5MPa, consolidation shrinkage and decantation rate <5%, slurry bleeding rate <3%, initial setting time 4-6h. According to the excavation and control of the risk source section in the early stage, the injection pressure is 3-4bar, and the grouting volume per ring is maintained at 6.5m 3 , which can meet the settlement control requirements.

[0063] In S43, cement-water glass double liquid slurry is used for secondary grouting, and secondary grouting is carried out in small amounts and multiple times to avoid disturbing the soil above.

[0064] In S5, the monitoring and control measures for construction monitoring are as follows: use an automatic detection total station to detect the settlement and differential settlement of the tunnel structure and track structure, with a detection frequency of 1 hour / time, combined with manual monitoring of the settlement and differential settlement of the tunnel structure and track structure, regular changes, and track height difference changes, with a manual detection frequency of 3 times / week.

[0065] In the description of the present invention, it is to be understood that the terms “center”, “longitudinal”, “lateral”, “length”, “width”, “thickness”, “up”, “down”, “front”, “back”, “left”, “right”, “vertical”, “horizontal”, “top”, “bottom”, “inside”, “outside”, “clockwise”, “counterclockwise”, “axial”, “radial”, “circumferential”, etc., indicating orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the present invention.

[0066] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of the present invention, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.

[0067] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral one; it can be a mechanical connection, an electrical connection, or communication with each other; it can be a direct connection, or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0068] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being "above", "above" or "above" a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being "below", "below" or "below" a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.

[0069] In the present invention, the terms "one embodiment", "some embodiments", "examples", "specific examples", or "some examples" etc. mean that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the described specific features, structures, materials or characteristics may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.

[0070] Although the embodiments of the present invention have been shown and described above, it is to be understood that the above embodiments are exemplary and are not to be construed as limitations of the present invention. A person skilled in the art may change, modify, replace and vary the above embodiments within the scope of the present invention.

Claims

1. Construction method of shield grinding ground-connected wall, It is characterized in that The following steps are involved: S1, select and transform the shield machine cutterhead: the cutterhead adopts a soft soil cutterhead with an opening rate of 40%-50%; S2, reinforcement area construction: reinforcement is carried out in the area adjacent to the existing ground connection wall in the tunnel path to form a reinforcement area; S3, shield machine wall grinding construction: S31, the shield machine starts to gradually reduce the thrust, rotation speed and propulsion speed when it is 1200-1300mm away from the ground-connected wall; S32, after the shield machine cutterhead reaches the ground-connected wall, the cutterhead speed is 0.8-1.2r / min, and the thrust is within 3000t; for every 1-2mm forward movement, the cutterhead rotates 4-5r in place; S4, grouting during construction: S41, shield grouting: injecting grouting effect into the periphery of the excavated tunnel to fill the pores created by the excavation; S42, synchronous grouting: synchronous grouting volume 6.5m 3 / ring, grouting pressure is 3-4bar; S43, secondary grouting: secondary grouting is carried out on the fifth ring behind the current propulsion ring, with a grouting pressure of 0.3-0.4MPa and a grouting volume of 0.8-1.0m 3 / ring.

2. The shield grinding ground-connected wall construction method according to claim 1, It is characterized in that In S1, the knife disc is equipped with a center shell knife, a high shell knife, a low shell knife, a cutting knife, a diameter protection knife, an edge cutting knife and a super digging knife. The distance between two adjacent high shell knives is 300mm or 150mm, the distance between two adjacent low shell knives is 300mm or 150mm, and some of the high shell knives and some of the low shell knives are staggered.

3. The shield grinding ground-connected wall construction method according to claim 1, It is characterized in that In S1, the opening ratio of the cutter disc is 46%.

4. The shield grinding ground-connected wall construction method according to claim 1, It is characterized in that In S2, during the construction of the reinforcement area, MJS large-diameter high-pressure rotary jet piles were used to reinforce the cutterhead of the corresponding shield machine. The reinforcement range was 3m on the left and right and 3m on the top and bottom of the corresponding shield machine outer skin, and 6m in length along the tunnel direction.

5. The shield grinding ground-connected wall construction method according to claim 4, It is characterized in that In S2, there are 48 MJS large-diameter high-pressure jet grouting piles installed. Pile, 11 Pile, effective pile length 12.6m.

6. The shield grinding ground-connected wall construction method according to claim 1, It is characterized in that In S31, during the period from when the shield machine is 1200 mm in front of the ground-connected wall to when the cutterhead contacts the ground-connected wall, the construction parameters are as follows: soil pressure: 1.9-2.0 bar, advancement speed: 2-5 mm / min, cutterhead rotation speed: 0.7-0.8 rpm, cutterhead torque: 1000-1500 kN·m.

7. The shield grinding ground-connected wall construction method according to claim 1, It is characterized in that In S32, high-concentration bentonite is added to the soil bin of the shield machine to complete the tunneling, and the construction parameters are as follows: soil pressure: 1.9-2.0 bar, advancement speed: 0-2 mm / min, the shield machine is started in low penetration mode, and the cutter head speed is 0.8 r / min; Cutter torque: 2000-3500 kN·m.

8. The shield grinding ground-connected wall construction method according to claim 1, It is characterized in that In S32, inert mortar is added to the soil bin of the shield machine, and the slurry setting time is not less than 12 hours.

9. The shield grinding ground-connected wall construction method according to claim 1, It is characterized in that In S42, the slurry parameters are as follows: cement content ≥ 120kg / m 3 , consistency ≤11cm, 1-day strength ≥0.2MPa, 28-day strength ≥2.5MPa, consolidation shrinkage and decantation rate <5%, slurry bleeding rate <3%, initial setting time 4-6h.

10. The shield grinding ground-connected wall construction method according to claim 1, It is characterized in that In S3, water and bentonite are used to lubricate and cool the cutter head and the cutter; and / or, in S43, cement-water glass double liquid slurry is used for secondary grouting.