Construction method of water diversion port of water delivery tunnel

By establishing a support system in the construction of water transmission tunnels, determining excavation methods and support parameters, conducting hollow grouting anchor construction, installing reinforced mesh and concrete jets, the construction safety of complex groundwater types and geological environments is solved and The efficiency issue has achieved improvements in construction safety and quality.

CN118933898APending Publication Date: 2024-11-12CHINA RAILWAY CONSTR BRIDGE ENG BUREAU GRP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411258307.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-09
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

During the construction of water transfer tunnels, the complex groundwater type and geological environment lead to low safety and efficiency of water separator construction, and the existing technology fails to effectively ensure the normal progress of construction.

Method used

A construction method is adopted, including establishing a support system before excavation, determining the excavation method and support parameters, carrying out water separation construction, hollow grouting anchor construction, installing a steel mesh, conducting steel support construction, and finally conducting concrete Injection to ensure the safety and quality of construction.

Benefits of technology

Under the complex groundwater type and geological environment, the safety and efficiency of construction have been improved, ensuring the quality of the tunnel.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933898A_ABST
    Figure CN118933898A_ABST
Patent Text Reader

Abstract

The invention discloses a construction method of a water diversion port of a water delivery tunnel. The construction method comprises the following steps that (1) a supporting system before excavation is built; 2) determining an excavation mode and support parameters; (3) water diversion port construction is conducted; (4) hollow grouting anchor rods are installed; the construction method provided by the invention aims at the construction of the water diversion port of the water delivery tunnel, can guarantee the safe and normal implementation of the construction under the complex underground water type and complex geological environment, and can guarantee the construction efficiency and the tunnel quality.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of tunnel construction methods, and in particular to a construction method for a water diversion outlet of a water delivery tunnel. Background Art

[0002] During the construction of the water conveyance tunnel, in order to ensure the safety of water diversion and water delivery, combined with the dispatching and operation of the water conveyance project, the upstream water level and water delivery flow rate are reasonably adjusted to meet the needs of water diversion or withdrawal, water flow cutoff, and maintenance to the next level of water conveyance channel. It is necessary to set up water diversion outlets with water withdrawal function in some parts of the tunnel.

[0003] The groundwater types in the section where the water diversion is located are complex, including pore water, fissure water, karst water and fault vein water, among which karst water includes both karst fissure water and karst pipeline water. At the same time, the geology of the water diversion is generally more complex than that of ordinary water diversion tunnels. At present, there is no targeted construction method to ensure the safe and normal construction of the water diversion of the water diversion tunnel. Summary of the invention

[0004] The object of the present invention is to provide a construction method for a water diversion outlet of a water conveyance tunnel, which can ensure the safe and normal implementation of the construction under complex groundwater types and complex geological environments, and can ensure the construction efficiency and tunnel quality.

[0005] The present invention is implemented by the following technical scheme: A construction method of a water diversion outlet of a water conveyance tunnel comprises the following steps: (1) Establish a support system before excavation; (2) Determine the excavation method and support parameters; (3) Carry out water diversion construction; (4) Carry out hollow grouting anchor construction; (5) Install steel mesh; (6) Carry out steel support construction; (7) Carry out concrete spraying.

[0006] In order to better implement the method of the present invention, further, in the step (1), the process of establishing the support system before excavation is as follows: before excavating the water diversion outlet, the surveying personnel lay out the outline of the water diversion outlet, carry out the construction of the advanced large pipe shed and small conduit, then chisel out the concrete within the water diversion outlet range, and use oxygen acetylene to cut off the steel supports within the outline one by one. After the steel supports are cut off, the first steel arch frame of the water diversion outlet is immediately constructed and firmly welded to the main hole steel support to establish a reliable support system. At the same time, monitoring points are buried and full-time personnel are assigned to conduct regular observations.

[0007] In order to better implement the method of the present invention, further, in the step (2), the excavation method determined is full-section mechanical excavation.

[0008] In order to better implement the method of the present invention, further, in the step (2), the support parameters are: the arch advance support adopts a 180° range Φ108 advance large pipe rack and a Φ42 advance small pipe, and a Φ25 system anchor hollow grouting is set, steel support I18, the spacing is 0.5m, and cross braces I18 are added one by one in the bottom plate C20 concrete cushion layer, which are firmly connected to the side top arch steel support to form a closed ring, and the cross braces are firmly connected longitudinally with steel bars C22@100cm.

[0009] In order to better implement the method of the present invention, further, in the step (3), the water diversion port construction includes a self-propelled large pipe shed construction process and an advanced small pipe construction process.

[0010] In order to better implement the method of the present invention, further, in step (3), the construction process of the self-propelled large pipe shed includes the following steps: (3.1.1) Drilling of pipe shed holes; (3.1.2) Installation of pipe shed; (3.1.3) Grouting of pipe shed; The advanced small conduit construction process comprises the following steps: (3.2.1) Seal the excavation surface with sprayed concrete; (3.2.2) Arrange holes along the perimeter of the excavation surface; (3.2.3) Process and manufacture a small grouting tube, and insert the processed small tube into the hole; (3.2.4) Prepare slurry and carry out grouting; (3.2.5) Carry out excavation work.

[0011] In order to better implement the method of the present invention, further, in step (4), the specific process of hollow grouting anchor construction is as follows: (4.1) Prepare materials; (4.2) Drilling of anchor holes; (4.3) Anchor bolt installation and grouting; (4.4) Mechanical quality inspection of installed hollow grouting anchor pipes.

[0012] In order to better implement the method of the present invention, further, in the step (5), the specific process of installing the steel mesh is as follows: the steel mesh is processed and formed in the steel processing field outside the cave according to the designed steel bar specifications and mesh size. Before processing, the steel bars must be straightened, rusted and degreased to ensure the construction quality. The mesh must be placed flat or upright during stacking and transportation to ensure that the mesh does not deform. The steel mesh is hung after the system anchor rod is applied. When hanging, the mesh is laid according to the actual ups and downs of the initial concrete spraying surface to ensure that the steel mesh is closely attached to the supported rock surface. The connection between the steel mesh and the connection between the steel mesh and the anchor rod is tied or spot welded together with lead wire to prevent the steel mesh from shaking when spraying concrete.

[0013] In order to better implement the method of the present invention, further, in the step (6), the specific process of steel support construction is as follows: the steel support is processed and formed outside the hole according to the design, and installed in the hole after the anchor rod hanging mesh construction. In order to ensure that the steel support is placed on a stable foundation, 0.15m~0.2m of original foundation is reserved at the foot of the steel support during construction; when the steel support is erected, a groove is dug in place, and channel steel is set at the foot of the steel support in weak areas to increase the bearing capacity of the base.

[0014] In order to better implement the method of the present invention, further, in the step (7), the specific process of concrete spraying is as follows: after excavation, first spray concrete 3cm~5cm to seal the surrounding rock, so as to shorten the exposure time of the surrounding rock, control the deformation of the surrounding rock, and prevent the surrounding rock from loosening and peeling in a short period of time. After the installation of anchor rods, hanging nets, and steel frame supports is completed, spray concrete to the designed thickness. The spray concrete is sprayed by a wet spraying machine, the sprayed material is mixed at a concrete mixing station, and the concrete mixer truck is transported to the spraying operation point.

[0015] Compared with the prior art, the present invention has the following advantages and beneficial effects: The construction method provided by the present invention is aimed at the construction of a water diversion outlet of a water conveyance tunnel. The construction method can ensure the safe and normal implementation of the construction under complex groundwater types and complex geological environments, and can ensure the construction efficiency and tunnel quality. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Other features, objects and advantages of the present invention will become more apparent from the detailed description of non-limiting embodiments with reference to the following drawings: Figure 1 This is a schematic diagram of the processing structure of the advanced small catheter in the present invention; Figure 2 This is a process flow chart of the advanced small-pipe grouting process in the present invention; Figure 3 This is a process flow chart of the advanced small conduit construction process in the present invention; Figure 4 It is a process flow chart of wet spraying concrete construction in the present invention. DETAILED DESCRIPTION

[0017] In order to make the purpose, process conditions and advantages of the present invention more clearly understood, the present invention is further described in detail in conjunction with the following embodiments, but the embodiments of the present invention are not limited thereto. Without departing from the above-mentioned technical ideas of the present invention, various substitutions and changes are made according to the common technical knowledge and customary means in the field, which should all be included in the scope of the present invention. The specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.

[0018] Embodiment 1: This embodiment provides a method for constructing a water diversion outlet of a water conveyance tunnel, comprising the following steps: (1) Establish a support system before excavation; (2) Determine the excavation method and support parameters; (3) Carry out water diversion construction; (4) Implement hollow grouting anchor installation; (5) Install steel mesh; (6) Carry out steel support construction; (7) Carry out concrete spraying.

[0019] The construction procedure of the water diversion is to first excavate the main hole and then open another hole to construct the water diversion. Therefore, part of the steel support of the main hole will be cut off before the water diversion enters the hole. The surrounding rock of the water diversion is poor, and the main hole support system will be affected when the water diversion enters the hole. At the same time, considering that the excavation section of the water diversion is small, the support needs to be completed as soon as possible after excavation.

[0020] Embodiment 2: Based on the above embodiment, this embodiment further defines that in step (1), the process of establishing the support system before excavation is as follows: before excavating the water diversion outlet, the surveying personnel release the water diversion outlet outline, carry out the construction of the advanced large pipe shed and small pipe, then chisel out the concrete within the water diversion outlet range, and use oxygen acetylene to cut off the steel supports within the outline one by one. After the steel supports are cut off, the first steel arch frame of the water diversion outlet is immediately constructed and firmly welded to the main hole steel support to establish a reliable support system, and at the same time, the monitoring points are buried and full-time personnel are assigned to conduct regular observations. The other parts of this embodiment are the same as the above embodiment and will not be repeated.

[0021] Embodiment 3: Based on the above embodiment, this embodiment further defines that in step (2), the excavation method determined is full-section mechanical excavation. The other parts of this embodiment are the same as the above embodiment and will not be repeated.

[0022] Embodiment 4: Based on the above embodiment, this embodiment is further defined as follows: in step (2), the support parameters are: the arch advance support adopts a 180° range Φ108 advance large pipe shed and a Φ42 advance small pipe, a Φ25 system anchor hollow grouting, steel support I18, spacing 0.5m, and a cross brace I18 is added to the bottom plate C20 concrete cushion layer one by one, which is firmly connected to the side top arch steel support to form a closed ring, and the cross braces are firmly connected longitudinally with steel bars C22@100cm. The other parts of this embodiment are the same as the above embodiment and will not be repeated.

[0023] Embodiment 5: Based on the above embodiment, this embodiment further defines that in step (3), the water diversion port construction includes a self-propelled large pipe shed construction process and an advanced small pipe construction process. The other parts of this embodiment are the same as the above embodiment and will not be repeated.

[0024] Embodiment 6: Based on the above embodiment, this embodiment further defines that in step (3), the construction process of the self-propelled large pipe shed includes the following steps: (3.1.1) Drilling of pipe shed holes; (3.1.1.1) Measure the position of the pipe rack and guide the drilling rig into position.

[0025] (3.1.1.2) According to the diameter and length of the self-propelled pipe rack, use DZ-15 down-the-hole drill to drill. According to the center line and elevation of each pipe rack and the angle of the pipe rack, install the guide rail and drilling rig.

[0026] (3.1.1.3) Install the pipe rack and drill bit: After the drilling rig is positioned, connect the special drill bit to the pipe rack (the special drill bit corresponding to each section of the pipe rack cannot be removed), and connect the Feng Shui pipe on the drilling rig.

[0027] (3.1.1.4) Pipe-roof drilling: In order to ensure the direction, slope and accuracy of the pipe-roof, the surveying personnel shall mark out the position of the pipe-roof before drilling. After the marking is completed, the drilling rig angle is adjusted to start drilling.

[0028] (3.1.1.5) Pipe-roof extension: A 12m long pipe-roof is made up of two 3m sections and one 6m section or two 6m sections. After the first section of the pipe-roof is drilled into place, the second section of the pipe-roof is connected using a special connection sleeve for the self-propelled pipe-roof, and the drilling is continued in this cycle.

[0029] (3.1.1.6) Remove the drilling rig: After the pipe shed is drilled into place, lock the drill clamp, reverse the drilling rig, remove the pipe shed from the drilling rig connection sleeve, and move the drilling rig away. Continue drilling and installing the next pipe shed.

[0030] (3.1.2) Installation of pipe shed; (3.1.2.1) The pipe rack holes should be inspected before installation, and those that do not meet the requirements should be handled.

[0031] (3.1.2.2) Steel pipe joints are connected by threaded connections with a thread length of 15 cm. To prevent the steel pipes from being staggered, steel pipes with odd numbers of holes are connected by three sections, using standard lengths of 3 m, 6 m, and 3 m respectively; steel pipes with even numbers of holes are connected by two sections of 6 m standard length.

[0032] (3.1.2.3) The overlap length of the two longitudinal pipe racks is 3m. (3.1.2.4) The ends of the steel pipes should be firmly welded to the arch guide tube or steel arch frame.

[0033] (3.1.2.5) After the pipe shed is installed, it shall be sealed with quick-setting mortar. Before the mortar strength reaches the design requirements, the pipe shed shall not be knocked, collided or pulled.

[0034] (3.1.3) Grouting of pipe shed; (3.1.3.1) Generally, pure cement slurry is used for grouting; (3.1.3.2) Before grouting, a grouting test should be conducted and the grouting parameters should be adjusted according to the test results. During the initial grouting test, the water-cement ratio of the cement slurry can be 1:0.5~1:1; (3.1.3.3) Grouting can be carried out by forward grouting during the drilling process or by orifice tube grouting after the drilling is completed.

[0035] (3.1.3.4) The initial grouting pressure should be 0.5~1.0MPa, and the final pressure should be 2.0MPa. The specific pressure should be determined by on-site grouting test according to the surrounding rock geological conditions and external water pressure. When the grouting volume of each hole reaches the designed grouting volume or the grouting pressure reaches 2.0MPa, the grouting can be stopped after maintaining it for more than 10 minutes.

[0036] (3.1.3.5) After grouting, the slurry in the pipe should be removed promptly and filled tightly with M30 cement mortar to enhance the rigidity of the steel pipe.

[0037] The construction process of the advanced small guide tube is to use a YT-28 pneumatic rock drill to drill holes, manually install the advanced small guide tube and weld it to the steel frame. The external insertion angle of the small guide tube conforms to the design. The grouting operation is carried out with a grouting pump to inject cement single-liquid slurry. The grouting pressure is generally 0.5~1.0MPa. Reasonable grouting parameters are determined according to field tests during construction.

[0038] The advanced small conduit is made in the component processing factory, with the front end made into a pointed cone, and the tail welded with a Φ8mm steel reinforcement hoop. Holes are drilled on the pipe wall every 15cm, and the diameter of the holes is 10mm. Figure 1 shown.

[0039] After drilling, insert the small conduit into the hole according to the design requirements. In areas with weak surrounding rock, use a jackhammer or rock drill to directly drive the small conduit into the middle of the grid steel frame. The tail is welded to the steel frame to form a pre-support system. Before grouting, spray 5-10cm of concrete to seal the face as a stop wall. When the grouting volume of a single hole reaches the designed grouting volume, the grouting is terminated. The grouting parameters should be adjusted according to the grouting test results and on-site conditions. Fill in the grouting records carefully during the grouting operation, analyze and improve the operation at any time, and pay attention to the status of the construction support working surface, such as Figure 2 shown.

[0040] Before excavation, test the face and proceed with excavation work when there is no obvious water seepage.

[0041] The specific process of advanced small duct construction is as follows: Figure 3 As shown, the following steps are included: (3.2.1) Seal the excavation surface with sprayed concrete; (3.2.2) Arrange holes along the perimeter of the excavation surface; (3.2.3) Process and manufacture a small grouting tube, and insert the processed small tube into the hole; (3.2.4) Prepare slurry and carry out grouting; (3.2.5) Carry out excavation work.

[0042] Embodiment 7: Based on the above embodiment, this embodiment further defines that in step (4), the specific process of hollow grouting anchor construction is as follows: (4.1) Prepare materials The body of A hollow grouting anchor is made of structural seamless steel pipe with grade Q345 in accordance with GB / T8162, and its performance indicators meet the requirements of relevant specifications.

[0043] The nominal diameter, nominal wall thickness, nominal cross-sectional area, nominal mass and allowable deviation of the B hollow grouting anchor body shall comply with the construction drawings and the requirements of Table 3 of the Technical Specifications for Hollow Anchors (TB / T3209-2008).

[0044] The yield strength, maximum force and elongation after fracture of C hollow grouting anchor body shall comply with the requirements of Table 4 of "Technical Specifications for Hollow Anchors" (TB / T3209-2008).

[0045] D The ratio of the measured maximum force of the hollow grouting anchor body to the measured yield force shall not be less than 1.25.

[0046] The ratio of the actual yield strength of the E hollow grouting anchor body to the minimum yield strength specified in the standard shall not exceed 1.30.

[0047] (4.2) Drilling of anchor holes The anchor holes are arranged according to the drilling positions in the construction drawings, and the hole position deviation is controlled to be no more than 100mm; The anchor hole depth must meet the requirements of the construction drawing, and the hole depth deviation value shall not exceed 50mm; The deviation of exposed steel bar length shall not exceed 50mm (unless otherwise specified in the design).

[0048] The anchor holes should be inspected before installation, and those that do not meet the requirements should be handled according to the supervisor's requirements.

[0049] (4.3) Anchor bolt installation and grouting aPreparation before installation Check whether the inner hole of the hollow anchor rod and the outlet hole of the plastic grouting anchor head are blocked by foreign objects. If there is any blockage, it should be cleaned up.

[0050] Screw the plastic grouting anchor head onto one end of the hollow anchor rod body until it can no longer be turned.

[0051] Check whether the diameter of the drill bit used meets the design requirements and select the appropriate drill bit type, using a cross drill bit.

[0052] bDrilling Use a rock drill or a down-the-hole drill to drill holes at the designated locations for installing anchor rods. Supply water and air before drilling.

[0053] c. Washing well After drilling is completed, pull the drill rod and drill bit out of the borehole, flush the borehole with compressed air, and blow out the accumulated water and rock powder in the hole.

[0054] d Insert anchor rod and plastic anchor head assembly Insert the anchor rod and plastic anchor head assembly into the drilled hole.

[0055] e. Insert the air inlet (exhaust) pipe and process the orifice (or insert the slurry stopper) Anchor system with air inlet (exhaust) pipe: insert the air inlet (exhaust) pipe into the hole about 12~15mm, seal the hole with quick-drying cement slurry and smooth the end surface of the hole.

[0056] Anchor system with grout stop plug: Insert the grout stop plug and push it into the drilled hole to press against the end face of the hole.

[0057] fInstall the plate and nut Insert the backing plate into the exposed end of the hollow anchor rod body, make sure that the air inlet (exhaust) pipe is aligned with the hole on the backing plate and passes through the hole, screw in the nut until the nut is in contact with the backing plate to prevent the hollow anchor rod body from being pulled out of the hole.

[0058] g Grouting Screw on the grouting joint at the exposed end of the hollow anchor body: Connect the grouting hose to the grouting joint: Mix the slurry evenly in a mixer at a water-cement ratio of (0.3~0.45):1 (0.35:1 is recommended). The grouting liquid is pure cement slurry. Cement mortar is strictly prohibited. Pour the cement slurry mixed in the mixer into the hopper of the grouting machine: Start grouting with a grouting pressure of 0.8~1MPa and a pump flow rate of 0.3~0.6m3. The grouting process is continuous and must be completed in one go. The pump is stopped when the grout overflows from the exhaust pipe or the end hole of the hollow anchor body.

[0059] h nut loading After the slurry dries, the nut can be slightly tightened. The loading force is applied according to the test results.

[0060] (4.4) Mechanical quality inspection of installed hollow grouting anchor pipes.

[0061] A hollow grouting anchor is tested for mortar density and anchor length using a mortar saturation instrument or ultrasonic geophysical detector. For support anchors, the supervisor shall designate spot checks according to the actual situation on site according to the work area, and the spot check ratio shall not be less than 3% of the total number of anchors. The minimum density of anchor grouting shall not be less than 80%.

[0062] B. When the pass rate of random inspection is greater than 80%, the anchor rods in the random inspection work area are considered qualified. When the pass rate is less than 80%, the random inspection ratio is increased to 6%; if the pass rate is still less than 80%, all anchor rods in the work area are inspected, and the unqualified anchor rods are re-constructed.

[0063] Embodiment 8: Based on the above embodiment, this embodiment further defines that in step (5), the specific process of installing the steel mesh is as follows: the steel mesh is processed and formed in a steel bar processing plant outside the cave according to the designed steel bar specifications and mesh size. Before processing, the steel bars must be straightened, rusted and degreased to ensure the construction quality. The mesh must be placed flat or upright during stacking and transportation to ensure that the mesh does not deform. The steel mesh is hung after the system anchor rod is installed. When hanging, the mesh is laid according to the actual undulations of the initial concrete spraying surface to ensure that the steel mesh is closely attached to the supported rock surface. The joints of the steel mesh and the connection between the steel mesh and the anchor rod are tied or spot welded together with lead wire to prevent the steel mesh from shaking easily during concrete spraying. The other parts of this embodiment are the same as the above embodiment and will not be repeated.

[0064] Embodiment 9: Based on the above embodiment, the present embodiment further defines that in step (6), the specific process of steel support construction is as follows: the steel support is processed and formed outside the hole according to the design, and installed in the hole after the anchor rod hanging mesh construction. In order to ensure that the steel support is placed on a stable foundation, 0.15m~0.2m of original foundation is reserved at the foot of the steel support during construction; when the steel support is erected, a groove is dug in place, and channel steel is set at the foot of the steel support in weak areas to increase the bearing capacity of the base.

[0065] The steel support plane should be perpendicular to the tunnel centerline, with an inclination of no more than 2°, and any part of the steel support should not deviate from the plumb plane by more than 5 cm.

[0066] The steel support is installed according to the designed position. During the installation process, when there is a large gap between the steel support and the initial sprayed layer, riding pads should be installed. The contact distance between the steel support and the surrounding rock (or pads) should not be greater than 50mm.

[0067] To enhance the overall stability of the steel support, the steel support is welded to the anchor rod. Longitudinal connecting steel bars are arranged along the steel support and are arranged at a circumferential spacing of 1m.

[0068] In order to accurately position the steel support, positioning reinforcement bars must be pre-installed before the steel support is erected. One end of the reinforcement bar is welded to the steel support, and the other end is anchored into the surrounding rock 0.5~1m and anchored with mortar. When there are anchor rods at the steel support erection location, try to use the anchor rods for positioning.

[0069] The steel support connection joints must be firmly connected. The arch foot is prone to plastic shear failure, so in addition to tensile testing, the joints in this area should also be welded on all four sides to ensure the rigidity and strength of the joints.

[0070] After the steel support is erected, spray concrete as soon as possible and cover the steel support completely so that the steel support and the spray concrete are jointly stressed. Spray concrete in layers, with each layer being about 5 to 6 cm thick, and spray upward from the arch foot or the wall foot first to prevent the upper spray material from covering the arch foot (wall foot) without being dense, resulting in insufficient strength and instability of the arch foot (wall foot). The rest of this embodiment is the same as the above embodiment and will not be repeated.

[0071] Embodiment 10: Based on the above embodiment, this embodiment further defines that in step (7), the specific process of concrete spraying is as follows: after excavation, 3 cm to 5 cm of concrete is initially sprayed to seal the surrounding rock, so as to shorten the exposure time of the surrounding rock, control the deformation of the surrounding rock, and prevent the surrounding rock from loosening and peeling in a short period of time. After the installation of anchor rods, hanging nets, and steel frame supports is completed, concrete is sprayed again to the designed thickness. The spraying concrete is sprayed by a wet spraying machine, the sprayed material is mixed at a concrete mixing station, and the concrete mixing truck is transported to the spraying operation point.

[0072] Before jet support, pry off the loose soil and under-excavated parts on the surface, and use high-pressure air to remove debris; when there is a large amount of water on the excavation surface, take measures to centrally drain the water.

[0073] Before spraying, check and test-run the equipment; provide adequate lighting and ventilation equipment on the sprayed surface and in various mechanical equipment operation areas.

[0074] According to the designed thickness, existing parts such as the exposed length of anchor rods can be used, or short steel bars can be driven into the rock surface and marked with scales as marks.

[0075] Coarse aggregate should be screened again before adding to the mix to prevent oversized aggregate from mixing in and causing pipe blockage. Fine aggregate should be stored in a rainproof material storage to control the moisture content.

[0076] The spraying direction is perpendicular to the sprayed surface. During operation, the nozzle and the sprayed surface are automatically controlled by a computer, and the spraying is perpendicular to the rock surface and equidistant. If the sprayed surface is covered by a steel frame or a steel mesh, the nozzle can be slightly tilted, but not less than 70°.

[0077] The thickness of one spraying should not exceed 5~6cm. If it is too thick, it will weaken the cohesion between concrete particles, causing the spraying layer to fall off in large pieces due to its own weight, or forming a gap between the spraying layer at the vault and the surrounding rock surface; if it is too thin, the coarse aggregate will easily rebound. Spray to the designed thickness in batches, and the time interval between two spraying layers is 15~20min. The main reasons affecting the thickness of the spraying layer are the effect of the accelerator and the temperature.

[0078] To improve work efficiency and ensure quality, the spraying operation should be carried out in sections. To prevent rebound objects from adhering to the unsprayed rock surface and affecting the bonding force between the sprayed layer and the rock surface, the construction process of spraying from bottom to top and the spiral trajectory spraying should be followed; before spraying, the concave part of the sprayed surface should be leveled first, and then the nozzle should be moved slowly and evenly in a spiral shape to ensure that the concrete surface is smooth.

[0079] The raw materials and mix ratio of the shotcrete (including the amount of the accelerating agent added) must not only meet the requirements, but also the setting time of the accelerating agent, the compatibility with cement, and the influence on the strength must meet the requirements. The other parts of this embodiment are the same as the above embodiment and will not be repeated.

[0080] Although the embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the claims and their equivalents.

Claims

1. A method for constructing a water diversion outlet of a water diversion tunnel, characterized in that: The following steps are involved: (1) Establish a support system before excavation; (2) Determine the excavation method and support parameters; (3) Carry out water diversion construction; (4) Carry out hollow grouting anchor construction; (5) Install steel mesh; (6) Carry out steel support construction; (7) Carry out concrete spraying.

2. A method for constructing a water diversion outlet of a water diversion tunnel according to claim 1, characterized in that: In the step (1), the process of establishing the support system before excavation is as follows: before excavating the water diversion outlet, the surveying personnel lay out the outline of the water diversion outlet, carry out the construction of the advance large pipe shed and small pipe, then chisel out the concrete within the water diversion outlet, and use oxygen acetylene to cut off the steel supports within the outline one by one. After the steel supports are cut off, the first steel arch frame of the water diversion outlet is immediately constructed and firmly welded to the main hole steel support to establish a reliable support system. At the same time, monitoring points are buried and full-time personnel are assigned to conduct regular observations.

3. A method for constructing a water diversion outlet of a water diversion tunnel according to claim 1 or 2, characterized in that: In the step (2), the excavation method determined is full-section mechanical excavation.

4. A method for constructing a water diversion outlet of a water diversion tunnel according to claim 3, characterized in that: In step (2), the support parameters are as follows: the arch top advance support adopts a 180° range Φ108 advance large pipe rack and a Φ42 advance small pipe, a Φ25 system anchor hollow grouting, steel support I18, with a spacing of 0.5m, and cross braces I18 are added one by one in the bottom plate C20 concrete cushion layer, which are firmly connected to the side top arch steel support to form a closed ring, and the cross braces are firmly connected longitudinally with steel bars C22@100cm.

5. A method for constructing a water diversion outlet of a water diversion tunnel according to claim 1 or 2, characterized in that: In the step (3), the water diversion outlet construction includes a self-propelled large pipe shed construction process and an advanced small pipe construction process.

6. A method for constructing a water diversion outlet of a water conveyance tunnel according to claim 5, characterized in that: In step (3), the construction process of the self-propelled large pipe shed includes the following steps: (3.1.1) Drilling of pipe shed holes; (3.1.2) Installation of pipe shed; (3.1.3) Grouting of pipe shed; The advanced small conduit construction process comprises the following steps: (3.2.1) Seal the excavation surface with sprayed concrete; (3.2.2) Arrange holes along the perimeter of the excavation surface; (3.2.3) Process and manufacture a small grouting tube, and insert the processed small tube into the hole; (3.2.4) Prepare slurry and carry out grouting; (3.2.5) Carry out excavation work.

7. A method for constructing a water diversion outlet of a water conveyance tunnel according to claim 1 or 2, characterized in that: In step (4), the specific process of hollow grouting anchor construction is as follows: (4.1) Prepare materials; (4.2) Drilling of anchor holes; (4.3) Anchor bolt installation and grouting; (4.4) Mechanical quality inspection of installed hollow grouting anchor pipes.

8. A method for constructing a water diversion outlet of a water diversion tunnel according to claim 1 or 2, characterized in that: In step (5), the specific process of installing the steel mesh is as follows: the steel mesh is processed and formed in a steel processing yard outside the hole according to the designed steel bar specifications and mesh size. Before processing, the steel bars must be straightened, rusted and degreased to ensure the construction quality. The mesh must be placed flat or upright during stacking and transportation to ensure that the mesh does not deform. The steel mesh is hung after the system anchor is installed. When hanging, the mesh is laid according to the actual ups and downs of the initial concrete surface to ensure that the steel mesh is closely attached to the supported rock surface; The connections between the steel mesh and the anchor rods are tied together with lead wire or spot welded together to prevent the steel mesh from shaking easily during concrete spraying.

9. A method for constructing a water diversion outlet of a water conveyance tunnel according to claim 1 or 2, characterized in that: In step (6), the specific process of steel support construction is as follows: the steel support is processed and formed outside the hole according to the design, and installed in the hole after the anchor rod hanging mesh construction. In order to ensure that the steel support is placed on a stable foundation, 0.15m~0.2m of original foundation is reserved at the foot of the steel support during construction; when the steel support is erected, a groove is dug in place, and channel steel is set at the foot of the steel support in weak areas to increase the bearing capacity of the base.

10. A method for constructing a water diversion outlet of a water conveyance tunnel according to claim 1 or 2, characterized in that: In step (7), the specific process of concrete spraying is as follows: after excavation, initially spray concrete to seal the surrounding rock with a thickness of 3 cm to 5 cm, so as to shorten the exposure time of the surrounding rock, control the deformation of the surrounding rock, and prevent the surrounding rock from loosening and peeling off in a short period of time; After the installation of anchor rods, hanging nets and steel frame supports is completed, concrete is sprayed to the designed thickness. The concrete is sprayed using a wet sprayer. The sprayed material is mixed at a concrete mixing station and transported to the spraying operation point by a concrete mixer truck.