Clip structure for pipeline limiting and pipeline positioning method

By using a combined structure of the clip body and the fixing cable, the kitchen and bathroom water supply and drainage pipes are fixed on the kitchen and bathroom floor, solving the problems of unsolid positioning and easy leakage in the existing technology, and achieving more efficient pipeline fixation and construction quality Improvement.

CN118935100APending Publication Date: 2024-11-12CHINA METALLURGICAL CONSTR ENG GRP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411214253.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-31
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

The existing kitchen and bathroom water supply and drainage pipe positioning methods have problems such as unsolid positioning, easy to damage and leak, which affects the construction quality and the overall effect of subsequent floors.

Method used

Using a pipe limit structure including a clip body, a fixing nail and a fixing cable, the clip body is penetrated into the ground base through an air compressor gun to form a fixing point, and the preset pipe is fixed to the clip body by using the fixing nail and a fixing cable. Ensure a stable position of the pipe.

Benefits of technology

The fixing efficiency and construction quality of the pipeline are improved, the problems of improper positioning, damage and leakage are avoided, the construction process is simplified, and the subsequent waterproofing and floor pouring are carried out normally.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118935100A_ABST
    Figure CN118935100A_ABST
Patent Text Reader

Abstract

The invention discloses a clamp structure for pipeline limiting and a pipeline positioning method.The clamp structure comprises a clamp body, a fixing nail and a fixing rope, the fixing rope is controlled to stretch or retract to limit a preset pipeline on the clamp body, and the clamp body is fixed at a preset position through the fixing nail; the drainage pipe can be fixed more conveniently, construction quality is guaranteed, negative effects caused by pipeline positioning are reduced, and construction efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of fixing kitchen and bathroom water supply and drainage pipelines, and in particular to a clamp structure for pipeline limiting and a pipeline positioning method. Background Art

[0002] Since the ground water supply and drainage points in the kitchen and bathroom have been located during the design drawings, the horizontal branch pipes for water supply and drainage in the kitchen and bathroom need to be effectively installed and fixed to avoid damage or displacement during the subsequent floor pouring process. The conventional construction method is to fix the pipes and floor drains with mortar, but it takes a certain amount of time for the mortar to become strong, and the overall fixing and positioning efficiency is low; or the horizontal pipes laid on the ground are fixed with iron nails and hammers, and often no effective fixing measures are taken due to the large diameter.

[0003] The conventional horizontal pipe positioning method has the problems of unstable positioning, damage to floor drains of subsequent construction pipelines, and even poor connection between the seat slurry and subsequent concrete, causing cold joints and leading to floor leakage. At the same time, the process is relatively complicated and can easily cause adverse effects such as secondary pollution of the base layer.

[0004] Therefore, in order to solve the above problems, a clip structure for pipe limiting and a pipe positioning method are needed, which can more conveniently fix the drainage pipe, ensure the construction quality, reduce the negative impact caused by pipe positioning, and improve construction efficiency. Summary of the invention

[0005] In view of this, the purpose of the present invention is to overcome the defects in the prior art and provide a clip structure and a pipeline positioning method for pipe limiting, which can more conveniently fix the drainage pipe, ensure construction quality, reduce the negative impact caused by pipeline positioning, and improve construction efficiency.

[0006] The clamp structure for limiting the position of a pipeline of the present invention comprises a clamp body, a fixing nail and a fixing rope. The fixing rope is controlled to extend or shorten to limit the preset pipeline on the clamp body. The clamp body is fixed at a preset position by the fixing nail.

[0007] Furthermore, the clip body is in the shape of an elongated strip, and the clip body is in a "Z" shape, and the fixing nails and fixing ropes are respectively and correspondingly connected to two parallel sides of the "Z" shape of the clip body.

[0008] Furthermore, the edge where the fixing nail and the clip are assembled is close to the preset position, and the edge where the fixing rope and the clip are assembled is close to the preset pipe.

[0009] Furthermore, after the back fixing nail of the clip body is fixed at a preset position, one end of the fixing rope of the clip body is suspended in the air.

[0010] Furthermore, the clip body has a functional portion bent downward at one end of the fixing rope.

[0011] Furthermore, the fixing nail is pre-connected to the clip body.

[0012] Furthermore, a line connecting the installation position of the fixing pin on the clip body and the installation position of the fixing cable on the clip body roughly coincides with a transverse midline of the clip body.

[0013] The present solution also discloses a pipeline positioning method based on the clamp structure for pipeline position limiting, wherein the clamp structure for pipeline position limiting is composed of multiple groups, and a preset pipeline is installed through multiple groups of the clamp structures for pipeline position limiting;

[0014] The following steps are also included:

[0015] S1. Preset pipeline installation and specify placement area;

[0016] S2. Use a fixing nail to fix the clamp body at a position close to the preset pipe;

[0017] S3. Use a fixing cable to fix the preset pipe to the clamp body;

[0018] S4. Repeat steps S2-S3 until the position of the preset pipeline is determined.

[0019] The beneficial effects of the present invention are as follows: a clamp structure and a pipeline positioning method for limiting the position of a pipeline disclosed in the present invention, wherein an air compressor is used to drive the clamp body into the ground base to form a fixed point (one end of the fixing piece is nailed to the base with a nail, and the other end is raised and provided with a round hole). After the horizontal pipe is installed, an iron wire or a tie wire is passed through the protruding hole of the fixing piece and then fastened to the horizontal pipe. Attention should be paid to selecting the fixing position such as the pipeline bend for better effect. The horizontal fixing method of the drainage pipe is convenient to construct and has high efficiency. It is not affected during the subsequent waterproofing construction and floor pouring process, and the quality is easy to ensure. The method is convenient to construct and has significant effect, and avoids the defects of conventional positioning such as being unstable, easy to damage, and easy to leak. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] The present invention will be further described below in conjunction with the accompanying drawings and embodiments:

[0021] Figure 1 It is a structural schematic diagram of the present invention;

[0022] Figure 2 It is a schematic structural diagram of the clip body of the present invention. DETAILED DESCRIPTION

[0023] Figure 1This is a schematic diagram of the structure of the present invention. As shown in the figure, the clamp structure 002 for pipe limiting in this embodiment includes a clamp body 1, a fixing nail 2 and a fixing rope 3. The fixing rope 3 is controlled to extend or shorten to limit the preset pipe on the clamp body 1. The clamp body 1 is fixed at a preset position by the fixing nail 2. This solution uses an air pressure gun to make the fixing nail 2 drive the clamp body 1 into the ground base to form a fixed point (one end of the fixing piece is nailed to the base with a nail, and the other end is raised and has a round hole). After the horizontal pipe is installed, a wire or a tie wire is passed through the protruding hole of the fixing piece and then fastened to the horizontal pipe. It is necessary to pay attention to the selection of the fixed position such as the pipe turning position for better effect; the horizontal fixing method of the drainage pipe 001 is convenient to construct and has high efficiency. It is not affected in the subsequent waterproof construction and floor pouring process, and the quality is easy to ensure; this method is convenient to construct and has significant effect, avoiding the defects of conventional positioning being unstable, easy to damage, and easy to leak.

[0024] In this embodiment, the clip body 1 is in the shape of an elongated strip, and the clip body 1 is in the shape of a "Z". The fixing nail 2 and the fixing rope 3 are respectively connected to the two parallel sides of the "Z" shape of the clip body 1. This makes the use of the two non-interfering with each other, and the operability is better; and the side where the fixing nail 2 and the clip are assembled is close to the preset position, and the side where the fixing rope 3 and the clip are assembled is close to the preset pipe. This makes the guidance of the preset drainage pipe 001 more reliable, which is conducive to ensuring the later construction. This horizontal fixing method of the drainage pipe 001 is convenient to construct and has high efficiency. It is not affected during the subsequent waterproofing construction and floor pouring process, and the quality is easy to ensure. This method is convenient to construct and has significant effects, and avoids the defects of conventional positioning that is not firm, easy to damage, and easy to leak.

[0025] In this embodiment, after the back fixing nail 2 of the clip body 1 is fixed at a preset position, one end of the fixing rope 3 of the clip body 1 is suspended in the air; wherein the fixing nail 2 and the fixing rope 3 are respectively pre-connected to the clip body 1 accordingly, so that it is more convenient and convenient in actual use and the construction progress is faster. The clip body 1 has an opening at one end of the fixing rope 3 for the fixing rope 3 to pass through and set a limit. Furthermore, the clip body 1 has a functional part with a downward bend at one end of the fixing rope 3, and this functional part can also limit the pipeline under extreme conditions and improve the binding quality.

[0026] In this embodiment, the line connecting the installation position of the fixing nail 2 on the clip body 1 and the installation position of the fixing rope 3 on the clip body 1 roughly coincides with the transverse center line of the clip body 1, so that the forces in the length direction of the clip body 1 are completely opposite, which is beneficial to ensure the strength of use.

[0027] The present scheme also discloses a pipeline positioning method based on the clip structure 002 for pipeline positioning, wherein the clip structure 002 for pipeline positioning is a plurality of groups, and a preset pipeline is installed through the plurality of groups of clip structures 002 for pipeline positioning; the plurality of groups of clip structures 002 for pipeline positioning bend the preset pipeline into a preset shape at a specified position; the purpose is to ensure that the subsequent waterproof construction and floor pouring process are not affected, and the quality is easy to ensure; and this method is convenient to construct, has significant effect, and avoids the defects of conventional positioning such as being unstable, easy to damage, and easy to leak.

[0028] The following steps are also included:

[0029] S1. Preset pipeline installation and specify placement area;

[0030] S2. Use the fixing nail 2 to fix the clamp body 1 in a position close to the preset pipe;

[0031] S3. The preset pipe is fixed to the clamp body 1 by using the fixing cable 3;

[0032] S4. Repeat steps S2-S3 until the position of the preset pipeline is determined.

[0033] S5. Carry out subsequent waterproofing and floor construction, and perform detailed processing on fixed locations.

[0034] In this embodiment, the clamp body 1 is driven into the ground base by an air pressure gun to form a fixed point (one end of the fixing piece is nailed to the base with a nail, and the other end is raised and has a round hole). After the horizontal pipe is installed, a wire or a tie wire is passed through the protruding hole of the fixing piece and then fastened to the horizontal pipe. It is necessary to pay attention to the selection of the fixed position such as the pipe bend for better effect; the horizontal fixing method of the drainage pipe 001 is convenient to construct and has high efficiency. It is not affected in the subsequent waterproof construction and floor pouring process, and the quality is easy to guarantee. This method is convenient to construct and has significant effects, avoiding the defects of conventional positioning that is not firm, easy to damage, and easy to leak.

[0035] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solution of the present invention can be modified or replaced by equivalents without departing from the purpose and scope of the technical solution of the present invention, which should be included in the scope of the claims of the present invention.

Claims

1. A clamp structure for limiting the position of a pipeline, characterized in that: The clamp comprises a clamp body, a fixing nail and a fixing rope. The fixing rope is controlled to be extended or shortened to limit a preset pipeline on the clamp body. The clamp body is fixed at a preset position by the fixing nail.

2. The clamp structure for limiting the position of a pipeline according to claim 1, characterized in that: The clip body is in the shape of an elongated strip, and the clip body is in the shape of a "Z". The fixing nails and fixing ropes are respectively and correspondingly connected to two parallel sides of the "Z" shape of the clip body.

3. The clamp structure for limiting the position of a pipeline according to claim 2 is characterized in that: The edge where the fixing nail and the clip are assembled is close to the preset position, and the edge where the fixing rope and the clip are assembled is close to the preset pipe.

4. The clamp structure for limiting the position of a pipeline according to claim 2, characterized in that: After the back fixing nail of the clip body is fixed at the preset position, one end of the clip body with the fixing rope is suspended.

5. The clamp structure for limiting the position of a pipeline according to claim 2, characterized in that: The clip body has a functional portion bent downward at one end of the fixing rope.

6. The clamp structure for limiting the position of a pipeline according to claim 1, characterized in that: The fixing nail is pre-connected to the clip body.

7. The clamp structure for limiting the position of a pipeline according to claim 1, characterized in that: The connecting line between the installation position of the fixing nail on the clip body and the installation position of the fixing cable on the clip body roughly coincides with the transverse center line of the clip body.

8. A pipeline positioning method based on the clamp structure for pipeline positioning according to any one of claims 1 to 7, characterized in that: The clamp structure for limiting the position of the pipeline is composed of multiple groups, and the preset pipeline is installed through the multiple groups of the clamp structure for limiting the position of the pipeline; The following steps are also included: S1. Preset pipeline installation and specify placement area; S2. Use a fixing nail to fix the clamp body at a position close to the preset pipe; S3. Use a fixing cable to fix the preset pipe to the clamp body; S4. Repeat steps S2-S3 until the position of the preset pipeline is determined.