Opposite-impacting speed-reducing air-closed type underwater rock plug blasting device and blasting method
By using slag collecting pit and deflector structures in underwater rock plug blasting device, the blasting shock waves are absorbed and attenuated, and the problem of blasting shock waves is solved during the passage of reservoirs and tunnels is improved, and construction efficiency and safety are avoided. The use of traditional plugs.
Patent Information
- Application Number
- CN202411301649.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-18
- Publication Date
- 2024-11-12
AI Technical Summary
During the passage of reservoirs and new tunnels, the existing underwater rock plug blasting method has the risk of damage to the gate by blasting shock waves. The casting and demolition projects of traditional plugs are large, and the demolition efficiency is low, which affects construction efficiency and safety.
The blasting and deceleration air-retaining underwater rock plug blasting device is adopted. The device includes a slag collecting pit, a recoil arc and a deflector. Through the water pad and deflector structure in the slag collecting pit, it absorbs and attenuates the blasting shock wave to avoid blocking. Use to simplify the construction process.
It effectively reduces the damage to the gate by blasting shock wave, improves construction efficiency, reduces project costs, simplifies process flow, and improves construction safety and project quality.
Smart Images

Figure CN118936255A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of blasting devices, and in particular to an impact, deceleration, air-locking underwater rock plug blasting device and a blasting method. Background Art
[0002] With the development of industrial and agricultural production and life, it is often necessary to divert water from water-rich areas to water-deficient areas in order to achieve resource allocation and water balance between regions and promote social and economic development. When the water level of the reservoir in the water supply area is high and the water level in the water receiving area is low, the water from the reservoir can be diverted to the water receiving area by gravity by building water diversion tunnels and channels, without the need to use water pumps, thereby saving operating costs. In this water intake method, when the elevation of the water intake sill of the water diversion tunnel is low and the reservoir is a newly built reservoir, the water level in the reservoir area is low, the water intake is exposed above the water surface, and construction can be carried out on dry land, and the reservoir hole of the water intake is easy to achieve. However, in many cases, the reservoir has been stored and operated, and the sill of the water intake of the newly built water diversion tunnel is often located near the dead water level of the reservoir, which is tens of meters or even hundreds of meters below the water surface of the reservoir. At this time, there are two conventional methods to achieve the penetration of the reservoir hole:
[0003] 1) Lower the reservoir water level to below the sill elevation of the tunnel water intake to create dry land construction conditions for the water intake. This method is stable and reliable, but it requires lowering the reservoir water level to below the sill elevation of the water intake of the diversion tunnel, which will affect the operation efficiency of the reservoir, is too costly, and may not even be allowed.
[0004] 2) Build a deep water cofferdam in the reservoir area near the water intake of the water diversion tunnel to enclose the water intake, and then drain the water in the cofferdam to create dry land construction conditions for the water intake construction. After the project is completed, the cofferdam will be removed to achieve the connection of the reservoir tunnel. This method will bring huge engineering investment and a long construction period, which is very uneconomical.
[0005] How to efficiently and economically connect the reservoir tunnel without lowering the water level of the reservoir and affecting the operation of the reservoir is a difficult problem that needs to be solved urgently. Experts at home and abroad have proposed the use of underwater rock plug blasting to achieve the connection between the existing reservoir and the newly built tunnel. Underwater rock plug blasting is an effective, convenient and economical construction method for building a tunnel inlet on an existing reservoir or lake. Its construction process is characterized by excavating the tunnel to the bottom of the reservoir, adjacent to a certain thickness of rock mass (i.e., rock plug). After the tunnel is built, the reserved rock mass is blasted away at one time by blasting, so that the tunnel and the reservoir are connected. In this way, the blasted inlet has the expected shape and meets the hydraulic requirements for the inlet. At the same time, it is necessary to ensure that the impact of the blasting on the surrounding rock mass and nearby buildings is reduced to an acceptable level.
[0006] Rock plug blasting has the characteristics of low cost, fast construction speed, and the construction period is not affected by seasons. Therefore, it has been increasingly used in the construction of underwater water inlet projects. However, underwater rock plug blasting is usually close to various hydraulic structures and hillsides, and some are even close to river dams. In addition, the construction work is carried out under deep water pressure, so the safety issue is very prominent and the absolute safety of blasting must be guaranteed. At the same time, rock plugs can only be blasted through once, which requires the water inlet to be well formed and the surrounding rock to be stable. Therefore, blasting must be carefully designed and constructed.
[0007] However, since the rock plug blasting method involves many influencing factors, complex technology, and very little related theoretical analysis and computational research, the method is still almost at the level of empirical judgment.
[0008] The main processes of rock blasting at present are:
[0009] 1) The gate well construction is completed and the tunnel construction reaches the downstream of the rock plug;
[0010] 2) The tunnel downstream of the gate shaft is sealed with a concrete plug;
[0011] 3) Networking of charging in rock plugs;
[0012] 4) Fill the tunnel with water through the gate well;
[0013] 5) Implement rock plug blasting to achieve the connection between the reservoir and the tunnel;
[0014] 6) After blasting, conduct underwater inspection;
[0015] 7) After passing the inspection, close the emergency gate in the gate well;
[0016] 8) Drain the water between the emergency gate and the tunnel plug by means of water pumps or other methods;
[0017] 9) Manually remove the concrete plug of the tunnel downstream of the gate shaft, discharge the slag through the gate shaft, and clean it up;
[0018] 10) Working gate in the gate well
[0019] 11) After the emergency gate is lifted in the gate shaft, the working gate can be used to control the water supply from the reservoir to the tunnel to realize water diversion.
[0020] During blasting, water is usually injected into the tunnel for pre-pressure (the water level is lower than the reservoir water level). On the one hand, the water injected into the tunnel can dissipate the energy of the blasted rock debris, preventing the rock debris from flying into the tunnel and causing blockage; on the other hand, water is injected into the tunnel to basically balance the water pressure of the reservoir after the blasting, effectively preventing the reservoir water from rushing into the tunnel in large quantities and quickly after the blasting, carrying rock debris into the tunnel and causing blockage or siltation. In order to maintain a certain water pressure in the tunnel, water can be blocked by the working gate under the gate shaft, or a plug can be used to block water in the tunnel downstream of the gate shaft. However, when the rock plug is blasted, the tunnel water flow can transmit the blasting shock wave to the gate shaft, generating a large impact force and endangering the safety of the gate. In order to prevent the blasting shock wave from damaging the gate, the gate is not used to directly block water at present, but a concrete plug is used in the tunnel downstream of the gate shaft for temporary blocking. This method can ensure the safety of the gate, but there are also the following problems: before blasting, a temporary reinforced concrete plug needs to be poured in the deep well tunnel, and after blasting, the water in the deep well needs to be drained first, and then the plug in the deep well tunnel needs to be removed. However, due to the small space in the deep well, the pouring and removal of the plug is large, and the hard plug needs to be removed manually, which has low removal efficiency. Summary of the invention
[0021] The embodiment of the present application provides a counter-impact deceleration air-tight underwater rock plug blasting device and blasting method to solve the problems existing in the related technology. The technical solution is as follows:
[0022] In a first aspect, an embodiment of the present application provides a counter-impact, deceleration and air-tight underwater rock plug blasting device, comprising:
[0023] Tunnel, the water inlet of the tunnel is provided with a rock plug;
[0024] A slag collection pit, which is located at the water inlet of the tunnel, is provided with a water cushion, has a slag collection pit inlet and a slag collection pit outlet, the slag collection pit inlet is located on one side of the rock plug, and the slag collection pit outlet is connected to the water outlet of the tunnel;
[0025] The first recoil arc is located in the slag collection pit;
[0026] A first guide plate, the first guide plate is located in the first recoil arc, a side of the first guide plate away from the first recoil arc forms a first drainage area, a side of the first guide plate close to the first recoil arc forms a first guide area, and the first drainage area and the first guide area form a first counter-attack area near the slag collection pit outlet;
[0027] The gate well assembly comprises a first gate well, the first gate well is located at the water outlet of the tunnel, a first gate is arranged in the first gate well, and the first gate is used to control the opening and closing of the water outlet of the tunnel.
[0028] In one embodiment, the counter-impact deceleration and air-tight underwater rock plug blasting device further comprises:
[0029] The first speed limit pit is located in the tunnel, the first speed limit pit is located between the slag collection pit and the first gate shaft, the first speed limit pit has a first speed limit entrance and a first speed limit exit, the first speed limit entrance is connected with the slag collection pit exit, the first speed limit exit is connected with the water outlet of the tunnel, the first speed limit pit includes a second recoil arc and a second guide plate, the second guide plate is located in the second recoil arc, the side of the second guide plate away from the second recoil arc forms a second diversion area, the side of the second guide plate close to the second recoil arc forms a second diversion area, the second diversion area and the second guide area form a second counter-attack area near the second speed limit exit.
[0030] In one embodiment, the counter-impact deceleration and air-tight underwater rock plug blasting device further comprises:
[0031] The second speed limit pit is located in the tunnel, the second speed limit pit is located between the first speed limit pit and the first gate shaft, the second speed limit pit has a second speed limit entrance and a second speed limit exit, the second speed limit entrance is connected with the first speed limit exit, the second speed limit exit is connected with the water outlet of the tunnel, the second speed limit pit includes a third recoil arc and a third guide plate, the third guide plate is located in the third recoil arc, the side of the third guide plate away from the third recoil arc forms a third diversion area, the side of the third guide plate close to the third recoil arc forms a third diversion area, the third diversion area and the third guide area form a third counter-attack area near the second speed limit exit.
[0032] In one embodiment, a first slope section is provided in the tunnel, one end of the first slope section is connected to the slag collection pit outlet, the other end of the first slope section is connected to the first speed limit entrance, and one end of the first slope section is inclined upward relative to the other end.
[0033] In one embodiment, a second slope section is provided in the tunnel, one end of the second slope section is connected to the first speed limit exit, the other end of the second slope section is connected to the second speed limit entrance, and one end of the second slope section is inclined upward relative to the other end.
[0034] In one embodiment, an air pipe is provided on the operating platform above the first gate shaft, a control valve is provided at one end of the air pipe, and the other end of the air pipe passes through the first gate shaft and is located inside the tunnel, and a pressure gauge is provided inside the tunnel.
[0035] In one embodiment, the gate well assembly further includes a second gate well, which is located on one side of the first gate well and communicates with the tunnel. A second gate for controlling the water flow in the tunnel is disposed in the second gate well.
[0036] In one embodiment, the elevation of the bottom plate of the first gate shaft is higher than the elevation of the bottom plate of the tunnel connected to the first gate shaft.
[0037] In one embodiment, the fluid flowing through the first drainage area and the fluid flowing through the first flow guide area have an impact angle α in the first impact area, and the range of the impact angle α is: 0°≤α≤90°.
[0038] In a second aspect, an embodiment of the present application provides a counter-impact deceleration and airtight underwater rock plug blasting method, which is applied to a counter-impact deceleration and airtight underwater rock plug blasting device as described in any one of the above items, and the counter-impact deceleration and airtight underwater rock plug blasting method comprises the following steps:
[0039] Excavate the first gate well and line the first gate well;
[0040] A tunnel and a slag collection pit are excavated along the bottom of the first gate shaft to the upstream reservoir until the side of the rock plug; a first recoil arc and a first guide plate are set in the slag collection pit, and the tunnel and the slag collection pit are lined;
[0041] Selecting a drilling location on the rock plug and drilling a blast hole, and installing explosives for blasting in the blast hole;
[0042] Inject a certain depth of water into the slag pit to form a water cushion;
[0043] Close the first gate in the first gate shaft, and make the tunnel in a sealed state through the first gate;
[0044] Blasting is carried out on the rock plug to achieve the connection between the reservoir and the tunnel.
[0045] The advantages or beneficial effects of the above technical solution include at least:
[0046] The underwater rock plug blasting device of the embodiment of the present application includes a tunnel, a slag collection pit, a first recoil arc, a first guide plate and a gate well assembly. A rock plug is provided at the water inlet of the tunnel, a water cushion is provided in the slag collection pit, and the first recoil arc is located inside the slag collection pit, and the first guide plate is located inside the first recoil arc. The side of the first guide plate away from the first recoil arc forms a first diversion area, and the side of the first guide plate close to the first recoil arc forms a first diversion area. The first diversion area and the first guide area form a first counter-charge area near the outlet of the slag collection pit. The gate well assembly includes a first gate well, the first gate well is located at the water outlet of the tunnel, and the first gate well is provided with a first gate for controlling the opening and closing of the tunnel water outlet. Since a slag collecting pit is provided and a water cushion is provided in the slag collecting pit, when the rock plug is blasted, the water cushion provides strong resistance to the slag flying into the water cushion, dissipates and absorbs the kinetic energy of the slag, reduces the slag flying out of the slag collecting pit, and prevents the flying slag from blocking the tunnel and causing damage to the first gate. Since the first recoil arc and the first guide plate are provided, the blasting shock wave entering through the entrance of the slag collecting pit can be reflected multiple times in the slag collecting pit to attenuate its intensity, block the shock wave from entering the tunnel, and prevent the first gate from being damaged by the impact. The mixed fluid of water, gas, etc. entering through the entrance of the slag collecting pit is diverted after encountering the first guide plate, part of the fluid enters the first diversion area, and part of the fluid enters the first diversion area. The fluid entering the first diversion area and the fluid entering the first diversion area collide with each other in the first counter-charge area, producing a blocking effect, greatly reducing the speed of the fluid, and preventing the fluid from bringing slag into the tunnel to cause siltation and blockage. Since the embodiment of the present application is provided with a slag collecting pit, a first recoil arc and a first guide plate, damage to the first gate by the blasting shock wave is avoided without providing a plug for sealing, and the casting and removal of the traditional plug and the drainage of the gate well are avoided, thereby improving the construction efficiency and reducing the project cost.
[0047] The above summary is for illustrative purposes only and is not intended to be limiting in any way. In addition to the illustrative aspects, embodiments and features described above, further aspects, embodiments and features of the present application will be readily apparent by reference to the accompanying drawings and the following detailed description. BRIEF DESCRIPTION OF THE DRAWINGS
[0048] In the accompanying drawings, unless otherwise specified, the same reference numerals throughout the multiple drawings represent the same or similar parts or elements. These drawings are not necessarily drawn to scale. It should be understood that these drawings only depict some embodiments disclosed in the present application and should not be regarded as limiting the scope of the present application.
[0049] Figure 1 It is a cross-sectional view of a counter-pressure deceleration and air-tight underwater rock plug blasting device;
[0050] Figure 2Another cross-sectional view of the counter-deceleration air-tight underwater rock plug blasting device;
[0051] Figure 3 It is a first cross-sectional view of the counter-deceleration air-tight underwater rock plug blasting device during the blasting process;
[0052] Figure 4 A second cross-sectional view of the counter-deceleration air-tight underwater rock plug blasting device during the blasting process;
[0053] Figure 5 It is a third cross-sectional view of the counter-deceleration air-tight underwater rock plug blasting device during the blasting process;
[0054] Figure 6 A fourth cross-sectional view of the counteracting deceleration and air-tight underwater rock plug blasting device during the blasting process;
[0055] Figure 7 A fifth cross-sectional view of the counteracting deceleration and air-tight underwater rock plug blasting device during the blasting process;
[0056] Description of reference numerals:
[0057] 1. Tunnel; 2. Rock plug; 3. Slag pit; 4. Water cushion; 31. Slag pit entrance; 32. Slag pit exit; 5. First recoil arc; 6. First guide plate; 7. First diversion area; 8. First diversion area; 9. First counter-charge area; 10. Gate shaft assembly; 101. First gate shaft; 102. First gate; 11. First speed limit pit; 111. First speed limit entrance; 112. First speed limit exit; 113. Second recoil arc; 114. Second guide plate; 115. Second diversion area; 116. First The second diversion area; 117, the second counter-attack area; 12, the second speed limit pit; 121, the second speed limit entrance; 122, the second speed limit exit; 123, the third recoil arc; 124, the third guide plate; 125, the third diversion area; 126, the third diversion area; 127, the third counter-attack area; 13, the first slope section; 14, the second slope section; 16, the operating platform; 17, the air pipe; 18, the control valve; 19, the pressure gauge; 103, the second gate well; 104, the second gate; 20, the reservoir; 21, the air cushion. DETAILED DESCRIPTION
[0058] In the following, only some exemplary embodiments are briefly described. As those skilled in the art will appreciate, the described embodiments may be modified in various ways without departing from the spirit or scope of the present application. Therefore, the drawings and descriptions are considered to be exemplary and non-restrictive in nature.
[0059] Embodiment 1:
[0060] like Figure 1As shown, the embodiment of the present application provides a counter-impact deceleration airtight underwater rock plug blasting device, comprising a tunnel 1, a slag collection pit 3, a first recoil arc 5, a first guide plate 6 and a gate shaft assembly 10. Among them, a rock plug 2 is provided at the water inlet of the tunnel 1; the slag collection pit 3 is located at the water inlet of the tunnel 1, and a water cushion 4 is provided in the slag collection pit 3. The slag collection pit 3 has a slag collection pit inlet 31 and a slag collection pit outlet 32. The slag collection pit inlet 31 is located on one side of the rock plug 2, and the slag collection pit outlet 32 is connected to the water outlet of the tunnel 1. The first recoil arc 5 is located in the slag collection pit 3, and the first guide plate 6 is located in the first recoil arc 5. The side of the first guide plate 6 away from the first recoil arc 5 forms a first diversion area 7, and the side of the first guide plate 6 close to the first recoil arc 5 forms a first diversion area 8. The first diversion area 7 and the first guide area 8 form a first counter-impact area 9 near the slag collection pit outlet 32. The gate well assembly 10 comprises a first gate well 101 , which is located at the water outlet of the tunnel 1 . A first gate 102 is arranged in the first gate well 101 , and the first gate 102 is used to control the opening and closing of the water outlet of the tunnel 1 .
[0061] Before blasting the rock plug 2, the counter-impact deceleration and airtight underwater rock plug blasting device of the embodiment of the present application needs to first close the first gate 102 to make the interior of the tunnel 1 in a closed state. Since the present embodiment is provided with a slag collection pit 3 and a water cushion 4 is provided in the slag collection pit 3, when the rock plug 2 is blasted, the water cushion 4 provides a strong resistance to the rock debris flying into the water cushion 4, dissipates and absorbs the kinetic energy of the rock debris, reduces the rock debris flying out of the slag collection pit 3, and avoids the flying rock debris from blocking the tunnel 1 and causing damage to the first gate 102. Since the first recoil arc 5 and the first guide plate 6 are provided, the blasting shock wave entering through the entrance of the slag collection pit 3 can be reflected multiple times in the slag collection pit 3 to attenuate its intensity, block the shock wave from entering the tunnel 1, and avoid the first gate 102 from being damaged by the impact. The mixed fluid of water, gas, etc. entering through the entrance of the slag pit 3 is diverted after encountering the first guide plate 6, and part of the fluid enters the first diversion area 7, and part of the fluid enters the first diversion area 8. The fluid entering the first diversion area 7 and the fluid entering the first diversion area 8 collide in the first counter-charge area 9, producing a blocking effect, greatly reducing the speed of the fluid, and preventing the fluid from bringing rock slag into the tunnel 1 to cause siltation and blockage. The embodiment of the present application is provided with a slag pit 3, a first recoil arc 5 and a first guide plate 6, and in the case of no plugging, the damage of the blasting shock wave to the first gate 102 is avoided, and the casting and removal of the traditional plug and the drainage of the gate well are avoided, thereby improving the construction efficiency and reducing the project cost.
[0062] Since a water cushion 4 is provided in the slag pit 3, the water cushion 4 dissipates and absorbs the kinetic energy of the slag when the rock plug 2 is blasted, and the greater the speed of the slag, the more significant the energy dissipation effect, thereby greatly limiting the movement distance of the slag, and effectively preventing the slag from directly colliding with the lining in the tunnel 1 and causing damage to the lining. The water cushion 4 can also absorb the heat of the high-temperature blasting gas very well, reduce the temperature of the blasting gas, and thus reduce the pressure of the blasting gas. In addition, the slag entering the slag pit 3 can be reflected in the slag pit 3, thereby effectively preventing the slag from splashing and rebounding into the interior of the tunnel 1 during blasting, and avoiding siltation and blockage in the tunnel 1 caused by the entry of slag.
[0063] For the fluid flowing from the tunnel 1 into the slag collection pit 3, the first recoil arc 5 and the first guide plate 6 will not have a blocking effect on the fluid, and the fluid can flow through with low resistance, and the flow rate of the fluid changes slightly after passing through the first recoil arc 5 and the first guide plate 6. For the fluid flowing from the slag collection pit inlet 31 into the slag collection pit 3, the first guide plate 6 and the first recoil arc 5 can achieve low-resistance flow of low-speed fluid and high-resistance flow of high-speed fluid.
[0064] like Figure 1 As shown by the arrow in the middle, assuming that the pressure value of the mixed fluid ① of water, gas, etc. is P1, the fluid ① is divided into fluid ② and fluid ③ after encountering the first guide plate 6. After the fluid ② enters the first drainage area 7, it flows to the slag pit outlet 32, and the fluid ③ enters the first guide area 8 and flows to the slag pit outlet 32. Under the guidance of the first recoil arc 5 and the first guide plate 6, the fluid ③ forms a backflow, and collide with the fluid ② in the first counter-attack area 9 at an angle α, resulting in a blocking effect, hindering the overall forward flow of the fluid, greatly reducing the overall speed of the fluid, and thus greatly reducing the ability of the water flow to carry rock debris, so as to avoid the water flow bringing rocks into the tunnel 1 and causing siltation and blockage. After the counter-attack and energy dissipation, the fluid ② and the fluid ③ converge into the fluid ④. Assuming that the pressure value of the fluid ④ is P4, the resistance pressure Pc of the first guide plate 6 and the first recoil arc 5 is Pc=P4-P1.
[0065] In this embodiment, the size of fluid ② and fluid ③ can be adjusted by adjusting the position and setting angle of the first guide plate 6 in the circuit, and the impact angle α of fluid ② and fluid ③ can be adjusted by adjusting the curvature of the first recoil arc 5, 0°≤α≤90°.
[0066] The blocking effect is closely related to the density and velocity of fluid ①, the position and angle of the first guide plate 6 in the circuit, and the impact angle α of fluid ② and fluid ③. The greater the velocity of fluid ①, the greater the impact strength, the greater the resistance pressure Pc, and the more significant the blocking effect; the smaller the velocity of fluid ①, the smaller the impact strength, the smaller the resistance pressure Pc, and the less obvious the blocking effect. Compared with the flow velocity V0 without the impact blockage, the flow velocity after the speed limit by the first guide plate 6 and the first recoil arc 5 can be reduced by 1% to 80%, wherein the greater the velocity of fluid ①, the greater the percentage of the flow velocity reduced after the speed limit, and the smaller the velocity of fluid ①, the smaller the percentage of the flow velocity reduced after the speed limit. Therefore, by selecting the appropriate position and angle of the first guide plate 6 and the impact angle α of fluid ② and fluid ③, the effect of low-speed fluid low-resistance flow and high-speed fluid high-resistance flow blocking can be achieved.
[0067] The blasting shock wave and the blasting gas generate huge pressure at the slag pit entrance 31 of the slag pit 3, and act on the water cushion 4. The closer to the rock plug 2, the greater the pressure, and the greater the pressure on the water surface, and vice versa. In the slag pit 3, near the slag pit entrance 31, the water cushion 4 is impacted by the shock wave, squeezed by the high-pressure blasting gas, and collided with the high-speed rock slag, forming a high-pressure and high-speed "water-gas" mixed fluid ① with the blasting gas, and is separated into an upper fluid ② and a lower fluid ③ when encountering the first guide plate 6. The upper fluid ② moves rapidly toward the low-pressure tunnel 1 along the side of the first guide plate 6 away from the first recoil arc 5, and at the same time, the lower fluid ③ moves toward the low-pressure tunnel 1 along the side of the first guide plate 6 close to the first recoil arc 5, and is guided by the first recoil arc 5 to form a backflow. The lower fluid ③ collides with the fluid ② at a high speed in the first collision area 9, encounters great resistance, and forms a blocking effect, which greatly reduces the speed and flow rate of fluid ② and fluid ③ entering the tunnel 1, thereby greatly reducing the ability of the water flow to carry rock debris, so as to effectively prevent fluid ② and fluid ③ from carrying rock debris to the tunnel 1 to form siltation and blockage.
[0068] like Figure 2 As shown, in one embodiment, the counter-speed reduction airtight underwater rock plug blasting device further includes a first speed limit pit 11, which is located in the tunnel 1, and the first speed limit pit 11 is located between the slag collection pit 3 and the first gate shaft 101. The first speed limit pit 11 has a first speed limit inlet 111 and a first speed limit outlet 112, the first speed limit inlet 111 is connected to the slag collection pit outlet 32 of the slag collection pit 3, and the first speed limit outlet 112 is connected to the water outlet of the tunnel 1. The first speed limit pit 11 includes a second recoil arc 113 and a second guide plate 114. The second guide plate 114 is located in the second recoil arc 113. The side of the second guide plate 114 away from the second recoil arc 113 forms a second diversion area 115. The side of the second guide plate 114 close to the second recoil arc 113 forms a second diversion area 116. The second diversion area 115 and the second guide area 116 form a second counter-attack area 117 near the second speed limit outlet 122.
[0069] The first speed limit pit 11 is set in the tunnel 1 adjacent to the slag collection pit 3. The first speed limit pit 11 includes a second recoil arc 113 and a second guide plate 114, which are similar to the structure composed of the first recoil arc 5 and the first guide plate 6, and the working principle is also similar. Similarly, for the fluid flowing from the tunnel 1 to the slag collection pit 3, the second recoil arc 113 and the second guide plate 114 can achieve low-resistance flow; for the fluid flowing from the slag collection pit 3 to the first speed limit pit 11, the second recoil arc 113 and the second guide plate 114 can achieve low-resistance flow of low-speed fluid and high-resistance flow of high-speed fluid.
[0070] like Figure 2 As shown in , the fluid ④ flowing out of the slag pit 3 is divided into fluid ⑤ and fluid ⑥ after encountering the second guide plate 114. After the fluid ⑥ enters the second diversion area 115, it flows toward the first speed limit outlet 112. After the fluid ⑤ enters the second guide area 116, it flows toward the first speed limit outlet 112. Under the guidance of the second recoil arc 113 and the second guide plate 114, the fluid ⑤ forms a backflow, and is collided with the fluid ⑥ in the second counter-attack area 117 at an angle β to converge into the fluid ⑦. Due to the blocking effect of the counter-attack, the overall forward flow of the fluid is hindered, and the overall speed of the fluid is greatly reduced, thereby greatly reducing the ability of the water flow to carry rock slag, so as to avoid the water flow bringing rocks into the tunnel 1 and causing siltation and blockage. The setting of the first speed limit pit 11 can prevent the shock wave transmitted from the slag pit 3 from directly impacting the first gate 102, and further reflect the blasting shock wave, dissipate the energy of the shock wave, and avoid the blasting shock wave from causing damage to the first gate 102. The first speed limiting pit 11 further increases the resistance of the water flow from the reservoir 20 to enter the tunnel 1 after blasting, thereby significantly reducing the maximum water flow speed and the ability of the water flow to carry rock debris, so as to avoid the water flow bringing rock debris into the tunnel 1 and causing siltation and blockage.
[0071] In one embodiment, the counter-speed reduction air-tight underwater rock plug blasting device further comprises a second speed limit pit 12, which is located in the tunnel 1, and the second speed limit pit 12 is located between the first speed limit pit 11 and the first gate shaft 101. The second speed limit pit 12 has a second speed limit entrance 121 and a second speed limit exit 122, the second speed limit entrance 121 is connected to the first speed limit exit 112, and the second speed limit exit 122 is connected to the water outlet of the tunnel 1. The second speed limit pit 12 comprises a third recoil arc 123 and a third guide plate 124, the third guide plate 124 is located in the third recoil arc 123, a side of the third guide plate 124 away from the third recoil arc 123 forms a third diversion area 125, a side of the third guide plate 124 close to the third recoil arc 123 forms a third diversion area 126, and the third diversion area 125 and the third diversion area 126 form a third counter-speed area 127 near the second speed limit exit 122.
[0072] The second speed limit pit 12 includes a third recoil arc 123 and a third guide plate 124, which are similar in structure to the first recoil arc 5 and the first guide plate 6, and have similar working principles. Similarly, for the fluid flowing from the tunnel 1 to the slag collection pit 3, the third recoil arc 123 and the third guide plate 124 can achieve low-resistance flow; for the fluid flowing from the slag collection pit 3 to the first speed limit pit 11, the third recoil arc 123 and the third guide plate 124 can achieve low-resistance flow for low-speed fluids and high-resistance flow for high-speed fluids.
[0073] like Figure 2 As shown in , the fluid ⑦ flowing out of the first speed limit pit 11 is divided into fluid ⑧ and fluid ⑨ after encountering the third guide plate 124. After the fluid ⑨ enters the third diversion area 125, it flows toward the second speed limit outlet 122. After the fluid ⑧ enters the third guide area 126, it flows toward the second speed limit outlet 122. Under the guidance of the third recoil arc 123 and the third guide plate 124, the fluid ⑧ forms a backflow, and collide with the fluid ⑨ in the second collision area 117 to converge into fluid ⑩. Due to the blocking effect caused by the collision, the overall forward flow of the fluid is hindered, which greatly reduces the overall speed of the fluid, thereby greatly reducing the ability of the water flow to carry rock debris, so as to avoid the water flow bringing rocks into the tunnel 1 and causing siltation and blockage. The setting of the second speed limit pit 12 can prevent the shock wave transmitted from the first speed limit pit 11 from directly impacting the first gate 102, and further reflect the blasting shock wave, dissipate the energy of the shock wave, and avoid the blasting shock wave from causing damage to the first gate 102. The second speed limiting pit 12 further increases the resistance of the water flow from the reservoir 20 to enter the tunnel 1 after blasting, thereby significantly reducing the maximum water flow speed and the ability of the water flow to carry rock debris, so as to avoid the water flow bringing rock debris into the tunnel 1 and causing siltation and blockage.
[0074] In order to achieve the connection between the slag pit 3 and the first speed limit pit 11, a first slope section 13 is provided in the tunnel 1, one end of the first slope section 13 is connected to the slag pit outlet 32, the other end of the first slope section 13 is connected to the first speed limit entrance 111, and one end of the first slope section 13 is inclined upward relative to the other end. In order to achieve the connection between the first speed limit pit 11 and the second speed limit pit 12, a second slope section 14 is provided in the tunnel 1, one end of the second slope section 14 is connected to the first speed limit exit 112, the other end of the second slope section 14 is connected to the second speed limit entrance 121, and one end of the second slope section 14 is inclined upward relative to the other end. By setting the first slope section 13 and the second slope section 14, it is ensured that the first gate shaft 101 is located at a high place in the tunnel 1, so that the bottom height of the first gate shaft 101 is higher than the heights of the slag pit 3, the first speed limit pit 11 and the second speed limit pit 12.
[0075] An air pipe 17 is provided on the operating platform 16 above the first gate shaft 101, one end of the air pipe 17 is provided with a control valve 18, and the other end of the air pipe 17 is located inside the tunnel 1 after passing through the first gate shaft 101, and a pressure gauge 19 is provided inside the tunnel 1. Preferably, the diameter of the air pipe 17 can be set to 0.05-0.2m, and the air pipe 17 can be pre-buried in the lining of the tunnel 1 and the wall of the first gate shaft 101. The air intake and exhaust of the air pipe 17 can be controlled by the control valve 18, and the air pressure in the tunnel 1 can be detected by the setting of the pressure gauge 19. The pressure gauge 19 can be an existing pressure gauge with a wireless transmission function, which can transmit the detected pressure data, thereby facilitating the reading of the pressure in the tunnel 1.
[0076] The gate well assembly 10 further includes a second gate well 103, which is located on one side of the first gate well 101 and communicates with the tunnel 1. A second gate 104 for controlling the water flow in the tunnel 1 is arranged in the second gate well 103. When the first gate 102 is closed, the tunnel 1 upstream of the first gate well 101 can be in a closed state. After the tunnel 1 is closed, when the water flows rapidly into the tunnel 1, an air cushion 21 with good deformation performance can be formed between the tunnel 1 and the first gate 102 to buffer the transient flow in the tunnel 1 and reduce the peak pressure of the transient flow.
[0077] In order to avoid affecting the tight closure of the first gate 102, the elevation of the bottom plate of the first gate shaft 101 is higher than the elevation of the bottom plate of the tunnel 1 at the connection with the first gate shaft 101, and the height difference can be 0.1 to 0.5 m to prevent the sediment in the tunnel 1 from entering the first gate shaft 101 and the second gate shaft 103 when the tunnel 1 is permanently in operation.
[0078] The counter-deceleration airtight underwater rock plug blasting device of the embodiment of the present application does not need to set a plug, thus avoiding the pouring and removal of the plug and the filling and drainage of the gate well in the traditional blasting process, simplifying the process, improving the project quality, shortening the construction period, and greatly saving the project investment. It avoids the damage to the lining, gate well and gate slot of the tunnel 1 caused by the removal of the plug and the slag discharge construction, avoids the drainage of the second gate well 103, simplifies the operation process and steps of the underwater rock plug 2 blasting, and is conducive to the control of the construction process, improves the project quality, and reduces the construction safety risk.
[0079] The embodiment of the present application can effectively eliminate the adverse effects of the blasting shock wave on the first gate 102 through the provision of the slag collecting pit 3, the water cushion 4, the first recoil arc 5, the first guide plate 6, the first speed limit pit 11, the second speed limit pit 12, etc., effectively avoid the damage of the gate shaft groove by the water hammer wave, effectively prevent the gushing water from bringing rock debris to the tunnel 1 to form siltation and blockage, effectively reduce the transient flow pressure peak of the tunnel 1, and effectively reduce the oscillation time of the transient flow in the tunnel 1.
[0080] The embodiment of the present application can greatly buffer the water hammer pressure of the water flow in the tunnel 1, thereby effectively reducing the dynamic load impact of the transient flow of the gushing water on the first gate 102. Therefore, compared with the gate of the normal working of the conventional tunnel 1, the embodiment of the present application can create a better hydraulic environment in the tunnel, so that the dynamic load pressure borne by the gate is smaller. When designing the structural strength of the first gate 102, it is not necessary to increase the design load due to the blasting shock wave and the gushing water impact, thereby improving the material utilization rate of the first gate 102. Although the present application directly adopts the first gate 102 to seal the tunnel 1, the first gate 102 still only needs to design the bearing capacity according to the static and dynamic water pressure of the normal working of the tunnel 1, and there is no need to increase the design bearing capacity due to the blasting water blocking situation, that is, there is no need to increase the cost of the first gate 102 due to the blasting water blocking. The water cushion 4 in the slag collection pit 3 plays an energy dissipation role on the high-speed rock slag, greatly reducing the movement speed of the rock slag, thereby reducing the collision and damage of the rock slag to the lining, and also reducing the possibility of rock slag splashing into the tunnel 1 to cause siltation and blockage. In addition, the present application can also optimize the speed limiting effect by selecting appropriate positions and angles of the first guide plate 6, the second guide plate 114 and the third guide plate 124, and the impact angles α and β, and is flexible to use.
[0081] The number of the first speed limit pit 11 and the second speed limit pit 12 can be set as needed. The first speed limit pit 11 and the second speed limit pit 12 may not be set, or only the first speed limit pit 11 may be set without the second speed limit pit 12, or the number of speed limit pits may be further increased. The number of speed limit pits may be increased or decreased according to actual usage. When the difference between the water level of the reservoir 20 and the top elevation of the gate well bottom plate is ≥50m, two or more speed limit pits may be set.
[0082] Embodiment 2:
[0083] The present embodiment is described in detail below with reference to the first embodiment:
[0084] like Figures 3 to 7 As shown, the embodiment of the present application provides a counter-impact deceleration and air-tight underwater rock plug blasting method, which is applied to the counter-impact deceleration and air-tight underwater rock plug blasting device as described in Example 1, and the counter-impact deceleration and air-tight underwater rock plug blasting method comprises the following steps:
[0085] S1: excavating the first gate shaft 101 and lining the first gate shaft 101.
[0086] Before this step, the operating platform 16 above the first gate shaft 101 needs to be arranged first, and then the first gate shaft 101 and the second gate shaft 103 are excavated from top to bottom, and the first gate shaft 101 and the second gate shaft 103 are lined.
[0087] S2: excavate the tunnel 1 and the slag collection pit 3 along the bottom of the first gate shaft 101 to the upstream reservoir 20 until the side of the rock plug 2, set the first recoil arc 5 and the first guide plate 6 in the slag collection pit 3, and line the tunnel 1 and the slag collection pit 3. During the excavation of the tunnel 1, set the first speed limit pit 11 and / or the second speed limit pit 12 in the tunnel.
[0088] S3: Select a drilling position on the rock plug 2 and drill a blast hole, and install explosives for blasting in the blast hole. The explosives for blasting can be controlled through networking.
[0089] S4: inject water to a certain depth into the slag collecting pit 3 to form a water cushion 4.
[0090] S5: Close the first gate 102 in the first gate shaft 101, and make the tunnel 1 in a closed state through the first gate 102.
[0091] After closing the first gate 102, it is also necessary to close the control valve 18 on the air pipe 17 to ensure that the tunnel 1 located upstream of the first gate shaft 101 is in a closed state.
[0092] S6: Blasting the rock plug 2 to achieve connection between the reservoir 20 and the tunnel 1.
[0093] After the blasting is carried out, the rock plug 2 forms rock slag, which realizes the connection between the reservoir 20 and the tunnel 1. The reservoir 20 gushes water into the tunnel 1, and the speed of the gushing water flow is attenuated after passing through the slag pit 3, the first speed limit pit 11 and / or the second speed limit pit 12. After a period of sufficient energy dissipation, the rock slag gathers near the slag pit 3 and the original rock plug 2. The pressure value in the tunnel 1 is read by the pressure gauge 19. After the pressure in the tunnel 1 is stable, the control valve 18 on the air pipe 17 is opened to slowly exhaust the mixed gas in the tunnel 1. Then close the second gate 104, open the first gate 102, and then control the water diversion flow in the tunnel 1 through the second gate 104.
[0094] The working principle of the counter-impact deceleration and air-tight underwater rock plug blasting method of this embodiment is as follows:
[0095] The water cushion 4 in the slag pit 3 dissipates the energy of the high-speed rock slag, greatly reducing the movement speed of the rock slag, thereby reducing the collision and damage of the rock slag to the lining, and also reducing the possibility of the rock slag splashing into the tunnel 1. The blasting shock wave and the high-temperature and high-pressure detonation gas form high pressure in the middle and front part of the slag pit 3, and act on the water cushion 4 to form a high-speed water-gas mixed fluid ①, and quickly move to the low-pressure tunnel 1. After encountering the first guide plate 6 and the first recoil arc 5, the shock wave is reflected and attenuated many times in the slag pit 3, so that the propagation is blocked and the destructive force is greatly weakened. At the same time, when the fluid ① moves to the first guide plate 6 in the slag pit 3, it is divided into fluid ② and fluid ③ by the guide plate. After entering the first drainage area 7, fluid ② flows toward the slag pit outlet 32. After entering the first diversion area 8, fluid ③ flows toward the slag pit outlet 32. Under the guidance of the first recoil arc 5 and the first guide plate 6, fluid ③ forms a backflow and collide with fluid ② in the first counter-impact area 9 at an angle α, producing a blocking effect, hindering the overall forward flow of the fluid, greatly reducing the overall velocity of the fluid, and thus greatly reducing the ability of the water flow to carry rock debris, so as to avoid the water flow bringing rocks into the tunnel 1 and causing siltation and blockage. After the counter-impact energy dissipation, fluid ② and fluid ③ converge into fluid ④.
[0096] After leaving the slag collection pit 3, the fluid ④ passes through the first slope section 13 and enters the first speed limit pit 11. After encountering the second guide plate 114, the fluid ④ flowing out of the slag collection pit 3 is divided into fluid ⑤ and fluid ⑥. After entering the second diversion area 115, the fluid ⑥ flows toward the first speed limit outlet 112. After entering the second diversion area 116, the fluid ⑤ flows toward the first speed limit outlet 112. Under the guidance of the second recoil arc 113 and the second guide plate 114, the fluid ⑤ forms a backflow and is countered with the fluid ⑥ in the second counter-attack area 117 at an angle β to converge into the fluid ⑦. Due to the blocking effect of the counter-attack, the overall forward flow of the fluid is hindered, which greatly reduces the overall speed of the fluid, thereby greatly reducing the ability of the water flow to carry slag, so as to avoid the water flow bringing rocks into the tunnel 1 and causing siltation and blockage. The setting of the first speed limiting pit 11 can prevent the shock wave transmitted from the slag collecting pit 3 from directly impacting the first gate 102 , and further reflect the blasting shock wave, dissipate the energy of the shock wave, and avoid the blasting shock wave from causing damage to the first gate 102 .
[0097] After the shock wave dissipates energy in the first speed limit pit 11, it enters the second speed limit pit 12 after passing through the second slope section 14. The shock wave is reflected and attenuated multiple times in the third guide plate 124, the third recoil arc 123 and the tunnel 1, so that the propagation is further blocked and the destructive force is further greatly weakened. At the same time, the fluid ⑦ flowing out of the first speed limit pit 11 is divided into fluid ⑧ and fluid ⑨ after encountering the third guide plate 124. After fluid ⑨ enters the third diversion area 125, it flows toward the second speed limit outlet 122. After fluid ⑧ enters the third guide area 126, it flows toward the second speed limit outlet 122. Under the guidance of the third recoil arc 123 and the third guide plate 124, fluid ⑧ forms a backflow, and collide with fluid ⑨ in the second collision area 117 to converge into fluid ⑩. Due to the blocking effect caused by the collision, the overall forward flow of the fluid is hindered, the overall speed of the fluid is greatly reduced, and thus the ability of the water flow to carry rock debris is greatly reduced, so as to avoid the water flow bringing rocks into the tunnel 1 to cause siltation and blockage.
[0098] The second speed limit pit 12 can prevent the shock wave from the first speed limit pit 11 from directly impacting the first gate 102, and further reflect the blasting shock wave, dissipate the energy of the shock wave, and prevent the blasting shock wave from causing damage to the first gate 102. The second speed limit pit 12 further increases the resistance of the water flow from the reservoir 20 to enter the tunnel 1 after the blasting, thereby greatly reducing the maximum water flow speed and the ability of the water flow to carry rock debris, so as to prevent the water flow from bringing rock debris into the tunnel 1 and causing siltation and blockage.
[0099] After leaving the second speed limit pit 12, the fluid ⑩ enters the end of the tunnel 1 with an upward slope. Since the tunnel 1 is sealed by the air pipe 17 and the first gate 102, the detonation gas and the water in the reservoir 20 rush into the slag pit 3 and the tunnel 1, occupying the space in the tunnel 1 and squeezing the air in the tunnel 1. The detonation gas mixes with the air in the tunnel 1 to form a mixed gas. The pressure of the mixed gas is greater than the air pressure in the tunnel 1 before the explosion, and reacts to the water flowing into the tunnel 1, with a tendency to hinder the water from flowing into the tunnel 1. The more water flows into the tunnel 1, the smaller the volume of the mixed gas, the greater the pressure, and the stronger the effect of hindering the water from flowing in. Until the water stops flowing in, the pressure of the mixed gas reaches the maximum, and is greater than the hydrostatic pressure in the tunnel 1, with a tendency to push the water flow in the opposite direction.
[0100] Since the pressure of the mixed gas is greater than the hydrostatic pressure in the tunnel 1, after a transient state of stillness, the water flow is pushed to move in the opposite direction, resulting in the phenomenon of tunnel 1 spitting back into the reservoir 20. Since the first guide plate 6, the first recoil arc 5, the first speed limit pit 11, and the second speed limit pit 12 have little resistance to the backflow, the impact is relatively weak. During the spitting process, the volume of the mixed gas in the tunnel 1 increases, the pressure decreases, and the driving effect on the water flow decreases. Until the water flow stops spitting back, at this time the pressure of the mixed gas is less than the hydrostatic pressure in the tunnel 1, and the water flow tends to rush into the tunnel 1.
[0101] Since the pressure of the mixed gas is lower than the hydrostatic pressure in tunnel 1, after a transient state of stillness, the water flows into tunnel 1 again, and is decelerated by the first speed limit pit 11 and the second speed limit pit 12 again, and the speed is further greatly reduced. After multiple influx and spitting processes and multiple energy dissipation and deceleration, the water flow in tunnel 1 eventually stabilizes and reaches equilibrium. At this time, the pressure of the mixed gas in tunnel 1 is equal to the hydrostatic pressure in tunnel 1, and the reading of the pressure gauge 19 stabilizes at the hydrostatic pressure. The slag is deposited at the bottom of the reservoir or the slag pit 3 and tends to be stable. Then open the control valve 18, exhaust the mixed gas in tunnel 1 through the air pipe 17, close the second gate 104, and then slowly open the first gate 102. After checking that everything is correct, open the second gate 104, and then the reservoir and tunnel are connected.
[0102] It should be noted that the structures used for opening and closing the first gate 102 and the second gate 104 are all existing technologies.
[0103] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine different embodiments or examples described in this specification and the features of different embodiments or examples, unless they are contradictory.
[0104] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include at least one of the features. In the description of this application, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.
[0105] The above is only a specific implementation of the present application, but the protection scope of the present application is not limited thereto. Any technician familiar with the technical field can easily think of various changes or substitutions within the technical scope disclosed in the present application, which should be included in the protection scope of the present application. Therefore, the protection scope of the present application should be based on the protection scope of the claims.
Claims
1. A counter-impact, deceleration and air-locking underwater rock plug blasting device, characterized in that: include: A tunnel, wherein a rock plug is provided at a water inlet of the tunnel; A slag collecting pit, the slag collecting pit is located at the water inlet of the tunnel, a water cushion is arranged in the slag collecting pit, the slag collecting pit has a slag collecting pit inlet and a slag collecting pit outlet, the slag collecting pit inlet is located on one side of the rock plug, and the slag collecting pit outlet is connected to the water outlet of the tunnel; a first recoil arc, wherein the first recoil arc is located in the slag collection pit; A first guide plate, wherein the first guide plate is located in the first recoil arc, a side of the first guide plate away from the first recoil arc forms a first guide area, a side of the first guide plate close to the first recoil arc forms a first guide area, and the first guide area and the first guide area form a first counter-impact area near the outlet of the slag collection pit; A gate well assembly, the gate well assembly includes a first gate well, the first gate well is located at the water outlet of the tunnel, a first gate is arranged in the first gate well, and the first gate is used to control the opening and closing of the water outlet of the tunnel.
2. The impact deceleration air-tight underwater rock plug blasting device according to claim 1 is characterized in that: The counter-impact deceleration and air-locking underwater rock plug blasting device also includes: A first speed limit pit, wherein the first speed limit pit is located in the tunnel, the first speed limit pit is located between the slag collection pit and the first gate shaft, the first speed limit pit has a first speed limit entrance and a first speed limit exit, the first speed limit entrance is connected to the slag collection pit exit, and the first speed limit exit is connected to the water outlet of the tunnel; the first speed limit pit comprises a second recoil arc and a second guide plate, the second guide plate is located in the second recoil arc, a side of the second guide plate away from the second recoil arc forms a second diversion area, a side of the second guide plate close to the second recoil arc forms a second diversion area, and the second diversion area and the second guide area form a second counter-flow area near the second speed limit exit.
3. The impact deceleration air-tight underwater rock plug blasting device according to claim 2 is characterized in that: The counter-impact deceleration and air-locking underwater rock plug blasting device also includes: A second speed limit pit, wherein the second speed limit pit is located in the tunnel, the second speed limit pit is located between the first speed limit pit and the first gate shaft, the second speed limit pit has a second speed limit entrance and a second speed limit exit, the second speed limit entrance is connected with the first speed limit exit, the second speed limit exit is connected with the water outlet of the tunnel, the second speed limit pit comprises a third recoil arc and a third guide plate, the third guide plate is located in the third recoil arc, a side of the third guide plate away from the third recoil arc forms a third diversion area, a side of the third guide plate close to the third recoil arc forms a third diversion area, and the third diversion area and the third guide area form a third counter-attack area near the second speed limit exit.
4. The impact deceleration air-tight underwater rock plug blasting device according to claim 3 is characterized in that: The tunnel has a first slope section, one end of which is connected to the slag collection pit outlet, the other end of which is connected to the first speed limit entrance, and one end of the first slope section is inclined upward relative to the other end.
5. The impact deceleration air-tight underwater rock plug blasting device according to claim 3 is characterized in that: The tunnel has a second slope section, one end of the second slope section is connected to the first speed limit exit, the other end of the second slope section is connected to the second speed limit entrance, and one end of the second slope section is inclined upward relative to the other end.
6. The impact, deceleration and airtight underwater rock plug blasting device according to any one of claims 1 to 5, characterized in that: An air pipe is provided on the operating platform above the first gate shaft, a control valve is provided at one end of the air pipe, and the other end of the air pipe is located inside the tunnel after passing through the first gate shaft, and a pressure gauge is provided inside the tunnel.
7. The impact, deceleration and airtight underwater rock plug blasting device according to any one of claims 1 to 5, characterized in that: The gate well assembly also includes a second gate well, which is located on one side of the first gate well and communicates with the tunnel. A second gate for controlling the water flow in the tunnel is arranged in the second gate well.
8. The impact, deceleration and airtight underwater rock plug blasting device according to any one of claims 1 to 5, characterized in that: The elevation of the bottom plate of the first gate shaft is higher than the elevation of the bottom plate of the tunnel at the location where the tunnel is connected to the first gate shaft.
9. The impact, deceleration and airtight underwater rock plug blasting device according to any one of claims 1 to 5, characterized in that: The fluid flowing through the first drainage area and the fluid flowing through the first guide area have an impact angle α in the first impact area, and the range of the impact angle α is: 0°≤α≤90°.
10. A counter-impact, deceleration and air-locking underwater rock plug blasting method, characterized in that: The counter-impact deceleration and airtight underwater rock plug blasting method is applied to the counter-impact deceleration and airtight underwater rock plug blasting device according to any one of claims 1 to 9, and the counter-impact deceleration and airtight underwater rock plug blasting method comprises the following steps: excavating a first gate well and lining the first gate well; Excavating a tunnel and a slag collection pit along the bottom of the first gate shaft to the upstream reservoir until the side of the rock plug; setting a first recoil arc and a first guide plate in the slag collection pit, and lining the tunnel and the slag collection pit; Selecting a drilling position on the rock plug and drilling a blast hole, and installing explosives for blasting in the blast hole; Injecting a certain depth of water into the slag collection pit to form a water cushion; closing the first gate in the first gate shaft, so that the tunnel is in a sealed state through the first gate; The rock plug is blasted to achieve the connection between the reservoir and the tunnel.
Citation Information
Patent Citations
Electric power plant circulating water rock plug type intake and construction method
CN101413255A
Underwater rock plug blasting construction method
CN104748632A
Rock plug blasting model test water-pressure testing method
CN104762918A
Vortex-free rock-plug blasting arrangement structure in open water area for secret-related projects
CN110260734A
Reservoir area diversion tunnel inlet rock plug blasting construction method
CN118128003A