In-situ calibration self-cleaning pore water pressure gauge
By using micron-scale graphite balls and self-cleaning driving mechanisms in the pore water pressure gauge, the problem of permeable stone blockage is solved, and the continuous detection and simplified proofreading process of the pore water pressure gauge is realized, which improves the accuracy and convenience of measurement sex.
Patent Information
- Application Number
- CN202411016633.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-29
- Publication Date
- 2024-11-12
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The permeable stone in the existing vibrating pore water pressure gauge is prone to blockage, resulting in large errors in the measurement results, and it is impossible to proofread and continuously detect during use, which is troublesome.
A self-cleaning pore water pressure gauge is designed in situ, using micron-scale graphite balls to replace permeable stones. The self-cleaning function is realized through lifting and rotating driving mechanisms, allowing calibration and detection during use, avoiding the blockage of permeable stones. question.
The continuous detection and use of pore water pressure gauge is realized, the proofreading steps are simplified, the limitations of equipment use are reduced, the advance soaking and cleaning steps of permeable stone is avoided, and the accuracy and convenience of measurement are improved.
Smart Images

Figure CN118936724A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of pore water pressure gauges, and in particular to an in-situ calibrated self-cleaning pore water pressure gauge. Background Art
[0002] Pore water pressure monitoring is used to measure the pore water pressure of soil at different depths outside the foundation pit. It plays a very important role in controlling the surface uplift caused by various piles and the surface settlement caused by the excavation of foundation pits. The reason is that the first thing that occurs after saturated soft clay is loaded is the change or migration of pore water pressure, followed by the consolidation and deformation of particles. The change of pore water pressure is a precursor to soil movement. By monitoring the changes in pore water pressure during the construction process, a reliable basis can be provided in time for controlling the pile sinking rate and excavation advance speed, so as to achieve the purpose of serving the construction. The purpose of pore water pressure observation is mainly to monitor the changes in pore water pressure during the construction process. As the basis for construction control, the distribution state of pore water pressure can be used as the basis for stability calculation in regional stability analysis. It is mainly used for foundation vibration compaction, strong compaction and strong compaction replacement, drainage consolidation and densification, construction monitoring of various piles, observation of regional pore water pressure, stability observation of excavated foundation pit slopes, and landslide stability observation.
[0003] At present, the vibrating-wire pore water pressure meter is composed of a reading instrument, a metal shell, a permeable stone, a sensor assembly, a signal transmission cable, etc. Among them, the sensor assembly includes a sensor element and a protective tube. The protective tube is equipped with a sensor element, which includes a pressure sensor and a thermal induction resistor. One end of the protective tube is placed with an inlay of a high-pressure or low-pressure permeable stone, and the other end is introduced with a sealed cable. The permeable stone is sealed with an O-ring at the front end of the protective tube. After passing through the permeable stone, the flexible membrane is isolated from the solid particles and only bears the liquid pressure to be measured. As shown in the attached figure Fig.11 As shown, the pore water pressure gauge is currently installed by drilling and burying. Specifically, a hole 18 is first drilled at the burying location. After reaching the required depth or elevation, the bottom of the hole is first filled with some clean fine sand, and the pore water pressure probe 21 is placed. Then, sand is filled around the pore water pressure probe 21 to form a sand filter layer 19, and finally, the upper part of the pore water pressure probe 21 is sealed with expansive clay 20. The pore water pressure probe 21 should be buried at least one week before construction by the drilling method, so that the excess pore water pressure caused by the burial has enough time to dissipate, thereby improving the accuracy of the subsequent test.
[0004] However, when the drilling method is used for construction, after the mud wall is used to form a hole, it is not easy to clean the hole, which may easily cause the blockage of the permeable stone at the front end of the pore water pressure gauge, resulting in large errors in the measurement results of the pore water pressure gauge. At this time, the sand filter layer 19 and the swelling clay 20 can only be cleaned and then the pore water pressure gauge is taken out to recalibrate the pore water pressure gauge. After the calibration is completed, the pore water pressure probe 21 is put in, and then the sand is filled around the pore water pressure probe 21, and finally the upper part of the pore water pressure probe 21 is sealed with swelling clay 20. It can be seen that the permeable stone in the current vibrating wire pore water pressure gauge is easy to be blocked, and it often needs to be taken out and recalibrated. It cannot be calibrated during use, cannot be continuously tested, and is troublesome to use. Summary of the invention
[0005] (I) The problem to be solved by the present invention is that the permeable stone in the current vibrating-wire pore water pressure gauge is easily clogged and often needs to be taken out and recalibrated. It is impossible to calibrate during use, cannot be continuously tested, and is troublesome to use.
[0006] (II) Technical solution
[0007] An in-situ calibrated self-cleaning pore water pressure gauge comprises a protection tube, a sensing element, a signal line, an outer shell, an inner tube, a cylinder, a water injection pipe, a drainage pipe, a lifting drive mechanism and a rotating drive mechanism; the sensing element is arranged inside the protection tube, and one end of the signal line extends into the protection tube and is connected to the sensing element;
[0008] The outer shell is cylindrical, and has a cylindrical cavity inside. The bottom and top of the outer shell are sealed. The inner tube is coaxially arranged in the cavity of the outer shell, and the cylinder is coaxially arranged inside the inner tube. The bottom end of the protection tube extends into the inside of the cylinder, and the top end of the protection tube extends from the top of the inner tube. The top of the outer shell is provided with a circular hole, and the top outer wall of the protection tube is sealed and connected with the inner wall of the circular hole at the top of the outer shell.
[0009] At least one water through hole is provided on the outer wall of the shell, at least one water passing hole is provided on the outer wall of the inner tube, and at least one water inlet hole is provided on the outer wall of the cylinder, and the water through holes, the water passing holes and the water inlet holes correspond to each other one by one;
[0010] A water inlet cavity is formed between the bottom end of the protection tube and the inner bottom wall of the cylinder, and the water inlet cavity is filled with graphite balls;
[0011] The lifting drive mechanism is used to drive the cylinder to move along the axial direction of the cylinder to reduce or expand the volume of the water inlet cavity;
[0012] The rotation drive mechanism is used to drive the inner tube to rotate around its axis. When the inner tube rotates to a first state, the water hole is connected to the corresponding water inlet hole and the water through hole; when the inner tube rotates to a second state, the water hole is staggered to the corresponding water inlet hole and the water through hole.
[0013] One end of the water injection pipe passes through the protection tube and extends into the water inlet cavity, and one end of the drainage pipe passes through the protection tube and extends into the water inlet cavity.
[0014] As an embodiment of the present invention, the pore water pressure meter includes an airbag assembly, which includes an annular airbag and a plurality of strip airbags connected to the annular airbag, the annular airbag is coaxially arranged on the top of the outer shell, and the plurality of strip airbags are evenly fitted on the side of the outer shell around the axis of the outer shell, and a gap is formed between two adjacent annular airbags.
[0015] As an embodiment of the present invention, the lifting drive mechanism includes a threaded rod, a driving pulley, a driven pulley, a transmission belt and a first motor;
[0016] A fixing seat is installed on the outer wall of the protective tube, and the fixing seat is located on the inner wall of the inner tube and is higher than the cylinder. The top end of the threaded rod is rotatably connected to the fixing seat, and the top end of the cylinder is provided with a threaded hole that passes through the cylinder. The threaded rod is threadedly connected to the threaded hole on the cylinder, and the bottom end of the threaded rod is lower than the cylinder. The driven pulley is fixed to the bottom end of the threaded rod, the first motor is installed on the inner bottom wall of the outer shell, the driving pulley is arranged at the output end of the first motor, and the transmission belt is drivingly connected between the driving pulley and the driven pulley.
[0017] As an embodiment of the present invention, the rotary drive mechanism includes a plurality of gear blocks, a large gear, a small gear and a second motor, the bottom surface of the inner tube is evenly provided with a plurality of gear blocks around its axis, the large gear is rotatably mounted on the inner bottom wall of the outer shell, and the large gear is meshed with the plurality of gear blocks on the bottom surface of the inner tube, the second motor is mounted on the inner bottom wall of the outer shell, the small gear is arranged at the output end of the second motor, and the small gear is meshed with the large gear.
[0018] As an embodiment of the present invention, a gauze mesh is sleeved on the inner wall of the cylinder.
[0019] As an embodiment of the present invention, a gauze is provided in the pipe opening of the water injection pipe extending into one end of the water inlet chamber, and a gauze is provided in the pipe opening of the drainage pipe extending into one end of the water inlet chamber.
[0020] As an embodiment of the present invention, a plurality of water through holes are provided, and the plurality of water through holes are evenly arranged around the axis of the outer shell; a plurality of water passing holes are provided, and the plurality of water passing holes are evenly arranged around the axis of the inner tube; a plurality of water inlet holes are provided, and the plurality of water inlet holes are evenly arranged around the axis of the water inlet holes.
[0021] As an embodiment of the present invention, at least one rubber ring is provided on the inner wall of the cylinder, and the rubber ring is higher than the water inlet hole on the cylinder.
[0022] As an embodiment of the present invention, a plurality of rubber rings are arranged on the inner wall of the inner tube, and the rubber rings are used to seal the gap between the inner tube and the cylinder.
[0023] Beneficial effects of the present invention:
[0024] The present invention provides an in-situ calibrated self-cleaning pore water pressure gauge, comprising a protective tube, a sensor element, a signal line, an outer shell, an inner tube, a cylinder, a water injection pipe, a drainage pipe, a lifting drive mechanism and a rotating drive mechanism; the sensor element is arranged inside the protective tube, and one end of the signal line extends into the interior of the protective tube and is connected to the sensor element; the outer shell is cylindrical, and has a cylindrical cavity inside, the bottom and top of the outer shell are both sealed, the inner tube is coaxially arranged in the cavity of the outer shell, the cylinder is coaxially arranged in the interior of the inner tube, the bottom end of the protective tube extends into the interior of the cylinder, and the top end of the protective tube extends from the top of the inner tube, the top of the outer shell is provided with a circular hole, and the top outer wall of the protective tube is sealed and connected to the inner wall of the circular hole at the top of the outer shell; at least one water hole is provided on the outer wall of the outer shell At least one water hole is provided on the outer wall of the inner tube, and at least one water inlet hole is provided on the outer wall of the cylinder, and the water holes, water holes and water inlet holes correspond to each other one by one; a water inlet cavity is formed between the bottom end of the protective tube and the inner bottom wall of the cylinder, and the water inlet cavity is filled with graphite balls; the lifting drive mechanism is used to drive the cylinder to move along the axial direction of the cylinder to reduce or expand the volume of the water inlet cavity; the rotating drive mechanism is used to drive the inner tube to rotate around its axis, when the inner tube rotates to the first state, the water hole and the corresponding water inlet hole and water hole are connected; when the inner tube rotates to the second state, the water hole and the corresponding water inlet hole and water hole are staggered; one end of the water injection pipe passes through the protective tube and extends into the water inlet cavity, and one end of the drainage pipe passes through the protective tube and extends into the water inlet cavity.
[0025] During proofreading, the cylinder is first driven downward by the lifting drive mechanism. As the cylinder gradually moves downward, the space in the water inlet chamber where the micron-sized graphite balls are located gradually increases. Since the water inlet chamber no longer restricts the micron-sized graphite balls, the micron-sized graphite balls are evenly scattered in the water inlet chamber. At this time, impurities such as mud, sand and gravel are also scattered into the pressurized water in the water inlet chamber. Subsequently, the inner tube is driven to rotate by a rotary drive mechanism, so that when the inner tube rotates to the second state, the water holes on the inner tube and the corresponding water inlet holes on the cylinder and the water holes on the outer shell are staggered, so that external water can no longer enter the interior of the outer shell and can no longer enter the water inlet chamber, so that the water inlet chamber is in a sealed state, and then water is pumped into the water injection pipe on the ground, and the water in the water injection pipe is flushed into the water inlet chamber in the cylinder. With continuous water injection, the water pressure in the water inlet chamber gradually increases, and mud, sand and gravel and other impurities overflow from the water inlet chamber together with the water and flow into the drain pipe, and finally the mud, sand and gravel and other impurities are discharged from the drain pipe together with the water, thereby completing the calibration of the pore water pressure gauge. Finally, the lifting drive mechanism drives the cylinder to move upward, gradually reducing the space of the water inlet chamber, so that the micron-sized graphite is tightly filled in the water inlet chamber again, and then the rotating drive mechanism is used to drive the inner tube to rotate around its axis, so that the inner tube rotates to the first state, and the water hole is connected with the corresponding water inlet hole and water through hole, and the pore water pressure gauge is adjusted to the detection state.
[0026] Compared with the traditional vibrating-wire pore water pressure gauge, the advantages of this pore water pressure gauge mainly include the following points: First, no permeable stone is used, so there is no need to soak the permeable stone in advance to exhaust the air in the permeable stone. Second, micron-grade graphite is used instead of permeable stone, and calibration can be performed at any time. There is no need to clean the sand filter layer and the swelling clay to take out the pore water pressure gauge for calibration. It is simpler and more convenient to use, reduces the tediousness of the calibration work steps, and can be tested continuously, which greatly reduces the limitations of the use of the pore water pressure gauge. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0028] Figure 1 A front view provided for an embodiment of the present invention;
[0029] Figure 2 A structural diagram of an embodiment of the present invention after removing the airbag assembly;
[0030] Figure 3A top view of an embodiment of the present invention with the airbag assembly removed;
[0031] Figure 4 The embodiment of the present invention provides Figure 3 Sectional view of AA in the middle;
[0032] Figure 5 The embodiment of the present invention provides Figure 3 Cross-sectional view of the middle BB;
[0033] Figure 6 The internal structure diagram of the embodiment of the present invention after removing the airbag assembly and the protection tube;
[0034] Figure 7 A structural diagram of an inner tube, a cylinder, a lifting drive mechanism and a rotating drive mechanism provided in an embodiment of the present invention;
[0035] Figure 8 A structural diagram of a protection pipe, a water injection pipe, a drainage pipe and a signal line provided in an embodiment of the present invention;
[0036] Fig. 9 A structural diagram of an inner tube provided in an embodiment of the present invention;
[0037] Fig.10 A structural diagram of a cylinder and a threaded rod provided in an embodiment of the present invention;
[0038] Fig.11 This is a schematic diagram of installing a pore water pressure gauge by drilling and burying in the prior art.
[0039] Icons: 1. Signal line; 2. Water injection pipe; 3. Drain pipe; 4. Annular airbag; 5. Strip airbag; 6. Outer shell; 601. Water hole; 7. Inner tube; 701. Gear block; 702. Water hole; 8. Cylinder; 801. Gauze; 802. Water inlet hole; 9. Protective tube; 10. Threaded rod; 11. Large gear; 12. First motor; 13. Small gear; 14. Driving pulley; 15. Driven pulley; 16. Transmission belt; 17. Second motor; 18. Holes; 19. Sand filter layer; 20. Swelling clay; 21. Pore water pressure probe. DETAILED DESCRIPTION
[0040] The technical solution of the present invention will be clearly and completely described below in conjunction with the embodiments. Obviously, the described embodiments are part of the embodiments of the present invention, rather than all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0041] like Figure 1-Figure 10As shown, an embodiment of the present invention provides an in-situ calibrated self-cleaning pore water pressure gauge, including a protection tube 9, a sensor element, a signal line 1, an outer shell 6, an inner tube 7, a cylinder 8, a water injection tube 2, a drainage tube 3, a lifting drive mechanism and a rotating drive mechanism; the sensor element is arranged inside the protection tube 9, one end of the signal line 1 extends into the protection tube 9 and is connected to the sensor element; the outer shell 6 is cylindrical, and has a cylindrical cavity inside, the bottom and top of the outer shell 6 are both sealed, the inner tube 7 is coaxially arranged in the cavity of the outer shell 6, the cylinder 8 is coaxially arranged in the inner tube 7, the bottom end of the protection tube 9 extends into the cylinder 8, and the top of the protection tube 9 extends from the top of the inner tube 7, the top of the outer shell 6 is provided with a circular hole, and the top outer wall of the protection tube 9 is sealed and connected to the inner wall of the circular hole at the top of the outer shell 6; at least one water hole 601 is provided on the outer wall of the outer shell 6, and the outer wall of the inner tube 7 At least one water hole 702 is provided on the wall, and at least one water inlet hole 802 is provided on the outer wall of the cylinder 8, and the water through hole 601, the water hole 702 and the water inlet hole 802 correspond to each other one by one; a water inlet cavity is formed between the bottom end of the protective tube 9 and the inner bottom wall of the cylinder 8, and the water inlet cavity is filled with graphite balls; the lifting drive mechanism is used to drive the cylinder 8 to move along the axial direction of the cylinder 8 to reduce or expand the volume of the water inlet cavity; the rotating drive mechanism is used to drive the inner tube 7 to rotate around its axis, when the inner tube 7 rotates to the first state, the water hole 702 and the corresponding water inlet hole 802 and the water through hole 601 are connected; when the inner tube 7 rotates to the second state, the water hole 702 and the corresponding water inlet hole 802 and the water through hole 601 are staggered; one end of the water injection pipe 2 passes through the protective tube 9 and extends into the water inlet cavity, and one end of the drainage pipe 3 passes through the protective tube 9 and extends into the water inlet cavity.
[0042] In this embodiment, the pore water pressure gauge is installed by drilling and embedding. Specifically, a hole 18 is first drilled at the embedding location. After reaching the required depth or elevation, the bottom of the hole is first filled with clean fine sand, the pore water pressure gauge is placed, and then the sand is filled around the pore water pressure gauge to form a sand filter layer 19. Finally, the upper part of the pore water pressure probe 21 is sealed with expansive clay 20 or dry soil balls. When the pore water pressure gauge is in the detection state, the water hole 601 on the shell 6, the water hole 702 on the inner tube 7 and the water inlet hole 802 on the cylinder 8 are in a connected state, and the volume of the water inlet cavity between the inner bottom wall of the cylinder 8 and the bottom of the protective tube 9 is in a minimum state. At this time, the micron-level graphite balls filled in the water inlet cavity are in a tight state, and the gap between the tightly fitted micron-level graphite balls becomes very small. The micron-level graphite balls can allow water to pass through, so that the pore water pressure gauge can accurately measure the pore water pressure in the soil and play a role in isolating the soil pressure, that is, it plays the same role as the permeable stone. The pressurized water acts on the pressure-bearing diaphragm on the protection tube 9 through the micron-sized graphite balls, causing the center of the diaphragm to bend, causing the stress of the steel string to change, and the natural frequency of the steel string to change accordingly.
[0043] Some impurities such as mud, sand and gravel in the pressurized water are mixed in the micron-sized graphite balls, which will also cause the gaps between the micron-sized graphite balls to be blocked to a certain extent. At this time, the pore water pressure gauge needs to be calibrated. Specifically, during calibration, the cylinder 8 is first driven downward by the lifting drive mechanism. As the cylinder 8 gradually moves downward, the space of the water inlet cavity where the micron-sized graphite balls are located gradually increases. Since the water inlet cavity no longer restricts the micron-sized graphite balls, the micron-sized graphite balls are evenly scattered in the water inlet cavity. At this time, impurities such as mud, sand and gravel are also scattered into the pressurized water in the water inlet cavity. Subsequently, the inner tube 7 is driven to rotate by the rotary drive mechanism, so that when the inner tube 7 rotates to the second state, the water hole 702 on the inner tube 7 and the corresponding water inlet hole 802 on the cylinder 8 and the water hole 601 on the outer shell 6 are staggered, so that the external water can no longer enter the inside of the outer shell 6 and can no longer enter the water inlet cavity, so that the water inlet cavity is in a sealed state, and then water is pumped into the water injection pipe 2 on the ground, and the water in the water injection pipe 2 is flushed into the water inlet cavity in the cylinder 8. With the continuous water injection, the water pressure in the water inlet cavity gradually increases, and the mud, sand and gravel and other impurities overflow from the water inlet cavity together with the water and flow into the drain pipe 3, and finally the mud, sand and gravel and other impurities are discharged from the drain pipe 3 together with the water, thereby completing the calibration of the pore water pressure gauge. Finally, the lifting drive mechanism drives the cylinder 8 to move upward, gradually reducing the space of the water inlet chamber, so that the micron-sized graphite is tightly filled in the water inlet chamber again, and then the rotating drive mechanism is used to drive the inner tube 7 to rotate around its axis, so that the inner tube 7 rotates to the first state, and the water hole 702 is connected with the corresponding water inlet hole 802 and the water hole 601, and the pore water pressure gauge is adjusted to the detection state.
[0044] It can be seen that the advantages of the pore water pressure meter in this embodiment compared with the traditional vibrating wire pore water pressure meter mainly include the following points: First, no permeable stone is used, so there is no need to soak the permeable stone in advance to exhaust the air in the permeable stone. Second, micron-grade graphite is used instead of permeable stone, and calibration work can be carried out at any time. There is no need to clean the sand filter layer 19 and the swelling clay 20 to take out the pore water pressure meter for calibration. It is simpler and more convenient to use, reduces the cumbersomeness of the calibration work steps, and can be continuously tested, which greatly reduces the limitations of the use of the pore water pressure meter.
[0045] It should be noted that before using the vibrating-wire pore water pressure gauge in the past, it is necessary to soak the permeable stone to exhaust the air in the permeable stone. This is because the permeable stone may inhale air during the manufacturing process. The presence of this air will affect the permeability of the permeable stone, and then affect the measurement accuracy of the pore water pressure gauge. Therefore, in order to ensure the permeability of the permeable stone, it is necessary to soak it in water before installation to exclude the air therein and make the permeable stone reach a saturated state. Specifically, the soaking process of the permeable stone can be achieved by two methods: one is to soak it in water for more than 24 hours, and the other is to boil it in boiling water for 1 to 2 hours. The advantage of doing this is that the permeable stone can fully absorb water and exclude the air therein, thereby ensuring the accuracy and reliability of the pore water pressure gauge when measuring the pore water pressure of the soil. The pore water pressure gauge in this embodiment no longer uses permeable stone, so there is no need to soak the permeable stone in advance to exhaust the air in the permeable stone, thereby shortening the preparation time.
[0046] As a preferred embodiment, it should be noted that Figure 4 and Figure 5 As shown, a gauze 801 is coaxially provided on the inner wall of the cylinder 8, the pores of the gauze 801 are smaller than the diameter of the micron-sized graphite balls, and the purpose of providing the gauze 801 is to prevent the micron-sized graphite balls from flowing out of the water inlet hole 802 on the cylinder 8 to the outside.
[0047] In addition, it should be noted that blocking members such as gauze or filter screens for blocking micron-sized graphite balls are evenly arranged in the water outlet of the water injection pipe 2 and the water inlet of the drainage pipe 3, so that when cleaning tiny impurities such as mud and sand and gravel particles in the water inlet cavity, the micron-sized graphite balls will not run out of the water inlet cavity.
[0048] It should be noted that if Figure 4 , Figure 5 and Figure 6 As shown, the outer shell 6 is cylindrical, and its top and bottom are both sealed. The inner tube 7 is coaxially arranged inside the outer shell 6, and the outer wall of the inner tube 7 fits with the inner wall of the outer shell 6. The cylinder 8 is coaxially arranged inside the inner tube 7, and the outer wall of the cylinder 8 fits with the inner wall of the inner tube 7. Further, the length of the cylinder 8 is less than the length of the inner tube 7. Preferably, the length of the cylinder 8 is 1 / 2-2 / 3 of the length of the inner tube 7. Further, a circular hole is provided at the center of the top of the outer shell 6, and the top outer wall of the protection tube 9 is fixedly connected to the inner wall of the circular hole on the outer shell 6. A hole for the water injection pipe 2 and the drainage pipe 3 to penetrate is provided at the top of the outer shell 6.
[0049] As a preferred embodiment, Figure 4 as well as Figure 5As shown, the lifting drive mechanism includes a threaded rod 10, a driving pulley 14, a driven pulley 15, a transmission belt 16 and a first motor 12; wherein, a fixed seat is installed on the outer wall of the upper half of the protective tube 9, the fixed seat is located inside the inner tube 7 and higher than the cylinder 8, the top of the threaded rod 10 is rotatably connected to the fixed seat, and the fixed seat serves to suspend the threaded rod 10, and a threaded hole penetrating the cylinder 8 is opened on the upper surface of the cylinder 8, the threaded rod 10 passes through the threaded hole on the cylinder 8 and is threadedly connected with the threaded hole on the cylinder 8, the bottom end of the threaded rod 10 extends to the inner bottom wall near the outer shell 6, the driven pulley 15 is coaxially fixed to the bottom end of the threaded rod 10, and a mounting groove is provided on the inner bottom wall of the outer shell 6, the first motor 12 is vertically installed in the mounting groove, and its output end faces upward, and a driving pulley 14 is installed on the output end of the first motor 12, and the transmission belt 16 is transmission-connected between the driving pulley 14 and the driven pulley 15.
[0050] In this way, when the cylinder 8 is driven to move up and down, the first motor 12 is turned on, and the first motor 12 drives the active pulley 14 to rotate, thereby driving the driven pulley 15 and the threaded rod 10 to rotate together through the transmission belt 16. Since the cylinder 8 is threadedly connected to the threaded rod 10 and the cylinder 8 itself is restricted by the inner tube 7, the cylinder 8 will move up and down along the threaded rod 10 to expand or reduce the space size of the water inlet chamber.
[0051] Optionally, in order to further improve the stability of the cylinder 8 during lifting and lowering, a limit rod can be vertically installed on the side wall of the protective tube 9, and a hole for the limit rod to pass through is opened on the upper surface of the cylinder 8. The limit rod passes through the cylinder 8, and the bottom end of the limit rod is flush with the bottom end of the threaded rod 10.
[0052] As a preferred embodiment, Figure 4 , Figure 5 , Figure 6 and Figure 7 As shown, the rotary drive mechanism includes a plurality of tooth blocks 701, a large gear 11, a rotating shaft, a small gear 13 and a second motor 17, wherein the bottom surface of the inner tube 7 is evenly provided with a plurality of tooth blocks 701 around its axis, a mounting hole is provided on the inner bottom wall of the outer shell 6, a bearing is installed in the mounting hole, the rotating shaft penetrates into the mounting hole and is connected with the bearing, the large gear 11 is fixedly installed on the top end of the rotating shaft, and the large gear 11 is meshed with the plurality of tooth blocks 701 on the bottom surface of the inner tube 7, further, a groove for installing the second motor 17 is provided on the inner bottom wall of the outer shell 6, the output end of the second motor 17 faces upward, the small gear 13 is provided at the output end of the second motor 17, and the small gear 13 is meshed with the large gear 11.
[0053] In this way, the small gear 13 is driven to rotate by the second motor 17, and the small gear 13 drives the large gear 11 to rotate. Since the large gear 11 is engaged with the multiple tooth blocks 701 on the bottom surface of the inner tube 7, the inner tube 7 can be driven to rotate around its own axis, so that the water hole 702 on the inner tube 7 is connected or staggered relative to the water hole 601 on the outer shell 6 and the water inlet hole 802 on the cylinder 8.
[0054] Preferably, a plurality of water holes 601 are provided, and the plurality of water holes 601 are evenly arranged around the axis of the outer shell 6; a plurality of water holes 702 are provided, and the plurality of water holes 702 are evenly arranged around the axis of the inner tube 7; a plurality of water inlet holes 802 are provided, and the plurality of water inlet holes 802 are evenly arranged around the axis of the water inlet hole 802.
[0055] It should be noted that in order to improve the sealing between the inner tube 7 and the cylinder 8, Figure 4 As shown in the figure, when the pore water pressure gauge is in the detection state, Figure 4 In the embodiment, at least one rubber ring is installed on the inner wall of the inner tube 7 above the water hole 702, and at least one rubber ring is also installed on the inner wall of the inner tube 7 below the water hole 702. Figure 4 In this state, the gap between the inner tube 7 and the cylinder 8 above the water hole 702 is blocked by the rubber ring, and the gap between the inner tube 7 and the cylinder 8 below the water hole 702 is also blocked by the rubber ring.
[0056] Optionally, a rubber sealing ring is installed on the inner wall of the cylinder 8 at a position higher than the water inlet hole 802 , and the rubber sealing ring is used to block the gap between the cylinder 8 and the protective tube 9 .
[0057] It should be noted that in the past, when installing a pore water pressure meter by drilling and burying, it was necessary to first fill the bottom of the hole with some clean fine sand, then put the pore water pressure meter in, and then fill sand around the pore water pressure meter to form a sand filter layer 19, and finally seal the upper part of the pore water pressure meter with expansive clay 20 or dry soil balls. Among them, the role of the sand filter layer 19 is to ensure that the water can flow smoothly and can also isolate the silt, thereby ensuring the measurement accuracy, and the role of sealing the upper part of the pore water pressure meter with expansive clay 20 or dry soil balls is to prevent the pressure of the upper and lower water layers from penetrating. However, each time the pore water pressure meter is installed, it is necessary to fill sand around the pore water pressure meter and seal the hole 18 with expansive clay 20 or dry soil balls, resulting in a more cumbersome and troublesome construction process.
[0058] To solve this problem, Figure 1As shown, an airbag assembly is installed on the shell 6, and the airbag assembly includes an annular airbag 4 and a plurality of strip airbags 5 connected to the annular airbag 4, and the strip airbags 5 are evenly arranged around the axis of the annular airbag 4. The annular airbag 4 is coaxially arranged on the top of the shell 6, and the top ends of the plurality of strip airbags 5 are connected to the annular airbag 4, and the strip airbags 5 are evenly attached to the side of the shell 6 around the axis of the shell 6. Further, after two adjacent strip airbags 5 are filled with air, a gap will be formed between the two strip airbags 5. In addition, a hose is installed on the annular airbag 4, and a valve body for controlling its on and off is installed on the hose, and the hose can extend to the ground.
[0059] When installing the pore water pressure meter by drilling and burying method, it is necessary to first fill the bottom of the hole with some clean fine sand, then put the pore water pressure meter in, and then connect the air inlet end of the hose on the annular airbag 4 to the joint of the air pump and open the valve body on the hose. Then the air pump injects air into the hose to gradually fill the annular airbag 4 and the strip airbag 5, so that the strip airbag 5 fits the inner wall of the hole 18. The gap between the strip airbags 5 can ensure that water can pass through the gap into the pore water pressure meter and can also play a role in isolating mud and sand. The annular airbag 4 is close to the inner wall of the hole 18 to play a blocking effect. Finally, the valve body can be closed.
[0060] It should be noted that the width of the gaps between the strip-shaped airbags 5 is 0.1-0.3 mm, which can isolate mud and sand while ensuring smooth water flow.
[0061] In this way, when the pore water pressure meter is installed by the drilling and embedding method, it is no longer necessary to fill sand around the pore water pressure meter to form a sand filter layer 19, and to seal the upper part of the pore water pressure meter with swelling clay 20 or dry soil balls. This reduces the construction process, makes the pore water pressure meter measurement more convenient, and improves work efficiency.
[0062] In addition, it should be noted that the previous drilling method required the pore water pressure gauge to be buried at least one week before construction. The reason for this is that when sand is filled around the pore water pressure gauge to form a sand filter layer 19 and the hole 18 is sealed with expansive clay 20, a large pressure will inevitably be applied to the inner wall of the hole 18. Therefore, in order to allow the excess pore water pressure caused by the burial to have enough time to dissipate and improve the accuracy of subsequent measurements, the pore water pressure gauge must be buried within one week before construction.
[0063] In this embodiment, the use of the strip airbags 5 and the annular airbags 4 will not cause a large pressure on the inner wall of the hole 18, so that no excess pore water pressure will be generated, and there is no need to bury the pore water pressure gauge within a week before construction, thereby speeding up the detection efficiency.
[0064] Optionally, the air pressure in the strip airbag 5 and the annular airbag 4 is detected, and air pressure sensors are installed in the annular airbag 4 and the strip airbag 5, so that the pressure of the strip airbag 5 and the annular airbag 4 on the inner wall of the hole 18 can be adjusted in real time according to the value of the air pressure sensor.
[0065] Preferably, the pore water pressure meter further comprises a control module, a wireless transmission module and an operation screen, wherein the wireless transmission module and the control module are integrated in the protection tube 9, the first motor 12, the second motor 17 and the air pressure sensor are connected to the control module by signal, and the operation of the first motor 12 and the second motor 17 is controlled by the control module. The wireless transmission module is connected to the control module by signal, and the operator stands on the ground to control the operation screen, and transmits instructions to the wireless transmission module through the operation screen, and the control module controls the operation of the first motor 12 and the second motor 17 according to the instructions received by the wireless transmission module. The air pressure value measured by the air pressure sensor is transmitted to the operation screen in real time through the wireless transmission module, and the operator can understand the air pressure value in the strip airbag 5 and the annular airbag 4 by observing the operation screen, so as to adjust the air pressure of the strip airbag 5 and the annular airbag 4 at any time.
[0066] In the description of the present invention, it should be noted that the terms "upper", "lower", etc., indicating the orientation or positional relationship are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first" and "second" are only used for descriptive purposes and cannot be understood as indicating or implying relative importance.
[0067] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be a connection between the inside of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances. In addition, in the description of the present invention, unless otherwise specified, "plurality" means two or more.
[0068] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. An in-situ calibrated self-cleaning pore water pressure gauge, characterized in that: It comprises a protective tube (9), a sensor element, a signal line (1), an outer shell (6), an inner tube (7), a cylinder (8), a water injection pipe (2), a drainage pipe (3), a lifting drive mechanism and a rotating drive mechanism; the sensor element is arranged inside the protective tube (9), and one end of the signal line (1) extends into the interior of the protective tube (9) and is connected to the sensor element; The outer shell (6) is cylindrical and has a cylindrical cavity inside. The bottom and top of the outer shell (6) are both sealed. The inner tube (7) is coaxially arranged in the cavity of the outer shell (6). The cylinder (8) is coaxially arranged inside the inner tube (7). The bottom end of the protective tube (9) extends into the inside of the cylinder (8), and the top end of the protective tube (9) extends from the top of the inner tube (7). The top of the outer shell (6) is provided with a circular hole, and the top outer wall of the protective tube (9) is sealedly connected to the inner wall of the circular hole at the top of the outer shell (6). At least one water through hole (601) is provided on the outer wall of the outer shell (6), at least one water passing hole (702) is provided on the outer wall of the inner tube (7), and at least one water inlet hole (802) is provided on the outer wall of the cylinder (8), and the water through hole (601), the water passing hole (702) and the water inlet hole (802) correspond to each other one by one; A water inlet cavity is formed between the bottom end of the protection tube (9) and the inner bottom wall of the cylinder (8), and the water inlet cavity is filled with graphite balls; The lifting drive mechanism is used to drive the cylinder (8) to move along the axial direction of the cylinder (8) to reduce or expand the volume of the water inlet chamber; The rotation drive mechanism is used to drive the inner tube (7) to rotate around its axis, and when the inner tube (7) rotates to a first state, the water hole (702) is connected to the corresponding water inlet hole (802) and the water through hole (601); when the inner tube (7) rotates to a second state, the water hole (702) is staggered to the corresponding water inlet hole (802) and the water through hole (601); One end of the water injection pipe (2) passes through the protective pipe (9) and extends into the water inlet cavity, and one end of the drainage pipe (3) passes through the protective pipe (9) and extends into the water inlet cavity.
2. The in-situ calibrated self-cleaning pore water pressure gauge according to claim 1, characterized in that: The pore water pressure gauge comprises an airbag assembly, which comprises an annular airbag (4) and a plurality of strip-shaped airbags (5) connected to the annular airbag (4), wherein the annular airbag (4) is coaxially arranged on the top of the outer shell (6), and the plurality of strip-shaped airbags (5) are evenly attached to the side surface of the outer shell (6) around the axis of the outer shell (6), and a gap is formed between two adjacent annular airbags (4).
3. The in-situ calibrated self-cleaning pore water pressure gauge according to claim 2, characterized in that: The lifting drive mechanism comprises a threaded rod (10), a driving pulley (14), a driven pulley (15), a transmission belt (16) and a first motor (12); A fixing seat is installed on the outer wall of the protection tube (9), the fixing seat is located on the inner wall of the inner tube (7) and is higher than the cylinder (8), the top end of the threaded rod (10) is rotatably connected to the fixing seat, the top end of the cylinder (8) is provided with a threaded hole penetrating the cylinder (8), the threaded rod (10) is threadedly connected to the threaded hole on the cylinder (8), the bottom end of the threaded rod (10) is lower than the cylinder (8), the driven pulley (15) is fixed to the bottom end of the threaded rod (10), the first motor (12) is installed on the inner bottom wall of the outer shell (6), the driving pulley (14) is arranged at the output end of the first motor (12), and the transmission belt (16) is transmission-connected between the driving pulley (14) and the driven pulley (15).
4. The in-situ calibrated self-cleaning pore water pressure gauge according to claim 3, characterized in that: The rotary drive mechanism comprises a plurality of tooth blocks (701), a large gear (11), a small gear (13) and a second motor (17); the bottom surface of the inner tube (7) is evenly provided with a plurality of tooth blocks (701) around its axis; the large gear (11) is rotatably mounted on the inner bottom wall of the outer shell (6), and the large gear (11) is meshed with the plurality of tooth blocks (701) on the bottom surface of the inner tube (7); the second motor (17) is mounted on the inner bottom wall of the outer shell (6); the small gear (13) is arranged at the output end of the second motor (17), and the small gear (13) is meshed with the large gear (11).
5. The in-situ calibrated self-cleaning pore water pressure gauge according to claim 3, characterized in that: The inner wall of the cylinder (8) is sleeved with a gauze mesh (801).
6. The in-situ calibrated self-cleaning pore water pressure gauge according to claim 1, characterized in that: The water injection pipe (2) extends into the pipe opening at one end of the water inlet chamber and is provided with gauze, and the drainage pipe (3) extends into the pipe opening at one end of the water inlet chamber and is provided with gauze.
7. The in-situ calibrated self-cleaning pore water pressure gauge according to claim 1, characterized in that: The water through holes (601) are provided in plurality, and the plurality of water through holes (601) are evenly arranged around the axis of the outer shell (6); the water passing holes (702) are provided in plurality, and the plurality of water passing holes (702) are evenly arranged around the axis of the inner tube (7); and the water inlet holes (802) are provided in plurality, and the plurality of water inlet holes (802) are evenly arranged around the axis of the water inlet holes (802).
8. The in-situ calibrated self-cleaning pore water pressure gauge according to claim 1, characterized in that: At least one rubber ring is provided on the inner wall of the cylinder (8), and the rubber ring is higher than the water inlet hole (802) on the cylinder (8).
9. The in-situ calibrated self-cleaning pore water pressure gauge according to claim 1, characterized in that: A plurality of rubber rings are arranged on the inner wall of the inner tube (7), and the rubber rings are used to seal the gap between the inner tube (7) and the cylinder (8).