Submarine cable passing through submarine oil and gas pipeline by adopting support frame and construction method of submarine cable passing through submarine oil and gas pipeline
Through the support frame device, the safety and stability problems of submarine cable construction when crossing under the submarine oil and gas pipeline are solved, and efficient and safe submarine cable laying is achieved. .
Patent Information
- Application Number
- CN202411290777.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-14
- Publication Date
- 2024-11-12
AI Technical Summary
Under the complex terrain and multi-pipe cable facilities around the offshore oil production platform, it is difficult to safely and effectively pass under the submarine oil and gas pipeline, which increases the construction time and joint risks, and it is difficult to construct in shallow and turbid areas.
The supporting frame device is adopted, including the supporting door frame, pipe hanging assembly and side arc bracket. The supporting door frame is spanned on the oil and gas pipeline and is fixed by the pipe hanging frame. The side arc bracket pulls the cable through to ensure that the cable and oil and gas are Safe spacing between pipes reduces underwater dredging work and prevents cables from bending.
It improves the safety and stability of submarine cable construction, reduces joint risks and construction time, ensures a safe distance between cables and oil and gas pipelines, and reduces risks in long-term operation.
Smart Images

Figure CN118943998A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of marine engineering construction, and in particular to a submarine cable that passes through a submarine oil and gas pipeline under a support frame and a construction method thereof. Background Art
[0002] In offshore oil development projects, it is necessary to build various platforms such as oil production platforms, living platforms, and central processing platforms at sea. In order to cooperate with the offshore oil production platforms in oil production operations, many pipe and cable facilities such as submarine cables and submarine oil pipelines are laid around the offshore oil production platforms to connect each other and the land refinery or centralized control center. Therefore, there are many facilities and complex terrain around each offshore oil production platform. In addition, with the rapid development of offshore wind power, each wind farm area is densely covered with a large number of submarine cables, and at the same time, the ocean connects the high-voltage cables of the land centralized control center.
[0003] Multiple wind farms and oil and gas facilities will make some areas connected to the land with a lot of pipes and cables. If submarine cable construction is carried out in such an area, it is generally not allowed to cross over the oil and gas pipelines. This requires the cable construction to pass under the oil and gas pipelines. If the cable is cut and passed through first, and then the joints are made, this will increase the construction time, and a sufficiently long weather window is required for the joint construction. The more submarine cable joints there are, the greater the transmission loss will be. At the same time, there is also a high risk of partial joint breakdown. The construction work from the bottom also needs to ensure that the cable is not damaged by bending, which makes the on-site excavation workload large and the construction in shallow and turbid areas is extremely difficult. How to reduce the number of cable joints to pass the submarine cable from under the oil and gas pipeline and keep a certain safety distance from the existing pipeline is a difficult problem in submarine cable construction.
[0004] In order to solve the above problems, we proposed a submarine cable passing through a submarine oil and gas pipeline under a support frame and a construction method thereof. Summary of the invention
[0005] In order to overcome the shortcomings of the prior art, the present invention provides a submarine cable that passes through a submarine oil and gas pipeline under a support frame and a construction method thereof. The present invention provides the following technical solutions: A support frame for the construction of a submarine cable crossing a submarine oil and gas pipeline comprises a support portal, a pipe hanger assembly is installed in the middle of the support portal, anti-sinking bottom plates are installed at the four corners of the bottom of the support portal, and side arc brackets are arranged on the support portal along the direction of newly laid cables.
[0006] Preferably, the supporting portal frame is composed of a main frame, transverse reinforcing diagonal braces and longitudinal reinforcing diagonal braces. The four end corners of the top of the main frame are respectively provided with lifting ears. A pipe hanger mounting seat that meets the installation requirements of the pipe hanger assembly is provided in the middle of the lower cross beam of the main frame. Transverse reinforcing diagonal braces and longitudinal reinforcing diagonal braces are welded between the main frame and the anti-sinking bottom plate.
[0007] Preferably, the pipe hanger assembly is a metal piece with threaded rods at both ends and a U-shaped bracket in the middle, and one set of the pipe hanger assembly is arranged along the front and back of the existing oil and gas pipeline.
[0008] Preferably, the side arc bracket is composed of an arc support plate and an oblique support frame, the arc support plate is formed by bending steel plates with opposite side arcs arranged upward, and the arc support plate is connected to the supporting portal through the oblique support frame.
[0009] Preferably, the arc-shaped support plate is provided with densely distributed holes.
[0010] The present invention also relates to a method for constructing a support frame for a submarine cable to pass through a submarine oil and gas pipeline. The method comprises the following steps: Step S1: Determine the main dimensions of the support gantry and the detailed specifications of the pipe hanger assembly according to the specifications and dimensions of the existing oil and gas pipelines and the required spacing with the newly laid cables; determine the size of the side arc bracket of the support frame device according to the outer diameter and bending radius of the newly laid cables and the performance characteristics of the corresponding construction ship and engine; determine the size and form of the anti-sinking bottom plate according to the geological conditions of the construction site; and finally complete the detailed design and manufacturing of the support frame device; Step S2: The manufactured support frame device is transported to the engineering ship. The ship is positioned at the set crossing intersection point and anchored. After being stabilized at the crossing point of the existing oil and gas pipeline, divers carry mud flushing equipment into the water to clear mud from the existing oil and gas pipeline area at the crossing point, forming a pit with a slope and a certain width at the bottom; the exposed existing oil and gas pipeline in the middle of the pit is cleaned of marine organisms or obstacles on the outside of the pipeline, and the support frame device is installed after checking that the pipeline is not damaged; Step S3: Hang the lock on the lifting ear, fasten the diagonal cable wind rope, lift the support frame device as a whole into the water by the crane, and lower it to the bottom of the anti-sinking bottom plate when it is stable and close to the upper part of the existing oil and gas pipeline. The diver checks the position underwater so that the gantry straddles the existing oil and gas pipeline. At the same time, the pipe hanger mounting seat is positioned along the route of the existing oil and gas pipeline. The cable wind rope is adjusted and slowly lowered. The diver assists in making the support frame device straddle the existing oil and gas pipeline. The anti-sinking bottom plate stably contacts the bottom of the pit. The support gantry is adjusted so that it is arranged close to the center. The U-shaped metal frame of the pipe hanger assembly is inserted upward from the bottom of the existing oil and gas pipeline to the pipe hanger mounting seat, nuts are fastened, and the front and rear sets of pipe hanger assemblies are adjusted and installed. , tighten the nuts after basically aligning them to complete the connection between the support frame device and the existing oil and gas pipeline; the diver checks the contact of the anti-sinking bottom plate. If there is local overhang, sandbags are used to level it to ensure that the four corners of the anti-sinking bottom plate are stably supported and no additional downward pressure is generated on the existing oil and gas pipeline; continue to press sandbags of a certain weight in the anti-sinking bottom plate area to ensure that the support frame device will not be lifted when the newly laid cable is pulled through; a thin steel wire rope is pre-threaded through the lower part of the existing oil and gas pipeline through the side arc bracket on one side and the side arc bracket on the other side, and underwater marks are made at both ends of the steel wire rope, and the rope is temporarily tied to the support gantry, and the lock on the lifting ear is unlocked to complete the installation of the support frame device; Step S4: The cable-laying vessel lays the newly laid cable in the water or on the deck, and releases it in an "8"-shaped coil until it comes out of the cable head; then the traction winch wire rope is lowered into the water, connected to the reserved wire rope end on the water entry side, and the deck auxiliary winch lowers the traction wire rope into the water, and connects the reserved wire rope end on the exit side; the auxiliary winch wire rope is recovered, and the traction winch wire rope is released synchronously, so that the traction winch wire rope passes through the support frame device to the cable-laying vessel, and is connected to the newly laid cable. Cable head pulling point; start the traction winch to pass the cable head of the newly laid cable from the support frame device into the side arc bracket and pass it to the other side, so as to achieve the lowering and passing through the existing oil and gas pipeline; then control the angle of the traction wire rope or the newly laid cable coming out of the side arc brackets on both sides, so that the upward lifting force on the support frame device is small when passing through the pulling point and the newly laid cable does not have obvious bending, gradually pull until the newly laid cable is completely passed out and recovered to the cable-laying ship, completing the construction of the newly laid cable passing under the existing oil and gas pipeline; Step S5: Fill the suspended part of the existing oil and gas pipeline at the support frame device position with underwater sandbags, and dig trenches to bury the newly laid cables to a certain depth, backfill the previously excavated pits, and complete the crossing point construction. After that, the cable-laying ship continues to lay the newly laid cables until it is finally completed.
[0011] Compared with the prior art, the present invention can achieve the following beneficial effects: This patent uses a steel structure portal frame support frame to cross the existing oil and gas pipeline, and uses a pipe hanger to connect the support frame to the oil and gas pipeline to support the local pipeline. The cable to be constructed is then pulled in from the arc-shaped bracket on the side, passes under the oil and gas pipeline and comes out from the other side, so that the intersection of the cable and the oil and gas pipeline has a safe spatial spacing distance, thereby improving safety and stability; the support frame can greatly reduce underwater dredging and silt removal operations, control the cable to avoid bending when it is inserted, and will not approach the oil and gas pipeline during long-term operation, and the oil and gas pipeline will not sink locally to squeeze the cable; the support frame of this patent has a stable structure, convenient and fast construction, and has good practical value. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] By reading the detailed description of the preferred embodiment below, various other advantages and benefits will become clear to those of ordinary skill in the art. The accompanying drawings are only used to illustrate the purpose of the preferred embodiment and are not considered to be limitations of the present invention. In the entire drawings, the same reference numerals are used to represent the same components.
[0013] In the attached picture: Figure 1 It is a schematic diagram of the overall structure of the support frame of a preferred embodiment of the present invention; Figure 2 It is a partial schematic diagram of the pipe and cable crossing components of the preferred embodiment of the present invention; Figure 3 This is a schematic diagram of pre-excavation for construction of a preferred embodiment of the present invention; Figure 4 This is a schematic diagram of the installation of the support frame of the preferred embodiment of the present invention; Figure 5 It is a schematic diagram of the completion of construction of a preferred embodiment of the present invention.
[0014] in, Figures 1 to 5 The corresponding relationship between the reference numerals and the components is as follows: 1. Existing oil and gas pipelines; 2. Newly laid cables; 3. Support frame device; 31. Support gantry; 311. Lifting lugs; 312. Main frame; 313. Horizontal reinforcing braces; 314. Longitudinal reinforcing braces; 315. Pipe hanger mounting base; 32. Pipe hanger assembly; 33. Anti-sinking bottom plate; 34. Side arc bracket; 341. Arc bracket; 342. Oblique support frame; 4. Seabed. DETAILED DESCRIPTION
[0015] In order to make the purpose, technical solution and advantages of the embodiment of the present invention clearer, the technical solution of the embodiment of the present invention will be clearly and completely described below in conjunction with the drawings of the embodiment of the present invention. Obviously, the described embodiment is a part of the embodiment of the present invention, not all of the embodiments. Based on the described embodiment of the present invention, all other embodiments obtained by ordinary technicians in this field belong to the scope of protection of the present invention.
[0016] It should be noted that the terms used herein are only for describing specific embodiments and are not intended to limit the exemplary embodiments according to the present application. As used herein, unless the context clearly indicates otherwise, the singular form is also intended to include the plural form. In addition, it should be understood that when the terms "comprise" and / or "include" are used in this specification, it indicates the presence of features, steps, operations, devices, components and / or combinations thereof.
[0017] Combine the following Figures 1 to 5 A submarine cable according to an embodiment of the present invention is used to pass through a submarine oil and gas pipeline under a support frame and a construction method thereof is specifically described.
[0018] A support frame for the construction of submarine cables crossing submarine oil and gas pipelines is a door-shaped frame structure with side arc brackets, which straddles the existing oil and gas pipeline 1 and is connected to the existing oil and gas pipeline 1, so that it is in a relatively fixed position. There are arc brackets on both sides perpendicular to the existing oil and gas pipeline 1 to facilitate the subsequent laying of new cables 2 through the lower part of the existing oil and gas pipeline 1. The size control of the structural parts meets the safety requirements of the distance between the center of the newly laid cable 2 and the existing oil and gas pipeline 1, and there will be no external contact. Figure 1~2 As shown, its components include: a supporting door frame 31, a pipe hanger assembly 32, an anti-sinking bottom plate 33, and a side arc bracket 34.
[0019] The support gantry 31 is the main structure of the support frame device 3. It is welded into a door-shaped structural member using steel pipes or H-shaped steel, etc., to meet the installation of the pipe hanger assembly 32 in the middle and lower part, the connection support of the anti-sinking bottom plate 33 at the bottom, and the connection and installation of the arc brackets 34 on both sides. The overall gantry is welded to form a strong structural frame, with a steel plate cut lifting lug 311 on the upper part, and one lug is arranged on each corner to achieve 4-point horizontal hanging. The main frame 312 of the main body is a door-shaped frame, with two layers of cross beams and longitudinal bars arranged on the upper part to form a frame structure, and a pipe hanger mounting seat 315 in the middle of the lower cross beam that meets the installation and connection of the pipe hanger assembly 32. The vertical rod at the bottom of the gantry determines the final height according to the geology of the installation area, the construction interval requirements, and the pre-excavation depth requirements to meet the installation requirements. The lower part of the support gantry 31 is welded and connected to the anti-sinking bottom plate 33, and is arranged with a transverse reinforcement brace 313 and a longitudinal reinforcement brace 314, all of which are welded with steel sections, making the connection between the two more stable and reliable. The pipe hanger mounting seat 315 is made by cutting and manufacturing steel plates and welded in the middle of the lower crossbeam of the main frame 312. Holes are opened corresponding to the screw spacing and diameter of the pipe hanger assembly 32 to allow the pipe hanger assembly 32 to pass through the rear nut for installation and tightening, thereby fixing the existing oil and gas pipeline 1 to the lower part of the support gantry 31. In order to ensure the stability of the structure, necessary reinforcing ribs are also provided to ensure reliable and stable load transmission. The main frame 312 also has a longitudinal cross bar at the root of the arc support plate 341 of the side arc support 34. The vertical spacing between the cross bar and the lower cross beam welded by the pipe hanger mounting seat 315 is adjusted, so that the existing oil and gas pipeline 1 and the newly laid cable 2 have a safe spatial spacing at the intersection of the support frame device 3, while also ensuring that the arc support plate 341 is welded reliably and improving stability.
[0020] The pipe hanger assembly 32 is installed in the middle of the support gantry 31, arranged along the direction of the existing oil and gas pipeline 1, and arranged in front and back. It is a metal part with threaded rods at both ends and a U-shaped support in the middle. The lower part of the existing oil and gas pipeline 1 is supported by the U-shaped support, and the upper end is connected with the pipe hanger mounting seat 315 of the support gantry 31 by nuts, and the existing oil and gas pipeline 1 is fixed in the fixed position of the support gantry 31. Through the adjustment of the nut, the existing oil and gas pipeline 1 can be well applied with a fixing force. In order to reduce the damage to the existing oil and gas pipeline 1, the U-shaped support and the contact position of the pipeline can be wrapped with a polyurethane pad. At the same time, a V-shaped frame is set at the bottom of the pipe hanger mounting seat 315, so that the existing oil and gas pipeline 1 is firmly fixed. According to the size of the existing oil and gas pipeline 1, the screw diameter of the pipe hanger assembly 32, the width and thickness of the U-shaped support steel plate are correspondingly enhanced. Further, in order to improve the connection reliability, more pipe hanger assemblies 32 can be arranged, and the corresponding pipe hanger mounting seat 315 is also increased to meet the installation needs.
[0021] The anti-sinking bottom plate 33 is welded or bolted to the four corners of the bottom of the support gantry 31, with intervals between them to meet the needs of offshore lifting construction, and will not bump into and damage the existing oil and gas pipeline 1 when installed on it. According to the different geology of the construction area, the area of the bottom plate is adjusted differently to prevent the support frame device 3 from sinking too much after installation, causing excessive external force to the existing oil and gas pipeline 1, affecting the safe operation of the existing oil and gas pipeline 1. At the same time, the anti-sinking bottom plate 33 is also welded to the bottom of the transverse reinforcement brace 313 and the longitudinal reinforcement brace 314 of the support gantry 31, making the connection between the two more stable and reliable. According to different characteristics and installation requirements, the anti-sinking bottom plate 33 can adopt a structure with buoyancy or negative pressure barrel, or a long pile to support its upper load without causing additional downward pressure on the connected existing oil and gas pipeline 1.
[0022] The side arc bracket 34 is arranged on the support frame device 3 along the direction of the newly laid cable 2. It is an arc support plate 341 with an upward arc arranged on the opposite side. It is made of a steel plate of a certain thickness and the bending radius is set according to the allowable radius for the construction of the newly laid cable 2. In order to reduce weight and avoid being affected by water flow in the water, the support plate is provided with densely distributed small-diameter holes, which will not affect the sliding passage of the newly laid cable 2 and can also reduce weight well. The extended arc support plate 341 is connected to the support portal 31 through multiple 3.4.2- inclined support frames arranged radially, so that the structure is stable and can withstand the pulling force of the cable when the newly laid cable 2 is passed through, and the structure will not be deformed and unstable. According to different construction needs, when the water depth exceeds 10m, it is necessary to install necessary rollers on the contact part between the arc support plate 341 and the newly laid cable 2 to reduce the sliding friction resistance of the newly laid cable 2 and facilitate the completion of the crossing construction.
[0023] The specific construction steps are: Step 1: Determine the main dimensions of the support gantry 31 and the detailed specifications of the pipe hanger assembly 32 based on the specifications and dimensions of the existing oil and gas pipeline 1 and the required spacing with the newly laid cable 2. Determine the size of the side arc bracket 34 of the support frame device 3 based on the outer diameter and bending radius of the newly laid cable 2 and the corresponding performance characteristics of the construction ship and machinery. Determine the size and form of the anti-sinking bottom plate 33 based on the geological conditions of the construction site. Finally, complete the detailed design and manufacturing of the support frame device 3.
[0024] Step 2: Transport the manufactured support frame device 3 to the engineering ship, and position the ship at the set crossing intersection. Anchoring is preferred, but dynamic positioning can also be used. After stabilizing at the crossing point of the existing oil and gas pipeline 1, divers carry mud flushing equipment into the water to clear the mud in the area of the existing oil and gas pipeline 1 at the crossing point, forming a pit with a slope and a certain width at the bottom. Clean the exposed existing oil and gas pipeline 1 in the middle of the pit, remove marine organisms or obstacles from the outside of the pipeline, and install the support frame device 3 after checking that the pipeline is not damaged. Figure 3 As shown; if there is only one crossing point, the support frame device 3 can be installed by the crane of the cable-laying ship after the cable-laying ship arrives at the crossing position. If the route has multiple crossing points, it is recommended to use a separate ship to centrally install the support frame device 3 to facilitate subsequent cable-laying operations.
[0025] Step 3: Hang the lock on the lifting ear 311, fasten the diagonal cable wind rope, lift the support frame device 3 as a whole and lower it into the water by the crane, and lower it to the bottom of the anti-sinking bottom plate 33 when it is stable and close to the upper part of the existing oil and gas pipeline 1. The diver checks the position underwater so that the gantry straddles the existing oil and gas pipeline 1. At the same time, the pipe hanger mounting seat 315 is positioned along the route of the existing oil and gas pipeline 1. The cable wind rope is adjusted and slowly lowered. The diver assists in making the support frame device 3 straddle the anti-sinking bottom plate 33 on the existing oil and gas pipeline 1 and stably contact the bottom of the pit. Adjust the support gantry 31 so that it is close to the center. Insert the U-shaped metal frame of the pipe hanger assembly 32 upward from the bottom of the existing oil and gas pipeline 1 to the pipe hanger mounting seat 315, put on the nut, and adjust and install the two sets of pipe hanger assemblies 32 before and after. Tighten the nut after it is basically aligned to complete the connection between the support frame device 3 and the existing oil and gas pipeline 1, such as Figure 4 As shown; the diver checks the contact condition of the anti-sinking bottom plate 33. If there is local overhang, sandbags can be used to level it to ensure that the four corners of the anti-sinking bottom plate 33 are stably supported and no additional downward pressure is generated on the existing oil and gas pipeline 1. Then continue to press sandbags of a certain weight in the area of the anti-sinking bottom plate 33 to ensure that the support frame device 3 will not be lifted when the newly laid cable 2 passes through and is pulled. Then, a thin steel wire rope is pre-threaded through the side arc bracket 34 on one side through the lower part of the existing oil and gas pipeline 1 to the side arc bracket 34 on the other side, and underwater markings are made at both ends of the steel wire rope. The rope is temporarily tied to the support door frame 31, and the lock on the lifting ear 311 is unlocked to complete the installation of the support frame device 3.
[0026] Step 4: The cable-laying vessel is laid to the crossing point, and the stored newly laid cable 2 is released into the water or onto the deck, and is laid in an "8"-shaped coil until it comes out of the cable head; then the traction winch wire rope is lowered into the water, and the reserved wire rope end on the entry side of the water is connected; the deck auxiliary winch lowers the traction wire rope into the water, and connects the reserved wire rope end on the exit side. Recover the auxiliary winch wire rope and release the traction winch wire rope synchronously, so that the traction winch wire rope passes through the support frame device 3 to the cable-laying ship and is connected to the cable head pulling point of the newly laid cable 2; start the traction winch to pass the cable head of the newly laid cable 2 from the support frame device 3 into the side arc bracket 34 and pass it out to the other side, so as to achieve the lowering and passing through of the existing oil and gas pipeline 1; then control the traction wire rope or the angle of the newly laid cable 2 coming out of the side arc bracket 34 on both sides, so that the support frame device 3 is subjected to a small upward lifting force when passing through the pulling point and the newly laid cable 2 does not have obvious bending, and gradually pull until the newly laid cable 2 is completely passed out and recovered to the cable-laying ship, completing the construction of the newly laid cable 2 passing under the existing oil and gas pipeline 1. Figure 5 shown.
[0027] Step 5: Fill the suspended part of the existing oil and gas pipeline 1 at the position of the support frame device 3 with underwater sandbags, and dig trenches to bury the newly laid cable 2 to a certain depth, backfill the previously excavated pit, and complete the crossing point construction. After that, the cable-laying ship continues to lay the newly laid cable 2 until it is finally completed.
[0028] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may include that the first and second features are in direct contact, or may include that the first and second features are not in direct contact but are in contact through another feature between them. Moreover, a first feature being "above", "above" and "above" a second feature includes that the first feature is directly above and obliquely above the second feature, or simply indicates that the first feature is higher in level than the second feature. A first feature being "below", "below" and "below" a second feature includes that the first feature is directly below and obliquely below the second feature, or simply indicates that the first feature is lower in level than the second feature.
Claims
1. A support frame for the construction of a submarine cable passing through a submarine oil and gas pipeline, comprising a support gantry (31), characterized in that: A pipe hanger assembly (32) is installed in the middle of the support portal (31), anti-sinking bottom plates (33) are installed at the four corners of the bottom of the support portal (31), and a side arc-shaped bracket arrangement (34) is arranged on the support portal (31) along the direction of the newly laid cable (2).
2. A support frame for the construction of a submarine cable passing through a submarine oil and gas pipeline according to claim 1, characterized in that: The support door frame (31) is composed of a main frame (312), a transverse reinforcing brace (313) and a longitudinal reinforcing brace (314); four end corners of the top of the main frame (312) are respectively provided with lifting ears (311); a pipe hanger mounting seat (315) for installing the pipe hanger assembly (32) is provided in the middle of the lower cross beam of the main frame (312); and a transverse reinforcing brace (313) and a longitudinal reinforcing brace (314) are welded between the main frame (312) and the anti-sinking bottom plate (33).
3. The support frame for the construction of a submarine cable passing through a submarine oil and gas pipeline according to claim 1, characterized in that: The pipe hanger assembly (32) is a metal piece with threaded rods at both ends and a U-shaped bracket in the middle. One set of the pipe hanger assembly (32) is arranged along the front and rear of the existing oil and gas pipeline (1).
4. A support frame for the construction of a submarine cable passing through a submarine oil and gas pipeline according to claim 1, characterized in that: The side arc-shaped bracket (34) is composed of an arc-shaped support plate (341) and an oblique support frame (342); the arc-shaped support plate (341) is formed by bending a steel plate with an arc-shaped opposite side facing upward; the arc-shaped support plate (341) is connected to the support door frame (31) via the oblique support frame (342).
5. The support frame for the construction of a submarine cable passing through a submarine oil and gas pipeline according to claim 1, characterized in that: The arc-shaped supporting plate (341) is provided with densely distributed holes.
6. A method for constructing a support frame for a submarine cable to pass through a submarine oil and gas pipeline, using a support frame for a submarine cable to pass through a submarine oil and gas pipeline as claimed in claims 1 to 5, characterized in that: The method for constructing a support frame for a submarine cable to pass through a submarine oil and gas pipeline comprises the following steps: Step S1: Determine the main dimensions of the support gantry (31) and the detailed specifications of the pipe hanger assembly (32) based on the specifications and dimensions of the existing oil and gas pipeline (1) and the required spacing from the newly laid cable (2); determine the dimensions of the side arc bracket (34) of the support frame device (3) based on the outer diameter and bending radius of the newly laid cable (2), the performance characteristics of the corresponding construction ship and engine, etc.; determine the dimensions and form of the anti-sinking bottom plate (33) based on the geological conditions of the construction site, and finally complete the detailed design and manufacturing of the support frame device (3); Step S2: The manufactured support frame device (3) is transported to the engineering ship. The ship is positioned at the set crossing intersection position and anchored. After being stabilized at the crossing point position of the existing oil and gas pipeline (1), divers carry mud flushing equipment and go into the water to clear mud in the existing oil and gas pipeline (1) at the crossing point position, forming a pit with a slope and a certain width at the bottom; the exposed existing oil and gas pipeline (1) in the middle of the pit is cleaned of marine organisms or obstacles on the outside of the pipeline, and the support frame device (3) is installed after checking that the pipeline is not damaged; Step S3: Hang the lock on the lifting lug (311), fasten the diagonal cable wind rope, and use the crane to hoist the support frame device (3) as a whole and lower it into the water. After it is stable, lower it to the bottom of the anti-sinking bottom plate (33) and when it is close to the upper part of the existing oil and gas pipeline (1), the diver checks the position underwater so that the gantry straddles the existing oil and gas pipeline (1). At the same time, the pipe hanger mounting seat (315) is positioned along the route of the existing oil and gas pipeline (1). The cable wind rope is adjusted and slowly lowered. The diver assists in making the support frame device (3) straddle the anti-sinking bottom plate (33) on the existing oil and gas pipeline (1) and stably contact the bottom of the pit. The support gantry (31) is adjusted so that it is arranged nearly in the center. The U-shaped metal frame of the pipe hanger assembly (32) is inserted upward from the bottom of the existing oil and gas pipeline (1) into the pipe hanger mounting seat (315), nuts are fastened, and the front and rear sets of pipe hanger assemblies (315) are adjusted and installed. 32), tighten the nuts after basically aligning them, and complete the connection between the support frame device (3) and the existing oil and gas pipeline (1); the diver checks the contact condition of the anti-sinking bottom plate (33), and if there is a local overhang, use sandbags to level it, to ensure that the four corners of the anti-sinking bottom plate (33) are stably supported and no additional downward pressure is generated on the existing oil and gas pipeline (1); continue to press a certain weight of sandbags in the anti-sinking bottom plate (33) area to ensure that the support frame device (3) will not be lifted when the newly laid cable (2) is pulled through; pre-thread a thin steel wire rope through the lower part of the existing oil and gas pipeline (1) through the side arc bracket (34) on one side to the side arc bracket (34) on the other side, and make underwater marks on both ends of the steel wire rope, and use the rope to temporarily tie it to the support door frame (31), unlock the lock on the lifting ear (311), and complete the installation of the support frame device (3); Step S4: The cable-laying vessel is laid to the crossing point, and the stored newly laid cable (2) is released into the water or onto the deck, and is laid in an "8"-shaped coil until it comes out of the cable head; then the traction winch wire rope is lowered into the water, and connected to the reserved wire rope end on the water entry side, and the deck auxiliary winch lowers the traction wire rope into the water, and connects to the reserved wire rope end on the exit side; the auxiliary winch wire rope is recovered, and the traction winch wire rope is released synchronously, so that the traction winch wire rope passes through the support frame device (3) to the cable-laying vessel, and is connected to the cable head pulling point of the newly laid cable (2); the traction winch is started to The cable head of the newly laid cable (2) passes through the side arc bracket (34) from the support frame device (3) and comes out from the other side, so as to be lowered and passed through the existing oil and gas pipeline (1); then, the angle of the traction wire rope or the newly laid cable (2) coming out of the side arc brackets (34) on both sides is controlled, so that the upward lifting force on the support frame device (3) is small when the traction passes through and the newly laid cable (2) does not have obvious bending, and the traction is gradually carried out until the newly laid cable (2) is completely passed out and recovered to the cable-laying ship, so that the construction of the newly laid cable (2) passing under the existing oil and gas pipeline (1) is completed; Step S5: Fill the suspended part of the existing oil and gas pipeline (1) at the position of the support frame device (3) with underwater sandbags, and dig a trench to bury the newly laid cable (2) to a certain depth, backfill the previously excavated pit, and complete the crossing point construction. After that, the cable-laying ship continues to lay the newly laid cable (2) until it is finally completed.