Ribbed floor forming structure capable of being efficiently installed and construction method
Through the combined structure of mold shells, columns, and cross beams and fastener connection, the problem of large workload and low safety in the construction of dense rib floor slabs is solved, efficient and safe construction methods are realized, and the reuse rate of components is improved and construction efficiency.
Patent Information
- Application Number
- CN202411369015.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-29
- Publication Date
- 2024-11-19
AI Technical Summary
The existing dense rib floor construction technology has problems such as huge workload, low safety, inconvenient height adjustment and few reusable components.
A combination structure of mold shell, column and beam is adopted. The mold shell is connected through fasteners. The column height is adjustable. The beam adopts a steel truss beam structure to build a multi-row door-shaped frame. Workers can install mold shells on the mobile platform and cancel the whole hall. Scaffolding, using a self-travel hydraulic lift truck.
It improves construction efficiency and safety, meets high load requirements, reduces material use, and the tight connection between mold shells avoids slurry leakage. The beam can meet a variety of span requirements, realizing the reuse of components.
Smart Images

Figure CN118979624A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building formwork, and in particular to a dense-ribbed floor slab forming structure that can be efficiently installed and a construction method. Background Art
[0002] A formwork used in dense-rib floor formwork construction projects, mainly used for cast-in-place concrete two-way dense-rib floor (floor) construction, suitable for large-span and large-load space construction, such as: underground garages, large shopping malls, multi-story factories, teaching buildings, civil air defense projects, etc.
[0003] In the prior art, a full-floor scaffold is generally built in advance, wooden boards are laid on the scaffold, and then the formwork is laid flat on the wooden boards. This method has the following problems: 1. The density of laying scaffolding in the whole floor is too high, the erection is complicated and the labor cost is high.
[0004] 2. After the full-floor scaffolding is laid, the bottom is inaccessible and workers can only climb to work, which is less safe.
[0005] 3. It is inconvenient to adjust the height of the full-floor scaffolding, and the height of each scaffolding pole needs to be adjusted individually.
[0006] 4. Only the mold shell can be reused, and there are fewer reusable parts. Summary of the invention
[0007] The problem to be solved by the present invention is that in the actual construction process, the prior art has the problems of huge workload, low safety, inconvenient height adjustment and few reusable parts. The present invention provides a dense-ribbed floor forming structure and a construction method that can be efficiently installed.
[0008] The present invention is implemented through the following technical scheme: a multi-ribbed floor slab forming structure that can be efficiently installed, including a plurality of formworks, columns, and beams. The mold shell comprises a mold shell top surface, and a circle around the mold shell top surface is connected with a mold shell side surface extending downward, and the mold shell top surface and the mold shell side surface enclosed therewith form a cavity, and the lower edge of the mold shell side surface continues to extend horizontally outward to form a flange edge, and the outer contour of a circle of flange edges is a rectangular, and the vertical end surface of the outer edge of the flange edge is a fitting surface between the mold shells; two, three or four adjacent fitting surfaces of the mold shell are provided with connecting holes, and the connecting holes are horizontally arranged to pass through the cavity to the fitting surface, The fitting surfaces of several mold shells are fitted in pairs to form a rectangular mold shell array. The lower bottom surfaces of all the mold shells are coplanar. The connection holes on the fitting surfaces of two adjacent mold shells match each other and are fastened together by fasteners penetrating the connection holes. The outermost edge of the mold shell array is placed on the existing main beam side mold, and the middle of the mold shell array is supported by several parallel beams. Each crossbeam supports the flange edges of two adjacent rows of formwork shells at the same time, the upper surface of the crossbeam abuts against the bottom surface of the flange edge of the formwork shell, and at least one corner of the formwork shell located at the edge is completely placed on the crossbeam. A column is arranged below each end of the crossbeam, the bottom of the column is supported on the ground or floor, the height of the column can be adjusted, the top of the column and the crossbeam are detachably connected or overlapped, and each column is connected to the main beam scaffolding and the adjacent column as a whole through a connecting piece.
[0009] Furthermore, the cross beam is one of section steel, steel truss beam, cantilever beam or a combination thereof.
[0010] Furthermore, the columns are constructed by scaffolding, including vertical poles, horizontal poles, and top supports.
[0011] Furthermore, the scaffolding is a disc-type scaffolding, the vertical poles are provided with buckled annular connecting plates, and the two ends of the cross bar are connected to the connecting plates of the vertical poles through pins.
[0012] Furthermore, the connecting piece is a crossbar for a scaffold.
[0013] Another aspect of the present invention provides a construction method for a multi-ribbed floor slab that can be installed efficiently, comprising: Preparation before construction: Complete the prefabrication of formwork and beams according to construction requirements, prepare the parts required for the columns, and set up the side formwork of the main beam according to the drawings to determine the installation height of the bottom surface of the ribbed floor; Construction content: including installation of columns and connectors, installation of beams, installation of formwork, specific: 1. Install columns and connectors: Install multiple columns near the main beam scaffolding. The multiple columns are arranged in two parallel rows. The two rows of columns are located near two opposite main beam scaffoldings. The center distance between adjacent columns is consistent with the width of the supported formwork. Each column is connected to the main beam scaffolding and the adjacent columns through connectors to form a whole; 2. Install the beams: install several prefabricated beams on the top of two columns, adjust the height of the columns to ensure that the height of the top of the beam is consistent with the top surface of the main beam side mold; 3. Install the formwork: start from a corner of the surrounding main beams and set up the formwork in sequence along one side of the main beam. Subsequently, set up the remaining formworks in sequence along the set up formworks or the edge of the main beam until the formworks cover all the places where they need to be laid. The edge of each formwork is set up on the side formwork of the main beam or the crossbeam, and the formwork at the edge has at least one corner completely set up on the crossbeam. Starting from the second formwork, each time a formwork is installed, the fitting surfaces of the newly installed formwork and the installed formwork are pressed tightly together, and the two formworks are fastened together by fasteners penetrating the connecting holes.
[0014] Furthermore, when installing the formwork, workers stand on a mobile platform to assist in the installation.
[0015] Furthermore, the columns are constructed by scaffolding, including vertical poles, horizontal poles, and top supports. When constructing the columns, multiple vertical poles are arranged in an array, at least two rows and two columns. The vertical poles are connected by horizontal poles, and the columns are fixed to the nearest main beam scaffolding through the horizontal poles.
[0016] Furthermore, the scaffolding is a disc-type scaffolding, the vertical poles are provided with buckled annular connecting plates, and the two ends of the cross bar are connected to the connecting plates of the vertical poles through pins.
[0017] Furthermore, after the formwork is installed, steel bars are tied, concrete is poured, and the structure is cured on the already erected ribbed floor slab forming structure. After curing and forming, the fasteners are removed, the height of the columns is lowered, and the formwork, columns, and beams are removed in preparation for turnover and reuse.
[0018] The beneficial effects of the present invention are: 1. The dense-ribbed floor forming structure of the present invention which can be efficiently installed is constructed into multiple rows of door-shaped frames through columns and beams, and the construction efficiency is very high.
[0019] 2. Each column of the present invention is connected to the main beam scaffold and the adjacent columns through a connecting piece to form a whole, thereby improving the strength of the column and meeting the requirements of high load.
[0020] 3. The cross beam of the present invention can adopt a steel truss beam structure, which can meet greater load-bearing requirements and bending resistance requirements with less material.
[0021] 4. The present invention eliminates the need for full-floor scaffolding, and the self-propelled hydraulic lift can move unimpeded. Workers can stand on the self-propelled hydraulic lift to perform installation work, which can improve the installation efficiency of the installation workers and eliminate the need to climb scaffolding, making it safer.
[0022] 5. The mold shell of the present invention is provided with through holes on the fitting surface, and the mold shells are fastened and connected with each other by fasteners penetrating through the through holes, so that the mold shells fit more closely and the problem of slurry leakage is avoided.
[0023] 6. The crossbeam of the present invention can support only one corner of the edge formwork, or it can support the entire flange edge. The same specification of the crossbeam can meet the erection of at least two standard span formworks. Therefore, a universal design can be performed. It is only necessary to set several fixed-length crossbeams according to the span requirements to meet the requirements of all span construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 A top three-dimensional view of a mold shell of an embodiment; Figure 2 A bottom three-dimensional view of a mold shell of an embodiment; Figure 3 It is a schematic diagram of the structure of the column and the beam in the first embodiment; Figure 4 for Figure 3 Middle partial enlarged picture; Figure 5 It is a front view of the column and the beam in the first embodiment; Figure 6 It is a front view of the column and beam in the second embodiment; Figure 7 This is a front view of the column and beam in Example 3; Figure 8 It is a front view of the column and beam in the fourth embodiment; Fig. 9 It is a structural schematic diagram of the main beam side form and the main beam scaffold in the fifth embodiment; Fig.10 This is a schematic diagram of the fifth embodiment after the erection of the columns is completed; Fig.11 This is a structural schematic diagram of the completed erection of the crossbeam in Example 5; Fig.12 It is a schematic diagram of setting up the first formwork in the fifth embodiment; Fig.13 for Fig.12 Middle partial enlarged picture; Fig.14 This is a schematic diagram of setting up the first row of formwork in Embodiment 5; Fig.15 This is a schematic diagram of the fifth embodiment after all the formwork has been set up.
[0025] In the figure: 10 mold shell; 11 mold shell top surface; 12 mold shell side surface; 13 cavity; 14 flange edge; 15 fitting surface; 16 connection hole; 20 upright column; 21 upright pole; 22 horizontal pole; 23 top support; 231 lead screw; 232 adjusting nut; 233 U-shaped support plate; 24 connecting plate; 30 beams; 41 main beam side form; 42 main beam scaffolding; 5 mobile platforms. DETAILED DESCRIPTION
[0026] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention. Embodiment 1
[0027] like Figure 1-5 As shown, a ribbed floor forming structure that can be efficiently installed includes a plurality of formworks 10, columns 20, and beams 30. like Figure 1-2 As shown, the mold shell 10 includes a mold shell top surface 11, and a circle of the mold shell top surface 11 is connected to a mold shell side surface 12 extending downward. The mold shell top surface 11 and the mold shell side surface 12 enclosed therewith form a cavity 13 inside, and the lower edge of the mold shell side surface 12 continues to extend horizontally outward to form a flange edge 14. The outer contour of a circle of flange edges 14 is a rectangle, and the vertical end surface of the outer edge of the flange edge 14 is a fitting surface 15 that abuts against each other between the mold shells 10; two, three or four adjacent fitting surfaces 15 of the mold shell 10 are provided with connecting holes 16, and the connecting holes 16 are horizontally arranged to pass through the cavity 13 to the fitting surface 15. The fitting surfaces 15 of several mold shells 10 are fitted together in pairs to form a rectangular mold shell array. The present scheme provides thirty-six mold shells 10, forming a mold shell array of six rows and six columns. The mold shells 10 located at the corners of the mold shell array 10 have two fitting surfaces 15 provided with connecting holes 16, the mold shells 10 on the sides have three fitting surfaces 15 provided with connecting holes 16, and the four fitting surfaces 15 of the central mold shell 10 are all provided with connecting holes 16, ensuring that there are no connecting holes 16 on the fitting surfaces 15 of the periphery of the mold shell array. In this way, after the concrete is poured and formed, the mold is removed, and the side of the main beam will not appear uneven due to the connecting holes 16, and there is no need to perform secondary processing on the side of the main beam. Of course, in other embodiments, all the mold shells 10 have four fitting surfaces 15 provided with connecting holes 16, and the fitting surfaces 15 of the periphery of the mold shell array are sealed with plugs, which can also achieve a smooth and flat side of the main beam, and should also be within the scope of protection of the present invention.
[0028] The bottom surfaces of all the mold shells 10 are coplanar, the connection holes 16 on the fitting surfaces 15 of two adjacent mold shells 10 are matched with each other, and are fastened and connected by fasteners penetrating the connection holes 16. The outermost edge of the mold shell array is set on the existing main beam side mold 41, and the fitting surface 15 of the mold shell 10 is flush with the inner side surface of the main beam side mold 41. The flange edge 14 of the mold shell 10 is fixed to the main beam side mold 41 by nails or other fasteners. The middle part of the mold shell array is set on five cross beams 30. Figure 11-14 Diagram of the formwork laying process.
[0029] Each crossbeam 30 supports the flange edges 14 of two adjacent rows of formwork shells 10 at the same time, and the upper surface of each crossbeam 30 abuts against the bottom surface of the flange edge 14 of the formwork shell 10. In this solution, the crossbeam 30 adopts a steel truss beam structure, which is welded by four parallel square tubes plus a number of straight braces and diagonal braces. Under the same load-bearing requirements and bending resistance requirements, the weight of the steel truss beam is lower, which has cost advantages, and the requirements for the bearing capacity of the lifting tools are lower, which is more convenient to install. At least one corner of the formwork shell 10 located at the edge is completely built on both ends of the crossbeam 30, meeting the minimum requirements for the support of the formwork shell 10.
[0030] A column 20 is provided below each end of the crossbeam 30. In the present scheme, the column 20 adopts a disc-type scaffolding, including a vertical pole 21, a horizontal pole 22, and a top support 23. Four vertical poles 21 are provided, which are arranged in a square shape. The center distance of the vertical poles 21 is 300 mm. The vertical poles 21 are connected by the horizontal pole 22. The horizontal pole 22 can be quickly fixed to the connecting plate 24 on the vertical pole 21 by a latch. The top support 23 includes a screw 231, an adjusting nut 232, and a U-shaped support plate 233. Of course, in other embodiments, the top support 23 can also be set to other structures to support the crossbeam. The cross beam 30 is a steel truss beam. During installation, it is hoisted by a tower crane or other hoisting machinery. The square tube of the steel truss beam is placed on the U-shaped support plate 233, leaving only one degree of freedom for the cross beam 30 to move in the length direction. The horizontal position of the cross beam 30 is adjusted. At least one corner of the formwork 10 located at the edge is completely placed on the cross beam 30. In this solution, the screw 231 is engaged with an adjustment nut 232. The lower end of the screw 231 is inserted into the top of the vertical pole 21. By turning the adjustment nut 232, the length of the screw 231 extending out of the vertical pole 21 can be adjusted, thereby changing the height of the cross beam 30. The bottom of the column 20 is supported on the ground or floor, and each column 20 is connected to the main beam scaffold 42 and the adjacent column 20 as a whole through a connector. The center distance between the uprights 21 of two adjacent uprights 20 is 900 mm, which is just suitable for the formwork 10 with a width of 1200 mm. The standard specifications of the disc-type crossbars 22 are available for both the 900 mm center distance and the 300 mm center distance, which are more convenient to install than the cross-buckle scaffolding.
[0031] In this solution, the columns 20 are erected on site, and two columns 20 support a beam 30. The beam 30 is a prefabricated part and is hoisted as a whole. Finally, the formwork 10 is laid on the main beam side formwork 41 and the beam 30, and connected in pairs by fasteners. The whole installation process is very convenient, and there is no need to erect a full-floor scaffolding, so the workload is small. Moreover, because there is no full-floor scaffolding, workers can stand on a mobile platform to operate during the erection process, which is safer than climbing on the scaffolding for installation. In addition, the formwork 10 is connected by fasteners, and the connection is tight to prevent leakage. Embodiment 2
[0032] like Figure 6 As shown, the difference from the first embodiment is that the cross beam 30 adopts a steel truss beam structure, and its front view is a triangular frame. It can also meet the bending strength required by the design, and has a higher bearing capacity and a lower manufacturing material cost. Embodiment 3
[0033] like Figure 7 As shown, the difference from the first embodiment is that the crossbeam 30 is made of H-shaped steel. Compared with the crossbeam 30 structure in the above embodiments, the H-shaped steel is easy to obtain and has a lower processing cost. It only needs to be selected and then cut to a suitable length. Embodiment 4
[0034] like Figure 8 As shown, the difference from Example 1 is that: the beam 30 adopts a cantilever beam structure. Compared with the beam 30 structure in the above embodiments, the cantilever beam can adjust the tension of the tension string according to the load, so that the flat plate on the top of the cantilever beam slightly bulges upward when there is no load. After pouring concrete, the flat plate on the top of the cantilever beam will be changed from slightly bulging to just keeping horizontal due to the pressure. Compared with the above embodiments, the beam 30 does not need to worry about the influence of force deformation, and the construction accuracy of the multi-ribbed floor is higher.
[0035] In other embodiments, the beam 30 may adopt other structures, including I-beams, square tubes, etc. The beam 30 only needs to meet the designed bending strength to ensure that the beam 30 can bear the weight of concrete during grouting and the bending amplitude is within an acceptable design range.
[0036] In other embodiments, the upright poles 21 of each upright column 20 may also be arranged in a 2×3 arrangement of 6 poles, or a 2×4 arrangement of 8 poles, or even a 3×3 arrangement of 9 poles, as needed, so long as the design requirements are met.
[0037] In other embodiments, the scaffolding used for the columns may also be connected by cross buckles.
[0038] In other embodiments, the column 20 may also adopt a prefabricated steel truss structure and be assembled on site by bolts.
[0039] In other embodiments, the steel truss beam is formed by splicing two detachable sections. Embodiment 5
[0040] like Figure 9-15 As shown, another aspect of the present invention provides a construction method of a multi-ribbed floor slab that can be installed efficiently, comprising: Preparation before construction: prefabricate the formwork 10 and the beam 30 according to the construction requirements, prepare the parts required for the column 20, and set up the main beam side formwork 41 according to the drawings to determine the installation height of the bottom surface of the multi-ribbed floor; The construction process includes installing the columns 20 and the connectors, installing the beams 30, and installing the formwork 10. The columns 20, the beams 30, and the formwork 10 adopt the structure of the first embodiment. Figure 1-5 As shown, specifically: 1. Erecting columns 20: Ten columns 20 are erected near the main beam scaffolding 42. The ten columns 20 are arranged in two parallel rows. The two rows of columns 20 are respectively located near two opposite main beam scaffoldings 42. The center distance between adjacent columns 20 is consistent with the width of the supported formwork 10, and each column 20 is connected to the main beam scaffolding 42 and the adjacent columns 20 through connecting pieces to form a whole. In this scheme, each column 20 is composed of four vertical rods 21, a plurality of cross bars 22 and a top support 23. The center distance of the vertical pole 21 is 300mm. The vertical poles 21 are connected in a disc-type manner through the cross bar 22. The cross bar 22 is fixed to the connecting plate 24 on the vertical pole 21 by a latch. The top support 23 includes a lead screw 231, an adjusting nut 232, and a U-shaped support plate 233. The lead screw 231 is engaged with an adjusting nut 232. The lower end of the lead screw 231 is inserted into the top of the vertical pole 21. By rotating the adjusting nut 232, the length of the lead screw extending out of the vertical pole 21 can be adjusted, thereby changing the height of the U-shaped support plate 233. After the vertical column 20 is erected, the adjacent vertical columns 20 are fixedly connected through the cross bar 22, and the vertical column 20 is connected to the closest main beam scaffolding 42 through the cross bar 22, so that the vertical column 20 and the main beam scaffolding 42 are connected into a whole, ensuring the overall stability of the vertical column 20. Of course, in other embodiments, the top support 23 can also be set to other structures to play a supporting role for the cross beam.
[0041] 2. Install the crossbeam 30: Lift the five prefabricated crossbeams 30 and install them on the tops of the ten columns 20. In this solution, the crossbeam 30 adopts a steel truss beam structure, which is welded by four parallel square tubes plus a number of straight braces and diagonal braces. It is hoisted by a tower crane or other hoisting machinery, and the square tube of the steel truss beam is placed on the U-shaped support plate 233, leaving only one degree of freedom for the crossbeam 30 to move in the length direction. The horizontal position of the crossbeam 30 is adjusted, and at least one corner of the formwork 10 located at the edge is completely placed on the crossbeam 30. By turning the adjusting nut 232, the length of the lead screw extending out of the vertical rod 21 can be adjusted, thereby changing the height of the U-shaped support plate 233, and finally achieving the height of the top of the crossbeam 30 to be consistent with the top surface height of the main beam side form 41; 3. Install the formwork 10: Start from one corner of the main beams around the formwork 10 and sequentially set up the formwork 10 along one side of the main beam, and then sequentially set up the remaining formwork 10 along the already set up formwork 10 or the side of the main beam, until the formwork 10 covers the places where it needs to be laid, and the side of each formwork 10 is set up on the side form 41 of the main beam or the cross beam 30, and the formwork 10 at the edge has at least one corner completely set up on the cross beam 30; starting from the second formwork 10, each time a formwork 10 is installed, the mating surface 15 of the newly installed formwork 10 and the installed formwork 10 are pressed tightly, and the two formworks 10 are fastened together by fasteners penetrating the connecting holes 16. In this solution, the formwork is installed in rows, for example Figure 12-13 As shown in FIG. 1 , it is a schematic diagram of the first formwork 10 after being erected. The first formwork 10 is installed at a corner position, wherein two sides are erected on the main beam side formwork 41, and one side is erected on the crossbeam 30. The two outer fitting surfaces 15 of the first formwork 10 are flush with the inner side surface of the main beam side formwork 41. The flange edge 14 of the formwork 10 is fixed to the main beam side formwork 41 by nails or other fasteners, and then gradually erected along a horizontal row, as shown in FIG. Fig.14 As shown in FIG. 1 , it is a schematic diagram of erecting the first row of formwork 10, and then erecting the second row, the third row, and so on in sequence until the erection is completed. Fig.15 As shown, the formwork 10 covers the entire plane.
[0042] In this solution, the columns 20 are erected on site, and the columns 20 adopt a disc-type scaffolding, which is very convenient to install. The beam 30 is hoisted as a whole, and two columns 20 support a beam 30. Finally, the formwork 10 is laid on the main beam side form 41 and the beam 30, and connected in pairs by fasteners. The whole installation process is very convenient, and there is no need to erect a full-floor scaffolding. The workload is small and can be assembled quickly. And precisely because there is no full-floor scaffolding, workers can stand on a mobile platform to operate during the erection process, which is safer than climbing on the scaffolding for installation. The formworks 10 are connected by fasteners penetrating the connecting holes, and the connection is tight and there will be no leakage. The columns 20, the beam 30, and the formwork 10 can all be reused. After multiple uses, the cost can be spread to a very low level.
[0043] In this solution, the outermost mold shell 10 does not need the cross beam 30 to support the entire flange edge 14, and only needs the cross beam 30 to support at least one corner of the outermost mold shell 10, for example Fig.15There are 6 formworks in a row, each with a width of 1200mm, so the entire span is 7200mm. The crossbeam 30 used in this solution is 6700mm, and the width of 400mm can cover the flange edges 14 of the two formworks 10. The crossbeam 30 is close to the main beam side form 41, and the contact surface length between the uppermost formwork and the crossbeam 30 is 950mm, which fully meets the support of the formwork 10. If the same crossbeam 30 is used to support a row of 7 formworks 10, each formwork 10 is 1200mm wide, so the entire span is 8400mm. After calculation, the contact surface length between the uppermost formwork 10 and the crossbeam 30 is 35 0mm, which is larger than a corner on the side of the formwork 10, so it can also meet the support of the formwork 10. It can be seen that the same length of beam 30 can meet the erection of at least two standard spans of formwork 10. Theoretically, in the case of non-standard span, a 6700mm beam 30 can meet the span of 7000mm-8800mm. Within a reasonable range, it is only necessary to change the distance from the column 20 to the main beam scaffolding 42. Therefore, this solution can be designed in a universal manner. It is only necessary to set several fixed-length beams 30 according to the span requirements to meet the requirements of all span construction.
[0044] In actual application, workers who install the mold shell 10 perform assisted installation through a mobile platform. The mobile platform adopts a self-propelled hydraulic lift. Workers stand on the self-propelled hydraulic lift to install it. After each mold shell 10 is installed, the self-propelled hydraulic lift moves to the appropriate position to install the fasteners between the mold shells 10. Then the self-propelled hydraulic lift continues to move to install the next mold shell 10. Since there is no scaffolding all over the floor, the self-propelled hydraulic lift can move unimpeded, which can improve the installation efficiency of the installers and does not require climbing scaffolding, which is safer. The mold shell can also be placed on the self-propelled hydraulic lift in advance, which is ready for use and improves the convenience of installation.
[0045] In practical applications, the scaffold is a disc-type scaffold, including uprights 21, crossbars 22, and top supports. The uprights 21 are provided with a circular connecting plate 24 that can be buckled. The two ends of the crossbar 22 are connected to the connecting plates 24 of the uprights 21 by bolts. When erecting the columns 20, multiple uprights 21 are arranged in an array, at least two rows and two columns. The uprights 21 are connected by crossbars 22, and the uprights 20 are fixed to the closest main beam scaffold 42 by crossbars 22. When the disc-type scaffold is used, the crossbars 22 and the uprights 21 can be fixed by inserting the pins, which has higher installation efficiency than other methods. Of course, in other embodiments, a scaffold with a cross-buckle connection method can also be used, or a prefabricated steel truss structure can be used, and assembled on site by bolts. The present invention does not limit the specific structural form of the column, and the above schemes should all fall within the protection scope of the present invention.
[0046] In practical applications, the top support 23 includes a lead screw 231, an adjusting nut 232, and a U-shaped support plate 233. The lead screw 231 is meshed with an adjusting nut 232. The lower end of the lead screw 231 is inserted into the top of the vertical pole 21. By turning the adjusting nut 232, the length of the lead screw extending out of the vertical pole 21 can be adjusted, thereby changing the height of the U-shaped support plate 233. After the erection of the column 20 is completed, the adjacent columns 20 are fixedly connected by the cross bar 22, and the column 20 is connected to the closest main beam scaffolding 42 by the cross bar 22, so that the column 20 and the main beam scaffolding 42 are connected into a whole, ensuring the overall stability of the column 20. Of course, in other embodiments, the top support 23 can also be set to other structures to support the cross beam.
[0047] In actual application, after the installation of the formwork 10 is completed, the steel bars are tied, concrete is poured and cured on the erected ribbed floor forming structure. After the curing and forming, the fasteners are removed, the height of the column 20 is lowered, and the formwork 10, the column 20 and the beam 30 are removed to prepare for turnover and reuse, thereby improving the reuse rate of materials and reducing costs.
[0048] In summary, the highly efficient ribbed floor forming structure and construction method of the present invention can reduce the number of scaffolding installations and the workload. By building the columns 20 and beams 30, the installation conditions of the formwork 10 can be quickly met, and there is no full-house scaffolding underneath, and the self-propelled hydraulic lift can move unimpeded, which can improve the installation efficiency of the installers, and there is no need to climb the scaffolding, which is safer. The formworks 10 are connected by fasteners, the connection is tight, and there is no leakage.
[0049] The above shows and describes the basic principles, main features and advantages of the present invention. Those skilled in the art should understand that the above implementation is only to illustrate the technical concept and features of the present invention, and its purpose is to enable people familiar with this technology to understand the content of the present invention and implement it, and it cannot be used to limit the protection scope of the present invention. All equivalent changes or modifications made according to the spirit of the present invention should be covered by the protection scope of the present invention.
Claims
1. A ribbed floor forming structure that can be efficiently installed, characterized in that: It includes a plurality of mold shells (10), columns (20), and beams (30). The mold shell (10) comprises a mold shell top surface (11), and a circle of the mold shell top surface (11) is connected to a mold shell side surface (12) extending downward. The mold shell top surface (11) and the mold shell side surface (12) enclosed therewith form a cavity (13) inside, and the lower edge of the mold shell side surface (12) continues to extend horizontally outward to form a flange edge (14), and the outer contour of a circle of the flange edge (14) is a rectangle, and the vertical end surface of the outer edge of the flange edge (14) is a fitting surface (15) that abuts against each other between the mold shells (10); connecting holes (16) are provided on two, three or four adjacent fitting surfaces (15) of the mold shell (10), and the connecting holes (16) are horizontally arranged to pass through the cavity (13) to the fitting surface (15). The fitting surfaces (15) of a plurality of mold shells (10) are fitted in pairs to form a rectangular mold shell array, the bottom surfaces of all the mold shells (10) are coplanar, the connection holes (16) on the fitting surfaces (15) of two adjacent mold shells (10) are matched with each other, and are fastened and connected by fasteners penetrating the connection holes (16), the outermost edge of the mold shell array is placed on the existing main beam side mold (41), and the middle of the mold shell array is supported by a plurality of parallel cross beams (30). Each crossbeam (30) supports the flange edges (14) of two adjacent rows of formwork shells (10) at the same time, the upper surface of the crossbeam (30) and the bottom surface of the flange edge (14) of the formwork shell (10) abut against each other, and at least one corner of the formwork shell (10) located at the edge is completely placed on the crossbeam (30). A column (20) is disposed below each end of the crossbeam (30); the bottom of the column (20) is supported on the ground or the floor; the height of the column (20) can be adjusted; the top of the column (20) and the crossbeam (30) are detachably connected or overlapped; each column (20) is connected to the main beam scaffold (42) and the adjacent column (20) via a connecting piece to form a whole.
2. The ribbed floor forming structure that can be efficiently installed according to claim 1 is characterized in that: The cross beam (30) is one of a steel section, a steel truss beam, a cantilever beam or a combination thereof.
3. An efficiently installable ribbed floor forming structure according to claim 1 or 2, characterized in that: The upright column (20) is constructed by scaffolding and comprises an upright pole (21), a cross pole (22), and a top support (23).
4. The ribbed floor forming structure that can be efficiently installed according to claim 3 is characterized in that: The scaffold is a disk-type scaffold, the vertical pole (21) is provided with a buckled annular connecting plate (24), and the two ends of the cross bar (22) are connected to the connecting plate (24) of the vertical pole (21) through a latch.
5. The ribbed floor forming structure that can be efficiently installed according to claim 3 is characterized in that: The connecting piece is a crossbar (22) used for a scaffold.
6. A construction method for a multi-ribbed floor slab that can be installed efficiently, characterized in that: include: Preparation before construction: prefabrication of the formwork (10) and the crossbeam (30) is completed according to the construction requirements, the parts required for the column (20) are prepared, and the side formwork (41) of the main beam is set up according to the drawings to determine the installation height of the bottom surface of the multi-ribbed floor; Construction content: including installation of columns (20) and connectors, installation of beams (30), and installation of formwork (10), specifically:
1. Installing columns (20) and connectors: installing a plurality of columns (20) near the main beam scaffolding (42), the plurality of columns (20) being arranged in two parallel rows, the two rows of columns (20) being respectively located near two opposite main beam scaffoldings (42), the center distance between adjacent columns (20) being consistent with the width of the supported formwork (10), and connecting each column (20) to the main beam scaffolding (42) and the adjacent columns (20) through the connecting members to form a whole; 2. Installing the cross beams (30): installing a plurality of prefabricated cross beams (30) on the tops of the two columns (20), adjusting the heights of the columns (20) to ensure that the height of the tops of the cross beams (30) meets the construction requirements; 3. Installing the formwork (10): Starting from a corner of the main beams on all four sides, the formwork (10) is sequentially installed along one side of the main beam, and then the remaining formwork (10) is sequentially installed along the already installed formwork (10) or the side of the main beam until the formwork (10) covers all the places where it needs to be installed, and the side of each formwork (10) is installed on the side formwork (41) of the main beam or the cross beam (30), and at least one corner of the formwork (10) located at the edge is completely installed on the cross beam (30); starting from the second formwork (10), each time a formwork (10) is installed, the mating surface (15) of the newly installed formwork (10) is tightly attached to the mating surface (15) of the installed formwork (10), and the two formworks (10) are fastened and connected by fasteners penetrating the connection holes (16).
7. The construction method of a multi-ribbed floor slab that can be installed efficiently according to claim 6, characterized in that: When installing the formwork (10), workers stand on the mobile platform to assist in the installation.
8. The construction method of a ribbed floor slab that can be installed efficiently according to claim 6, characterized in that: The upright posts (20) are constructed by scaffolding, and include upright posts (21), cross bars (22), and top supports (23). When the upright posts (20) are constructed, a plurality of upright posts (21) are arranged in an array, at least in two rows and two columns. The upright posts (21) are connected by cross bars (22), and the upright posts (20) are fixed to the nearest main beam scaffolding (42) by the cross bars (22).
9. A construction method for a multi-ribbed floor slab that can be installed efficiently according to claim 8, characterized in that: The scaffold is a disk-type scaffold, the vertical pole (21) is provided with a buckled annular connecting plate (24), and the two ends of the cross bar (22) are connected to the connecting plate (24) of the vertical pole (21) through a latch.
10. The construction method of a multi-ribbed floor slab that can be installed efficiently according to claim 6, characterized in that: After the formwork (10) is installed, steel bars are tied to the already erected ribbed floor slab forming structure, concrete is poured, and curing is performed. After curing and forming, the fasteners are removed, the height of the columns (20) is lowered, and the formwork (10), the columns (20), and the beams (30) are removed to prepare for turnover and reuse.