Boiler waste heat recovery method
By monitoring the efficiency curve and deviation of boiler waste heat recovery equipment in real time, identifying and maintaining abnormal equipment in advance, the energy efficiency loss and environmental impact caused by the decrease in boiler waste heat recovery efficiency is solved, and the energy efficiency and environmental protection effect of the system are improved.
Patent Information
- Application Number
- CN202411165060.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-23
- Publication Date
- 2024-11-19
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The prior art When the efficiency of the boiler waste heat recovery equipment decreases, the equipment is usually stopped for maintenance after reaching the early warning threshold, resulting in serious waste heat loss of the boiler during the efficiency decline, affecting the system's energy efficiency and possibly having an adverse impact on the environment.
By determining the use cycle of the boiler during the monitoring cycle, obtaining waste heat recovery efficiency in real time and drawing a curve, calculating the deviation degree and filtering abnormal equipment, and performing maintenance in advance to avoid a decrease in waste heat recovery efficiency.
Effectively screen and maintain abnormal equipment to prevent the reduction of waste heat recovery efficiency, improve system energy efficiency, and reduce environmental impact.
Smart Images

Figure CN118980086A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of data analysis, and in particular to a boiler waste heat recovery method. Background Art
[0002] Boiler waste heat refers to the heat that is not fully utilized and discharged during the industrial production process. It is a secondary energy source and is the product of the conversion of primary energy and combustible materials. The rational use of this part of heat is of great significance for energy conservation and emission reduction. The methods of waste heat recovery include but are not limited to waste heat recovery equipment, heat exchange technology, heat-to-work conversion technology, etc.
[0003] For the method of recovering waste heat through waste heat recovery equipment, in order to be able to recover the boiler waste heat normally, it is necessary to ensure the normal operation of the waste heat recovery equipment. Most of the existing methods to ensure the normal operation of waste heat recovery equipment are to stop the equipment and perform maintenance after detecting that the waste heat recovery efficiency is lower than the preset range. Although this method can accurately determine the abnormal equipment, during the period when the waste heat recovery efficiency drops to the warning threshold, the boiler's waste heat loss is very large, which not only affects the energy efficiency of the system, but may also have an adverse impact on the environment. Based on this, a boiler waste heat recovery method is provided, which can screen out abnormal equipment in advance according to the recovery efficiency of the boiler waste heat to avoid affecting the energy efficiency of the system. Summary of the invention
[0004] The purpose of the present invention is to provide a boiler waste heat recovery method to solve the following technical problems:
[0005] The conventional method is usually to stop the equipment and perform maintenance after detecting that the waste heat recovery efficiency is lower than the preset range. Although this method can accurately identify abnormal equipment, during the period when the waste heat recovery efficiency drops to the warning threshold, the boiler's waste heat loss is very large, which not only affects the energy efficiency of the system, but may also have an adverse impact on the environment.
[0006] The purpose of the present invention can be achieved through the following technical solutions:
[0007] A boiler waste heat recovery method, comprising a waste heat recovery device, comprises the following steps:
[0008] S1: Taking the current time as the starting point, determine a monitoring period of length T along the reverse time axis, and determine the boiler usage period [T j,sta +ΔT,T j,end +ΔT] represents the jth use cycle of the boiler, j∈[1,m], m represents the total number of use cycles, T j,sta represents the time when the boiler starts to be used for the jth time, T j,endrepresents the time point when the boiler ends its use for the jth time, and ΔT represents the preset time length;
[0009] S2: obtaining the waste heat recovery efficiency of the waste heat recovery device in real time during the use period, and drawing a curve of the waste heat recovery efficiency changing with time, and using it as the target curve f(t);
[0010] Sort the target curves in the order of the time axis, and let the Ath target curve f in the sorting be A (t) and the adjacent previous target curve f A-1 The time point corresponding to the starting point of (t) is 0, and the evaluation curve F(t)=f A-1 (t)-f A (t);
[0011] The intersection of the evaluation curve and the x-axis is recorded as a reference point, and the starting point and the end point of the evaluation curve are recorded as reference points. When the evaluation curve between two adjacent reference points is above the x-axis, it is marked as an abnormal curve;
[0012] S3: Calculate the deviation K based on the evaluation curve and the abnormal curve, and generate a deviation set K jh =(K1, K2, ..., K m-1 ), K m-1 Indicates the deviation between the mth target curve in the sorting and the adjacent previous target curve m-1;
[0013] Determine the maximum deviation Kmax = max(K jh ), and screen abnormal equipment according to the maximum deviation, and remind staff to maintain the abnormal equipment.
[0014] As a further solution of the present invention: in the step S3, the process of calculating the deviation K according to the evaluation curve and the abnormal curve specifically includes:
[0015] The deviation K is calculated by a formula, wherein the formula specifically includes:
[0016]
[0017] Where ε represents the preset correction coefficient and ε>0, N represents the total number of abnormal curves, T N ' represents the total time length corresponding to the abnormal curve, and T' represents the standard time length.
[0018] As a further solution of the present invention: the process of determining the standard time length specifically includes:
[0019] Determine the target curve f A (t) and f A-1(t) and the time length corresponding to it, and the smaller one is recorded as the standard time length T';
[0020] The target curve Aund that does not correspond to the standard time length T' is marked as an undetermined curve, and the undetermined curve within [0, T'] is intercepted as the target curve Aund.
[0021] As a further solution of the present invention: in the step S3, the process of screening abnormal devices according to the maximum deviation specifically includes:
[0022] Determine the maximum deviation of all waste heat recovery equipment, calculate the average maximum deviation Kmax', and calculate the evaluation value ΔK i =Kmax i -Kmax',Kmax i Indicates the maximum deviation of the i-th waste heat recovery device, when the evaluation value ΔK i ≥ΔK', the i-th waste heat recovery device is marked as an abnormal device, and ΔK' represents the preset evaluation value threshold.
[0023] As a further solution of the present invention: the process of screening abnormal devices according to the maximum deviation also includes the following steps:
[0024] When the average maximum deviation Kmax'≥Kmax ys When the maximum deviation Kmax ≥ Kmax ys The waste heat recovery equipment is marked as abnormal equipment, Kmax ys Indicates the preset average maximum deviation threshold.
[0025] As a further solution of the present invention: in the step S2, when the waste heat recovery efficiency during the use period is less than the preset waste heat recovery efficiency threshold, the subsequent steps are not executed, and the corresponding waste heat recovery equipment is regarded as an abnormal equipment.
[0026] As a further solution of the present invention: in the step S1, the time point when the waste heat recovery equipment starts to be put into use is recorded as the input point T in , and when the monitoring period T corresponding to the waste heat recovery equipment Y contains the input point, perform the following steps:
[0027] Determine the starting point T of the monitoring cycle sta and the end point T end , and when (T in -T sta ) / ()T end -T sta When ≥0.2, it is determined that the waste heat recovery equipment Y is not an abnormal equipment.
[0028] As a further solution of the present invention: the waste heat recovery equipment includes but is not limited to a heat exchanger.
[0029] Beneficial effects of the present invention: In the present invention, the monitoring period is first determined, and the use period of the boiler within the monitoring period is determined; it can be understood that starting from the current time, determining the monitoring period along the reverse time axis direction can make the acquired data closer to the current period. The jth use period is [T j,sta +ΔT,T j,end +ΔT] specifically include: in actual situations, when the boiler starts working, the waste heat recovery equipment starts working. In the early stage of using the boiler, since the boiler has not yet fully reached a stable working state, there may be insufficient waste heat. Therefore, it is necessary to add a time length ΔT at the initial use time point to ensure that the data after the boiler gradually enters a stable working state can be captured during the use period, so as to ensure the accuracy and effectiveness of the data in subsequent processing; then the waste heat recovery efficiency is obtained in real time and the target curve is determined, and the evaluation curve is determined based on the target curve, and the abnormal curve on the evaluation curve is determined; it is worth noting that the time point corresponding to the starting point of the two target curves is recorded as 0, which can ensure that the points on the two target curves with the same time interval from their corresponding starting points are compared. Specifically, it is ensured that the point on target curve A with an interval of Ta from the starting point of target curve A and the point on target curve A-1 with an interval of Ta from the starting point of target curve A-1 are compared with the point on target curve A-2 with an interval of Ta from the starting point of target curve A-3. The points with intervals of Ta are compared; it can be understood that the evaluation curve reflects the downward trend of the waste heat recovery efficiency in two adjacent use cycles. When the evaluation curve between two adjacent reference points is above the x-axis, it means that the waste heat recovery efficiency in the Ath use cycle in this period (i.e., the time period between two adjacent reference points) has decreased more, so it is taken as an abnormal curve; then, the deviation is calculated and the deviation set is determined, and the maximum deviation in the deviation set is determined, and the abnormal equipment is screened according to the maximum deviation; it is worth noting that the deviation is used to reflect the comprehensive decline in the waste heat recovery efficiency when the waste heat recovery equipment is used twice adjacently. The greater the deviation, the higher the decline. The comprehensive decline of normal waste heat recovery equipment is very different from that of abnormal waste heat recovery equipment. Therefore, abnormal equipment is screened according to the maximum deviation K to avoid the situation where the waste heat recovery efficiency of the waste heat recovery equipment is not maintained until it drops to the warning range. The present invention can screen abnormal equipment according to the decline in waste heat recovery efficiency to prevent the decline in system energy efficiency due to abnormal waste heat recovery equipment. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] The present invention will be further described below in conjunction with the accompanying drawings.
[0031] Figure 1 It is a schematic flow diagram of a boiler waste heat recovery method of the present invention. DETAILED DESCRIPTION
[0032] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0033] See also Figure 1 As shown, the present invention is a boiler waste heat recovery method, including a waste heat recovery device, comprising the following steps:
[0034] S1: Taking the current time as the starting point, determine a monitoring period of length T along the reverse time axis, and determine the boiler usage period [T j,sta +ΔT,T j,end +ΔT] represents the jth use cycle of the boiler, j∈[1,m], m represents the total number of use cycles, T j,sta represents the time when the boiler starts to be used for the jth time, T j,end represents the time point when the boiler ends its use for the jth time, and ΔT represents the preset time length;
[0035] S2: obtaining the waste heat recovery efficiency of the waste heat recovery device in real time during the use period, and drawing a curve of the waste heat recovery efficiency changing with time, and using it as the target curve f(t);
[0036] Sort the target curves in the order of the time axis, and let the Ath target curve f in the sorting be A (t) and the adjacent previous target curve f A-1 The time point corresponding to the starting point of (t) is 0, and the evaluation curve F(t)=f A-1 (t)-f A (t);
[0037] The intersection of the evaluation curve and the x-axis is recorded as a reference point, and the starting point and the end point of the evaluation curve are recorded as reference points. When the evaluation curve between two adjacent reference points is above the x-axis, it is marked as an abnormal curve;
[0038] S3: Calculate the deviation K based on the evaluation curve and the abnormal curve, and generate a deviation set K jh =(K1, K2, ..., K m-1 ), K m-1 Indicates the deviation between the mth target curve in the sorting and the adjacent previous target curve m-1;
[0039] Determine the maximum deviation Kmax = max(K jh ), and screen abnormal equipment according to the maximum deviation, and remind staff to maintain the abnormal equipment.
[0040] It should be noted that the monitoring period is first determined, and the boiler usage period within the monitoring period is determined; it can be understood that starting from the current time, determining the monitoring period along the reverse time axis can make the acquired data closer to the current period. The jth usage period is [T j,sta +ΔT,T j,end +ΔT] specifically include: in actual situations, when the boiler starts working, the waste heat recovery equipment starts working. In the early stage of using the boiler, since the boiler has not yet fully reached a stable working state, there may be insufficient waste heat. Therefore, it is necessary to add a time length ΔT at the initial use time point to ensure that the data after the boiler gradually enters a stable working state can be captured during the use period, so as to ensure the accuracy and effectiveness of the data in subsequent processing; then the waste heat recovery efficiency is obtained in real time and the target curve is determined, and the evaluation curve is determined based on the target curve, and the abnormal curve on the evaluation curve is determined; it is worth noting that the time point corresponding to the starting point of the two target curves is recorded as 0, which can ensure that the points on the two target curves with the same time interval from their corresponding starting points are compared. Specifically, it is ensured that the point on target curve A with an interval of Ta from the starting point of target curve A and the point on target curve A-1 with an interval of Ta from the starting point of target curve A-1 are compared with the point on target curve A-2 with an interval of Ta from the starting point of target curve A-3. The points with an interval of Ta are compared; it can be understood that the evaluation curve reflects the downward trend of the waste heat recovery efficiency in two adjacent use cycles. When the evaluation curve between two adjacent reference points is above the x-axis, it means that the waste heat recovery efficiency in the Ath use cycle in this period (i.e., the time period between two adjacent reference points) decreases more, so it is taken as an abnormal curve; then, the deviation is calculated and the deviation set is determined, and the maximum deviation in the deviation set is determined, and the abnormal equipment is screened according to the maximum deviation; it is worth noting that the deviation is used to reflect the comprehensive decline in the waste heat recovery efficiency when the waste heat recovery equipment is used twice adjacently. The larger the deviation, the higher the decline. The comprehensive decline of normal waste heat recovery equipment is very different from that of abnormal waste heat recovery equipment. Therefore, abnormal equipment is screened according to the maximum deviation K to avoid the situation where the waste heat recovery efficiency of the waste heat recovery equipment is not maintained until it drops to the warning range.
[0041] In another preferred implementation of the present invention, in step S3, the process of calculating the deviation K according to the evaluation curve and the abnormal curve specifically includes:
[0042] The deviation K is calculated by a formula, wherein the formula specifically includes:
[0043]
[0044] Where ε represents the preset correction coefficient and ε>0, N represents the total number of abnormal curves, T N ' represents the total time length corresponding to the abnormal curve, and T' represents the standard time length.
[0045] It is worth noting that the deviation is used to reflect the comprehensive decline in waste heat recovery efficiency when the waste heat recovery equipment is used twice adjacently. The evaluation curve F(t) reflects the downward trend of waste heat recovery efficiency in two adjacent use cycles. The larger the max(F(t)), the greater the decline in waste heat recovery efficiency, and the greater the deviation K should be. The relationship between the remaining parameters and the deviation can be analogous to the above ideas and will not be repeated here; ε can be set by experience.
[0046] In another preferred implementation of the present invention, the process of determining the standard time length specifically includes:
[0047] Determine the target curve f A (t) and f A-1 (t) and the time length corresponding to it, and the smaller one is recorded as the standard time length T';
[0048] The target curve Aund that does not correspond to the standard time length T' is marked as an undetermined curve, and the undetermined curve within [0, T'] is intercepted as the target curve Aund.
[0049] It is understandable that it is worth noting that the lengths of two adjacent usage cycles may not be the same, so the two need to be unified, that is, a part is intercepted from the longer target curve (that is, the target curve Aund) to replace the target curve. Considering that the length of use may affect the waste heat recovery efficiency, in order to improve the accuracy of subsequent judgments, the interception is performed from the starting point of the target curve Aund.
[0050] In another preferred implementation of the present invention, in step S3, the process of screening abnormal devices according to the maximum deviation specifically includes:
[0051] Determine the maximum deviation of all waste heat recovery equipment, calculate the average maximum deviation Kmax', and calculate the evaluation value ΔK i =Kmax i -Kmax',Kmax i Indicates the maximum deviation of the i-th waste heat recovery device, when the evaluation value ΔK i ≥ΔK', the i-th waste heat recovery device is marked as an abnormal device, and ΔK' represents the preset evaluation value threshold.
[0052] It should be noted that the average maximum deviation Kmax' reflects the average situation of the maximum deviation. When the difference between the maximum deviation and the average situation of a waste heat recovery device exceeds the preset range, it means that the maximum deviation of the waste heat recovery device may be abnormal. Therefore, the corresponding waste heat device is marked as an abnormal device, and the staff is notified to perform maintenance on it during the period when the boiler is not working, thereby reducing the decline in system energy efficiency caused by the abnormality of the waste heat recovery equipment.
[0053] In another preferred implementation of the present invention, the process of screening abnormal devices according to the maximum deviation also includes the following steps:
[0054] When the average maximum deviation Kmax'≥Kmax ys When the maximum deviation Kmax ≥ Kmax ys The waste heat recovery equipment is marked as abnormal equipment, Kmax ys Indicates the preset average maximum deviation threshold.
[0055] It should be noted that in actual situations, the average maximum deviation Kmax' may exceed expectations (i.e., greater than Kmax ys ), which indicates that there are many abnormal devices. Therefore, the abnormal devices are no longer screened by the average maximum deviation Kmax', but the abnormal devices are screened by the preset average maximum deviation threshold, which can be set by experience.
[0056] In another preferred implementation of the present invention, in the step S2, when the waste heat recovery efficiency during the use period is less than a preset waste heat recovery efficiency threshold, subsequent steps are not executed, and the corresponding waste heat recovery equipment is treated as an abnormal equipment.
[0057] In another preferred embodiment of the present invention, in step S1, the time point when the waste heat recovery equipment starts to be put into use is recorded as the input point T in , and when the monitoring period T corresponding to the waste heat recovery equipment Y contains the input point, perform the following steps:
[0058] Determine the starting point T of the monitoring cycle sta and the end point T end , and when (T in -T sta ) / ()T end -T sta When ≥0.2, it is determined that the waste heat recovery equipment Y is not an abnormal equipment.
[0059] It is worth noting that when (T in -T sta ) / ()T end -Tsta When ≥0.2, it means that the waste heat recovery equipment Y has been in use for a short time. At this time, there is no need for subsequent processing. It is sufficient to directly determine that the waste heat recovery equipment Y is not an abnormal device, which can improve the efficiency of screening abnormal equipment.
[0060] In another preferred embodiment of the present invention, the waste heat recovery equipment includes but is not limited to a heat exchanger.
[0061] The above is a detailed description of an embodiment of the present invention, but the content is only a preferred embodiment of the present invention and cannot be considered to limit the scope of implementation of the present invention. All equivalent changes and improvements made within the scope of the present invention should still fall within the scope of the patent coverage of the present invention.
Claims
1. A boiler waste heat recovery method, comprising a waste heat recovery device, characterized in that: The following steps are involved: S1: Taking the current time as the starting point, determine a monitoring period of length T along the reverse time axis direction, and determine the use period of the boiler within the monitoring period. [Tj, sta+ΔT, Tj, end+ΔT] represents the jth use period of the boiler, j∈[1, m], m represents the total number of use periods, Tj, sta represents the time point when the boiler starts to be used for the jth time, Tj, end represents the time point when the boiler ends to be used for the jth time, and ΔT represents the preset time length; S2: obtaining the waste heat recovery efficiency of the waste heat recovery device in real time during the use period, and drawing a curve of the waste heat recovery efficiency changing with time, and using it as the target curve f(t); Sort the target curves in the order of the time axis, and let the Ath target curve f in the sorting be A (t) and the adjacent previous target curve f A-1 The time point corresponding to the starting point of (t) is 0, and the evaluation curve F(t)=f A-1 (t)-f A (t); The intersection of the evaluation curve and the x-axis is recorded as a reference point, and the starting point and the end point of the evaluation curve are recorded as reference points. When the evaluation curve between two adjacent reference points is above the x-axis, it is marked as an abnormal curve; S3: Calculate the deviation K according to the evaluation curve and the abnormal curve, and generate a deviation set Kjh=(K1, K2, ..., Km-1), where Km-1 represents the deviation between the mth target curve in the sorting and the adjacent previous target curve m-1; The maximum deviation Kmax=max(Kjh) is determined, and abnormal equipment is screened according to the maximum deviation, and the staff is reminded to perform maintenance on the abnormal equipment.
2. A boiler waste heat recovery method according to claim 1, characterized in that: In step S3, the process of calculating the deviation K according to the evaluation curve and the abnormal curve specifically includes: The deviation K is calculated by a formula, wherein the formula specifically includes: Where ε represents the preset correction coefficient and ε>0, N represents the total number of abnormal curves, T N ' represents the total time length corresponding to the abnormal curve, and T' represents the standard time length.
3. A boiler waste heat recovery method according to claim 2, characterized in that: The process of determining the standard time length specifically includes: Determine the target curve f A (t) and f A-1 (t) and the time length corresponding to it, and the smaller one is recorded as the standard time length T'; The target curve Aund that does not correspond to the standard time length T' is marked as an undetermined curve, and the undetermined curve within [0, T'] is intercepted as the target curve Aund.
4. A boiler waste heat recovery method according to claim 1, characterized in that: In step S3, the process of screening abnormal devices according to the maximum deviation specifically includes: Determine the maximum deviation of all waste heat recovery devices, calculate the average maximum deviation Kmax', and calculate the evaluation value ΔKi=Kmaxi-Kmax', Kmaxi represents the maximum deviation of the i-th waste heat recovery device, when the evaluation value ΔKi≥ΔK', the i-th waste heat recovery device is marked as an abnormal device, ΔK' represents the preset evaluation value threshold.
5. A boiler waste heat recovery method according to claim 4, characterized in that: The process of screening abnormal devices according to the maximum deviation also includes the following steps: When the average maximum deviation Kmax'≥Kmaxys, the waste heat recovery equipment with the maximum deviation Kmax≥Kmaxys is marked as an abnormal equipment, and Kmaxys represents a preset average maximum deviation threshold.
6. A boiler waste heat recovery method according to claim 1, characterized in that: In the step S2, when the waste heat recovery efficiency in the use cycle is less than a preset waste heat recovery efficiency threshold, the subsequent steps are not executed, and the corresponding waste heat recovery device is regarded as an abnormal device.
7. A boiler waste heat recovery method according to claim 1, characterized in that: In the step S1, the time point when the waste heat recovery device starts to be put into use is recorded as the input point Tin, and when the monitoring period T corresponding to the waste heat recovery device Y contains the input point, the following steps are performed: The starting point Tsta and the end point Tend of the monitoring period are determined, and when (Tin-Tsta) / (Tend-Tsta)≥0.2, it is determined that the waste heat recovery device Y is not an abnormal device.
8. The method for recovering waste heat from a boiler according to claim 1, characterized in that: The waste heat recovery equipment includes but is not limited to a heat exchanger.
Citation Information
Cited By
Power equipment energy recovery method based on multi-modal processing
CN120125223A
Boiler waste heat recovery energy scheduling management method and system and medium
CN120370710A