Guide rod device, pile frame and vibroflotation rod connecting method
By first lowering and docking the guide rod, combined with the design of positioning connectors, the problems of limited length and poor accuracy in the existing technology are solved, and efficient and accurate guide rod lowering and connection are achieved to meet the ultra-deep vibration requirements. .
Patent Information
- Application Number
- CN202411361132.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-27
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2044-09-27
AI Technical Summary
In the construction of ultra-deep vibration piles, the length of the guide rod is limited by the lifting height of the crane, resulting in low joint efficiency and poor vertical accuracy, and the telescopic guide rod processing is complex and costly.
The first guide rod is first lowered and then moved to the second guide rod to connect it with the first guide rod, and the connection between the water pipe and the air pipe is achieved through the positioning connection member, thereby improving the joint efficiency and vertical accuracy.
Meet the requirements of ultra-deep vibration, improve the vertical accuracy and jointing efficiency during the guide rod drop, and reduce costs.
Smart Images

Figure CN118997110A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of construction equipment, and more specifically, to a guide rod device. In addition, the present invention also relates to a pile frame including the guide rod device and a vibro-impact connecting rod method applied to the pile frame. Background Art
[0002] Vibroflotation is a foundation treatment method. Generally, a vibrator with a guide rod is hoisted by a crane or a drilling rig. The soft foundation soil layer is vibrated and compacted under the action of the exciting force generated by the vibrator, or a hole is vibrated in the foundation soil layer, and then crushed stone is filled into the hole. The crushed stone is vibrated and compacted section by section to form vibroflotated crushed stone piles, which form a composite foundation with the surrounding foundation soil, thereby achieving the foundation treatment purpose of improving the bearing capacity of the foundation, increasing the foundation stability, and improving the foundation's ability to resist earthquake liquefaction.
[0003] Conventional construction of ultra-deep vibratory piles of 75 to 100 meters usually uses a crane equipped with a guide rod of a certain length to connect the vibrator. In this method, a crane is used as the main body, equipped with a guide rod of a certain length, and connected to the vibrator. Due to the limitation of the lifting height of the crane, the guide rod is generally not too long. For example, a 70-meter guide rod requires a 320-ton crane, and there is no way to effectively prevent the vibrator from rotating, resulting in uncertain drilling direction, low precision, and poor quality.
[0004] In addition, a rotary drilling or pile frame 11 with a telescopic guide rod can be used to connect the vibrator; the telescopic guide rod is provided with multiple sections of telescopic rods, and each section of the telescopic rod needs to be processed with multiple sealing surfaces. Moreover, since the outer diameter of each section of the telescopic rod is larger than the outer diameter of the previous section of the telescopic rod, the outer diameter of the telescopic guide rod of the vibrator with the same power is larger. For example, a 225kW vibrator is equipped with a telescopic guide rod with a maximum outer diameter of 540mm, while a 260kW vibrator is equipped with an ordinary guide rod with a maximum outer diameter of only 377mm. In addition, the processing technology of the telescopic guide rod is complicated and the volume is large, resulting in higher costs.
[0005] In summary, how to provide a guide rod device with high rod connection efficiency and controllable vertical precision is a problem that needs to be urgently solved by those skilled in the art. Summary of the invention
[0006] In view of this, the purpose of the present invention is to provide a guide rod device, which first lowers the first guide rod and then moves the second guide rod to dock with the first guide rod, thereby meeting the requirements of ultra-deep vibration and effectively improving the rod connection efficiency and the vertical accuracy during the guide rod lowering process.
[0007] Another object of the present invention is to provide a pile frame including the above-mentioned guide rod device and a vibro-impact connecting rod method applied to the above-mentioned pile frame.
[0008] In order to achieve the above object, the present invention provides the following technical solutions:
[0009] A guide rod device, comprising:
[0010] The first guide rod is a hollow structure, and is axially provided with a first axial hole for passing the cable; a water pipe adapter and an air pipe adapter are provided at one axial end of the first guide rod, and the other axial end of the first guide rod is used to install a vibrator; a card slot and a first positioning connector are provided on the outer peripheral side surface of the first guide rod near the end where the water pipe adapter and the air pipe adapter are installed;
[0011] The second guide rod is a hollow structure, and is axially provided with a second axial hole for passing the cable; one axial end of the second guide rod is provided at the water pipe joint and the air pipe joint, and the other axial end of the second guide rod is provided with a second positioning connector for cooperating with the first positioning connector;
[0012] When the first positioning connector is connected with the second positioning connector, the pipeline where the water pipe adapter is located is connected with the pipeline where the water pipe joint is located; the gas path where the air pipe adapter is located is connected with the gas path where the air pipe joint is located.
[0013] Optionally, the cross-section of the first guide rod and the cross-section of the second guide rod are both open ring structures, and the cable enters the first guide rod and the second guide rod through the openings.
[0014] Optionally, a top guide device is provided at one end of the second guide rod close to the water pipe joint and the air pipe joint, and a guide wheel for guiding the cable is provided in the top guide device.
[0015] A pile frame, comprising any one of the guide rod devices described above, the pile frame comprising:
[0016] The equipment body is provided with a column;
[0017] A goose head, mounted on the top of the column;
[0018] A top retainer, one end of the second guide rod on which the water pipe joint and the air pipe joint are installed is connected to the top retainer; the goose head is connected to the top retainer and drives the end of the second guide rod connected to the top retainer to move;
[0019] An upper retainer is arranged along the column so as to be liftable, and the upper retainer is used to be clamped on one end of the first guide rod provided with a slot;
[0020] a first cable guide frame, mounted on the upper retainer, the first cable guide frame being used to wind the cable passing through the upper portion of the first guide rod; and the first cable guide frame being switchable to a first angular position or a second angular position;
[0021] a lower slide device, mounted on the column, the lower slide device being provided with a fixing portion connected to one end of the second guide rod on which the second positioning connector is mounted, and a moving assembly driving the fixing portion to move between a first position and a second position; when the fixing portion is located at the first position, the second guide rod is tilted, and when the fixing portion is located at the second position, the second guide rod is vertically arranged and located directly above the first guide rod;
[0022] a second cable guide frame, installed on the lower slide device, the second cable guide frame being used to wind the cable passing through the lower portion of the second guide rod; and the second cable guide frame being switchable to a third angle position or a fourth angle position;
[0023] A lower retainer is installed on the column, and the lower retainer is used to clamp one end of the first guide rod on which the vibrator is installed.
[0024] Optionally, the goose head comprises:
[0025] A mounting frame, mounted on the column;
[0026] A first pulley block is mounted on the mounting frame;
[0027] The first telescopic power member is installed on the mounting frame, and the telescopic end of the first telescopic power member is connected to the first pulley block to drive the first pulley block to move.
[0028] Optionally, the top retainer comprises:
[0029] A connecting portion connected to the column;
[0030] A fixed outer sleeve, fixedly arranged on the connecting portion;
[0031] The movable inner sleeve is provided with a first connecting pin shaft for connecting with the second guide rod; the movable inner sleeve is provided with a second pulley block, and the wire rope is wound around the first pulley block and the second pulley block, so as to drive the movable inner sleeve to move to the third position or the fourth position through the first telescopic power member;
[0032] When the movable inner sleeve is located at the third position, the second guide rod is arranged to avoid the first guide rod. When the movable inner sleeve is located at the fourth position, the second guide rod is located directly above the first guide rod.
[0033] Optionally, the upper retainer includes a first mounting body, the first mounting body includes an upper retaining fixture and an upper retaining movable member flipably disposed on the upper retaining fixture, and the upper retaining fixture is slidably disposed along the column;
[0034] The first mounting body is provided with a first through hole for allowing the first guide rod to pass through and a first latch mechanism arranged around the outer circumference of the first through hole. The first latch mechanism can be extended or retracted along the radial direction of the first through hole to clamp the first guide rod. The first through hole simultaneously passes through the upper retaining fixed part and the upper retaining movable part.
[0035] Optionally, the outer side wall of the first guide rod is provided with a groove, the inner side wall of the first through hole in the first installation body is provided with a key bar for being clamped in the groove of the first guide rod, and the key bar protrusion is provided on the inner side wall of the first through hole.
[0036] Optionally, the upper retainer also includes a third pulley group and a locking member for locking the upper retaining fixed member and the upper retaining movable member, and a wire rope connected to the winch is wound around the third pulley group to drive the upper retainer to rise and fall along the column.
[0037] Optionally, the first cable guide frame comprises:
[0038] a first guide frame, the first guide frame being mounted on the upper retainer through a fixing pin; the upper retainer being provided with a first mounting position and a second mounting position; when the first guide frame is fixedly mounted on the first mounting position of the upper retainer, the first cable guide frame is at a first angular position; when the first guide frame is fixedly mounted on the second mounting position of the upper retainer, the first cable guide frame is at a second angular position;
[0039] A first roller, mounted on the first guide frame, and the cable is wound around the first roller;
[0040] The first gear lever assembly is provided with a second telescopic power member and a first telescopic gear lever that is telescopically driven by the second telescopic power member. When the first telescopic gear lever is in an extended state, the first telescopic gear lever is located on the outside of the cable wound in the first roller to prevent the cable from falling off; when the first telescopic gear lever is in a retracted state, the first telescopic gear lever deviates from the cable wound in the first roller, and the cable can fall off the first roller.
[0041] Optionally, the glideslope device comprises:
[0042] A sliding pulley seat, mounted on the column, the moving assembly being mounted on the sliding pulley seat;
[0043] The slide is provided with the fixing part, and the slide is slidably arranged along the sliding pulley seat so that the fixing part moves to the first position or the second position.
[0044] Optionally, the second cable guide frame comprises:
[0045] a second guide frame, the second guide frame being mounted on the sliding pulley seat through a fixing pin; the sliding pulley seat being provided with a third mounting position and a fourth mounting position; when the second guide frame is fixedly mounted on the third mounting position of the sliding pulley seat, the second cable guide frame is at a third angular position; when the second guide frame is fixedly mounted on the fourth mounting position of the upper retainer, the first cable guide frame is at a fourth angular position;
[0046] a second roller, mounted on the second guide frame, and the cable is wound around the second roller;
[0047] The second lever assembly is provided with a third telescopic power member and a second telescopic lever that is telescopically driven by the third telescopic power member. When the second telescopic lever is in an extended state, the second telescopic lever is located outside the cable wound in the second roller to prevent the cable from falling off. When the second telescopic lever is in a retracted state, the second telescopic lever deviates from the cable wound in the second roller, and the cable can fall off from the second roller.
[0048] A deflection force member has one end connected to the sliding pulley seat and the other end connected to the second guide frame.
[0049] Optionally, the lower retainer comprises:
[0050] A second installation body, the second installation body comprising a lower retaining fixture and a lower retaining movable member flipably disposed on the lower retaining fixture, the lower retaining fixture being slidably disposed along the column;
[0051] The second mounting body is provided with a second through hole for the first guide rod to pass through and a second latch mechanism arranged around the outer circumference of the second through hole, the second latch mechanism can be extended or retracted along the radial direction of the second through hole to clamp the first guide rod, and the second through hole simultaneously passes through the lower retaining fixed part and the lower retaining movable part.
[0052] A vibro-shafting connecting rod method, applied to any of the pile frames described above, the vibro-shafting connecting rod method comprising:
[0053] The control cable passes through the first guide rod, the first cable guide frame, the second cable guide frame, and the second guide rod in sequence;
[0054] Control the water pipe adapter of the first guide rod to be connected to an external water pipe, and the air pipe adapter to be connected to an external air pipe;
[0055] Controlling the upper retainer to clamp the first guide rod;
[0056] Controlling the hoisting and releasing rope to lower the first guide rod until the first guide rod is lowered to a preset depth;
[0057] Controlling the fixing part in the lower slide device to move to the second position, and controlling the goose head to drive the part of the top retainer connected to the second guide rod to rise until the second guide rod is located directly above the first guide rod;
[0058] Controlling the second cable guide frame to swing to a fourth angle position, and controlling the first cable guide frame to swing to a second angle position to avoid the space directly above the first guide rod;
[0059] Controlling the disconnection between the water pipe adapter of the first guide rod and the external water pipe, and between the air pipe adapter and the external air pipe;
[0060] The goose head is controlled to drive the part of the top retainer connected to the second guide rod to descend, so that the first positioning connector is connected with the second positioning connector, so that the pipeline where the water pipe adapter is located is connected with the pipeline where the water pipe joint is located; the gas path where the gas pipe adapter is located is connected with the gas path where the gas pipe joint is located;
[0061] The hoisting and releasing rope is controlled to lower the second guide rod until the second guide rod is lowered to a preset depth.
[0062] In the process of using the guide rod device provided by the present invention, the cable needs to be passed through the first guide rod and the second guide rod in sequence, the water pipe adapter of the first guide rod is connected to the external water pipe, and the air pipe adapter is connected to the external air pipe; the upper retainer is controlled to clamp the first guide rod, and the winch is controlled to release the rope to make the first guide rod descend until the first guide rod descends to a preset depth, the fixed part in the slideway device is controlled to move to the second position, and the goose head is controlled to drive the part connected to the second guide rod in the top retainer to rise until the second guide rod is located directly above the first guide rod, and then, the water pipe adapter of the first guide rod is disconnected from the external water pipe, and the air pipe adapter is disconnected from the external air pipe; the first positioning connector is connected with the second positioning connector to realize the connection between the pipeline where the water pipe adapter is located and the pipeline where the water pipe connector is located; the air path where the air pipe adapter is located is connected to the air path where the air pipe connector is located. The winch is controlled to release the rope to make the second guide rod descend until the second guide rod descends to a preset depth.
[0063] Compared with the prior art, in the actual use of the guide rod device provided by the present invention, the first guide rod can be lowered first, and then the first guide rod and the second guide rod are connected, the first positioning connector and the second positioning connector are matched and connected, and the first guide rod and the second guide rod after being lowered and connected can meet the requirements of ultra-deep vibration and effectively ensure the verticality of the guide rod during the vibration process, in addition, the first guide rod and the second guide rod can be positioned and connected by the first positioning connector and the second positioning connector, which can effectively improve the connection efficiency.
[0064] In addition, the present invention also provides a pile frame including the guide rod device and a vibro-impact connecting rod method applied to the pile frame. BRIEF DESCRIPTION OF THE DRAWINGS
[0065] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the provided drawings without paying creative work.
[0066] Figure 1 A schematic structural diagram of a specific embodiment of a pile frame provided by the present invention;
[0067] Figure 2 It is a schematic diagram of the structure of a goose head;
[0068] Figure 3 is a schematic diagram of the structure of the top retainer;
[0069] Figure 4 is a top view schematic diagram of the top retainer;
[0070] Figure 5 is a structural schematic diagram of a first cable guide frame;
[0071] Figure 6 is a partial structural schematic diagram of a first cable guide frame;
[0072] Figure 7 is a front view schematic diagram of the upper retainer;
[0073] Figure 8 is a side view schematic diagram of the upper retainer;
[0074] Fig. 9 is a top view schematic diagram of the upper retainer;
[0075] Fig.10 is an axonometric structural diagram of the upper retainer;
[0076] Fig.11 is a schematic structural diagram of a first guide rod;
[0077] Fig.12 is a schematic structural diagram of the second guide rod;
[0078] Fig.13 is a schematic diagram of the structure of the glide path device;
[0079] Fig.14 It is a structural schematic diagram of the glide path device from another angle;
[0080] Fig.15This is the formal schematic diagram of the lower retainer;
[0081] Fig.16 is a top view schematic diagram of the lower retainer;
[0082] Fig.17 It is a structural schematic diagram of the initial installation state of the first guide rod and the second guide rod;
[0083] Fig.18 for Fig.17 A schematic diagram of the structure of the middle pile frame from another angle;
[0084] Fig.19 It is a structural schematic diagram showing that the first guide rod is lowered to a suitable position;
[0085] Fig. 20 for Fig.19 A partial enlarged schematic diagram of a part of the structure of the middle pile frame;
[0086] Fig.21 It is a structural schematic diagram showing that the second guide rod moves to be directly above the first guide rod;
[0087] Fig. 22 for Fig.21 A schematic diagram of the structure of the middle pile frame from another angle;
[0088] Fig.23 A schematic diagram of the structure of the second guide rod and the first guide rod being plugged and connected;
[0089] Fig.24 for Fig.23 A schematic diagram of the structure of the middle pile frame from another angle;
[0090] Fig.25 A schematic diagram of the overall structure of a pile frame in which the second guide rod is plugged into the first guide rod;
[0091] Fig.26 for Fig.25 A schematic diagram of the structure of the middle pile frame from another angle;
[0092] Fig. 27 It is a schematic diagram of the overall falling process composed of the second guide rod and the first guide rod;
[0093] Fig.28 It is a schematic diagram of the structure in which the second guide rod and the first guide rod are integrally dropped to a suitable position;
[0094] Fig.29 for Fig. 27 The overall structural diagram of the pile frame corresponding to the middle structure;
[0095] Fig.30 for Fig.28 The overall structural diagram of the pile frame corresponding to the middle structure;
[0096] Fig.31 It is a schematic diagram of the docking process between the second guide rod and the first guide rod;
[0097] Fig.32 is a schematic diagram showing that the cross section of the second guide rod is a closed ring;
[0098] Fig.33 is a schematic diagram of a cross section of the second guide rod being an open ring structure;
[0099] Fig.34 for Fig.33 A schematic diagram of the docking process between the second guide rod and the first guide rod shown in;
[0100] Fig.35 It is a structural schematic diagram of the lower slide device being installed on the column and the second cable guide frame being at a fourth angle position;
[0101] Fig.36 It is a structural schematic diagram of the lower slide device being installed on the column and the second cable guide frame being at a third angle position;
[0102] Fig.37 A schematic structural diagram of the glide path device and the second cable guide frame from another angle;
[0103] Fig.38 The present invention is a schematic flow chart of a specific embodiment of the vibro-impact connecting rod method provided by the present invention.
[0104] Figure 1-Figure 38 middle:
[0105] 1-goose head;
[0106] 1.1-first pulley block, 1.2-first telescopic power member, 1.3-mounting frame;
[0107] 2 - Top retainer;
[0108] 2.1-movable inner sleeve, 2.2-first connecting pin, 2.3-fixed outer sleeve, 2.4-connecting part;
[0109] 3- first cable guide frame;
[0110] 3.1-first gear lever cylinder, 3.2-first roller, 3.3-rotating pin, 3.4 fixed pin, 3.5 first guide frame;
[0111] 4- Upper retainer;
[0112] 4.1-upper retaining movable part, 4.2-first latch mechanism, 4.3-first key bar, 4.4-third pulley block, 4.5-third connecting pin shaft, 4.6-first claw, 4.7-fastener, 4.8-card, 4.9-upper retaining fixed part;
[0113] 5- first guide rod;
[0114] 5.1-water pipe adapter, 5.2-first slot, 5.3-head end guide rod section, 5.4-second slot, 5.5-first standard guide rod section, 5.6-air pipe adapter, 5.7-water pipe quick-change connector, 5.8-air pipe quick-change connector;
[0115] 6- second guide rod;
[0116] 6.1-top connection device, 6.2-water pipe joint, 6.3-top guide device, 6.4-second standard guide rod section, 6.5-guide rod section body, 6.6-air pipe joint;
[0117] 7- Glide path device;
[0118] 7.1-connecting seat, 7.2-sliding pulley seat, 7.3-fixed rod, 7.4-second cable guide frame, 7.5-telescopic cylinder, 7.6-sway cylinder, 7.7-slideway, 7.8-wire rope, 7.9-lower slideway pulley, 7.10-slideway;
[0119] 8-lower retainer;
[0120] 8.1-lower retaining movable part, 8.2-second latch mechanism, 8.3-second key bar, 8.4-lower retaining fixed part, 8.5-second claw, 8.6-second connecting pin shaft;
[0121] 9- vibrator;
[0122] 10- Cable reel;
[0123] 11- Pile frame;
[0124] 12- Cable;
[0125] 13- Pillar. DETAILED DESCRIPTION
[0126] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0127] The core of the present invention is to provide a guide rod device, which can meet the requirements of ultra-deep vibro-punching by first lowering the first guide rod and then moving the second guide rod to dock with the first guide rod, effectively improving the rod connection efficiency and the vertical accuracy during the guide rod lowering process.
[0128] Another core of the present invention is to provide a pile frame including the above-mentioned guide rod device and a vibro-impact connecting rod method applied to the above-mentioned pile frame.
[0129] The present specific embodiment discloses a guide rod device, which includes a first guide rod 5 and a second guide rod 6, wherein the first guide rod 5 is a hollow structure, and the first guide rod 5 is axially provided with a first axial hole for allowing a cable 12 to pass through; a water pipe adapter 5.1 and an air pipe adapter 5.6 are provided at one axial end of the first guide rod 5, and the other axial end of the first guide rod 5 is used to install a vibrator 9; a card slot and a first axial hole are provided on the outer peripheral side surface of the first guide rod 5 near the end where the water pipe adapter 5.1 and the air pipe adapter 5.6 are installed A positioning connector; the second guide rod 6 is a hollow structure, and the second guide rod 6 is axially provided with a second axial hole for passing the cable 12; one axial end of the second guide rod 6 is provided at the water pipe joint 6.2 and the air pipe joint 6.6, and the other axial end of the second guide rod 6 is provided with a second positioning connector for cooperating with the first positioning connector; when the first positioning connector is connected with the second positioning connector, the pipeline where the water pipe adapter 5.1 is located is connected with the pipeline where the water pipe joint 6.2 is located; the air path where the air pipe adapter 5.6 is located is connected with the air path where the air pipe joint 6.6 is located.
[0130] like Fig.11 As shown, the first guide rod 5 includes a head end guide rod section 5.3 and a first standard guide rod section 5.5, the head end guide rod section 5.3 is provided with a first card slot 5.2, a second card slot 5.4, an air pipe quick-change joint 5.8 and a water pipe quick-change joint 5.7, the water pipe quick-change joint 5.7 can be connected to the water pipe adapter 5.1, and the air pipe quick-change joint 5.8 can be connected to the air pipe adapter 5.6; in actual use, when it is necessary to connect an external pipeline, the water pipe quick-change joint 5.7 can be connected to the water pipe adapter 5.1, and the air pipe quick-change joint 5.8 can be connected to the air pipe adapter 5.6; when it is necessary to position and cooperate the first guide rod 5 and the second guide rod 6, the air pipe adapter 5.6 and the water pipe adapter 5.1 can be removed.
[0131] like Fig.12 As shown, the second guide rod 6 includes a top connecting device 6.1, a water pipe joint 6.2, a top guiding device 6.3, a second standard guide rod section 6.4, a guide rod section body 6.5, and an air pipe joint 6.6. The top connecting device 6.1 is connected to the top retainer 2 through a pin shaft, the water pipe joint 6.2 can be connected to an external water pipe, and the air pipe joint 6.6 can be connected to an external air pipe. The top guiding device 6.3 is internally equipped with rollers similar to those of the first cable guide frame 3 to constrain the path of the cable 12.
[0132] When using the guide rod device provided in this specific embodiment, it is first necessary to pass the cable 12 through the first guide rod 5 and the first guide rod 5 in sequence. The water pipe adapter 5.1 of the first guide rod 5 is connected to the external water pipe, and the air pipe adapter 5.6 is connected to the external air pipe; the upper retainer 4 is controlled to clamp the first guide rod 5, and the winch is controlled to release the rope to make the first guide rod 5 descend until the first guide rod 5 descends to a preset depth, the fixed part in the lower slide device 7 is controlled to move to the second position, and the goose head 1 is controlled to drive the part of the top retainer 2 connected to the second guide rod 6 to rise until the second guide rod 6 is directly above the first guide rod 5, and then, the water pipe adapter 5.1 of the first guide rod 5 is disconnected from the external water pipe, and the air pipe adapter 5.6 is disconnected from the external air pipe; the first positioning connector is connected with the second positioning connector to realize that the pipeline where the water pipe adapter 5.1 is located is connected to the pipeline where the water pipe joint 6.2 is located; the air path where the air pipe adapter 5.6 is located is connected to the air path where the air pipe joint 6.6 is located. The hoisting and releasing rope is controlled to lower the second guide rod 6 until the second guide rod 6 is lowered to a preset depth.
[0133] Compared with the prior art, in the actual use of the guide rod device provided in this specific embodiment, the first guide rod 5 can be lowered first, and then the first guide rod 5 and the second guide rod 6 can be connected, the first positioning connector and the second positioning connector can be connected in cooperation, and the first guide rod 5 and the second guide rod 6 after being lowered and connected can meet the requirements of ultra-deep vibration and effectively ensure the verticality of the guide rod during the vibration. In addition, the first guide rod 5 and the second guide rod 6 can be positioned and connected by the first positioning connector and the second positioning connector, which can effectively improve the connection efficiency.
[0134] Based on the above embodiments, Fig.32 As shown, the cross-section of the first guide rod 5 and the second guide rod 6 can be set to a closed ring. In actual use, Fig.31 As shown, the cable 12 passes through the first guide rod 5 or one end of the first guide rod 5 and passes through the other end.
[0135] Of course, the first guide rod 5 and the second guide rod 6 can also be set to have an open ring structure. Fig.34 As shown, the cable 12 can directly enter the first guide rod 5 or the second guide rod 6 from the first guide rod 5 or one side of the first guide rod 5 .
[0136] Of course, the first guide rod 5 and the second guide rod 6 may also be other structural forms that meet the requirements, which are determined according to actual conditions and will not be elaborated here.
[0137] In addition to the guide rod device mentioned above, the present invention also discloses a pile frame including the guide rod device, the pile frame including an equipment body, a goose head 1, a top retainer 2, an upper retainer 4, a first cable guide frame 3, a lower slide device 7, a second cable guide frame 7.4, a lower retainer 8 and a pile frame 11, wherein the equipment body is provided with a column 13; the goose head 1 is installed on the top of the column 13; the second guide rod 6 is provided with a water pipe joint 6.2 and one end of the air pipe joint 6.6 connected to the top retainer 2; the goose head 1 is connected to the top retainer 2, and drives the second guide rod 6 to move at one end connected to the top retainer 2; the upper retainer 4 can be raised and lowered along the column 13, and the upper retainer 4 is used to be clamped at one end of the first guide rod 5 provided with a slot; the first cable guide frame 3 is installed on the upper retainer 4, and the first cable guide frame 3 is used to surround the cable passing through the upper part of the first guide rod 5 Cable 12; and the first cable guide frame 3 can be switched to a first angular position or a second angular position; the lower slide device 7 is installed on the column 13, and the lower slide device 7 is provided with a fixing portion for connecting to one end of the second guide rod 6 on which the second positioning connector is installed, and a moving component for driving the fixing portion to move between the first position and the second position; when the fixing portion is in the first position, the second guide rod 6 is tilted, and when the fixing portion is in the second position, the second guide rod 6 is vertically arranged and located directly above the first guide rod 5; the second cable guide frame 7.4 is installed on the lower slide device 7, and the second cable guide frame 7.4 is used to wind the cable 12 passing through the lower part of the second guide rod 6; and the second cable guide frame 7.4 can be switched to a third angular position or a fourth angular position; the lower retainer 8 is installed on the column 13, and the lower retainer 8 is used to clamp one end of the vibrator 9 installed in the first guide rod 5.
[0138] In actual use, it is first necessary to control the cable 12 to pass through the first guide rod 5, the first cable guide frame 3, the second cable guide frame 7.4, and the second guide rod 6 in sequence, and move the fixed part of the slideway device 7 to the first position, and the second guide rod 6 is tilted; the water pipe adapter 5.1 of the first guide rod 5 is connected to the external water pipe, and the air pipe adapter 5.6 is connected to the external air pipe; the upper retainer 4 is controlled to clamp the position where the card slot is provided in the first guide rod 5, and then, the winch is controlled to release the rope to make the first guide rod 5 descend until the first guide rod 5 descends to a preset depth; the winch in this specific embodiment is a winch conventionally set in the pile frame, and the wire rope 7.8 wound by the winch is simultaneously wound around the third pulley group 4.4 on the upper retainer 4. The operation of the winch to collect and release the rope can drive the upper retainer 4 to rise and fall along the column 13, thereby realizing the lifting and lowering of the first guide rod 5; when the first guide rod 5 descends to the preset depth, the slideway device is controlled The fixing part in 7 moves to the second position, and the goose head 1 is controlled to drive the part of the top retainer 2 connected with the second guide rod 6 to rise, until the second guide rod 6 switches from the inclined state to be located directly above the first guide rod 5; then the second cable guide frame 7.4 is swung to the fourth angle position, and the first cable guide frame 3 is controlled to be swung to the second angle position to avoid the space directly above the first guide rod 5; the connection between the water pipe adapter 5.1 of the first guide rod 5 and the external water pipe, and the connection between the air pipe adapter 5.6 and the external air pipe is disconnected; the goose head 1 is controlled to drive the part of the top retainer 2 connected with the second guide rod 6 to descend, so that the first positioning connector and the second positioning connector are matched and connected, so as to realize that the pipeline where the water pipe adapter 5.1 is located is connected to the pipeline where the water pipe joint 6.2 is located; the air path where the air pipe adapter 5.6 is located is connected to the air path where the air pipe joint 6.6 is located; the winch is controlled to release the rope to make the second guide rod 6 descend until the second guide rod 6 descends to a preset depth.
[0139] The pile frame provided in this specific embodiment can realize the connection between the first guide rod 5 and the second guide rod 6. Compared with directly lowering a longer guide rod in the prior art, the verticality of the guide rod can be effectively guaranteed. In addition, the first guide rod 5 and the second guide rod 6 can be positioned and connected by the first positioning connector and the second positioning connector, which can effectively improve the connection efficiency.
[0140] On the basis of the above embodiment, the goose head 1 can include a mounting frame 1.3, a first pulley block 1.1, and a first telescopic power member 1.2; the mounting frame 1.3 is installed on the column 13; the first pulley block 1.1 is installed on the mounting frame 1.3; the first telescopic power member 1.2 is installed on the mounting frame 1.3, and the telescopic end of the first telescopic power member 1.2 is connected to the first pulley block 1.1 to drive the first pulley block 1.1 to move.
[0141] like Figure 2As shown, H1 is the telescopic distance of the first telescopic power member 1.2. The first telescopic power member 1.2 can be set as a telescopic cylinder 7.5. The first telescopic power member 1.2 is connected to the first pulley block 1.1. The telescopic movement of the first telescopic power member 1.2 can drive the first pulley block 1.1 to move. The first pulley block 1.1 is connected to the pulley block on the movable inner sleeve 2.1 of the top retainer 2 through the wound wire rope 7.8. Therefore, the movement of the movable inner sleeve 2.1 in the top retainer 2 can be realized through the telescopic movement of the first telescopic power member 1.2.
[0142] In a specific embodiment, the top retainer 2 includes a connecting portion 2.4, a fixed outer sleeve 2.3, and a movable inner sleeve 2.1, and the connecting portion 2.4 is connected to the column 13; the fixed outer sleeve 2.3 is fixed to the connecting portion 2.4; the movable inner sleeve 2.1 is provided with a first connecting pin 2.2 for connecting to the second guide rod 6; the movable inner sleeve 2.1 is provided with a second pulley group, and the wire rope 7.8 is wound around the first pulley group 1.1 and the second pulley group to drive the movable inner sleeve 2.1 to move to the third position or the fourth position through the first telescopic power member 1.2.
[0143] like Figure 3 As shown, H2 is the distance between the third position and the fourth position. When the movable inner sleeve 2.1 is located at the third position, the second guide rod 6 is set away from the first guide rod 6. When the movable inner sleeve 2.1 is located at the fourth position, the second guide rod 6 is located directly above the first guide rod 5.
[0144] In a specific embodiment, the upper retainer 4 includes a first mounting body, which includes an upper retaining fixed member 4.9 and an upper retaining movable member 4.1 which is flippably arranged on the upper retaining fixed member 4.9, and the upper retaining fixed member 4.9 is slidably arranged along the column 13; the first mounting body is provided with a first through hole for allowing the first guide rod 5 to pass through and a first latch mechanism 4.2 arranged around the outer periphery of the first through hole, and the first latch mechanism 4.2 can be extended or retracted along the radial direction of the first through hole to clamp the first guide rod 5, and the first through hole simultaneously passes through the upper retaining fixed member 4.9 and the upper retaining movable member 4.1.
[0145] The radial movement of the first latch mechanism 4.2 can be controlled by an oil cylinder or other power structures that meet the requirements. The specific movement is determined according to actual conditions and will not be elaborated here.
[0146] The upper retainer 4 also includes a third pulley block 4.4 and a locking member for locking the upper retaining fixed member 4.9 and the upper retaining movable member 4.1. The wire rope 7.8 connected to the winch is wound around the third pulley block 4.4 to drive the upper retainer 4 to rise and fall along the column 13.
[0147] In actual use, when the first guide rod 5 needs to be erected, the upper retaining movable member 4.1 can be rotated to an open position relative to the upper retaining fixed member 4.9, so that the first guide rod 5 in a horizontal state can extend into the first through hole, and then the upper retaining movable member 4.1 is rotated to a closed position relative to the upper retaining fixed member 4.9, and the wire rope 7.8 is wound around the third pulley group 4.4, and the upper retainer 4 is driven to rise along the column 13 through the wire rope 7.8. In the process of the upper retainer 4 rising along the column 13, the upper retainer 4 drives the first guide rod 5 to stand up.
[0148] like Figure 8 As shown, the upper retaining movable part 4.1 is rotatably connected to the upper retaining fixed part 4.9 via a third connecting pin 4.5. When the upper retaining movable part 4.1 is rotated to a closed position relative to the upper retaining fixed part 4.9, the upper retaining movable part 4.1 and the upper retaining fixed part 4.9 can be locked and fixed by a fastener 4.7.
[0149] like Figure 7 As shown, the upper retaining fixture 4.9 is provided with a first claw 4.6, which is connected to the column 13 and can slide along the column 13.
[0150] A first raised key strip 4.3 may also be provided on the periphery of the first mounting hole to prevent the guide rod of the working chamber vibrator 9 from rotating. Figure 7 As shown, the upper retainer 4 further includes a clamping plate 4.8, which is used to be clamped on the outer periphery of the first guide rod 5 to limit the first guide rod 5 in radial direction.
[0151] On the basis of the above embodiment, the first cable guide frame 3 can include a first guide frame 3.5, a first roller 3.2, and a first gear assembly, wherein the first guide frame 3.5 is installed on the upper retainer 4 through a fixed pin shaft 3.4, and the first guide frame 3.5 is rotatable around the fixed pin shaft 3.4; the upper retainer 4 is provided with a first mounting position and a second mounting position; when the first guide frame 3.5 is fixedly arranged at the first mounting position of the upper retainer 4, the first cable guide frame 3 is in a first angular position; when the first guide frame 3.5 is fixedly arranged at the second mounting position of the upper retainer 4, the first cable guide frame 3 is in a second angular position; the first roller 3.2 is installed on the first guide frame 3.5, and the cable 12 is wound around the first roller 3.2; the first gear assembly is provided with a second telescopic power member and a first telescopic gear rod that is telescopically driven by the second telescopic power member, and when the first telescopic gear rod is in an extended state, the first telescopic gear rod is located on the outside of the cable 12 wound around the first roller 3.2, such as Figure 6 When the first telescopic lever is in the retracted state, the first telescopic lever deviates from the cable 12 wound in the first roller 3.2, and the cable 12 can fall off from the first roller 3.2.
[0152] like Figure 5 As shown, the upper retainer 4 is provided with an arc-shaped slide groove. When the rotating pin 3.3 is fixed to the Figure 5 In the first installation position shown, the first guide frame 3.5 is fixed to a first angular position relative to the upper retainer 4. At this time, the first guide frame 3.5 is located directly above the first guide rod 5. Fig. 22 As shown, the rotating pin 3.3 is fixed at the second installation position, and the first guide frame 3.5 is fixed to the second angular position relative to the upper retainer 4. At this time, the first guide frame 3.5 is arranged to avoid being directly above the first guide rod 5.
[0153] In a specific embodiment, the lower slide device 7 includes a sliding pulley seat 7.2 and a slide 7.10. The sliding pulley seat 7.2 is installed on the column 13, and the sliding pulley seat 7.2 is installed with a moving component; the slide 7.10 is provided with a fixed part, and the slide 7.10 can be slidably arranged along the sliding pulley seat 7.2 to move the fixed part to the first position or the second position.
[0154] like Fig.14 As shown, H3 is the sliding distance of the slide 7.10 along the slideway 7.7 relative to the sliding pulley seat 7.2. The lower slide device 7 includes a connecting seat 7.1, a sliding pulley seat 7.2, a fixing rod 7.3, a second cable guide frame 7.4, a telescopic cylinder 7.5, a tilting cylinder 7.6, a slideway 7.7, a wire rope 7.8, a lower slide pulley 7.9 and a slide 7.10. Figure 35 to Figure 37 As shown, the sliding pulley seat 7.2 is installed to the column 13 through the connecting seat 7.1, and the sliding pulley seat 7.2 is supported by the fixing rod 7.3, so that the extending direction of the sliding pulley seat 7.2 is perpendicular to the extending direction of the column 13, the second cable guide frame 7.4 is installed on the slide 7.10, and the slide 7.10 moves relative to the sliding pulley seat 7.2; the telescopic cylinder 7.5 is used to drive the slide 7.10 to move along the slideway 7.7 relative to the sliding pulley seat 7.2; the yaw cylinder 7.6 controls the second cable guide frame 7.4 to swing to different angular positions relative to the slide 7.10; one end of the wire rope 7.8 is connected to the slide 7.10, and the other end is wound around the lower slideway pulley 7.9.
[0155] The second cable guide frame 7.4 comprises a second guide frame, a second roller, a second gear lever assembly and a deflection force member. The second guide frame is mounted on the sliding pulley seat 7.2 through a fixed pin shaft 3.4; the sliding pulley seat 7.2 is provided with a third mounting position and a fourth mounting position; when the second guide frame is fixedly mounted on the third mounting position of the sliding pulley seat 7.2, the second cable guide frame 7.4 is at a third angular position; when the second guide frame is fixedly mounted on the fourth mounting position of the upper retainer 4, the first cable guide frame 3 is at a fourth angular position; the second roller is mounted on the second guide frame, The cable 12 is wound around the second roller; the second gear lever assembly is provided with a third telescopic power member and a second telescopic gear lever that is telescopically driven by the third telescopic power member. When the second telescopic gear lever is in an extended state, the second telescopic gear lever is located on the outside of the cable 12 wound around the second roller to prevent the cable 12 from falling off; when the second telescopic gear lever is in a retracted state, the second telescopic gear lever deviates from the cable 12 wound around the second roller, and the cable 12 can fall off the second roller; one end of the deflecting power member is connected to the sliding pulley seat 7.2, and the other end is connected to the second guide frame.
[0156] In actual use, the yaw force member is the yaw cylinder 7.6, such as Fig.35 As shown, by extending the yaw cylinder 7.6, the second cable guide frame 7.4 can be controlled to swing to a fourth angle position, at which time the second cable guide frame 7.4 avoids the position axially opposite to the second guide rod 6; Fig.36 As shown, by extending the sway cylinder 7.6, the second cable guide frame 7.4 can be controlled to swing to a third angle position. At this time, the second cable guide frame 7.4 is located at a position axially opposite to the second guide rod 6.
[0157] On the basis of the above embodiment, the lower retainer 8 can include a second mounting body; the second mounting body includes a lower retaining fixture 8.4 and a lower retaining movable member 8.1 which is flippably arranged on the lower retaining fixture 8.4, and the lower retaining fixture 8.4 is slidably arranged along the column 13; the second mounting body is provided with a second through hole for the first guide rod 5 to pass through and a second latch mechanism 8.2 arranged around the outer periphery of the second through hole, and the second latch mechanism 8.2 can be extended or retracted along the radial direction of the second through hole to clamp the first guide rod 5, and the second through hole simultaneously passes through the lower retaining fixture 8.4 and the lower retaining movable member 8.1.
[0158] like Fig.15 , Fig.16As shown, the lower retainer 8 includes a lower retaining movable part 8.1, a second latch mechanism 8.2, a second key bar 8.3, a lower retaining fixed part 8.4, a second claw 8.5, and a second connecting pin shaft 8.6; the second claw 8.5 is installed on the column 13, and the lower retaining movable part 8.1 is rotatably installed on the lower retaining fixed part 8.4 through the second connecting pin shaft 8.6; the lower retainer 8 adopts an opening and closing design to facilitate the installation of the first guide rod 5, and is designed with three raised second key bars 8.3 inside, and the second key bar 8.3 is used to prevent the vibrator 9 guide rod from rotating. Three groups of second latch mechanisms 8.2 are installed on the top, which are controlled by a cylinder to drive the latch to retract and retract, thereby clamping the second guide rod 6 for fixing.
[0159] In addition to the above pile frame, the present invention also discloses a vibro-shafting connecting rod method applied to the above pile frame, the vibro-shafting connecting rod method comprising:
[0160] Step S1, the control cable 12 passes through the first guide rod 5, the first cable guide frame 3, the second cable guide frame 7.4, and the second guide rod 6 in sequence;
[0161] In the above step S1, if Fig.17 , Fig.18 As shown, the cable 12 passes through the first guide rod 5, the first cable guide frame 3, the second cable guide frame 7.4, and the second guide rod 6 in sequence.
[0162] Step S2, controlling the water pipe adapter 5.1 of the first guide rod 5 to connect to an external water pipe, and the air pipe adapter 5.6 to connect to an external air pipe;
[0163] Step S3, controlling the upper retainer 4 to clamp the first guide rod 5;
[0164] In step S3, the latch of the first latch mechanism 4.2 of the upper retainer 4 is controlled to clamp the first slot 5.2 of the first guide rod 5; of course, depending on the actual clamping position, in some cases, the latch of the first latch mechanism 4.2 can also be clamped in the position of the second slot 5.4, which is determined according to actual conditions.
[0165] When the first guide rod 5 and the second guide rod 6 are installed, the first guide rod 5 is in a vertical state, and the second guide rod 6 is in an inclined state.
[0166] Step S4, controlling the hoisting and releasing rope to lower the first guide rod 5 until the first guide rod 5 drops to a preset depth;
[0167] In step S4, the first guide rod 5 is lowered by the winch wire rope 7.8. When the upper retainer 4 approaches the lower slide device 7, the first gear rod cylinder 3.1 is controlled to retract, so that the cable 12 is separated from the first guide frame 3.5. The second gear rod cylinder is controlled to retract, so that the cable 12 is separated from the second guide frame, and the first guide rod 5 is continued to be lowered, so that the upper retainer 4 stops when it approaches the lower retainer 8, and the Fig.19 , Fig. 20 During this process, the cable reel 10 moves with the movement to keep the cable 12 with a certain pre-tightening force at all times.
[0168] Step S5, controlling the fixing part in the lower slide device 7 to move to the second position, controlling the goose head 1 to drive the part of the top retainer 2 connected to the second guide rod 6 to rise, until the second guide rod 6 is located directly above the first guide rod 5;
[0169] In step S5, Fig.21 As shown, the telescopic oil cylinder 7.5 of the lower slide device 7 is driven to retract, driving the sliding pulley seat 7.2, and the slide 7.10 is moved leftward along the slide 7.7 through the action of the wire rope 7.8, thereby moving the lower end of the second guide rod 6 to just above the first guide rod 5.
[0170] Step S6, controlling the second cable guide frame 7.4 to swing to a fourth angle position, and controlling the first cable guide frame 3 to swing to a second angle position, avoiding the space directly above the first guide rod 5;
[0171] In step S6, Fig. 22 As shown, the yaw cylinder 7.6 on the lower slide device 7 extends to drive the second cable guide frame 7.4 to the fourth angle position, and the first guide frame 3.5 of the upper retainer 4 is removed from the fixing pin 3.4 and swung clockwise by gravity to the fourth angle position. Fig. 22 The position shown makes room for the connection between the first guide rod 5 and the second guide rod 6. In the process, the cable reel 10 moves with the cable 12 to keep a certain preload at all times.
[0172] Step S7, controlling to disconnect the water pipe adapter 5.1 of the first guide rod 5 from the external water pipe, and the air pipe adapter 5.6 from the external air pipe;
[0173] In step S7, the external water pipe and air pipe of the first guide rod 5 are removed, and the water and air pipe conversion joints are removed, exposing the water pipe quick-change joint 5.7 and the air pipe quick-change joint 5.8, in preparation for connection with the water pipe joint 6.2 and the air pipe joint 6.6 in the hexagonal female joint at the lower end of the second guide rod 6.
[0174] Step S8, control the goose head 1 to drive the part of the top retainer 2 connected to the second guide rod 6 to descend, so that the first positioning connector and the second positioning connector are connected in coordination, so that the pipeline where the water pipe adapter 5.1 is located is connected to the pipeline where the water pipe connector 6.2 is located; the gas path where the air pipe adapter 5.6 is located is connected to the gas path where the air pipe connector 6.6 is located;
[0175] In step S8, the first pulley block 1.1 on the goose head 1 is pushed out through the telescopic oil cylinder 7.5, and then the movable inner sleeve 2.1 of the top retainer 2 is extended through the steel wire rope 7.8 between the pulleys of the top retainer 2, so that the second guide rod 6 is in a vertical state, and then the second guide rod 6 is lowered through the top retainer 2, and the hexagonal male connector of the first guide rod 5 is connected with the hexagonal female connector of the second guide rod 6, and fixed by manual pins. The first guide rod 5 and the second guide rod 6 are connected as a whole, and the first guide rod 5 and the second guide rod 6 are connected as a whole, so as to achieve the following Figure 23 to Figure 26 In this process, the cable drum 10 moves with the cable 12 to keep the cable 12 with a certain preload at all times.
[0176] Step S9, controlling the hoisting and releasing rope to lower the second guide rod 6 until the second guide rod 6 is lowered to a preset depth.
[0177] In step S9, the water and air pipes of the second guide rod 6 are connected to the backstage, and the latch device of the upper retainer 4 is retracted so that it is disengaged from the slot of the first guide rod 5, and then the first guide rod 5 and the second guide rod 6 continue to fall through the bottom retainer, so as to achieve the following Figures 27 to 30 In this process, the cable drum 10 moves with the cable 12 to keep the cable 12 with a certain preload at all times.
[0178] In this specification, each embodiment is described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the embodiments can be referred to each other. Any combination of all embodiments provided by the present invention is within the protection scope of this invention and will not be described in detail here.
[0179] The guide rod device, pile frame and vibro-impact connecting rod method provided by the present invention are introduced in detail above. Specific examples are used in this article to illustrate the principle and implementation mode of the present invention. The description of the above embodiments is only used to help understand the method and core idea of the present invention. It should be pointed out that for ordinary technicians in this technical field, without departing from the principle of the present invention, several improvements and modifications can be made to the present invention, and these improvements and modifications also fall within the scope of protection of the claims of the present invention.
Claims
1. A guide rod device, characterized in that: include: The first guide rod (5) is a hollow structure, and is axially provided with a first axial hole for allowing the cable (12) to pass through; a water pipe adapter (5.1) and an air pipe adapter (5.6) are provided at one axial end of the first guide rod (5), and the other axial end of the first guide rod (5) is used for mounting a vibrator (9); a slot and a first positioning connector are provided on the outer peripheral side surface of the first guide rod (5) near the end where the water pipe adapter (5.1) and the air pipe adapter (5.6) are mounted; The second guide rod (6) is a hollow structure, and is axially provided with a second axial hole for allowing the cable (12) to pass through; one axial end of the second guide rod (6) is provided at the water pipe joint (6.2) and the air pipe joint (6.6), and the other axial end of the second guide rod (6) is provided with a second positioning connector for cooperating with the first positioning connector; When the first positioning connector and the second positioning connector are connected in cooperation, the pipeline where the water pipe adapter (5.1) is located is connected to the pipeline where the water pipe joint (6.2) is located; and the gas path where the air pipe adapter (5.6) is located is connected to the gas path where the air pipe joint (6.6) is located.
2. The guide rod device according to claim 1, characterized in that: The cross-section of the first guide rod (5) and the cross-section of the second guide rod (6) are both open ring structures, and the cable (12) enters the first guide rod (5) and the second guide rod (6) through the openings.
3. The guide rod device according to claim 1, characterized in that: A top guide device (6.3) is provided at one end of the second guide rod (6) close to the water pipe joint (6.2) and the air pipe joint (6.6), and a guide wheel for guiding the cable (12) is provided inside the top guide device (6.3).
4. A pile frame, characterized in that: The pile frame comprises the guide rod device according to any one of claims 1 to 3, wherein the pile frame comprises: The main body of the device is provided with a column (13); A goose head (1), mounted on the top of the column (13); A top retainer (2), one end of the second guide rod (6) having a water pipe joint (6.2) and an air pipe joint (6.6) installed therein is connected to the top retainer (2); the goose head (1) is connected to the top retainer (2) and drives the end of the second guide rod (6) connected to the top retainer (2) to move; An upper retainer (4) is arranged along the upright column (13) so as to be liftable, and the upper retainer (4) is used to be clamped on an end of the first guide rod (5) provided with a slot; a first cable guide frame (3) mounted on the upper retainer (4), the first cable guide frame (3) being used to wind the cable (12) passing through the upper part of the first guide rod (5); and the first cable guide frame (3) can be switched to a first angular position or a second angular position; a lower slide device (7) mounted on the column (13), the lower slide device (7) being provided with a fixing portion connected to one end of the second guide rod (6) on which the second positioning connector is mounted, and a moving assembly driving the fixing portion to move between a first position and a second position; when the fixing portion is located at the first position, the second guide rod (6) is arranged obliquely, and when the fixing portion is located at the second position, the second guide rod (6) is arranged vertically and is located directly above the first guide rod (5); a second cable guide frame (7.4) installed on the lower slide device (7), the second cable guide frame (7.4) being used to wind the cable (12) passing through the lower part of the second guide rod (6); and the second cable guide frame (7.4) can be switched to a third angle position or a fourth angle position; A lower retainer (8) is mounted on the column (13), and the lower retainer (8) is used to clamp one end of the vibrator (9) mounted in the first guide rod (5).
5. The pile frame according to claim 4, characterized in that: The goose head 1 comprises: A mounting frame (1.3) mounted on the column (13); A first pulley block (1.1) mounted on the mounting frame (1.3); A first telescopic power member (1.2) is mounted on the mounting frame (1.3), and a telescopic end of the first telescopic power member (1.2) is connected to the first pulley block (1.1) to drive the first pulley block (1.1) to move.
6. The pile frame according to claim 5, characterized in that: The top retainer (2) comprises: A connecting portion (2.4) connected to the column (13); A fixed outer sleeve (2.3) fixedly arranged on the connecting portion (2.4); The movable inner sleeve (2.1) is provided with a first connecting pin (2.2) for connecting to the second guide rod (6); the movable inner sleeve (2.1) is provided with a second pulley block, and a steel wire rope (7.8) is wound around the first pulley block (1.1) and the second pulley block, so as to drive the movable inner sleeve (2.1) to move to a third position or a fourth position through the first telescopic power member (1.2); When the movable inner sleeve (2.1) is located at the third position, the second guide rod (6) is arranged away from the second guide rod (6); when the movable inner sleeve (2.1) is located at the fourth position, the second guide rod (6) is located directly above the first guide rod (5).
7. The pile frame according to claim 4, characterized in that: The upper retainer (4) comprises a first mounting body, the first mounting body comprising an upper retaining fixture (4.9) and an upper retaining movable member (4.1) which is flippably arranged on the upper retaining fixture (4.9), the upper retaining fixture (4.9) being slidably arranged along the column (13); The first mounting body is provided with a first through hole for allowing a first guide rod (5) to pass through, and a first latch mechanism (4.2) arranged around the outer periphery of the first through hole, the first latch mechanism (4.2) being able to extend or retract along the radial direction of the first through hole to clamp the first guide rod (5), and the first through hole simultaneously passes through the upper retaining fixed member (4.9) and the upper retaining movable member (4.1).
8. The pile frame according to claim 7, characterized in that: The outer side wall of the first guide rod (5) is provided with a groove, the inner side wall of the first through hole in the first installation body is provided with a key bar for being clamped in the groove of the first guide rod (5), and the key bar protrusion is provided on the inner side wall of the first through hole.
9. The pile frame according to claim 7, characterized in that: The upper retainer (4) further comprises a third pulley block (4.4) and a locking member for locking the upper retaining fixed member (4.9) and the upper retaining movable member (4.1); a steel wire rope (7.8) connected to the winch is wound around the third pulley block (4.4) to drive the upper retainer (4) to rise and fall along the column (13).
10. The pile frame according to claim 4, characterized in that: The first cable guide frame (3) comprises: a first guide frame (3.5), the first guide frame (3.5) being mounted on the upper retainer (4) via a fixing pin shaft (3.4); the upper retainer (4) being provided with a first mounting position and a second mounting position; when the first guide frame (3.5) is fixedly mounted on the first mounting position of the upper retainer (4), the first cable guide frame (3) is in a first angular position; when the first guide frame (3.5) is fixedly mounted on the second mounting position of the upper retainer (4), the first cable guide frame (3) is in a second angular position; A first roller (3.2) is mounted on the first guide frame (3.5), and a cable (12) is wound around the first roller (3.2); A first lever assembly is provided with a second telescopic power member and a first telescopic lever that is telescopically driven by the second telescopic power member; when the first telescopic lever is in an extended state, the first telescopic lever is located outside a cable (12) wound in the first roller (3.2) to prevent the cable (12) from falling off; when the first telescopic lever is in a retracted state, the first telescopic lever deviates from the cable (12) wound in the first roller (3.2), and the cable (12) can fall off the first roller (3.2).
11. The pile frame according to claim 4, characterized in that: The glide path device (7) comprises: A sliding pulley seat (7.2) is mounted on the column (13), and the moving assembly is mounted on the sliding pulley seat (7.2); The slide (7.10) is provided with the fixing portion, and the slide (7.10) is slidably arranged along the sliding pulley seat (7.2) so that the fixing portion moves to the first position or the second position.
12. The pile frame according to claim 11, characterized in that The second cable guide frame (7.4) comprises: a second guide frame, the second guide frame being mounted on the sliding pulley seat (7.2) via a fixing pin shaft (3.4); the sliding pulley seat (7.2) being provided with a third mounting position and a fourth mounting position; when the second guide frame is fixedly mounted on the third mounting position of the sliding pulley seat (7.2), the second cable guide frame (7.4) is at a third angular position; when the second guide frame is fixedly mounted on the fourth mounting position of the upper retainer (4), the first cable guide frame (3) is at a fourth angular position; A second roller mounted on the second guide frame, and a cable (12) is wound around the second roller; A second lever assembly is provided with a third telescopic power member and a second telescopic lever that is telescopically driven by the third telescopic power member; when the second telescopic lever is in an extended state, the second telescopic lever is located outside the cable (12) wound in the second roller to prevent the cable (12) from falling off; when the second telescopic lever is in a retracted state, the second telescopic lever deviates from the cable (12) wound in the second roller, and the cable (12) can fall off the second roller; A deflection force member, one end of which is connected to the sliding pulley seat (7.2) and the other end of which is connected to the second guide frame.
13. The pile frame according to claim 4, characterized in that: The lower retainer (8) comprises: A second installation body, the second installation body comprising a lower retaining fixture (8.4) and a lower retaining movable member (8.1) which is flippably arranged on the lower retaining fixture (8.4), the lower retaining fixture (8.4) being slidably arranged along the upright column (13); The second mounting body is provided with a second through hole for allowing the first guide rod (5) to pass through, and a second latch mechanism (8.2) arranged around the outer circumference of the second through hole, the second latch mechanism (8.2) being able to extend or retract along the radial direction of the second through hole to clamp the first guide rod (5), and the second through hole simultaneously passes through the lower retaining fixed member (8.4) and the lower retaining movable member (8.1).
14. A vibro-impact connecting rod method, characterized in that: Applied to the pile frame according to any one of claims 4 to 13, the vibro-connecting rod method comprises: The control cable (12) passes through the first guide rod (5), the first cable guide frame (3), the second cable guide frame (7.4), and the second guide rod (6) in sequence; Controlling the water pipe adapter (5.1) of the first guide rod (5) to be connected to an external water pipe, and the air pipe adapter (5.6) to be connected to an external air pipe; Controlling the upper retainer (4) to clamp the first guide rod (5); Controlling the hoisting and releasing rope to lower the first guide rod (5) until the first guide rod (5) is lowered to a preset depth; Controlling the fixed portion in the lower slide device (7) to move to a second position, and controlling the goose head (1) to drive the portion of the top retainer (2) connected to the second guide rod (6) to rise until the second guide rod (6) is located directly above the first guide rod (5); Controlling the second cable guide frame (7.4) to deflect to a fourth angle position, and controlling the first cable guide frame (3) to deflect to a second angle position, avoiding the space directly above the first guide rod (5); Controlling the disconnection between the water pipe adapter (5.1) of the first guide rod (5) and the external water pipe, and between the air pipe adapter (5.6) and the external air pipe; The goose head (1) is controlled to drive the portion of the top retainer (2) connected to the second guide rod (6) to descend, so that the first positioning connector and the second positioning connector are connected in coordination, thereby achieving communication between the pipeline where the water pipe adapter (5.1) is located and the pipeline where the water pipe joint (6.2) is located; and communication between the gas path where the gas pipe adapter (5.6) is located and the gas path where the gas pipe joint (6.6) is located; The hoisting and releasing rope is controlled to lower the second guide rod (6) until the second guide rod (6) is lowered to a preset depth.
Citation Information
Patent Citations
Ultra-deep vibroflotation pile construction method
CN112502152A
Large electromechanical piling device and method for constructional engineering
CN115125951A
Pore-forming method of vibro-replacement stone column machine
CN115704212A
Method for controlling construction perpendicularity of vibro-replacement stone column machine under ultra-strong seismic belt
CN116791567A
Ultra-deep vibro-replacement gravel pile drilling machine and construction method thereof
CN116927665A