Upright internal heating type semi-coke furnace and coal briquette pyrolysis purification system
By using a gas mixing chamber surrounded by chromium steel and jade bricks in an upright internal heated ylcon furnace for high-temperature pyrolysis, the problems of low gas value and limited production capacity of traditional furnaces are solved, and efficient gas utilization and environmentally friendly industrial use are achieved application.
Patent Information
- Application Number
- CN202411300080.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-18
- Publication Date
- 2024-11-26
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The gas calorific value of traditional internal heat lantern charcoal furnaces is low and the production capacity is limited. The small round furnace has shortcomings in large-scale, intelligent, environmentally friendly and energy-saving, making it difficult to meet the needs of large-scale industrial applications.
Adopt an upright internal heated orchid furnace, the gas mixing chamber is surrounded by chrome steel jade bricks, and the mixed gas is sprayed into the carbonization chamber for high-temperature pyrolysis, which improves the quality of orchid and gas production, and controls the temperature through the mixing of air and flue gas. Reduce energy consumption and environmental pollution.
The quality of orchid carbon and gas production have been improved, and the gas calorific value has been increased to about 2,000 kcal. It is suitable for high demand occasions such as metal magnesium kilns and power generation, reducing the maintenance frequency and maintenance cost of carbonization chambers, and meeting large-scale industrial applications.
Smart Images

Figure CN119020051A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of coal block pyrolysis, and in particular relates to an upright internal heating type blue charcoal furnace and a coal block pyrolysis purification system. Background Art
[0002] Traditional internal heating type semi-coke furnace mainly heats the coal with a mixture of gas and air to produce semi-coke. However, in this way, 40% of the gas is used for heating in the furnace, and the remaining 60% is used for other purposes, such as power generation, etc., and the calorific value of the gas is low, only 1700 kcal-1800 kcal.
[0003] In addition, in Fugu, Shaanxi, due to the large number of magnesium kilns, enterprises all use small round furnaces that only blow air to produce semi-coke and supply gas. However, the existing small round furnaces have limited production capacity, with a maximum single furnace capacity of only 30,000 tons, and are insufficient in terms of large-scale, intelligent, environmental protection and energy saving. Summary of the invention
[0004] In order to solve the above technical problems, the purpose of the present invention is to provide an upright internal heating type blue charcoal furnace and a coal block pyrolysis purification system. The gas mixing chamber of the internal heating type blue charcoal furnace of the present invention is composed of chrome corundum bricks. The mixed gas is sprayed from the gas mixing chamber into the carbonization chamber to heat and pyrolyze the coal blocks in the carbonization chamber, which not only improves the quality of the blue charcoal, but also increases the gas production.
[0005] In order to achieve the above object, the technical solution adopted by the present invention is:
[0006] A vertical internal heating type blue charcoal furnace, comprising:
[0007] Coal box on the top of the furnace, for coal blocks to enter;
[0008] An auxiliary coal box connected to the lower end of the furnace top coal box;
[0009] A furnace wall, arranged at the lower end of the auxiliary coal box and used to support the auxiliary coal box and the furnace top coal box, the furnace wall encloses a cavity, a plurality of spaced walls are arranged at the lower part of the cavity, and the upper part of the cavity is communicated with the auxiliary coal box;
[0010] A carbonization chamber is arranged in the furnace wall and is composed of gaps between adjacent walls, and is used for mixed gas pyrolysis of coal blocks in the carbonization chamber;
[0011] A gas mixing chamber, embedded in the upper end of the wall and connected to the carbonization chamber, for spraying the mixed gas into the carbonization chamber;
[0012] A burner, one end of which passes through the furnace wall and is connected to the gas mixing chamber, and is used to transport the mixed gas into the gas mixing chamber;
[0013] A large coke quenching tank is arranged at the lower end of the furnace wall and is connected therewith, and is used for receiving and quenching the blue coke from the carbonization chamber;
[0014] A hydraulic coke pusher is arranged at the lower end of the carbonization chamber and is used for pushing the blue coke into the large coke quenching tank.
[0015] Furthermore, it also includes a main air fan and an exhaust gas fan, one end of the main air fan is connected to the burner nozzle for conveying air to the burner nozzle; one end of the exhaust gas fan is connected to the burner nozzle for conveying flue gas to the burner nozzle, and the flue gas and the air are mixed in the burner nozzle to form the mixed gas.
[0016] Furthermore, it also includes a coke supporting plate, which is arranged at the lower end of the hydraulic coke pusher and communicates with the carbonization chamber, and is used to support the blue coke flowing out from the lower end of the carbonization chamber.
[0017] Furthermore, the fixed end of the hydraulic coke pusher is arranged on the outside of the furnace wall, and the telescopic end of the hydraulic coke pusher extends into the coke supporting plate.
[0018] Furthermore, the burner includes a flue gas U-tube, an air U-tube and a plurality of burner nozzles, the flue gas U-tube and the air U-tube are sleeved on the outer periphery of the furnace wall, one end of each of the burner nozzles is connected with the flue gas U-tube and the air U-tube, and the other end of each of the burner nozzles passes through the furnace wall and is connected with the corresponding gas mixing chamber.
[0019] Furthermore, the burner includes a straight air pipe and a straight flue gas pipe which are spaced apart from each other, one end of the straight air pipe is connected to the U-shaped air pipe, and one end of the straight flue gas pipe is connected to the U-shaped flue gas pipe.
[0020] Furthermore, the gas mixing chamber is formed by enclosing chrome corundum bricks, and the fire holes of the chrome corundum bricks radially penetrate the carbonization chamber.
[0021] Furthermore, a peephole is provided at one end of the burner nozzle.
[0022] The present invention also provides a coal block pyrolysis purification system, comprising the upright internal heating blue charcoal furnace described in the present invention, and also comprising a countercurrent spray tower for cooling and washing furnace top gas, an electric tar collector for separating coal tar, a gas blower for pressurizing furnace top gas and a rotary trap for dehydrating furnace top gas, which are connected in series in sequence. The countercurrent spray tower is connected to the auxiliary coal box.
[0023] Furthermore, it also includes a mixing tank, which is connected to the countercurrent spray tower, the electric tar collector, the gas blower and the rotary collector for collecting and separating ammonia water and coal tar.
[0024] The present invention adopts the above technical solution, which has the following advantages and effects:
[0025] (1) The vertical internal heating type semi-coke furnace and coal block pyrolysis purification system provided by the present invention has a gas mixing chamber made of chrome corundum bricks. The mixed gas is sprayed into the carbonization chamber through the fire holes of the chrome corundum bricks to form a high temperature of 1100°C to pyrolyze the coal blocks, which not only improves the quality of the semi-coke, but also increases the gas output by 40% and the calorific value of the gas to about 2000 kcal, effectively improving the utilization value of the gas; and the purified gas is suitable for high-demand occasions such as metal magnesium kilns and gas power generation, and can meet large-scale industrial applications.
[0026] (2) The upright internally heated blue charcoal furnace and coal block pyrolysis purification system provided by the present invention adopt an air intake method of "blowing only air, not blowing coal gas", using air as the only heating medium, and controlling the temperature by adjusting the mixing ratio of air and flue gas to avoid burning the carbonization chamber, while reducing energy consumption and environmental pollution; and the gas mixing chamber is enclosed by chrome corundum bricks to form a cavity structure, which can withstand high temperatures, reduce slag and burning, and reduce the maintenance frequency and maintenance cost of the carbonization chamber. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 It is a schematic structural diagram of the upright internal heating type blue charcoal furnace of the present invention.
[0028] Figure 2 It is a schematic diagram of a partially enlarged structure of the gas mixing chamber of the present invention.
[0029] Figure 3 It is a schematic diagram of the top view of the structure of the connection between the burner and the wall.
[0030] Figure 4 It is a partial enlarged structural schematic diagram of the connection between the burner nozzle and the wall of the present invention.
[0031] Figure 5 The figure is a schematic diagram of the structure of the coal block pyrolysis purification system provided by the present invention.
[0032] The accompanying drawings are marked as follows: 1- furnace top coal box, 2- auxiliary coal box, 3- carbonization chamber, 4- gas mixing chamber, 401- chrome corundum brick, 402- wall, 5- burner nozzle, 51- burner nozzle, 52- air U-shaped pipe, 53- flue gas U-shaped pipe, 521- air inlet, 531- flue gas inlet, 511- air straight pipe, 512- flue gas straight pipe, 5121- peep hole, 6-Hydraulic coke pusher, 7-coke quenching tank, 8-exhaust fan, 801-flue gas pipe, 9-kiln, 10-coke support plate, 11-furnace wall, 1101-gas pipeline, 12-belt conveyor, 13-lignite shed, 14-main air fan, 1401-air pipe, 15-rotary catcher, 16-gas fan, 17-electric tar precipitator, 18-countercurrent spray tower, 19-mixing tank. DETAILED DESCRIPTION
[0033] The embodiments of the present invention will be described in detail below in conjunction with the accompanying drawings so that the purpose, features and advantages of the present invention can be more clearly understood. It should be understood that the embodiments shown in the accompanying drawings are not intended to limit the scope of the present invention, but are only intended to illustrate the essential spirit of the technical solution of the present invention.
[0034] like Figure 1-Figure 4 As shown. The vertical internal heating type blue charcoal furnace provided by the present invention includes a furnace top coal box 1, an auxiliary coal box 2, a carbonization chamber 3, a gas mixing chamber 4, a burner 5, a large coke quenching tank 7, a hydraulic coke pusher 6 and a furnace wall 11. The furnace top coal box 1 is used for coal blocks to enter, and the auxiliary coal box 2 is connected to the lower end of the furnace top coal box 1. The furnace wall 11 is arranged at the lower end of the auxiliary coal box 2 to support the auxiliary coal box 2 and the furnace top coal box 1. The furnace wall 11 is enclosed to form a cavity, and a plurality of spaced walls 402 are arranged at the lower part of the cavity, and the upper part of the cavity is connected to the auxiliary coal box 2. The carbonization chamber 3 is arranged at the lower part of the furnace wall 11, and is composed of the gaps between adjacent walls 402. The carbonization chamber 3 is used to heat and pyrolyze the coal blocks entering from the furnace top coal box 1 to form blue charcoal. The gas mixing chamber 4 is embedded in the upper end of the wall 402 and is connected to the carbonization chamber 3. The gas mixing chamber 4 is used to transport mixed gas to the carbonization chamber 3. One end of the burner 5 passes through the furnace wall 11 and is connected to the gas mixing chamber 4. The quenching tank 7 is arranged at the lower end of the furnace wall 11 and is connected thereto. The quenching tank 7 is used to receive and extinguish the semi-coke from the carbonization chamber 3. The hydraulic coke pusher 6 is arranged at the lower end of the carbonization chamber 3 and is used to slowly push the carbonized semi-coke into the quenching tank 7.
[0035] Specifically, the furnace top coal box 1 is a double cone box, the upper end of the auxiliary coal box 2 is a cone structure, and the upper end of the auxiliary coal box 2 is connected to the lower end of the furnace top coal box 1. The furnace wall 11 is a square cavity structure, and the upper end of the furnace wall 11 is supported on the lower end of the auxiliary coal box 2 and is connected to the auxiliary coal box 2. The large coke quenching tank 7 is arranged at the lower end of the furnace wall 11 and is connected to the furnace wall 11.
[0036] The carbonization chamber 3 is arranged at the lower part of the inner cavity of the furnace wall 11. The gap between the wall 402 and the wall 402 forms the carbonization chamber 3 for accommodating the coal blocks. The upper inner cavity of the furnace wall 11 is a hollow cavity, which is connected to the auxiliary coal box 2. After the coal blocks enter the carbonization chamber 3 through the hollow cavity, they are pyrolyzed by the mixed gas to form blue charcoal. The large coke quenching tank 7 is arranged at the lower end of the furnace wall 11, and the lower end of the wall 402 is connected to the large coke quenching tank 7. A burner 5 is arranged at both ends of each wall 402. One end of the burner 5 penetrates the furnace wall 11 and then penetrates the gas mixing chamber 4 on the wall 402. A pair of burners 5 penetrate the two ends of the gas mixing chamber 4 relatively. The other end of each burner 5 is connected to a gas pipeline, which transports flue gas and air, which enter the gas mixing chamber 4 through the burner 5 to form a mixed gas, and enter the carbonization chamber 3 through the fire hole on the gas mixing chamber 4, so that the coal blocks in the carbonization chamber 3 are accelerated to be pyrolyzed. The coal blocks at the bottom of the carbonization chamber 3 are continuously heated and slowly move vertically downward to be pyrolyzed into blue coke, which are slowly pushed into the large coke quenching tank 7 through the coke pusher 6.
[0037] The gas mixing chamber 4 is located at the upper end of the carbonization chamber 3 and is used to withstand the high temperature of the mixed gas. After passing through the gas mixing chamber 4, the mixed gas enters the upper end area of the carbonization chamber 3 to form a high temperature, which is the area for high-temperature pyrolysis of coal blocks. A belt conveyor 12 is arranged on the top of the furnace top coal box 1. The belt conveyor 12 can convey the screened qualified coal blocks to the furnace top coal box 1, keep the furnace top coal box 1 full, and finally enter the carbonization chamber 3 through the auxiliary coal box 2 for pyrolysis.
[0038] A gas outlet is provided at the upper end of the furnace wall 11, and a gas pipeline 1101 is connected to the gas outlet. The gas generated after the pyrolysis of the coal block is output through the gas pipeline 1101 for further utilization.
[0039] Furthermore, the upright internal heating blue charcoal furnace of the present invention also includes a main air fan 14 and an exhaust gas fan 8. One end of the main air fan 14 is connected to the burner 5 for delivering air to the burner 5. One end of the exhaust gas fan 8 is connected to the burner 5 for delivering flue gas to the burner 5. The flue gas is mixed with air to form a mixed gas.
[0040] Specifically, one end of the exhaust gas fan 8 is connected to the burner 5 through the flue gas pipe 801. The exhaust gas fan 8 draws the flue gas after combustion in the kiln 9 and sends it into the burner 5 through the flue gas pipe 801. The main air fan 14 is connected to the burner 5 through the air pipe 1401. After the main air fan 14 draws air, it sends the air into the burner 5 through the air pipe 1401 to mix with the flue gas.
[0041] Furthermore, the vertical internal heating type blue charcoal furnace of the present invention also includes a coke supporting plate 10, which is arranged at the lower end of the hydraulic coke pusher 6 and is connected to the carbonization chamber 3, and is used to support the blue char flowing out from the lower end of the carbonization chamber 3.
[0042] Specifically, the coke supporting plate 10 is a flat plate structure, the upper end of the coke supporting plate 10 is connected to the carbonization chamber 3, the lower end of the carbonization chamber 3 passes through the coke supporting plate 10, and the lignite at the bottom of the carbonization chamber 3 falls into the coke supporting plate 10. The coke pusher 6 can slowly push the lignite in the coke supporting plate 10 into the large coke quenching tank 7.
[0043] Further, the fixed end of the hydraulic coke pusher 6 is arranged on the outside of the furnace wall 11, and the telescopic end of the hydraulic coke pusher 6 extends into the coke supporting plate 10. The hydraulic coke pusher 6 is an electro-hydraulic telescopic mechanism, the fixed end is fixed on the side wall of the furnace wall 11, and the telescopic end is telescoped into the coke supporting plate 10 at the lower end of the carbonization chamber 3 of the furnace wall 11. The telescopic end is provided with a push plate, and the semi-coke is slowly pushed into the large coke quenching tank 7 by telescopically moving the push plate.
[0044] Furthermore, the burner 5 includes a flue gas U-tube 53, an air U-tube 52 and a plurality of burner nozzles 51. The flue gas U-tube 53 and the air U-tube 52 are sleeved on the outer periphery of the furnace wall 11. One end of each burner nozzle 51 is connected to the flue gas U-tube 53 and the air U-tube 52, and the other end of each burner nozzle 51 passes through the furnace wall 11 and is connected to the corresponding gas mixing chamber 4.
[0045] Specifically, the flue gas U-tube 53 and the air U-tube 52 form a U-shaped cavity tube structure, the inner diameter of the air U-tube 52 is smaller than the inner diameter of the flue gas U-tube 53, and the flue gas U-tube 53 is sleeved on the outer circumference of the air U-tube 52. Multiple burners 51 pass through the furnace wall 11 at multiple points to enter the gas mixing chamber 4, one end of each burner 51 is connected to the gas mixing chamber 4, and the other end of each burner 51 is simultaneously connected to the flue gas U-tube 53 and the air U-tube 52 for conveying flue gas and air, and the air and flue gas are mixed in the burner 51 and then enter the gas mixing chamber 4 and are sprayed into the carbonization chamber 3.
[0046] Furthermore, the burner 51 includes an air straight pipe 511 and a flue gas straight pipe 512 which are mutually annularly spaced. One end of the air straight pipe 511 is connected to the air U-shaped pipe 52, and one end of the flue gas straight pipe 512 is connected to the flue gas U-shaped pipe 53. The flue gas straight pipe 512 and the air straight pipe 511 are annularly spaced to form the burner 51. One end of the flue gas straight pipe 512 extends out of the air straight pipe 511, and a peep hole 5121 is provided at the end of the extended flue gas straight pipe 512.
[0047] Furthermore, the outer end of the burner 51 is provided with a peephole 5121 for observing the slag condition of the gas mixing chamber 4. If the slag condition of the gas mixing chamber 4 is serious, it can be repaired and maintained. In the present invention, the peephole 5121 is a transparent window, and the peephole 5121 is provided at the outer end of the flue gas straight pipe 512.
[0048] Further, the flue gas U-shaped tube 53 is connected to the exhaust gas fan 8, and the air U-shaped tube 52 is connected to the main air fan 14. The flue gas U-shaped tube 53 is provided with a flue gas inlet 531, and the air U-shaped tube 52 is provided with an air inlet 521. The flue gas inlet 531 is connected to the exhaust gas fan 8 through the flue gas pipe 801, and the air inlet 521 is connected to the main air fan 14 through the air pipe 1401.
[0049] Furthermore, in order to control the high temperature in the lignite furnace, the exhaust gas fan 8 draws the flue gas after combustion to the combustion nozzle 5 and mixes it with the air extracted by the main air fan 14, and by adjusting the mixing ratio of air and flue gas, the temperature of the carbonization chamber 3 can be controlled within 1100°C, which will not cause the gas mixing chamber 4 to be burned by high temperature, and there is enough air volume, so that the lignite production is increased and the amount of coal gas is increased.
[0050] Furthermore, in order to facilitate the transportation of lignite, a lignite belt conveyor is provided at one end of the large quenching tank 7, and the quenched lignite is transported to the lignite field shed 13 via the lignite belt conveyor.
[0051] Furthermore, a plurality of walls 402 are arranged at intervals in the furnace wall 11, and the gas mixing chamber 4 is embedded in the upper end of the wall 402. The gas mixing chamber 4 is formed by chrome corundum bricks 401 and is arranged in the upper end of the wall 402 to form a cavity structure. The fire holes of the chrome corundum bricks 401 radially penetrate the inside and outside of the gas mixing chamber 4, and the gas mixing chamber 4 and the carbonization chamber 3 are mutually connected through the fire holes. The wall 402 is built on a steel platform with a height of 2.5m, and the coke supporting plate 10 is located at the lower end of the steel platform. The mixed gas enters the carbonization chamber 3 through the fire holes of the chrome corundum bricks 401, pyrolyzes the coal blocks to form blue coke, and the blue coke falls down along the wall 402 to the coke supporting plate 10 in turn, and is pushed into the coke quenching tank 7 by the hydraulic coke pusher 6 to quench the coke.
[0052] Furthermore, the chrome corundum brick 401 is made of chrome corundum material. The chrome corundum brick 401 is not only resistant to high temperatures but also not prone to slagging, which reduces the maintenance frequency and maintenance costs, allowing the semi-coke furnace to operate continuously for more than four years.
[0053] Specifically, the mixed gas enters the coal block area at the upper end of the carbonization chamber 3 through the fire holes of the chrome corundum bricks 401 to pyrolyze the coal blocks. The height of this area is about 1m, and the temperature of the area is about 1100°C. The high-temperature gas diffuses upward and preheats the coal blocks in the upper part of the carbonization chamber 3. The chrome corundum bricks 401 can withstand the high temperature without being burned.
[0054] When the upright internal heating blue charcoal furnace provided by the present invention is in use, the coal blocks in the furnace are ignited at the initial stage to raise the temperature in the furnace, and then the main air blower 14 is used to blow air into the carbonization chamber to assist combustion and heat the temperature. When the temperature in the carbonization chamber reaches about 1100°C, the exhaust gas blower 8 is used to blow flue gas into the furnace and mix it with air to keep the temperature in the furnace at about 1100°C to pyrolyze the coal blocks. The coal gas generated from the top of the furnace can be used as external coal gas after purification.
[0055] like Figure 5 The present invention also provides a coal block pyrolysis purification system, comprising the vertical internal heating type blue charcoal furnace of the present invention, and also comprising a countercurrent spray tower 18 for cooling and washing the furnace top gas, an electric tar collector 17 for separating coal tar, a gas blower 16 for pressurizing the furnace top gas, and a rotary trap 15 for dehydrating the furnace top gas, which are connected in series in sequence. The countercurrent spray tower 18 is connected to the auxiliary coal box 2 through a gas pipeline 1101.
[0056] Specifically, the top gas is connected from the auxiliary coal box 2 through the gas pipeline 1101 and enters the lower part of the countercurrent spray tower 18. After the gas is cooled and washed in the countercurrent spray tower 18, it enters the electric tar precipitator 17 from the top of the countercurrent spray tower 18 through a pipeline to recover the coal tar. The upper part of the electric tar precipitator 17 is connected to the inlet of the gas blower 16 through a pipeline. The previous section is a negative pressure section. The top gas entering the gas blower 16 enters the rotary capture device 15 after being pressurized, and is dehydrated and purified by the rotary capture device 15 and then transported to the power plant or the metal magnesium kiln.
[0057] Furthermore, the coal block pyrolysis purification system of the present invention also includes a mixing tank 19, which is connected to the countercurrent spray tower 18, the electric tar collector 17, the gas blower 16 and the rotary collector 15, and is used to collect and statically separate ammonia water and coal tar.
[0058] Specifically, when the furnace top gas passes through the countercurrent spray tower 18, part of the ammonia water and part of the coal tar are collected at the lower part of the countercurrent spray tower 18, when the furnace top gas passes through the electric tar collector 17, the coal tar is collected at the lower part of the electric tar collector 17, when the furnace top gas passes through the gas blower 16, part of the ammonia water and part of the coal tar are collected at the lower part of the gas blower 16, and the collected ammonia water and coal tar enter the mixing tank 19 at the same time for oil and water to stand and then separate the ammonia water and coal tar. The separation of ammonia water and coal tar is achieved by relying on the difference in specific gravity. The specific gravity of ammonia water is 1, and the specific gravity of coal tar is 1.04-1.06. After static stratification, the lower layer is coal tar.
[0059] When the coal block pyrolysis purification system of the present invention is used, the main air blower 14 is first used to transport air into the vertical internal heating type blue charcoal furnace to heat the coal blocks, and then the flue gas after combustion is extracted by the exhaust gas blower 8 and mixed with air to form a mixed gas, and the ratio of air and flue gas in the mixed gas is adjusted to control the temperature in the carbonization chamber 3 within 1100°C, and finally the produced blue charcoal is dropped from the bottom of the carbonization chamber 3 into the coke support plate 10, and then slowly pushed into the coke quenching tank 7 by the coke pusher 6 for quenching. At the same time, the generated furnace top gas can be transported to a power plant or a metal magnesium kiln for use after being purified by a countercurrent spray tower 18, an electric tar collector 17, and a rotary catcher 15.
Claims
1. A vertical internal heating blue charcoal furnace, characterized in that: include: A coal box (1) on the top of the furnace, for coal blocks to enter; An auxiliary coal box (2) connected to the lower end of the furnace top coal box (1); A furnace wall (11) is arranged at the lower end of the auxiliary coal box (2) and is used to support the auxiliary coal box (2) and the furnace top coal box (1); the furnace wall (11) is enclosed to form a cavity; a plurality of spaced walls (402) are arranged at the lower part of the cavity; and the upper part of the cavity is connected to the auxiliary coal box (2); The carbonization chamber (3) is arranged in the furnace wall (11), and is composed of gaps between adjacent walls (402), and is used for pyrolyzing coal blocks in the carbonization chamber (3) with mixed gas; a gas mixing chamber (4), embedded in the upper end of the wall (402) and connected to the carbonization chamber (3), and used for spraying the mixed gas into the carbonization chamber (3); A burner (5), one end of which passes through the furnace wall (11) and is connected to the gas mixing chamber (4), and is used to transport the mixed gas into the gas mixing chamber (4); A large coke quenching tank (7) is arranged at the lower end of the furnace wall (11) and is connected thereto, and is used to receive and quench the blue coke from the carbonization chamber (3); A hydraulic coke pusher (6) is arranged at the lower end of the carbonization chamber (3) and is used to push the blue coke into the large coke quenching tank (7).
2. The vertical internal heating type blue charcoal furnace according to claim 1, characterized in that: It also includes a main air fan (14) and an exhaust gas fan (8), wherein one end of the main air fan (14) is connected to the burner (5) for conveying air to the burner (5); one end of the exhaust gas fan (8) is connected to the burner (5) for conveying flue gas to the burner (5), and the flue gas and the air are mixed in the burner (5) to form the mixed gas.
3. The vertical internal heating type blue charcoal furnace according to claim 1 or 2, characterized in that: It also includes a coke supporting plate (10), which is arranged at the lower end of the hydraulic coke pusher (6) and communicates with the carbonization chamber (3) and is used to support the blue coke flowing out from the lower end of the carbonization chamber (3).
4. The vertical internal heating type blue charcoal furnace according to claim 3, characterized in that: The fixed end of the hydraulic coke pusher (6) is arranged on the outside of the furnace wall (11), and the telescopic end of the hydraulic coke pusher (6) extends into the coke supporting plate (10).
5. The vertical internal heating type blue charcoal furnace according to claim 4, characterized in that: The burner (5) comprises a flue gas U-shaped tube (53), an air U-shaped tube (52) and a plurality of burner nozzles (51); the flue gas U-shaped tube (53) and the air U-shaped tube (52) are sleeved on the outer periphery of the furnace wall (11); one end of each of the burner nozzles (51) is connected to the flue gas U-shaped tube (53) and the air U-shaped tube (52); the other end of each of the burner nozzles (51) passes through the furnace wall (11) and is connected to the corresponding gas mixing chamber (4).
6. The vertical internal heating type blue charcoal furnace according to claim 5, characterized in that: The burner (51) comprises a straight air pipe (511) and a straight flue gas pipe (512) which are spaced apart from each other, one end of the straight air pipe (511) being connected to the air U-shaped pipe (52), and one end of the straight flue gas pipe (512) being connected to the flue gas U-shaped pipe (53).
7. The vertical internal heating type blue charcoal furnace according to claim 6, characterized in that: The gas mixing chamber (4) is formed by enclosing chrome corundum bricks (401), and the fire holes of the chrome corundum bricks (401) radially penetrate the carbonization chamber (3).
8. The vertical internal heating type blue charcoal furnace according to claim 5, characterized in that: A peep hole (5121) is provided at one end of the burner nozzle (51).
9. A coal block pyrolysis purification system, characterized in that: It comprises the upright internally heated blue charcoal furnace as described in any one of claims 1 to 8, and also comprises a countercurrent spray tower (18) for cooling and washing furnace top gas, an electric tar collector (17) for separating coal tar, a gas blower (16) for pressurizing furnace top gas and a rotary trap (15) for dehydrating furnace top gas, which are connected in series in sequence, and the countercurrent spray tower (18) is connected to the auxiliary coal box (2).
10. The coal block pyrolysis purification system according to claim 9, characterized in that: It also comprises a mixing tank (19), wherein the mixing tank (19) is connected to the countercurrent spray tower (18), the electric tar collector (17), the gas blower (16) and the rotary trap (15), and is used for collecting and separating ammonia water and coal tar.
Citation Information
Patent Citations
Oxygen-enriched low-carbon pyrolysis system utilizing boiler flue gas and use method
CN113416562A
Only use vertical rectangle retort of air heating dry distillation semicoke
CN206232659U
Nitrogenfree process systems of pyrolysis of coal
CN208733021U
Semi-coke coal gas upgrading device of internal heating type vertical furnace
CN216837817U
Continuous wood charring and gasifying method and apparatus
WO2015192609A1
Cited By
Swing type coke pusher for semi-coke furnace and working method of swing type coke pusher
CN120365935A