Pi-shaped composite pile supporting structure construction method
Through the construction method of π-type combined pile support structure, the problem of low construction efficiency of deep foundation pit support structures is solved, efficient and stable support effect is achieved, damage to underground structures and floor area occupation is avoided, and construction is improved Safety and efficiency.
Patent Information
- Application Number
- CN202411208590.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-30
- Publication Date
- 2024-11-26
AI Technical Summary
The construction efficiency of the existing deep foundation pit support structure is low, affecting the construction of adjacent subways and underground structures and plot development, and occupying a large space and making construction difficult.
The construction method of π-type combined pile support structure is adopted to form π-type combined piles by constructing horizontal and vertical piles facing downwards, and a crown beam and connecting beam are built on the top, combined with inclination angle support to form stable support. Structure to avoid exceeding the land red line and reduce land area occupation.
The construction efficiency and stability of the deep foundation pit support structure is improved, damage to the underground structure is avoided, the floor area occupation and construction difficulty are reduced, and the stability and construction safety of the foundation pit are ensured.
Smart Images

Figure CN119021237A_ABST
Abstract
Description
Technical Field
[0001] The invention patent relates to the technical field of support structures, specifically, to a construction method of a π-type combined pile support structure. Background Art
[0002] The following options are available for deep foundation pit support structures: row pile prestressed anchor cable support structure, row pile second connecting beam support structure, double (multiple) row pile support structure, reverse construction of ground-connected wall, etc.
[0003] The pile row prestressed anchor cable support structure can be cast-in-place piles, interlocking piles, ground-connected walls, or prefabricated piles (prestressed pipe piles, prefabricated square piles), etc., to form a joint support structure with prestressed anchor cables. The disadvantage is that prestressed anchor cables often extend beyond the land red line, which will affect the safety of adjacent buildings and structures, the construction of adjacent subways and underground structures, and the development of adjacent plots. In recent years, the use of prestressed anchor cables has gradually been restricted.
[0004] The second connecting beam support structure of the pile row can be cast-in-place piles, interlocking piles, or ground-connected walls. The second connecting beam can be a concrete second connecting beam or a steel support. The plane layout is a brace, angle brace, or circular ring brace. For linear foundation pits, such as subway stations and open-cut sections, concrete brace (or steel support) support structures are often used. For block foundation pits, a combined support structure of concrete braces, angle braces, and circular ring braces is often used. The disadvantage is that the second connecting beam often affects the construction of civil structures, and the braces need to be removed and replaced, affecting the construction progress.
[0005] The double (multi) row pile support structure is a cantilever pile support structure that takes up little space. The disadvantage is that it is only applicable to a limited depth of foundation pit.
[0006] The reverse construction scheme of the ground-connected wall is a combination of two walls, namely the foundation pit support wall and the basement exterior wall, and the basement pile column floor is fully utilized as the second connecting beam. The underground part and the ground part are constructed at the same time. The disadvantages are that the earthwork excavation is difficult, the construction progress is slow, and the construction technology requirements are high. Summary of the invention
[0007] The purpose of the present invention is to provide a π-type composite pile support structure construction method, aiming to solve the problem of low construction efficiency of deep foundation pit support structure in the prior art.
[0008] The present invention is implemented in this way: the π-type combined pile support structure construction method comprises the following construction steps:
[0009] 1) constructing horizontally arranged piles from the ground downwards, wherein the horizontal piles extend along the periphery of the foundation pit;
[0010] 2) constructing two rows of vertical piles arranged longitudinally from the ground downwards, with the two rows of vertical piles arranged at intervals; the two rows of vertical piles are formed in the foundation pit and are orthogonally connected to the horizontal piles to form a π-shaped combined pile; the two vertical piles are respectively enclosed with the horizontal piles to form a right angle area;
[0011] 3) constructing a crown beam on the top of the horizontal row of piles and the top of the vertical row of piles, respectively, and constructing a first connecting beam between the two rows of the vertical row of piles, wherein the first connecting beam is connected to the two rows of vertical row of piles respectively;
[0012] 4) A first-floor angle support is constructed in the right-angle region to form an inclined arrangement, one end of the first-floor angle support is butted against the horizontal row of piles, and the other end of the first-floor angle support is butted against the vertical row of piles.
[0013] Optionally, the π-type combined pile support structure construction method further includes:
[0014] Construction step 5), excavate the earth to the set height, set waist beams on the horizontal and vertical piles respectively, and then construct the lower angle support in the right angle area to form an inclined arrangement, one end of the lower angle support is connected to the horizontal piles, and the other end of the lower angle support is connected to the vertical piles.
[0015] Optionally, the construction step 5) is repeated until the excavation reaches the bottom of the foundation pit, and the first-layer angle supports and the plurality of lower-layer angle supports are arranged at intervals along the depth of the foundation pit.
[0016] Optionally, in the construction step 3), a plurality of the first connecting beams are constructed between two of the vertical rows of piles, and the plurality of the first connecting beams are arranged at intervals along a direction deviating from the horizontal row of piles.
[0017] Optionally, in the construction step 3), the first connecting beam and the two vertical rows of piles are arranged orthogonally.
[0018] Optionally, the structure of the first-floor corner support is consistent with that of the lower-floor corner support, including two inclined supports arranged at an angle, the two inclined supports are arranged in parallel with an interval, one end of the inclined support is connected to the horizontal row of piles, and the other end of the inclined support is connected to the vertical row of piles.
[0019] Optionally, a second connecting beam is provided between the two oblique supports, and two ends of the second connecting beam are respectively butted against the two oblique supports; the second connecting beam is orthogonally butted against the oblique supports to form a butt joint.
[0020] Optionally, in the construction step 2), columns are lowered into the foundation pit, and the columns are located in right-angle areas; in the construction step 4), the docking positions of the first-floor corner supports are connected to the columns.
[0021] Optionally, the second connecting beam includes a middle head, threaded rods are respectively extended outward at both ends of the middle head, the ends of the threaded rods are connected to end heads, the end heads include an inner cavity with an outer end opening, the threaded rods are passed through the inner end of the end head, extend into the inner cavity, and are threadedly connected to the end heads;
[0022] The outer end of the end head has a pressing ring surrounding the outer circumference of the outer end opening, the pressing ring is recessed inward to form an inner ring groove, and the inner ring groove is arranged around the outer circumference of the outer end opening; the inner ring groove is filled with an elastic body, and a movable ring is arranged in the inner ring groove, the inner end of the movable ring is fixedly connected to the elastic body, and the outer end of the movable ring is exposed outside the pressing ring due to the pressing effect of the elastic body;
[0023] The second connecting beam is arranged between the two oblique supports, and the two threaded rods are driven to rotate by the middle head, so that the two end heads move toward the oblique supports until the movable ring abuts against the oblique supports;
[0024] After adjusting the position of the middle head so that the threaded rod is orthogonal to the oblique support, the middle head continues to drive the two threaded rods to rotate, the movable ring is squeezed, and the elastic body is compressed to deform until the movable ring is completely embedded in the inner ring groove, and the outer end of the movable ring and the movable ring are respectively abutted against the oblique support.
[0025] Optionally, two sides of the elastic body are fixedly docked on two sides of the inner ring groove, an elastic gap exists between the inner end of the elastic body and the inner end of the inner ring groove, and the outer end of the elastic body is fixedly connected to the movable ring and extends to surround both sides of the movable ring;
[0026] When the movable ring is pressed toward the inner ring groove by the inclined support, the elastic body is squeezed and deformed toward the inner end of the inner ring groove, and the elastic interval is reduced until the movable ring is completely embedded in the inner ring groove.
[0027] Compared with the prior art, the π-type composite pile support structure construction method provided by the present invention, the horizontal row of piles and the two rows of vertical row of piles form a π-type composite pile, which can be directly used as a foundation pit support structure, or angle supports can be set at the right angles on both sides of the π-type composite piles to form a combined support structure for deep foundation pit support. For large-scale deep foundation pit support, one or more groups of π-type composite pile support structures are set in the middle section of each side of the foundation pit to ensure the stability of the foundation pit support structure; the vertical row of piles and angle supports are arranged in the pit without exceeding the red line of the land. After the construction of the underground structure is completed, the vertical row of piles, angle supports, etc. located in the pit will be removed and will not occupy the underground space.
[0028] Compared with the pile row prestressed anchor cable support structure, the support structure does not exceed the land red line, avoiding damage to the underground structure, underground pipelines, and building foundations outside the land red line.
[0029] Compared with the double (multi) row cantilever pile support structure, it occupies less ground area and can better control foundation pit deformation.
[0030] Compared with the second connecting beam support structure of pile rows, it avoids the use of a large number of long braces and long angle braces, which are difficult to construct and expensive. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] Figure 1 It is a schematic diagram of the process of the construction method of the π-type combined pile support structure provided by the present invention;
[0032] Figure 2 It is a schematic plan view of the π-type combined pile support structure provided by the present invention;
[0033] Figure 3 It is a cross-sectional schematic diagram of the π-type combined pile support structure provided by the present invention;
[0034] Figure 4 It is a cross-sectional schematic diagram of the middle head and the end head provided by the present invention. DETAILED DESCRIPTION
[0035] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention.
[0036] The implementation of the present invention is described in detail below in conjunction with specific embodiments.
[0037] The same or similar numbers in the drawings of this embodiment correspond to the same or similar parts; in the description of the present invention, it should be understood that if the terms "upper", "lower", "left", "right" and the like indicate directions or positional relationships based on the directions or positional relationships shown in the drawings, it is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction. Therefore, the terms describing the positional relationship in the drawings are only used for illustrative purposes and cannot be understood as limitations on this patent. For ordinary technicians in this field, the specific meanings of the above terms can be understood according to specific circumstances.
[0038] Reference Figure 1-4 The figure shows a preferred embodiment of the present invention.
[0039] The π-type combined pile support structure construction method provided by the present invention comprises the following construction steps:
[0040] 1) constructing horizontally arranged piles 100 from the ground downwards, and the horizontal piles 100 are arranged along the periphery of the foundation pit;
[0041] 2) constructing two rows of vertical piles 200 arranged vertically from the ground downwards, with the two rows of vertical piles 200 arranged at intervals; the two rows of vertical piles 200 are formed in the foundation pit and are orthogonally connected to the horizontal piles 100 to form a π-shaped combined pile; the two vertical piles 200 are respectively enclosed with the horizontal piles 100 to form a right angle area;
[0042] 3) A crown beam 110 is constructed on the top of the horizontal row of piles 100 and the top of the vertical row of piles 200, and a first connecting beam 210 is constructed between the two rows of vertical piles 200. The first connecting beam 210 is connected to the two rows of vertical piles 200 respectively;
[0043] 4) A first-floor angle support is constructed in a right-angle area to form an inclined arrangement, one end of the first-floor angle support is butted against the horizontal row of piles 100 , and the other end of the first-floor angle support is butted against the vertical row of piles 200 .
[0044] In the above-mentioned π-type composite pile support structure construction method, the horizontal row of piles 100 and the two rows of vertical row of piles 200 form a π-type composite pile, which can be directly used as a foundation pit support structure, or angle supports can be set at the right angles on both sides of the π-type composite piles to form a combined support structure for deep foundation pit support. For large-scale deep foundation pit support, one or more groups of π-type composite pile support structures are set in the middle section of each side of the foundation pit to ensure the stability of the foundation pit support structure; the vertical row of piles 200 and the angle supports are all arranged in the pit and do not exceed the red line of the land. After the construction of the underground structure is completed, the vertical row of piles 200 and the angle supports located in the pit will be removed and will not occupy the underground space.
[0045] Compared with the pile row prestressed anchor cable support structure, the support structure does not exceed the land red line, avoiding damage to the underground structure, underground pipelines, and building foundations outside the land red line.
[0046] Compared with the double (multi) row cantilever pile support structure, it occupies less ground area and can better control foundation pit deformation.
[0047] Compared with the supporting structure of the second connecting beam 310 of the row of piles, it avoids the use of a large number of long braces and long angle braces, which are difficult to construct and expensive.
[0048] The construction method of the π-type composite pile support structure also includes:
[0049] In this embodiment, in construction step 5, excavation is performed to a set height, and after the waist beams 120 are respectively arranged on the horizontal piles 100 and the vertical piles 200, a lower angle support arranged in an inclined manner is constructed in the right angle area, and one end of the lower angle support is connected to the horizontal piles 100, and the other end of the lower angle support is connected to the vertical piles 200. In this way, when the set depth is deeper, secondary excavation is performed to construct the lower waist beams 120 and the lower angle supports to form a multi-layer second connecting beam 310 structure.
[0050] In this embodiment, the construction step 5) is repeated until the excavation reaches the bottom of the foundation pit, and the first-layer angle support and multiple lower-layer angle supports are arranged at intervals along the depth of the foundation pit. In this way, the depth is set according to the deep foundation pit, and multiple layers of lower-layer angle supports are formed to ensure the support effect.
[0051] In construction step 3), a plurality of first connecting beams 210 are constructed between two vertical rows of piles 200, and the plurality of first connecting beams 210 are arranged at intervals along the direction deviating from the horizontal row of piles 100. In this way, the connection between the plurality of first connecting beams 210 and the vertical row of piles 200 forms a more stable frame system, enhances the overall rigidity of the support structure, and is conducive to resisting the horizontal displacement and deformation generated during the foundation pit excavation process.
[0052] Specifically, in construction step 3), the first connecting beam 210 is orthogonally arranged with the two vertical piles 200. In this way, the orthogonally arranged first connecting beam 210 and the vertical piles 200 form a stable grid structure. The lateral stiffness of a single vertical pile 200 is enhanced, and the force between the vertical piles 200 is effectively transmitted and dispersed through the first connecting beam 210, thereby improving the overall stiffness of the entire support structure. This makes the support structure more stable when subjected to external loads, reducing the risk of deformation and displacement.
[0053] The structure of the first floor angle support is consistent with that of the lower floor angle support, including two inclined supports 300 arranged in an inclined manner, arranged in parallel with each other, one end of the inclined support 300 butting against the horizontal pile 100, and the other end of the inclined support 300 butting against the vertical pile 200. In this way, a stable triangular support system is formed. This structure performs well in resisting horizontal loads, can significantly improve the lateral stiffness of the structure, and reduce the horizontal displacement of the structure.
[0054] A second connecting beam 310 is provided between the two oblique supports 300, and the two ends of the second connecting beam 310 are respectively connected to the two oblique supports 300; the second connecting beam 310 and the oblique supports 300 are orthogonally connected to form a connection position. In this way, the second connecting beam 310 connects the two oblique supports 300, and the second connecting beam 310, as an additional supporting member, works together with the oblique supports 300, which significantly improves the overall rigidity of the support structure.
[0055] In construction step 2), the column 320 is lowered into the foundation pit, and the column 320 is located in the right angle area; in construction step 4), the docking position of the first-floor angle support is connected to the column 320. In this way, the column 320 is connected to the docking position, which further enhances the strength of the second connecting beam 310 and the oblique support 300 and improves the overall rigidity of the support structure.
[0056] In this embodiment, the second connecting beam 310 includes a middle head 301, and threaded rods 3010 are respectively extended outward at both ends of the middle head 301, and the ends of the threaded rods 3010 are connected to the end heads 302, and the end heads 302 include an inner cavity with an outer end opening, and the threaded rods 3010 are passed through the inner end of the end heads 302, extend into the inner cavity, and are threadedly connected to the end heads 302;
[0057] The outer end of the end head 302 has a pressing ring 3022 surrounding the outer periphery of the outer end opening, the pressing ring 3022 is recessed inward to form an inner ring groove 3020, and the inner ring groove 3020 is arranged around the outer periphery of the outer end opening; the inner ring groove 3020 is filled with an elastic body 3021, and a movable ring is arranged in the inner ring groove 3020, the inner end of the movable ring is fixedly connected to the elastic body 3021, and the outer end of the movable ring is exposed outside the pressing ring 3022 due to the pressing effect of the elastic body 3021;
[0058] The second connecting beam 310 is arranged between the two oblique supports 300, and the two threaded rods 3010 are driven to rotate by the middle head 301, so that the two end heads 302 move toward the oblique supports 300 until the movable ring abuts against the oblique supports 300;
[0059] After adjusting the position of the middle head 301 so that the threaded rod 3010 is orthogonal to the oblique support 300, the middle head 301 continues to drive the two threaded rods 3010 to rotate, the movable ring is squeezed, and the compression elastic body 3021 is deformed until the movable ring is completely embedded in the inner ring groove 3020, and the outer end of the movable ring and the movable ring are respectively abutted on the oblique support 300. In this way, by driving the threaded rod 3010 to rotate by the middle head 301, the distance between the two end heads 302 and the oblique support 300 can be accurately adjusted until the movable ring abuts on the oblique support 300. This adjustment method is not only accurate, but also flexible, and the relative position between the second connecting beam 310 and the oblique support 300 can be adjusted according to actual needs. When the movable ring is completely embedded in the inner ring groove 3020 and abuts on the oblique support 300 at the same time, the second connecting beam 310 is firmly fixed between the oblique supports 300, forming a stable support structure. The elastic body 3021 filled in the inner ring groove 3020 and the movable ring fixedly connected thereto can be elastically deformed when subjected to the reaction force of the oblique support 300, thereby playing a role in buffering and shock absorption. The direct contact between the movable ring and the oblique support 300, and the tight fit of the movable ring under the action of the elastic body 3021, both enhance the connection strength between the second connecting beam 310 and the oblique support 300. This tight connection not only improves the overall stability of the support structure, but also helps prevent safety accidents caused by loose or failed connections. In addition, after the construction of the underground structure is completed, the overall structure is easy to disassemble.
[0060] The two sides of the elastic body 3021 are fixedly connected to the two sides of the inner ring groove 3020, and there is an elastic gap between the inner end of the elastic body 3021 and the inner end of the inner ring groove 3020. The outer end of the elastic body 3021 is fixedly connected to the movable ring and extends to surround the two sides of the movable ring.
[0061] When the movable ring is pressed by the oblique support 300 toward the inner ring groove 3020, the elastic body 3021 is squeezed and deformed toward the inner end of the inner ring groove 3020, and the elastic interval is reduced until the movable ring is completely embedded in the inner ring groove 3020. In this way, the design of the elastic interval provides a deformation space and plays a buffering role.
[0062] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A π-type composite pile support structure construction method, characterized in that: The construction steps include: 1) constructing horizontally arranged piles from the ground downwards, wherein the horizontal piles extend along the periphery of the foundation pit; 2) constructing two rows of vertical piles arranged longitudinally from the ground downwards, with the two rows of vertical piles arranged at intervals; Two rows of vertical piles are formed in the foundation pit and are orthogonally connected to the horizontal piles to form a π-shaped combined pile; the two vertical piles are respectively enclosed with the horizontal piles to form a right angle area; 3) constructing a crown beam on the top of the horizontal row of piles and the top of the vertical row of piles, respectively, and constructing a first connecting beam between the two rows of the vertical row of piles, wherein the first connecting beam is connected to the two rows of vertical row of piles respectively; 4) A first-floor angle support is constructed in the right-angle region to form an inclined arrangement, one end of the first-floor angle support is butted against the horizontal row of piles, and the other end of the first-floor angle support is butted against the vertical row of piles.
2. The π-type composite pile support structure construction method according to claim 1, characterized in that: The π-type combined pile support structure construction method also includes: Construction step 5), excavate the earth to the set height, set waist beams on the horizontal and vertical piles respectively, and then construct the lower angle support in the right angle area to form an inclined arrangement, one end of the lower angle support is connected to the horizontal piles, and the other end of the lower angle support is connected to the vertical piles.
3. The π-type composite pile support structure construction method according to claim 2, characterized in that: Repeat the construction step 5) until the excavation reaches the bottom of the foundation pit, and the first-layer angle supports and the plurality of lower-layer angle supports are arranged at intervals along the depth of the foundation pit.
4. The π-type composite pile support structure construction method according to claim 1, characterized in that: In the construction step 3), a plurality of the first connecting beams are constructed between two of the vertical rows of piles, and the plurality of the first connecting beams are arranged at intervals along a direction deviating from the horizontal row of piles.
5. The π-type composite pile support structure construction method according to claim 1, characterized in that: In the construction step 3), the first connecting beam and the two vertical rows of piles are arranged orthogonally.
6. The π-type composite pile support structure construction method according to claim 3, characterized in that: The structure of the first-floor corner support is consistent with that of the lower-floor corner support, and includes two inclined supports arranged in an inclined manner, the two inclined supports are arranged in parallel with an interval, one end of the inclined support is connected to the horizontal row of piles, and the other end of the inclined support is connected to the vertical row of piles.
7. The π-type composite pile support structure construction method according to claim 6, characterized in that: A second connecting beam is provided between the two oblique supports, and two ends of the second connecting beam are respectively butted against the two oblique supports; the second connecting beam is orthogonally butted against the oblique supports to form a butt joint.
8. The π-type composite pile support structure construction method according to claim 7, characterized in that: In the construction step 2), columns are lowered into the foundation pit, and the columns are located in the right-angle area; in the construction step 4), the docking position of the first-floor corner support is connected to the column.
9. The π-type composite pile support structure construction method according to claim 7, characterized in that: The second connecting beam comprises a middle head, and threaded rods are respectively extended outward at both ends of the middle head, and the ends of the threaded rods are connected to end heads, and the end heads comprise an inner cavity with an outer end opening, and the threaded rods are passed through the inner end of the end head, extend into the inner cavity, and are threadedly connected to the end heads; The outer end of the end head has a pressing ring surrounding the outer circumference of the outer end opening, the pressing ring is recessed inward to form an inner ring groove, and the inner ring groove is arranged around the outer circumference of the outer end opening; the inner ring groove is filled with an elastic body, and a movable ring is arranged in the inner ring groove, the inner end of the movable ring is fixedly connected to the elastic body, and the outer end of the movable ring is exposed outside the pressing ring due to the pressing effect of the elastic body; The second connecting beam is arranged between the two oblique supports, and the two threaded rods are driven to rotate by the middle head, so that the two end heads move toward the oblique supports until the movable ring abuts against the oblique supports; After adjusting the position of the middle head so that the threaded rod is orthogonal to the oblique support, the middle head continues to drive the two threaded rods to rotate, the movable ring is squeezed, and the elastic body is compressed to deform until the movable ring is completely embedded in the inner ring groove, and the outer end of the movable ring and the movable ring are respectively abutted against the oblique support.
10. The π-type composite pile support structure construction method according to claim 9, characterized in that: The two sides of the elastic body are fixedly docked on the two sides of the inner ring groove, there is an elastic gap between the inner end of the elastic body and the inner end of the inner ring groove, and the outer end of the elastic body is fixedly connected to the movable ring and extends to surround the two sides of the movable ring; When the movable ring is pressed toward the inner ring groove by the inclined support, the elastic body is squeezed and deformed toward the inner end of the inner ring groove, and the elastic interval is reduced until the movable ring is completely embedded in the inner ring groove.