Production plan optimization method for ship assembly carrying
Through the iterative calculation method of 'key link', the problems of resource scheduling and production plan optimization in dock stage in ship production were solved, the scientificity and accuracy of production plan were achieved, resource utilization and efficiency were improved, costs were reduced, and the promotion of The lean development of ship production.
Patent Information
- Application Number
- CN202411117999.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-15
- Publication Date
- 2024-11-26
AI Technical Summary
During the ship production process, there are bottlenecks in resource scheduling and production planning optimization in the dock stage, making it difficult to effectively achieve efficient utilization of resources and cost reduction. The existing digital methods are difficult to accurately convert the management logic of the production administrator into calculation logic, resulting in insufficient production planning. Scientific and accurate.
Using the iterative calculation method of 'key link', the key link is determined by setting the production cycle and order relationship between the ship's total group and the loading stage, and based on the principles of end time node alignment and dynamic calculation, the key link is gradually adjusted to ensure production. The plan is closely matched with actual needs.
It has achieved optimization of production plans, met production management needs, improved production efficiency and resource utilization, reduced costs, and promoted the lean development of ship production.
Smart Images

Figure CN119026242A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of shipbuilding, and in particular relates to a method for optimizing a production plan for a ship assembly. Background Art
[0002] Traditional industries rely mainly on human experience, and digitalization can avoid a series of defects such as human error, volatility, imbalance, and poor inheritance. At the same time, we must also realize that digitalization itself has its own defects, mainly because it is not as flexible as the human brain. In terms of processing and analyzing problems, it can only be done according to the fixed mode set by computer software. Once the framework logic needs to be modified, human intervention is required. In the final analysis, digitalization is just a tool. To apply digitalization well, the communication and instruction problems between people and machines must be properly answered, so that people's ideas and needs are fully and accurately reflected in the framework logic of digital software.
[0003] In shipbuilding enterprises, the dock stage is always a bottleneck, mainly because the dock and gantry crane and other equipment and facilities occupy the largest area, construction period, cost investment, etc. Therefore, the core limited resources in the dock stage are the key to revitalizing production, improving efficiency and reducing costs. At present, our company is promoting the design of the dock core resource planning and scheduling system, hoping to optimize the scheduling of large-scale and multi-interference dock production sites and crane resources through digital means, and obtain scientific and accurate production plans to guide the entire production process towards lean development.
[0004] The design process of the core resource planning and scheduling system for shipping services includes basic information collection, real-life modeling, software programming, etc., which can be completed in a certain amount of time. The key difficulty is how to transform the management logic expected by the production manager into the calculation logic of the scheduling system? How to design an algorithm to accurately achieve the shortest total control cycle and meet production needs? In order to solve this problem, after a long discussion, we determined the "key link" iterative calculation method as the basic framework logic of scheduling calculation. Summary of the invention
[0005] The purpose of the present invention is to overcome the deficiencies in the above-mentioned prior art and to provide a method for optimizing the production plan for a ship assembly. The present invention can meet the application requirements of production management personnel for scheduling software through the "critical link" iterative calculation method, closely fit the actual needs of production, and realize the effective connection between digital management and industrial production needs.
[0006] In order to achieve the above invention purpose, the technical solution provided by the present invention is as follows:
[0007] A method for optimizing a production plan for a ship assembly, the method specifically comprising the following steps:
[0008] S1, setting the production cycle and sequence relationship of each section in the ship assembly and loading stage;
[0009] S2, determine the key links in the assembly and loading phases. Based on the principle of terminal time node alignment, find the longest time line for the construction of all sub-segments and the whole segment in the assembly and loading phases as the key links;
[0010] S3, after the critical link is determined, the first segment or the whole segment is constructed according to the sequence of segments and the whole segment in the critical link. After the first segment or the whole segment is constructed, the critical links of the remaining segments or the whole segment that have not been constructed are re-determined;
[0011] S4, construct the first segment or the whole segment in the re-determined key link, and repeat S3 until all segments or the whole segment are constructed.
[0012] Furthermore, the production cycle and sequence relationship of each section in the ship assembly and loading stage are specifically set as follows: they are set according to the loading order of the whole ship in the XY plane and the Z direction, and the special sections in the whole ship are not set in the loading order of the whole ship, and the special sections enter the dock for loading.
[0013] Furthermore, the recalculation of the critical links after the first segment or block is completed is based on the dynamic calculation principle. The determination of the critical links is also based on the latest critical chain sorting principle, and the non-critical segments or blocks are arranged at the later time nodes of the ship loading.
[0014] Furthermore, after the critical links are recalculated in S3, if the segments or the whole segment in the first sequence are not unique, the construction periods of the segments or the whole segment in the first sequence are compared, and the construction is performed in descending order according to the construction period to complete the construction of all the segments or the whole segment in the first sequence.
[0015] Based on the above technical solution, the method for optimizing the production plan for the ship assembly in the present invention has achieved the following technical advantages through practical application:
[0016] 1. The method for optimizing the production plan carried by a ship assembly of the present invention can meet the application requirements of production management personnel for scheduling software through a "key link" iterative calculation method, closely fit the actual needs of production, and realize the effective connection between digital management and industrial production needs. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is a schematic diagram of a loading network in a method for optimizing a production plan for loading a total ship assembly according to the present invention. DETAILED DESCRIPTION
[0018] In order to make the purpose, technical scheme and advantages of the present invention clearer, the present invention is described below by the specific examples shown in the accompanying drawings. However, it should be understood that these descriptions are only exemplary and are not intended to limit the scope of the present invention. In addition, in the following description, the description of well-known structures and technologies is omitted to avoid unnecessary confusion of the concept of the present invention.
[0019] The present invention relates to a method for optimizing a production plan for a ship assembly, and the method specifically comprises the following steps:
[0020] S1, setting the production cycle and sequence relationship of each section in the ship assembly and loading stage;
[0021] like Figure 1 As shown, the loading order is carried out according to the arrow direction in the loading network diagram; the influence of the overall group order can be ignored. The production cycle is set according to the empirical value. The overall group is mainly the total cycle for the completion of all types of work such as assembly, welding, grinding, and painting (for example, the bottom section is generally completed in 15 days, and a value is set in the software constraints); the loading is set according to the limit constraint relationship between the upper and lower layers and adjacent sections, mainly considering the two aspects of safety and precision quality, and is also set as a value in the software constraints.
[0022] The concept of assembly is to combine the intermediate products of several segment manufacturing stages, the segments, into a larger intermediate product, the total segment, at the assembly site. The weight of the total segment cannot exceed the lifting capacity of the dock gantry crane. As the assembly site has good production conditions and a large area, it saves more man-hours than the dock, so assembly has become the first stage of dock production and is widely used.
[0023] The concept of loading is to load the intermediate product of the completed assembly - the main section - into the dock through a gantry crane to assemble the entire ship.
[0024] After understanding the concepts of assembly and loading, we can know that the object of loading is the block and the object of assembly is the segment. The assembly of the segment is to close and splice the edges of several segments and assemble them into a block through welding, so it requires a certain production cycle; further, the segments after loading also need to be closed and spliced at the edges. Since the three-dimensionality of the whole ship is different from the assembly site, in addition to the order in the XY plane, the loading order in the Z direction must also be considered. There is no necessary order relationship between some segments, and some segments must meet a fixed loading order and loading welding cycle to ensure safety and precision quality; finally, some extremely special segments are not suitable for assembly due to their line shape, weight, loading position and other reasons. They can skip the assembly and be loaded directly into the dock. This type of segment is called "single loading".
[0025] We set the production cycle and sequence relationship of each section in the assembly and loading stage according to the "Loading Network Diagram", such as Figure 1 As shown, arrows indicate the order that must be followed, and those without arrows indicate no necessary connection. Since the object to be carried is the total segment, the order of the carrying network also guides the order of the total group. Then, based on basic conditions such as personnel, equipment and facilities, the estimated total group and carrying production cycle are given and input into the software as the basic attributes of the calculation object.
[0026] S2, determine the key links in the assembly and loading phases. Based on the principle of terminal time node alignment, find the longest time line for the construction of all sub-segments and the whole segment in the assembly and loading phases as the key links;
[0027] First, based on the principle of "end time node alignment", we iteratively calculated the line with the longest total cycle. This line is the so-called "critical link". All the sub-sections and total sections on it are "critical sub-sections / total sections", that is, these sub-sections / total sections must strictly control the production cycle. Once they are out of date, it will affect the completion node of the entire ship. The production cycle of other sub-sections / total sections that are not on the critical link is flexible, and they can be used as reserve resources to flexibly allocate labor and production equipment and facilities.
[0028] Secondly, we must clearly realize that the key link is not static and may change due to fluctuations in the production cycle and various complex factors. Therefore, the second principle followed by the scheduling software in finding the key link is "dynamic calculation", that is, after the first key sub-section / total section is hoisted, the sub-section / total section is deleted, and the entire ship is recalculated to determine the new key link (regardless of whether it changes) and the immediately preceding sub-section / total section as the second key sub-section / total section, and so on.
[0029] Third, the key link search should follow the principle of "latest key chain sorting", that is, the "non-critical" sub-sections / general sections should be moved closer to the later time nodes and closer to the "node 1" on the right side of the road. The purpose of this design is to provide margin for the start-up reserve cycle of the sub-sections and general sections. Because resources are not unlimited, it is impossible for all sub-sections / general sections to start as early as possible at the same time. As long as the requirements of the latest node are met, this design is more in line with production reality;
[0030] S3, after the critical link is determined, the first segment or the whole segment is constructed according to the sequence of segments and the whole segment in the critical link. After the first segment or the whole segment is constructed, the critical links of the remaining segments or the whole segment that have not been constructed are re-determined;
[0031] S4, construct the first segment or the whole segment in the re-determined key link, and repeat S3 until all segments or the whole segment are constructed.
[0032] The setting of the production cycle and sequence relationship of each section in the ship assembly and loading stage is specifically: it is set according to the loading order of the whole ship in the XY plane and the Z direction. The special sections in the whole ship are not set in the loading order of the whole ship, and the special sections enter the dock for loading; special sections are sections that are not assembled.
[0033] The recalculation of the critical links after the first segment or block is completed is based on the dynamic calculation principle. The determination of the critical links is also based on the latest critical chain sorting principle, and the non-critical segments or blocks are arranged at the later time nodes of the ship.
[0034] After the critical links are recalculated in S3, if the segments or the whole segment in the first sequence are not unique, the construction cycles of the segments or the whole segment in the first sequence are compared, and the construction is carried out in descending order according to the construction cycle time to complete the construction of all the segments or the whole segment in the first sequence.
[0035] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, ordinary technicians in the field should understand that the specific implementation methods of the invention can still be modified or some technical features can be replaced by equivalents without departing from the spirit of the technical solution of the present invention, which should be included in the scope of the technical solution for protection of the present invention.
Claims
1. A method for optimizing the production plan for a ship assembly, characterized in that: The method specifically comprises the following steps: S1, setting the production cycle and sequence relationship of each section in the ship assembly and loading stage; S2, determine the key links in the assembly and loading phases. Based on the principle of terminal time node alignment, find the longest time line for the construction of all sub-segments and the whole segment in the assembly and loading phases as the key links; S3, after the critical link is determined, the first segment or the whole segment is constructed according to the sequence of segments and the whole segment in the critical link. After the first segment or the whole segment is constructed, the critical links of the remaining segments or the whole segment that have not been constructed are re-determined; S4, construct the first segment or the whole segment in the re-determined key link, and repeat S3 until all segments or the whole segment are constructed.
2. A method for optimizing the production plan for a ship assembly according to claim 1, characterized in that: The production cycle and sequence relationship of each section in the ship assembly and loading stage are specifically set as follows: it is set according to the loading order of the whole ship in the XY plane and the Z direction. The special sections in the whole ship are not set in the loading order of the whole ship, and the special sections enter the dock for loading.
3. A method for optimizing production plan for ship assembly according to claim 1, characterized in that: The recalculation of the critical link after the construction of the first section or the whole section is completed is based on the dynamic calculation principle. The determination of the critical link is also based on the latest critical chain sorting principle, and the non-critical sections or the whole section are arranged at the later time node of the ship loading.
4. A method for optimizing the production plan for ship assembly according to claim 1, characterized in that: After the critical links are recalculated in S3, if the segments or the whole segment in the first sequence are not unique, the construction cycles of the segments or the whole segment in the first sequence are compared, and the construction is carried out in descending order according to the construction cycle time to complete the construction of all the segments or the whole segment in the first sequence.