Protocol conversion system and conversion method of photovoltaic inverter
Through the photovoltaic inverter specification conversion system, the USB/network converter and 4G/5G wireless network connection are used to realize the direct specification conversion of the inverter, solving the problems of complex installation and difficult troubleshooting in the existing technology. Reduces operation and maintenance costs and improves the stability and controllability of the system.
Patent Information
- Application Number
- CN202411094945.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-11
- Publication Date
- 2024-11-26
- Estimated Expiration
- Not applicable · inactive patent
Smart Images

Figure CN119031046A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of photovoltaic inverters, and in particular to a protocol conversion system and conversion method for photovoltaic inverters. Background Art
[0002] The "explosive" development of distributed photovoltaics has brought great challenges to the balance of the power grid and safe and reliable operation. In 2023, during the peak period of new energy power generation, various types of power sources will be needed to control the output. However, since distributed photovoltaic projects do not have the "four capabilities" (observable, measurable, adjustable, and controllable), problems in grid balance, voltage quality, and line loss management are prominent. At present, the existing technical solution for newly installed distributed photovoltaic users is to install a communication protocol converter and a communication interface converter on the grid side to connect to the photovoltaic inverter. The communication protocol converter can convert the proprietary communication protocols (MBUS) of various photovoltaic inverters into the DL / T698.45 communication protocol used by State Grid Corporation, read the inverter operating status and control the output power, and realize the "four capabilities" control of the photovoltaic inverter through the electricity information collection system.
[0003] In the existing technical solutions, the on-site installation requires that the communication protocol converter, interface converter and electric energy meter be installed in the same meter box. Due to the limited space in the meter box, the converter is large in size, and three communication lines are required to be connected to the communication protocol converter, wireless communication equipment and photovoltaic inverter respectively, which makes on-site wiring and installation complicated. The equipment operation and maintenance is difficult. Due to the large number of equipment installed on-site and the complex wiring, the wire connection parts are often not connected properly, and the joint debugging reports errors. It is necessary to go back and forth to the site to check and deal with them one by one, resulting in an increase in the frequency of on-site operation and maintenance and high technical difficulty. At the same time, due to the large number of protocol converter manufacturers, some are incompatible with the carrier module and need to be upgraded or replaced. The equipment installation standards are not unified. Due to the wide variety of inverter and converter manufacturers, it is difficult to unify the wiring method, resulting in frequent changes in on-site installation and subsequent operation and maintenance technology. It is difficult for grassroots front-line personnel to handle various faults in a short time. Summary of the invention
[0004] The purpose of the embodiments of the present application is to provide a protocol conversion system and conversion method for a photovoltaic inverter, which has the function of a meter module while realizing the function of a protocol converter, thereby realizing functional integration and directly connecting to the inverter through the meter RS485 function.
[0005] To achieve the above objectives, this application provides the following technical solutions:
[0006] In a first aspect, an embodiment of the present application provides a protocol conversion system for a photovoltaic inverter, comprising a USB / Ethernet port converter inserted into the photovoltaic inverter, a communication device being connected to the USB / Ethernet port converter, and the USB / Ethernet port converter being connected to the protocol converter via a communication line.
[0007] The communication equipment adopts 4G / 5G wireless network communication equipment.
[0008] In a second aspect, an embodiment of the present application provides a photovoltaic inverter protocol conversion method, comprising the following specific steps:
[0009] The protocol converter is plugged into the meter, and the device is powered on and initialized. At this time, the carrier chip starts to perform baud rate adaptation to read the meter and network. After reading the meter and networking, the device is networked and waits for the networking to be completed.
[0010] Automatically detect the protocol library and update it. After the update is completed, start single / dual channel detection. If it is detected as a single channel, it is necessary to send a switching command to switch to the grid channel, and then perform inverter addressing operations. If it is detected as a dual channel, the inverter addressing is directly performed. If the inverter does not respond, switch to different modbus addresses for reading until the inverter responds;
[0011] After the inverter responds, it performs self-identification of the manufacturer's protocol, traverses the entire protocol library, and identifies the manufacturer in the protocol library based on the manufacturer's characteristic data items until the correct manufacturer is identified;
[0012] After identifying the manufacturer, start reading the inverter related parameters regularly;
[0013] When the master station sends a command to the device, the device parses it after receiving the command. If it is meter reading data, the device does not process the data and directly transmits it to the meter. If it is a soft control command, the device immediately responds to adjust the inverter. Before adjustment, if the external interface is a single-channel interface, it is necessary to send a switching command to switch to the grid channel, adjust the release bus, and send a switching command to switch to the manufacturer channel.
[0014] If a single-channel interface is detected at the beginning of the single / dual-channel detection process, the bus needs to be released after reading the inverter data, and a switching command needs to be sent to switch to the manufacturer channel. Before reading the inverter parameters next time, a switching command needs to be sent again to switch to the grid channel.
[0015] Compared with the prior art, the beneficial effects of the present invention are: reducing the flexible adjustment equipment of photovoltaic inverters, simplifying equipment installation and wiring, reducing equipment failure points and later operation and maintenance workload, and reducing equipment use and installation costs. At the same time, the technical solution does not require upgrading the existing power grid enterprise power collection system. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the embodiments of the present application will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present application and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.
[0017] Figure 1 is a system structure diagram according to an embodiment of the present invention;
[0018] Figure 2 It is a flow chart of the method of this application. DETAILED DESCRIPTION
[0019] The technical solutions in the embodiments of the present application will be described below in conjunction with the drawings in the embodiments of the present application. It should be noted that similar reference numerals and letters represent similar items in the following drawings, so once an item is defined in one drawing, it does not need to be further defined and explained in the subsequent drawings.
[0020] The terms "comprises," "comprising," or any other variation thereof are intended to encompass non-exclusive inclusion, such that a process, method, article, or apparatus that includes a list of elements includes not only those elements, but also other elements not explicitly listed, or elements inherent to such process, method, article, or apparatus. In the absence of further limitations, an element defined by the phrase "comprising a ..." does not exclude the presence of additional identical elements in the process, method, article, or apparatus that includes the element.
[0021] like Figure 1 As shown, an embodiment of the present application provides a protocol conversion system for a photovoltaic inverter, including a USB / Ethernet port converter 2 inserted into a photovoltaic inverter 1, a communication device 3 is connected to the USB / Ethernet port converter 2, and the USB / Ethernet port converter 2 is connected to a protocol converter 4 via a 485 communication line.
[0022] The communication device 3 adopts 4G / 5G wireless network communication equipment.
[0023] like Figure 2 As shown, the embodiment of the present application provides a protocol conversion method for a photovoltaic inverter, comprising the following specific steps:
[0024] The protocol converter is plugged into the meter, and the device is powered on and initialized. At this time, the carrier chip starts to perform baud rate adaptation to read the meter and network. After reading the meter and networking, the device is networked and waits for the networking to be completed.
[0025] Automatically detect the protocol library and update it. The protocol library is sent to the device storage area via Bluetooth. The program updates according to the manufacturer number, self-identification information, number of protocol lists, and protocol attributes. After the update is completed, the device sends a switching command to start single / dual channel detection. If the switching command is responded to, the detection result is single channel. It is necessary to send a switching command to switch to the grid channel, and then perform inverter addressing. Otherwise, if the command is not responded, it is detected as dual channel. The current channel is the grid channel and the inverter can be directly addressed. Then traverse from address 01-247. If the inverter does not respond, switch the modbus address for the next round of reading until the inverter responds, then the modbus address of the inverter can be identified;
[0026] Then, according to the identified inverter address, the manufacturer protocol self-identification is performed. The self-identification process is to read several special registers of each manufacturer, such as the system clock and other characteristic registers, and then analyze and identify the inverter manufacturer in the protocol library according to the data affected by the device;
[0027] After identifying the manufacturer, start reading the inverter related parameters regularly;
[0028] When the master station sends a command to the device, the device parses it after receiving the command. If it is meter reading data, the device does not process the data and directly transmits it to the meter. If it is a soft control command, the device immediately responds to adjust the inverter. Before adjustment, if the external interface is a single-channel interface, it is necessary to send a switching command to switch to the grid channel, adjust the release bus, and send a switching command to switch to the manufacturer channel.
[0029] If a single-channel interface is detected at the beginning of the single / dual-channel detection process, the bus needs to be released after reading the inverter data, and a switching command needs to be sent to switch to the manufacturer channel. Before reading the inverter parameters next time, a switching command needs to be sent again to switch to the grid channel.
[0030] The power generation user *** in a certain area (concentrator address 800080064124) uses an inverter module address of 990502040007. The user's inverter uses the Jinlong GCL-3P13K-5G protocol.
[0031] Daily communication method: The protocol converter is connected to the inverter via the RS485 interface through the interface converter. During communication, a switching command is sent to inform the interface converter to switch to the grid channel. Then the protocol converter communicates with the inverter and collects the required inverter data.
[0032] After collecting the data, the new protocol converter converts the data into State Grid DL / T698 data and interacts with the substation concentrator through a carrier signal, transmitting the inverter power data back to the grid master station through the substation concentrator.
[0033] Power regulation method: The power grid master station sends PV soft control instructions to the substation concentrator. After receiving the instructions, the concentrator transmits them to the new protocol converter through the DL / T698 carrier signal. The new protocol converter changes the data into modbus instructions through the RS485 interface and the developed interface converter to flexibly control the PV inverter.
[0034] There are many photovoltaic inverter manufacturers at present, and each manufacturer uses a different Modbus protocol. The new protocol converter is compatible with all inverter protocols and unifies the protocol, so that the inverter power generation output can be flexibly controlled in a unified manner.
[0035] The above description is only an embodiment of the present application and is not intended to limit the protection scope of the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.
Claims
1. A photovoltaic inverter protocol conversion system, characterized in that: It comprises a USB / network port converter inserted into a photovoltaic inverter, a communication device is connected to the USB / network port converter, and the USB / network port converter is connected to a protocol converter through a communication line.
2. The photovoltaic inverter protocol conversion system according to claim 1, characterized in that: The communication equipment adopts 4G / 5G wireless network communication equipment.
3. A photovoltaic inverter protocol conversion method, characterized in that: The specific steps include: The protocol converter is plugged into the meter, and the device is powered on and initialized. At this time, the carrier chip starts to perform baud rate adaptation to read the meter and network. After reading the meter and networking, the device is networked and waits for the networking to be completed. Automatically detect the protocol library and update it. After the update is completed, start single / dual channel detection. If it is detected as a single channel, it is necessary to send a switching command to switch to the grid channel, and then perform inverter addressing operations. If it is detected as a dual channel, the inverter addressing is directly performed. If the inverter does not respond, switch to different modbus addresses for reading until the inverter responds; After the inverter responds, it performs self-identification of the manufacturer's protocol, traverses the entire protocol library, and identifies the manufacturer in the protocol library based on the manufacturer's characteristic data items until the correct manufacturer is identified; After identifying the manufacturer, start reading the inverter related parameters regularly; When the master station sends a command to the device, the device parses it after receiving the command. If it is meter reading data, the device does not process the data and directly transmits it to the meter. If it is a soft control command, the device immediately responds to adjust the inverter. Before adjustment, if the external interface is a single-channel interface, it is necessary to send a switching command to switch to the grid channel, adjust the release bus, and send a switching command to switch to the manufacturer channel.
4. The photovoltaic inverter protocol conversion method according to claim 3, characterized in that: If a single-channel interface is detected at the beginning of the single / dual-channel detection process, the bus needs to be released after reading the inverter data, and a switching command needs to be sent to switch to the manufacturer channel. Before reading the inverter parameters next time, a switching command needs to be sent again to switch to the grid channel.
Citation Information
Patent Citations
Internet of Things meter reading method, system and device based on photovoltaic inverter
CN115175023A
Protocol adaptive method between photovoltaic protocol converter and photovoltaic inverter
CN116320062A
Distributed photovoltaic communication protocol complete conversion device
CN117793216A
Photovoltaic inverter identification and working method
CN117880380A
Pouch type rechargeable-battery and method for manufacturing the same
KR1020230013599A