Pull-out test device for steel fibers in epoxy resin modified rubber concrete and use method of pull-out test device
By adopting a multi-motor-driven jacket structure and anti-slip saw tooth design in the steel fiber drawing test device, the test data error problem caused by steel fiber sliding is solved, and more accurate pull test results are achieved.
Patent Information
- Application Number
- CN202411449628.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-17
- Publication Date
- 2024-11-29
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
In the drawing test, the existing steel fiber fixture device has a thin and smooth surface, which leads to error in the test data.
A pulling test device for steel fibers in epoxy resin modified rubber concrete is designed, and a jacket structure driven by a multi-motor is adopted. The steel fibers are wound and fixed by the motor through the screw and gear system. The outer circumference of the jacket is equipped with anti-slip saw teeth. , prevent sliding.
It effectively prevents the sliding of steel fibers during the drawing process, improves the accuracy of the test data, and avoids detection errors.
Smart Images

Figure CN119043918A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of steel fiber pull-out testing, in particular to a pull-out testing device for steel fibers in epoxy resin modified rubber concrete and a use method thereof. Background Art
[0002] In epoxy modified rubber concrete, steel fibers can play a role in strengthening and toughening. There are many types of steel fibers, including straight, pressed edge, corrugated, hooked, big head, double pointed, etc. The reinforcing effect of steel fibers of different shapes in concrete may vary. Steel fibers can be produced by cutting fine steel wire, shearing cold rolled strip, milling steel ingots, or rapid condensation of molten steel. Steel fibers have high strength and toughness, which can improve the tensile strength, flexural strength and crack resistance of concrete. At the same time, steel fibers can also increase the durability and wear resistance of concrete. Steel fibers are often used in concrete structures, such as bridges, roads, buildings, etc., to enhance the bearing capacity and stability of the structure. In epoxy modified rubber concrete, steel fibers can further improve the performance of concrete, making it more suitable for special engineering needs; For example, publication number CN220322934U discloses a clamp device for steel fiber concrete fiber pulling test. It includes a concrete fixed test platform and a steel fiber clamp, the steel fiber clamp includes a fixed clamp body and a movable clamp body, and also includes a clamp locking mechanism for locking the clamp of the steel fiber clamp, the clamp locking mechanism includes a spindle bolt rod, the spindle bolt rod is fixedly connected with the rolling spiral member by a flat key to achieve synchronous rotation; a spindle bolt rod mounting hole for the spindle bolt rod to pass through is provided in the fixed clamp body; a threaded section is provided at the end of the spindle bolt rod, and when the movable clamp body slides to an appropriate position, the threaded section at the end of the spindle bolt rod cooperates with the bolt rod nut to fix the movable clamp body, which is suitable for steel fiber concrete cubic specimen pulling tests of different sizes and can achieve high-strength bite; During the use of this device, the following problems were found: since the jaws of the steel fiber clamp in the device are in a roughly straight structure, and the steel fiber itself is relatively thin and has a smooth surface, when the steel fiber is clamped and pulled, the steel fiber is prone to slippage during pulling, which in turn leads to errors in the test data. Therefore, in order to solve this problem, it is necessary to invent a pulling test device for steel fibers in epoxy resin modified rubber concrete and a method for using the same. Summary of the invention
[0003] The purpose of the present invention is to solve the above-mentioned problems. The present application provides a pull-out test device for steel fibers in epoxy resin modified rubber concrete and a method for using the same.
[0004] The technical solution adopted by the present invention is as follows: a pull-out test device for steel fibers in epoxy resin modified rubber concrete and a method of using the same, comprising a base plate, the four ends of the bottom of the base plate are fixedly mounted with movers, the top of the base plate is fixedly mounted with a middle plate, the top of the middle plate is fixedly mounted with a guide plate and a second electric push rod, the top of the second electric push rod is fixedly mounted with a cross-rail plate, both sides of the top of the cross-rail plate are slidably mounted with clamping plates, and the rear side of the clamping plate is fixedly connected with a linkage rod sliding on the guide plate.
[0005] A back plate is fixedly installed on the top rear side of the bottom plate, a hydraulic rod is fixedly installed on the bottom of the back plate, a tension sensor is fixedly installed on the bottom of the hydraulic rod, a pull plate is fixedly installed on the bottom of the tension sensor, sliders are slidably installed on both sides in front of the pull plate, a side plate is fixedly installed on the front side of the slider, a rack is slidably installed on the top of the side plate, a gear is meshed on the top of the rack, and the outer end of the gear is rotatably connected to the side plate, a connecting rod is fixedly connected to the inner end of the gear, and a sleeve is fixedly connected to the inner end of the connecting rod, a pair of baffles are slidably installed on the top front side of the middle plate, the sliding ends of the two baffles are respectively threadedly connected with a No. 5 screw rod with opposite external threads, and a second double-headed motor with two output ends fixed to two No. 5 screw rods is fixedly installed inside the middle plate.
[0006] Preferably, a rubber anti-skid pad is provided at the bottom of the mover, a first electric push rod is fixedly installed on the inner wall of the mover, a wedge plate is hingedly installed at the extended end of the first electric push rod, and a roller is rotatably installed at the bottom of the wedge plate.
[0007] Preferably, the top of the wedge plate is designed as an inclined surface, and an extrusion rod is fixedly installed inside the mover above the inclined surface of the top of the wedge plate. The inner side of the top of the wedge plate is fixedly connected to the inner wall of the mover through a return spring.
[0008] Preferably, the second electric push rod is located at the front side of the guide plate, and the opposite surfaces of the two clamping plates are provided with trapezoidal clamping grooves.
[0009] Preferably, a No. 2 slide groove matched with the clamping plate is provided on the top of the cross rail plate, a pair of limit rods are plugged and installed on the bottom end of the clamping plate, and both ends of the limit rods are fixedly connected to the No. 2 slide groove.
[0010] Preferably, the guide plate is provided with a guide bevel groove adapted to the linkage rod, and the linkage rod is slidably installed in the guide bevel groove, and the guide bevel groove is designed with the top end inclined inwards.
[0011] Preferably, a No. 3 slide groove adapted to the two sliders is opened on the front side of the pull plate, and the sliding ends of the two sliders are respectively threadedly connected with a No. 3 screw rod with opposite external threads, and a first double-headed motor with two output shafts fixed to the No. 3 screw rod is fixedly installed in the middle part of the pull plate.
[0012] Preferably, a No. 4 slide groove matched with the rack is opened on the top of the side plate, a No. 4 screw rod is threadedly connected to the rack, and a No. 4 motor whose output shaft is fixed to the No. 4 screw rod is fixed at the front end of the side plate.
[0013] Preferably, an arc-shaped clamping groove is provided at the inner end of the jacket, and anti-slip serrations are provided at the outer periphery of the jacket.
[0014] Preferably, the method of using the device is as follows: S1: By setting the relevant components on the mover, when it is necessary to move the device to the laboratory for testing, the first electric push rod is first started to extend, driving the wedge plate to move away from the first electric push rod. At this time, the wedge plate with an inclined top will be squeezed by the squeezing rod, forcing the wedge plate to stretch the reset spring and bend downward. At this time, the roller at the bottom of the wedge plate will contact the ground, and the mover will be lifted, so that the rubber anti-skid pad at the bottom of the mover leaves the ground, so that the device can be moved. When it is moved into place, the first electric push rod is started to retract, so that the wedge plate is pulled by the reset spring and returns to the initial position. At this time, the rubber anti-skid pad at the bottom of the mover contacts the ground again, so that the device can be fixed; S2: After the position of the device is fixed, a prefabricated concrete test block with a special shape and wrapped with steel fibers can be placed on the clamping grooves on the opposite sides of the two clamping plates, and then the second electric push rod is started to extend. At this time, the cross rail plate drives the clamping plate to move upward, and then the linkage rod on the rear side of the clamping plate is squeezed and guided to move inward by the guide inclined groove in the process of following the clamping plate to move upward, so that the two clamping plates are close to each other, and then the concrete test block is effectively clamped and fixed, so as to prepare for the subsequent steel fiber pulling; S3: When the concrete test block is fixed, start the hydraulic rod to extend, and the jacket will move to the bottom. At this time, move the top of the steel fiber exposed on the concrete test block to the arc-shaped clamping groove on the opposite surface of the two jackets. Note that the steel fiber is not completely straightened at this time, but has a straightening margin. Then start the first double-headed motor to drive the No. 3 screw to rotate. At this time, the two sliders drive the two side plates to approach each other, so that the two jackets dock with each other to clamp and fix the top of the steel fiber. This process is completed, start the No. 4 motor to drive the No. 4 screw to rotate, thereby moving the rack, and then the rack meshing gear drives the jacket to rotate. At this time, the clamped top of the steel fiber is wrapped around the jacket. Wrap it around for a few weeks until the steel fiber is slightly straightened, then start the second double-headed motor to drive the two No. 5 screws to rotate to control the two baffles to fit together as a resistance protection. Finally, after calibrating the initial value of the tension sensor, start the hydraulic rod to contract, and drive the jacket carrying the wrapped steel fiber to pull upward until the steel fiber is pulled out of the concrete test block clamped by the plywood. At this time, the tension sensor transmits the data to the computer for analysis by the test personnel. In this process, due to the anti-slip serrations on the outer periphery of the jacket, combined with the winding of the steel fiber, the connection between the steel fiber and the jacket is stable, thereby effectively preventing the steel fiber from sliding during pulling, so as to avoid detection errors.
[0015] In summary, due to the adoption of the above technical solution, the beneficial effects of the present invention are: 1. In the present invention, by setting relevant components on the mover, when it is necessary to move the device to the laboratory for testing, the first electric push rod is first started to extend, driving the wedge plate to move in the direction away from the first electric push rod. At this time, the wedge plate with an inclined top will be squeezed by the squeezing rod, forcing the wedge plate to stretch the reset spring and bend downward. At this time, the roller at the bottom of the wedge plate contacts the ground, and the mover is lifted, so that the rubber anti-skid pad at the bottom of the mover leaves the ground, so that the device can be moved. When the device is moved into place, the first electric push rod is started to contract, so that the wedge plate is pulled by the reset spring and returns to the initial position. At this time, the rubber anti-skid pad at the bottom of the mover contacts the ground again, so that the device can be fixed. 2. In the present invention, when the device is used, a prefabricated concrete test block with a special shape and wrapped with steel fibers can be placed on the clamping grooves on the opposite sides of the two clamps, and then the second electric push rod is started to extend. At this time, the cross rail plate drives the clamps to move upward, and then the linkage rod on the rear side of the clamp is squeezed and guided to move inward by the guide inclined groove in the process of following the upward movement of the clamps, so that the two clamps are close to each other, thereby effectively clamping and fixing the concrete test block. When the concrete test block is fixed, the hydraulic rod is started to extend, and the jacket will move to the bottom. At this time, the top of the steel fiber exposed on the concrete test block will be moved to the arc-shaped clamping grooves on the opposite sides of the two jackets. Note that the steel fibers are not completely straightened at this time, but there is a straightening margin. Then the first double-headed motor is started to drive the No. 3 screw rod to rotate. At this time, the two sliders drive the two side plates to approach each other, so that the two jackets are butted against each other to clamp the top of the steel fibers. The end is clamped and fixed, and this process is completed. The No. 4 motor is started to drive the No. 4 screw to rotate, which in turn makes the rack move, and then the rack meshes with the gear to drive the jacket to rotate. At this time, the top of the steel fiber being clamped will wrap around the jacket for a few weeks until the steel fiber is slightly straightened. Then the second double-headed motor is started to drive the two No. 5 screws to rotate to control the two baffles to fit each other as a resistance protection. Finally, after calibrating the initial value of the tension sensor, the hydraulic rod is started to contract, which drives the jacket carrying the wrapped steel fiber to pull upward until the steel fiber is pulled out of the concrete test block clamped by the plywood. At this time, the tension sensor transmits data to the computer for analysis by the test personnel. In this process, since the anti-slip serrations are set on the outer periphery of the jacket, combined with the winding of the steel fiber, the connection between the steel fiber and the jacket is stable, thereby effectively preventing the steel fiber from sliding during pulling, so as to avoid detection errors. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a structural stereogram of the present invention.
[0017] Figure 2 For the present invention Figure 1 Schematic diagram of the structure of A.
[0018] Figure 3 It is a structural schematic diagram of the top of the middle plate in the present invention.
[0019] Figure 4 It is a schematic diagram of the pull plate and its surrounding structure in the present invention.
[0020] Figure 5 It is a schematic diagram of the structure of the baffle in the present invention.
[0021] Markings in the figure: 1-bottom plate, 2-mover, 3-first electric push rod, 4-wedge plate, 5-extrusion rod, 7-middle plate, 8-guide plate, 9-second electric push rod, 10-cross rail plate, 11-clamping plate, 12-limiting rod, 13-linkage rod, 14-guide chute, 15-back plate, 16-hydraulic rod, 17-tension sensor, 18-pull plate, 19-slider, 20-No. 3 screw rod, 21-first double-headed motor, 22-side plate, 23-rack, 24-No. 4 screw rod, 25-No. 4 motor, 26-gear, 27-connecting rod, 28-jacket, 29-baffle, 30-No. 5 screw rod, 31-second double-headed motor. DETAILED DESCRIPTION
[0022] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in combination with the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0023] The following will be combined Figure 1-Figure 5 A pull-out test device for steel fiber in epoxy resin modified rubber concrete and a method for using the same are described in detail in an embodiment of the present invention.
[0024] Example: Reference Figure 1 , 2 A pull-out test device for steel fiber in epoxy resin modified rubber concrete and a method of using the same include a bottom plate 1, a mover 2 is fixedly installed at the four ends of the bottom of the bottom plate 1, a rubber anti-skid pad is provided at the bottom of the mover 2, a first electric push rod 3 is fixedly installed on the inner wall of the mover 2, a wedge plate 4 is hingedly installed at the extended end of the first electric push rod 3, a roller is rotatably installed at the bottom of the wedge plate 4, the top of the wedge plate 4 is designed as an inclined surface, an extrusion rod 5 is fixedly installed inside the mover 2 above the inclined surface of the top of the wedge plate 4, and the inner side of the top of the wedge plate 4 is fixedly connected to the inner wall of the mover 2 through a reset spring.
[0025] By setting the relevant components on the mover 2, when it is necessary to move the device to the laboratory for testing, the first electric push rod 3 is first started to extend, driving the wedge plate 4 to move in the direction away from the first electric push rod 3. At this time, the wedge plate 4 with an inclined top will be squeezed by the squeezing rod 5, forcing the wedge plate 4 to stretch the reset spring and bend downward. At this time, the roller at the bottom of the wedge plate 4 contacts the ground, and the mover 2 is lifted, so that the rubber anti-skid pad at the bottom of the mover 2 leaves the ground, so that the movement of the device can be achieved. When it is moved into place, the first electric push rod 3 is started to contract, so that the wedge plate 4 is pulled by the reset spring and returns to the initial position. At this time, the rubber anti-skid pad at the bottom of the mover 2 contacts the ground again, so that the fixation of the device can be achieved.
[0026] Reference Figure 1 , 3 A middle plate 7 is fixedly installed on the top of the bottom plate 1, a guide plate 8 and a second electric push rod 9 are fixedly installed on the top of the middle plate 7, the second electric push rod 9 is located on the front side of the guide plate 8, and a cross-rail plate 10 is fixedly installed on the top of the second electric push rod 9. Clamps 11 are slidably installed on both sides of the top of the cross-rail plate 10, and the opposite surfaces of the two clamps 11 are provided with trapezoidal clamping grooves, and a No. 2 slide groove matched with the clamp 11 is opened on the top of the cross-rail plate 10. A pair of limit rods 12 are plugged and installed at the bottom end of the clamp 11, and the two ends of the limit rod 12 are fixedly connected to the No. 2 slide groove, and a linkage rod 13 sliding on the guide plate 8 is fixedly connected to the rear side of the clamp 11. A guide inclined groove 14 matched with the linkage rod 13 is opened on the guide plate 8, and the linkage rod 13 is slidably installed in the guide inclined groove 14, and the guide inclined groove 14 is designed with the top end tilted inward.
[0027] By setting the clamping plates 11, after the position of the device is fixed, the prefabricated concrete test block with special shape and wrapped with steel fibers can be placed on the clamping grooves on the opposite sides of the two clamping plates 11, and then the second electric push rod 9 is started to extend. At this time, the cross rail plate 10 drives the clamping plate 11 to move upward, and then the linkage rod 13 on the rear side of the clamping plate 11 is squeezed and guided to move inward by the guide inclined groove 14 in the process of following the clamping plate 11 to move upward, so that the two clamping plates 11 are close to each other, and the concrete test block is effectively clamped and fixed, so as to prepare for the subsequent steel fiber pulling.
[0028] Reference Figure 1 , 3, 4, 5, a back plate 15 is fixedly installed on the top rear side of the bottom plate 1, a hydraulic rod 16 is fixedly installed on the top and lower part of the back plate 15, a tension sensor 17 is fixedly installed on the bottom of the hydraulic rod 16, a pull plate 18 is fixedly installed on the bottom of the tension sensor 17, sliders 19 are slidably installed on both sides of the front of the pull plate 18, a No. 3 slide groove adapted to the two sliders 19 is opened on the front side of the pull plate 18, the sliding ends of the two sliders 19 are respectively threadedly connected with a No. 3 screw rod 20 with opposite external threads, a first double-headed motor 21 with two output shafts fixed to the No. 3 screw rod 20 is fixedly installed in the middle of the pull plate 18, a side plate 22 is fixedly installed on the front side of the slider 19, a rack 23 is slidably installed on the top of the side plate 22, and a No. 2 slide groove adapted to the two sliders 19 is opened on the front side of the pull plate 18, and a No. 2 slide groove adapted to the two sliders 19 is opened on the front side of the pull plate 18, and a No. 2 screw rod 20 with opposite external threads is respectively threadedly connected to the sliding ends of the two sliders 19, and a first double-headed motor 21 with two output shafts fixed to the No. 3 screw rod 20 is fixedly installed in the middle part of the pull plate 18, a side plate 22 is fixedly installed on the front side of the slider 19, a rack 23 is slidably installed on the top of the side plate 22, and a No. 2 slide groove adapted to the two sliders 19 is opened on the top of the side plate 22 3, a No. 4 slide groove adapted to each other, a No. 4 screw rod 24 is threadedly connected to the rack 23, a No. 4 motor 25 whose output shaft is fixed to the No. 4 screw rod 24 is fixedly installed at the front end of the side plate 22, a gear 26 is meshed with the top of the rack 23, and the outer end of the gear 26 is rotatably connected to the side plate 22, the inner end of the gear 26 is fixedly connected to a connecting rod 27, the inner end of the connecting rod 27 is fixedly connected to a sleeve 28, the inner end of the sleeve 28 is provided with an arc-shaped groove, and the outer periphery of the sleeve 28 is provided with anti-slip serrations, a pair of baffles 29 are slidably installed on the top front side of the middle plate 7, the sliding ends of the two baffles 29 are respectively threadedly connected with a No. 5 screw rod 30 with opposite external threads, and a second double-headed motor 31 with two output ends fixed to the two No. 5 screw rods 30 is fixedly installed inside the middle plate 7.
[0029] By setting the jacket 28, when the concrete test block is fixed, the hydraulic rod 16 is started to extend, and the jacket 28 will move to the bottom. At this time, the top of the steel fiber exposed on the concrete test block is moved to the arc-shaped clamping groove on the opposite sides of the two jackets 28. Note that the steel fiber is not completely straightened at this time, but a straightening margin is left. Then the first double-headed motor 21 is started to drive the third screw rod 20 to rotate. At this time, the two sliders 19 drive the two side plates 22 to approach each other, so that the two jackets 28 are connected to each other to clamp and fix the top of the steel fiber. This process is completed, and the fourth motor 25 is started to drive the fourth screw rod 24 to rotate, thereby moving the rack 23, and then the rack 23 meshes with the gear 26 to drive the jacket 28 to rotate. At this time, the clamped top of the steel fiber is Wrap it around the jacket 28 for a few weeks until the steel fiber is slightly straightened, then start the second double-headed motor 31 to drive the two No. 5 screws 30 to rotate to control the two baffles 29 to fit each other as a resistance protection. Finally, after calibrating the initial value of the tension sensor 17, start the hydraulic rod 16 to contract, and drive the jacket 28 to carry the wrapped steel fiber and pull it upward until the steel fiber is pulled out of the concrete test block clamped by the clamp 11. At this time, the tension sensor 17 transmits the data to the computer for analysis by the test personnel. In this process, since the outer periphery of the jacket 28 is provided with anti-slip serrations, combined with the winding of the steel fiber, the connection between the steel fiber and the jacket 28 is stable, thereby effectively preventing the steel fiber from sliding during the pulling process to avoid detection errors.
[0030] The implementation principle of the pull-out test device for steel fiber in epoxy resin modified rubber concrete and the use method thereof in the present application is as follows: Firstly, by setting the relevant components on the mover 2, when it is necessary to move the device to the laboratory for testing, the first electric push rod 3 is first started to extend, driving the wedge plate 4 to move in the direction away from the first electric push rod 3. At this time, the wedge plate 4 with an inclined top will be squeezed by the squeezing rod 5, forcing the wedge plate 4 to stretch the reset spring and bend downward. At this time, the roller at the bottom of the wedge plate 4 contacts the ground, and the mover 2 is lifted, so that the rubber anti-skid pad at the bottom of the mover 2 leaves the ground, so that the movement of the device can be achieved. When it is moved into place, the first electric push rod 3 is started to contract, so that the wedge plate 4 is pulled by the reset spring and returns to the initial position. At this time, the rubber anti-skid pad at the bottom of the mover 2 contacts the ground again, so that the device can be fixed.
[0031] Furthermore, by setting the clamping plates 11, after the position of the device is fixed, a prefabricated concrete test block of a special shape and wrapped with steel fibers can be placed on the clamping grooves on the opposite sides of the two clamping plates 11, and then the second electric push rod 9 is started to extend. At this time, the cross rail plate 10 drives the clamping plate 11 to move upward, and then the linkage rod 13 on the rear side of the clamping plate 11 is squeezed and guided inward by the guide groove 14 in the process of following the clamping plate 11 to move upward, so that the two clamping plates 11 are close to each other, and the concrete test block is effectively clamped and fixed, so as to prepare for the subsequent steel fiber pulling.
[0032] More importantly, by setting the jacket 28, when the concrete test block is fixed, the hydraulic rod 16 is started to extend, and the jacket 28 will move to the bottom. At this time, the top of the steel fiber exposed on the concrete test block is moved to the arc-shaped clamping groove on the opposite sides of the two jackets 28. Note that the steel fiber is not completely straightened at this time, but there is a straightening margin. Then the first double-headed motor 21 is started to drive the third screw rod 20 to rotate. At this time, the two sliders 19 drive the two side plates 22 to approach each other, so that the two jackets 28 are connected to each other to clamp and fix the top of the steel fiber. This process is completed, and the fourth motor 25 is started to drive the fourth screw rod 24 to rotate, thereby moving the rack 23, and then the rack 23 engages with the gear 26 to drive the jacket 28 to rotate. At this time, the steel fiber is clamped. The top end is then wrapped around the jacket 28 for a few weeks until the steel fiber is slightly straightened, and then the second double-headed motor 31 is started to drive the two No. 5 screws 30 to rotate to control the two baffles 29 to fit each other as a resistance protection. Finally, after the initial value of the tension sensor 17 is calibrated, the hydraulic rod 16 is started to contract, which drives the jacket 28 to carry the wrapped steel fiber and pull it upward until the steel fiber is pulled out of the concrete test block clamped by the clamp 11. At this time, the tension sensor 17 transmits the data to the computer for analysis by the test personnel. In this process, since the outer periphery of the jacket 28 is provided with anti-slip serrations, combined with the winding of the steel fiber, the connection between the steel fiber and the jacket 28 is stable, thereby effectively preventing the steel fiber from sliding during the pulling process to avoid detection errors.
[0033] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.
[0034] The above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit the same. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features may be replaced by equivalents. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.
Claims
1. A pull-out test device for steel fibers in epoxy resin modified rubber concrete, comprising a bottom plate (1), characterized in that: The four ends of the bottom of the base plate (1) are fixedly mounted with movers (2); the top of the base plate (1) is fixedly mounted with a middle plate (7); the top of the middle plate (7) is fixedly mounted with a guide plate (8) and a second electric push rod (9); the top of the second electric push rod (9) is fixedly mounted with a cross rail plate (10); both sides of the top of the cross rail plate (10) are slidably mounted with clamping plates (11); the rear side of the clamping plate (11) is fixedly connected with a linkage rod (13) that slides on the guide plate (8); A back plate (15) is fixedly mounted on the rear side of the top of the bottom plate (1), a hydraulic rod (16) is fixedly mounted below the top of the back plate (15), a tension sensor (17) is fixedly mounted on the bottom of the hydraulic rod (16), a pull plate (18) is fixedly mounted on the bottom of the tension sensor (17), sliders (19) are slidably mounted on both sides of the front of the pull plate (18), a side plate (22) is fixedly mounted on the front side of the slider (19), a rack (23) is slidably mounted on the top of the side plate (22), and the top of the rack (23) is meshed with a A gear (26) is provided, and the outer end of the gear (26) is rotatably connected to the side plate (22); the inner end of the gear (26) is fixedly connected to a connecting rod (27); the inner end of the connecting rod (27) is fixedly connected to a jacket (28); a pair of baffles (29) are slidably mounted on the top front side of the middle plate (7); the sliding ends of the two baffles (29) are respectively threadedly connected to a No. 5 screw rod (30) with opposite external threads; and a second double-headed motor (31) with two output ends fixed to the two No. 5 screw rods (30) is fixedly mounted inside the middle plate (7).
2. The pull-out test device for steel fiber in epoxy resin modified rubber concrete according to claim 1, characterized in that: A rubber anti-skid pad is provided at the bottom of the mover (2), a first electric push rod (3) is fixedly mounted on the inner wall of the mover (2), a wedge plate (4) is hingedly mounted on the extended end of the first electric push rod (3), and a roller is rotatably mounted on the bottom of the wedge plate (4).
3. The pull-out test device for steel fiber in epoxy resin modified rubber concrete according to claim 2, characterized in that: The top of the wedge plate (4) is designed as an inclined surface, and an extrusion rod (5) is fixedly installed inside the mover (2) above the inclined surface at the top of the wedge plate (4). The inner side of the top of the wedge plate (4) is fixedly connected to the inner wall of the mover (2) via a return spring.
4. The pull-out test device for steel fiber in epoxy resin modified rubber concrete according to claim 1, characterized in that: The second electric push rod (9) is located on the front side of the guide plate (8), and the opposing surfaces of the two clamping plates (11) are provided with trapezoidal clamping grooves.
5. The pull-out test device for steel fiber in epoxy resin modified rubber concrete according to claim 1, characterized in that: The top of the cross rail plate (10) is provided with a second slide groove matched with the clamping plate (11), and the bottom end of the clamping plate (11) is plugged with a pair of limit rods (12), and the two ends of the limit rods (12) are fixedly connected to the second slide groove.
6. The pull-out test device for steel fiber in epoxy resin modified rubber concrete according to claim 1, characterized in that: The guide plate (8) is provided with a guide inclined groove (14) adapted to the linkage rod (13), and the linkage rod (13) is slidably mounted in the guide inclined groove (14), and the guide inclined groove (14) is designed with its top end tilted inwards.
7. The pull-out test device for steel fiber in epoxy resin modified rubber concrete according to claim 1, characterized in that: The front side of the pull plate (18) is provided with a No. 3 slide groove adapted to the two sliders (19); the sliding ends of the two sliders (19) are respectively threadedly connected with No. 3 screw rods (20) with opposite external threads; and a first double-headed motor (21) having two output shafts fixed to the No. 3 screw rods (20) is fixedly mounted in the middle of the pull plate (18).
8. The pull-out test device for steel fiber in epoxy resin modified rubber concrete according to claim 1, characterized in that: A fourth slide groove matched with the rack (23) is provided on the top of the side plate (22); a fourth screw rod (24) is threadedly connected to the rack (23); and a fourth motor (25) whose output shaft is fixed to the fourth screw rod (24) is fixedly mounted at the front end of the side plate (22).
9. The pull-out test device for steel fiber in epoxy resin modified rubber concrete according to claim 1, characterized in that: An arc-shaped clamping groove is provided at the inner end of the clamping sleeve (28), and anti-slip serrations are provided at the outer periphery of the clamping sleeve (28).
10. The method for using the pull-out test device for steel fiber in epoxy resin modified rubber concrete according to claim 1, characterized in that: The method of using this device is as follows: S1: By setting the relevant components on the mover (2), when it is necessary to move the device to the laboratory for testing, the first electric push rod (3) is first started to extend, driving the wedge plate (4) to move in a direction away from the first electric push rod (3). At this time, the wedge plate (4) with an inclined top is squeezed by the squeezing rod (5), forcing the wedge plate (4) to stretch the reset spring and bend downward. At this time, the roller at the bottom of the wedge plate (4) contacts the ground, and the mover (2) is lifted, so that the rubber anti-skid pad at the bottom of the mover (2) leaves the ground, so that the device can be moved. When the device is moved into place, the first electric push rod (3) is started to retract, so that the wedge plate (4) is pulled by the reset spring and returns to the initial position. At this time, the rubber anti-skid pad at the bottom of the mover (2) contacts the ground again, so that the device can be fixed; S2: After the position of the device is fixed, a prefabricated concrete test block with a special shape and wrapped with steel fibers can be placed on the clamping grooves on the opposite sides of the two clamping plates (11), and then the second electric push rod (9) is started to extend. At this time, the cross rail plate (10) drives the clamping plate (11) to move upward, and then the linkage rod (13) on the rear side of the clamping plate (11) is guided by the inclined groove (14) to move inward during the process of following the clamping plate (11) to move upward, so that the two clamping plates (11) are close to each other, and the concrete test block is effectively clamped and fixed, so as to prepare for the subsequent steel fiber pulling; S3: After the concrete test block is fixed, the hydraulic rod (16) is started to extend. At this time, the clamp (28) moves to the bottom. At this time, the top of the steel fiber exposed on the concrete test block is moved to the arc-shaped clamping groove on the opposite surface of the two clamps (28). Note that the steel fiber is not completely straightened at this time, but a straightening margin is left. Then the first double-headed motor (21) is started to drive the third screw rod (20) to rotate. At this time, the two sliders (19) drive the two side plates (22) to approach each other, so that the two clamps (28) are connected to each other to clamp and fix the top of the steel fiber. This process is completed, and the fourth motor (25) is started to drive the fourth screw rod (24) to rotate, thereby causing the rack (23) to move, and then the rack (23) meshes with the gear (26) to drive the clamp (28) to rotate. At this time, the clamped top of the steel fiber is The steel fiber is wound around the jacket (28) for several weeks until the steel fiber is slightly straightened, and then the second double-headed motor (31) is started to drive the two No. 5 screws (30) to rotate to control the two baffles (29) to fit each other as a resisting protection. Finally, after the initial value of the tension sensor (17) is calibrated, the hydraulic rod (16) is started to contract, which drives the jacket (28) to carry the wound steel fiber and pull it upward until the steel fiber is pulled out of the concrete test block clamped by the clamp (11). At this time, the tension sensor (17) transmits data to the computer for analysis by the test personnel. During this process, since the outer periphery of the jacket (28) is provided with anti-slip serrations, the connection between the steel fiber and the jacket (28) is stable in combination with the winding of the steel fiber, thereby effectively preventing the steel fiber from sliding during the pulling process to avoid detection errors.