Mounting manipulator for building engineering construction and mounting operation method thereof
The installation robot addresses the hazards and inflexibility of manual lifting by providing a flexible, multi-point operation system for metal doors and windows, enhancing safety and efficiency in construction projects.
Patent Information
- Application Number
- CN202411534222.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-31
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2044-10-31
AI Technical Summary
Existing installation methods for metal doors and windows in construction projects rely heavily on manual lifting, which can be hazardous to workers, and existing manipulators lack flexibility and adaptability in adjusting to the size and shape of metal doors and windows during installation.
An installation robot with a redesigned structure featuring a robot arm, adjustable components, and multiple suction cups connected to an air pipeline, allowing for multi-point operation and flexible adjustment of the suction cup positions to adapt to different sizes and shapes of metal doors and windows.
The robot enhances the flexibility and adaptability of the installation process, reducing operational difficulty and ensuring safer, more efficient installation of glass and other components by enabling multi-point operation and precise positioning.
Smart Images

Figure CN119057758A_ABST
Abstract
Description
Technical Field
[0001] The present application belongs to the field of building construction equipment, and more specifically, particularly relates to an installation robot for building engineering construction and an installation operation method thereof. Background Art
[0002] During the construction of a building project, it is often necessary to install metal doors and windows. In the prior art, the installation of metal doors and windows (including frames and hollow glass located in the frames) is mostly done by manual lifting, which is likely to cause harm to workers. To avoid this situation, the Chinese patent publication number CN118493425A discloses an installation manipulator for construction engineering and its installation operation method, and specifically discloses the following technical solutions: including a fixed frame, the top of the fixed frame is fixedly connected to a mounting column, the top of the fixed frame is fixedly connected to a hoisting frame; an adjustment component, the adjustment component is used to adjust the adaptation range of the manipulator, and the adjustment component is connected to the fixed frame. By setting a cleaning component, the present invention can use the downward pressure of the manipulator during the use of the manipulator, and the elastic plate in the cleaning component is deformed under the action of pressure, and the second arc surface outside the elastic plate expands outward under the action of pressure, pushing the cleaning rubber to contact the glass surface.
[0003] However, in the above technical solution, it emphasizes the cleaning effect of the suction cup adsorption area, but this cleaning effect can often be achieved manually without the need for a complex mechanical structure. Secondly, its adaptability to the single-point operation area is low, and the position of the suction cup cannot be flexibly moved to adapt to the effective adsorption of metal doors and windows. Thirdly, the above existing technology cannot achieve the adaptation of the manipulator to the size of metal doors and windows during installation, and achieve flexibility and adjustment of the size by changing the relative distance between multiple points. Summary of the invention
[0004] The present application discloses an installation robot for construction engineering and an installation operation method thereof, which is suitable for the installation of glass and the like during construction, by redesigning the structure of the robot to improve its synchronization and the flexibility of multi-point operation, and helps to reduce the operational difficulty of glass installation.
[0005] To achieve the above technical effects, this application is implemented through the following technical solutions: The installation robot for construction engineering described in the present application includes a robot arm connecting seat connected to the robot arm, the robot arm connecting seat is fixedly connected to the fixed plate, the fixed plate is connected to the tube body connecting plate through a hinged adjustment plate, the tube body connecting plate is located on both sides of the fixed plate, and the fixed plate drives the hinged adjustment plate by extending the drive cylinder; an execution unit is installed on the tube body connecting plate, and the execution unit includes a primary bottom plate, the primary bottom plate is coaxially connected to a primary rotating plate through a bottom plate rotating shaft, a plurality of primary arc holes are machined on the primary rotating plate, and a primary bottom plate guide hole is machined at a position corresponding to the primary arc hole, and the primary bottom plate guide hole and the first arc hole are A secondary guide sleeve is slidably arranged, one end of the secondary guide sleeve is connected to the secondary drive mounting plate, and the secondary drive mounting plate is slidably arranged on a side of the primary base plate away from the primary rotating plate; the other end of the secondary guide sleeve passes through the primary arc hole and is connected to the secondary base plate, and a secondary rotating plate is coaxially rotatably connected to the secondary base plate, the rotating shaft of the secondary rotating plate is the output shaft of the secondary drive motor, and the secondary drive motor is fixed on the secondary drive mounting plate; a plurality of secondary arc holes are machined on the secondary rotating plate, and secondary base plate guide holes are machined on the secondary base plate corresponding to the secondary arc holes, and gas rods with suction cups are passed through the secondary base plate guide holes and the secondary arc holes, and the suction cups are connected to the external air pipeline.
[0006] As one of the preferred technical solutions of the present application, a plurality of auxiliary gears are distributed on the first-level base plate in the circumferential direction of the first-level rotating plate, and a first-level driving wheel is arranged on the first-level base plate, and the first-level driving wheel is connected to the first-level driving motor on the first-level base plate; the first-level base plate is provided with guide rails in parallel on both sides of the guide hole of the first-level base plate, and a guide slider is slidably arranged on the guide rails, and the guide slider is connected to the secondary drive mounting plate.
[0007] As one of the preferred technical solutions of the present application, a secondary base plate base is provided on the side of the secondary base plate away from the secondary rotating plate, and a suction cup guide rod is provided on the secondary base plate base. The suction cup guide rod and the suction cup guide seat are slidably arranged, and the suction cup guide seat is located at the tail end of the suction cup gas rod.
[0008] As one of the preferred technical solutions of the present application, the primary base plate is fixedly connected to the executive telescopic rod, the executive telescopic rod is inserted in the telescopic guide tube, the telescopic guide tube is fixedly connected to a tube body connecting base at one end away from the primary base plate, the tube body connecting base is fixedly connected to the tube body connecting plate, the tube body connecting plate is fixedly connected to a screw drive motor at one end away from the tube body connecting base, the drive shaft of the screw drive motor is connected to a drive screw, the drive screw extends into the threaded hole of the executive telescopic rod and is threadedly connected to the executive telescopic rod; the executive telescopic rod is provided with a base plate rotating shaft at the end facing the primary rotating plate, and the base plate rotating shaft is rotatably connected to the primary rotating plate.
[0009] As one of the preferred technical solutions of the present application, the fixed plate is hinged with a hinged adjustment plate at both ends through a hinge shaft, the hinged adjustment plate is hinged with a tube connection base at the end away from the fixed plate through a hinge shaft, an adjustment shaft body is arranged inside the hinged adjustment plate, an adjustment shaft body is rotatably connected to the adjustment shaft body, the adjustment shaft sleeve is connected to the telescopic end of the extension drive cylinder body, and the tail end of the extension drive cylinder body is arranged on the hinge seat of the fixed plate.
[0010] As one of the preferred technical solutions of the present application, the tube body connecting plate is connected to a slide rod guide sleeve at the top and bottom ends respectively through an axle body, and the slide rod guide sleeve is arranged parallel to the end face of the tube body connecting plate; the slide rod guide sleeve is arranged on the posture slide rod and slides along the posture slide rod; the two ends of the posture slide rod are located on the outside of the tube body connecting plate and the adjacent posture slide rods are fixedly connected through the slide rod connecting plate.
[0011] A method for installing and operating a construction engineering installation robot, the method comprising the following steps: Step 1: Connect the robot arm through the robot arm connecting seat, and drive the adjustment sleeve and the adjustment shaft body by extending the drive cylinder to make the hinge adjustment plate expand or retract relative to the fixed plate, and the hinge adjustment plate drives the tube body connecting plate to expand or retract, and the slide rod guide sleeve slides along the attitude slide rod to ensure that the end face of the tube body connecting plate is always parallel to the fixed plate; Step 2: The primary driving motor on the primary bottom plate starts to work and drives the primary driving wheel to rotate. The primary driving wheel meshes with the gear structure on the circumference of the primary rotating plate to drive the primary rotating plate to start rotating relative to the primary bottom plate. The rotation of the primary rotating plate enables the primary arc hole to drive the secondary guide sleeve to move in the guide hole of the primary bottom plate, thereby adjusting the distance between adjacent secondary guide sleeves. Step 3: The secondary drive motor starts to work, and the drive shaft of the secondary drive motor drives the secondary rotating plate to rotate relative to the secondary bottom plate. The secondary rotating plate allows the suction cup gas rod to move in the secondary bottom plate guide hole on the secondary bottom plate through the secondary arc hole, so that the distance between adjacent suction cups changes; Step 4: The screw drive motor starts to work, and the screw drive motor drives the execution telescopic rod to move relative to the telescopic guide tube, so that the execution unit approaches the area to be adsorbed and the suction cup is attached to the position to be adsorbed; the negative pressure generating device connected to the suction cup starts to work, so that the suction cup and the position to be adsorbed are adsorbed; Step 5: The robot arm starts working to transfer the adsorbed structure to the installation position. After the installation is completed, the suction cup is separated from the position to be adsorbed under the action of the connected negative pressure generating device, and the entire mechanism is reset.
[0012] Compared with the prior art, this application has the following technical effects: The present application sets up structures such as a pipe body connecting plate, a fixed plate, and a hinged adjustment plate that can move relatively, and can ensure the movement posture of the pipe body connecting plate relative to the above structures through structures such as a posture slide bar and a slide bar guide sleeve, which helps to expand the construction range and improve the adaptability of the manipulator.
[0013] The present application can increase the working area in the single-point action area by setting up a first-level bottom plate, a first-level rotating plate, a second-level bottom plate, a second-level rotating plate and other structures, and then adjust the suction cup posture in different ranges according to the actual situation of the single-point action area. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 This application is a three-dimensional Figure 1 .
[0015] Figure 2 yes Figure 1 A partial enlarged view of part I.
[0016] Figure 3 yes Figure 1 A partial enlarged view of part II.
[0017] Figure 4 This application is a three-dimensional Figure 2 .
[0018] Figure 5 yes Figure 4 A partial enlarged view of part III.
[0019] Figure 6 It is a top view of this application.
[0020] Figure 7 yes Figure 6 A partial enlarged view of part IV.
[0021] In the figure: 1. actuator; 2. actuator telescopic rod; 3. telescopic guide tube; 4. tube body connection base; 5. tube body connection plate; 6. attitude slide bar; 7. hinge adjustment plate; 8. fixed plate; 9. robot arm connection seat; 10. adjustment shaft sleeve; 11. slide bar connection plate; 12. slide bar guide sleeve; 13. adjustment shaft body; 14. screw drive motor; 15. drive screw; 16. primary drive wheel; 17. primary bottom plate; 18. primary rotating plate; 19. primary arc shaped hole; 20, auxiliary gear; 21, primary base plate guide hole; 22, secondary base plate; 23, secondary rotating plate; 24, suction cup; 25, secondary arc hole; 26, base plate shaft; 27, secondary base plate guide hole; 28, guide rail; 29, secondary drive mounting plate; 30, secondary drive motor; 31, guide slider; 32, suction cup guide seat; 33, suction cup guide rod; 34, secondary guide sleeve; 35, secondary base plate seat; 36, extension drive cylinder. DETAILED DESCRIPTION
[0022] The technical solution of the present application is further described below in conjunction with the accompanying drawings.
[0023] Example 1: Figures 1 to 7 As shown, the installation manipulator for construction engineering construction includes a manipulator arm connecting seat 9 connected to the manipulator arm, the manipulator arm connecting seat 9 is fixedly connected to the fixed plate 8, the fixed plate 8 is connected to the tube body connecting plate 5 through the hinge adjustment plate 7, the tube body connecting plate 5 is located on both sides of the fixed plate 8, and the fixed plate 8 drives the hinge adjustment plate 7 by extending the drive cylinder 36; an execution unit 1 is installed on the tube body connecting plate 5, and the execution unit 1 includes a primary bottom plate 17, the primary bottom plate 17 is coaxially connected to the primary rotating plate 18 through the bottom plate rotating shaft 26, and the primary rotating plate 18 is processed with a plurality of primary arc holes 19, and the primary bottom plate 17 is processed with a primary bottom plate guide hole 21 at a position corresponding to the primary arc hole 19, and a secondary guide hole 21 is slidably arranged in the primary bottom plate guide hole 21 and the primary arc hole 19 Toward sleeve 34, one end of the secondary guide sleeve 34 is connected to the secondary drive mounting plate 29, and the secondary drive mounting plate 29 is slidably arranged on the side of the primary bottom plate 17 away from the primary rotating plate 18; the other end of the secondary guide sleeve 34 passes through the primary arc hole 19 and is connected to the secondary bottom plate 22, and the secondary bottom plate 22 is coaxially rotatably connected with the secondary rotating plate 23, and the rotating shaft of the secondary rotating plate 23 is the output shaft of the secondary drive motor 30, and the secondary drive motor 30 is fixed on the secondary drive mounting plate 29; a plurality of secondary arc holes 25 are machined on the secondary rotating plate 23, and a secondary bottom plate guide hole 27 is machined on the secondary bottom plate 22 corresponding to the secondary arc hole 25, and a gas rod of a suction cup 24 is passed through the secondary bottom plate guide hole 27 and the secondary arc hole 25, and the suction cup 24 is connected to an external air pipeline.
[0024] Example 2: Continue to see Figures 1 to 7, a manipulator for installation of construction engineering, wherein the first-level bottom plate 17 is provided with a plurality of auxiliary gears 20 distributed in the circumferential direction of the first-level rotating plate 18, and a first-level driving wheel 16 is provided on the first-level bottom plate 17, and the first-level driving wheel 16 is connected to the first-level driving motor 37 on the first-level bottom plate 17; the first-level bottom plate 17 is provided with guide rails 28 in parallel on both sides of the first-level bottom plate guide hole 21, and a guide slider 31 is slidably provided on the guide rail 28, and the guide slider 31 is connected to the second-level driving mounting plate 29. The second-level bottom plate 22 is provided with a second-level bottom plate seat body 35 on the side away from the second-level rotating plate 23, and a suction cup guide rod 33 is provided on the second-level bottom plate seat body 35, and the suction cup guide rod 33 is slidably provided with the suction cup guide seat 32, and the suction cup guide seat 32 is located at the tail end of the suction cup 24 gas rod. The primary bottom plate 17 is fixedly connected to the execution telescopic rod 2, the execution telescopic rod 2 is inserted into the telescopic guide tube 3, the telescopic guide tube 3 is fixedly connected to a tube body connecting base 4 at the end away from the primary bottom plate 17, the tube body connecting base 4 is fixedly connected to a tube body connecting plate 5, the tube body connecting plate 5 is fixedly connected to a screw drive motor 14 at the end away from the tube body connecting base 4, the drive shaft of the screw drive motor 14 is connected to a drive screw 15, the drive screw 15 extends into the threaded hole of the execution telescopic rod 2 and is threadedly connected to the execution telescopic rod 2; the execution telescopic rod 2 is provided with a bottom plate rotating shaft 26 at the end facing the primary rotating plate 18, and the bottom plate rotating shaft 26 is rotatably connected to the primary rotating plate 18. The fixed plate 8 is hinged with an articulated adjustment plate 7 at both ends through an articulated shaft, and the articulated adjustment plate 7 is hinged with a tube body connection base 4 at the end away from the fixed plate 8 through an articulated shaft. An adjustment shaft body 13 is arranged inside the articulated adjustment plate 7, and an adjustment sleeve 10 is rotatably connected to the adjustment shaft body 13. The adjustment sleeve 10 is connected to the telescopic end of the extension drive cylinder 36, and the tail end of the extension drive cylinder 36 is arranged on the articulated seat of the fixed plate 8. The tube body connecting plate 5 is connected with a slide rod guide sleeve 12 at the top and bottom ends through an axis respectively, and the slide rod guide sleeve 12 is arranged parallel to the end surface of the tube body connecting plate 5; the slide rod guide sleeve 12 is sleeved on the posture slide rod 6 and slides along the posture slide rod 6; the two ends of the posture slide rod 6 are located outside the tube body connecting plate 5 and the adjacent posture slide rods 6 are fixedly connected through the slide rod connecting plate 11.
[0025] The structure and connection relationship of the remaining parts are the same as those described in Example 1, and will not be described again here to avoid cumbersome writing.
[0026] Embodiment 3: A method for installing and operating the installation robot for construction engineering using the installation robot described in Embodiment 1 or Embodiment 2, the method for installing and operating comprises the following steps: Step 1: Connect the robot arm through the robot arm connecting seat 9, and drive the adjustment sleeve 10 and the adjustment shaft body 13 by extending the drive cylinder 36 to make the hinge adjustment plate 7 expand or retract relative to the fixed plate 8, and the hinge adjustment plate 7 drives the tube body connecting plate 5 to expand or retract, and the slide rod guide sleeve 12 slides along the posture slide rod 6 to ensure that the end surface of the tube body connecting plate 5 is always parallel to the fixed plate 8; Step 2: The primary driving motor 37 on the primary bottom plate 17 starts to work and drives the primary driving wheel 16 to rotate. The primary driving wheel 16 is meshed with the gear structure on the circumference of the primary rotating plate 18 to drive the primary rotating plate 18 to start rotating relative to the primary bottom plate 17. The rotation of the primary rotating plate 18 enables the primary arc hole 19 to drive the secondary guide sleeve 34 to move in the primary bottom plate guide hole 21, thereby adjusting the distance between adjacent secondary guide sleeves 34. Step 3: The secondary drive motor 30 starts to work, and the drive shaft of the secondary drive motor 30 drives the secondary rotating plate 23 to rotate relative to the secondary bottom plate 22. The secondary rotating plate 23 allows the gas rod of the suction cup 24 to move in the secondary bottom plate guide hole 27 on the secondary bottom plate 22 through the secondary arc hole 25, so that the distance between adjacent suction cups 24 changes; Step 4: The screw drive motor 14 starts to work, and the screw drive motor 14 drives the execution telescopic rod 2 to move relative to the telescopic guide tube 3, so that the execution unit 1 approaches the area to be adsorbed and the suction cup 24 is attached to the position to be adsorbed; the negative pressure generating device connected to the suction cup 24 starts to work, so that the suction cup 24 is adsorbed to the position to be adsorbed; Step 5: The robot arm starts to work, so that the adsorbed structure is transferred to the installation position. After the installation is completed, the suction cup 24 is separated from the position to be adsorbed under the action of the connected negative pressure generating device, and the entire mechanism is reset.
[0027] Based on the above embodiments, the following paragraphs will continue to describe in detail the technical features involved and the functions and roles played by the technical features in the present technical solution, so as to help technicians in this field to fully understand the technical solution and reproduce it.
[0028] In the present application, the robot arm connecting seat 9 is used to connect with the robot arm to achieve multi-dimensional adjustment through the robot arm. The robot arm connecting seat 9 is fixed on the fixed plate 8, and the fixed plate 8 is a rectangular block structure.
[0029] In the present application, hinge shafts are provided on both sides of the fixed plate 8, and are hinged to the hinge adjustment plate 7 through the hinge shafts. The hinge adjustment plate 7 is composed of parallel plate bodies, and an adjustment shaft body 13 is fixedly connected between adjacent parallel plate bodies in the hinge adjustment plate 7, and the two ends of the adjustment shaft body 13 are respectively connected to the corresponding plate bodies. The adjustment shaft body 13 is rotatably connected to an adjustment sleeve 10 composed of a sleeve, and the adjustment sleeve 10 is connected to the telescopic end of the extension drive cylinder body 36, and the bottom end of the extension drive cylinder body 36 is hinged to the corresponding hinge seat on the fixed plate 8.
[0030] In the present application, the hinged adjustment plate 7 is hingedly connected with a tube body connecting plate 5 at one end away from the fixed plate 8, and both ends of the tube body connecting plate 5 are respectively in contact with the plate body of the hinged adjustment plate 7 at corresponding positions.
[0031] The tube body connecting plate 5 is connected to a slide rod guide sleeve 12 at the top and bottom ends through an axle body, and the slide rod guide sleeve 12 is arranged parallel to the top and bottom ends of the tube body connecting plate 5 and arranged along the length direction of the tube body connecting plate 5. The slide rod guide sleeve 12 is a hollow cylinder, and the slide rod guide sleeve 12 is sleeved on the posture slide rod 6 and slides along the posture slide rod 6. The ends of the posture slide rod 6 above and below the tube body connecting plate 5 are connected as a whole through the slide rod connecting plate 11. The posture slide rod 6 can be connected to the fixed plate 8 at the middle position through the plate body driving the guide hole to ensure the stability of the posture of the posture slide rod 6 itself.
[0032] In the structure described in the above paragraph, when the extension drive cylinder 36 is in motion, the extension drive cylinder 36 can drive the adjustment sleeve 10 through the telescopic end, and the adjustment sleeve 10 is located on the adjustment shaft body 13, and the hinge adjustment plate 7 is rotated relative to the fixed plate 8 around the hinge axis through the adjustment shaft body 13. The hinge adjustment plate 7 can drive the hinged tube body connection plate 5 to move closer to the sides or the inside, and the tube body connection plate 5 slides along the attitude slide bar 6 through the slide bar guide sleeve 12, and during the sliding process, it is ensured that the end surface of the tube body connection plate 5 connected to the tube body connection base 4 is always parallel to the end surface of the fixed plate 8.
[0033] In the present application, the tube body connection base 4 can make the connection between the tube body connection plate 5 and the telescopic guide tube 3 present a stable state, and the connection position between the tube body connection base 4 and the tube body connection plate 5 can be connected by fasteners to achieve a detachable function.
[0034] In the present application, a screw drive motor 14 is provided on the tube body connecting plate 5, and the drive shaft of the screw drive motor 14 is connected to the drive screw 15. The drive screw 15 driven by the screw drive motor 14 extends into the interior of the telescopic guide tube 3 and is threadedly connected to the execution telescopic rod 2.
[0035] The telescopic guide tube 3 has a chamber for accommodating the telescopic rod 2. The telescopic guide tube 3 is coaxially arranged with the telescopic rod 2. The inner wall of the telescopic guide tube 3 and the outer wall of the telescopic rod 2 are provided with a limiting structure for preventing the telescopic rod 2 from rotating circumferentially, such as a limiting bump and a limiting groove.
[0036] The telescopic actuator 2 is processed with a threaded hole formed by a blind hole at the central axis position, and the telescopic actuator 2 is threadedly connected to a driving screw 15 driven by a screw driving motor 14 through the threaded hole. When the screw driving motor 14 drives the driving screw 15, the driving screw 15 can drive the telescopic actuator 2 through the threaded connection structure, and the telescopic actuator 2 can move relatively in the telescopic guide tube 3 through the coaxially connected telescopic guide tube 3, and due to the anti-circumferential rotation limiting structure set between the telescopic guide tube 3 and the telescopic actuator 2, the movement of the telescopic guide tube 3 and the telescopic actuator 2 in the axial direction is stably realized.
[0037] In the present application, the tail end of the telescopic actuator rod 2 is fixedly connected to a primary bottom plate 17 , which is a circular plate body, and a primary bottom plate guide hole 21 consisting of a plurality of linear bar-shaped through holes is distributed on the primary bottom plate 17 .
[0038] The first-stage bottom plate 17 is fixedly provided with a guide rail 28 on the end surface facing the tube body connecting plate 5, and the guide rail 28 is located on both sides of the first-stage bottom plate guide hole 21. At least one guide slider 31 is respectively provided on the guide rail 28, and the guide slider 31 is located on both sides of the second-stage drive mounting plate 29. The second-stage drive mounting plate 29 is slidably arranged with the guide rail 28 through the guide slider 31.
[0039] In the present application, the telescopic guide tube 3 is also provided with a bottom plate shaft 26 , which is rotatably connected to a primary rotating plate 18 via a bearing structure, and the outer diameter of the primary rotating plate 18 is smaller than the outer diameter of the primary bottom plate 17 .
[0040] A plurality of primary arc holes 19 are distributed on the primary rotating plate 18, and the primary arc holes 19 are arranged corresponding to the primary bottom plate guide holes 21. Secondary guide sleeves 34 are inserted into the primary arc holes 19 and the primary bottom plate guide holes 21. When the primary rotating plate 18 rotates relative to the primary bottom plate 17, the primary arc holes 19 on the primary rotating plate 18 can drive the secondary guide sleeves 34 to move in the primary bottom plate guide holes 21, thereby adjusting the distance between adjacent secondary guide sleeves 34.
[0041] One end of the secondary guide sleeve 34 is connected to the secondary drive mounting plate 29 , and the secondary guide sleeve 34 is fixedly connected to the secondary bottom plate 22 at one end passing through the primary arc hole 19 . The secondary guide sleeve 34 is a hollow cylindrical structure.
[0042] See also Figure 2The primary rotating plate 18 is processed with a plurality of gear teeth structures in the circumferential direction, and a plurality of auxiliary gears 20 and a primary driving wheel 16 are arranged on the primary bottom plate 17. The primary driving wheel 16 is driven by a primary driving motor 37 installed on the primary bottom plate 17. The primary driving motor 37 is located on the side of the primary bottom plate 17 away from the primary rotating plate 18.
[0043] When the primary driving motor 37 drives the primary driving wheel 16 to rotate, the primary driving wheel 16 drives the primary rotating plate 18 through the gear structure meshing therewith, and the primary rotating plate 18 rotates around the bottom plate rotating shaft 26, thereby driving the secondary guide sleeve 34 to move in the primary bottom plate guide hole 21 through the primary arc hole 19.
[0044] In the present application, the execution unit 1 further includes a secondary bottom plate 22, the secondary bottom plate 22 is fixedly connected to the secondary guide sleeve 34, and a through hole communicating with the secondary guide sleeve 34 is provided at the middle position of the secondary bottom plate 22. The secondary bottom plate 22 is a circular plate body, and the driving shaft of the secondary driving motor 30 passes through the secondary bottom plate 22 via the secondary guide sleeve 34 and is connected to the secondary rotating plate 23.
[0045] The secondary bottom plate 22 is processed with a secondary bottom plate guide hole 27 consisting of a plurality of linear bar-shaped through holes, and the secondary rotating plate 23 is processed with a secondary arc hole 25 corresponding to the secondary bottom plate guide hole 27. The gas rod of the suction cup 24 is inserted into the secondary arc hole 25 and the corresponding secondary bottom plate guide hole 27, and the gas rod of the suction cup 24 is connected to the external negative pressure generating device through a pipeline. A suction cup guide seat 32 is provided at the end of the suction cup 24, and the suction cup guide seat 32 has a through hole for the suction cup guide rod 33 to be inserted. The suction cup guide seat 32 is slidably arranged with the suction cup guide rod 33 through the through hole, and a nut can be threadedly connected to the top of the suction cup guide rod 33 to achieve position limiting.
[0046] The tail end of the suction cup guide rod 33 is fixed to the secondary bottom plate seat 35 on the secondary bottom plate 22. The secondary bottom plate seat 35 is a rectangular plate body arranged around the secondary guide sleeve 34.
[0047] The above structure can achieve the relative approach and separation of the suction cup 24 and the gas rod on the secondary rotating plate 23, so as to achieve adaptive adjustment within the single-point operation area.
[0048] Finally, although this specification is described according to implementation methods, not every implementation method contains only one independent technical solution. This narrative method of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment can also be appropriately combined to form other implementation methods that can be understood by those skilled in the art.
Claims
1. An installation manipulator for construction engineering, comprising a manipulator arm connection seat (9) connected to a manipulator arm, the manipulator arm connection seat (9) being fixedly connected to a fixing plate (8), Features: The fixed plate (8) is connected to the tube body connecting plate (5) via a hinged adjustment plate (7). The tube body connecting plate (5) is located on both sides of the fixed plate (8). The fixed plate (8) drives the hinged adjustment plate (7) by extending the drive cylinder (36). An execution unit (1) is installed on the tube body connecting plate (5). The execution unit (1) comprises a primary bottom plate (17). The primary bottom plate (17) is coaxially connected to a primary rotating plate (18) via a bottom plate rotating shaft (26). The primary rotating plate (18) is machined with a plurality of primary arc holes (19). A primary bottom plate guide hole (21) is machined at a position corresponding to the primary arc hole (19). A secondary guide sleeve (34) is slidably arranged in the primary bottom plate guide hole (21) and the primary arc hole (19). One end of the secondary guide sleeve (34) is connected to the secondary drive mounting plate. The secondary driving mounting plate (29) is slidably arranged on a side of the primary bottom plate (17) away from the primary rotating plate (18); the other end of the secondary guide sleeve (34) passes through the primary arc hole (19) and is connected to the secondary bottom plate (22); a secondary rotating plate (23) is coaxially rotatably connected to the secondary bottom plate (22); the rotating shaft of the secondary rotating plate (23) is the output shaft of the secondary driving motor (30); the secondary driving motor (30) is fixed to the secondary driving mounting plate (29); a plurality of secondary arc holes (25) are machined on the secondary rotating plate (23); a secondary bottom plate guide hole (27) is machined on the secondary bottom plate (22) corresponding to the secondary arc holes (25); a gas rod with a suction cup (24) is inserted in the secondary bottom plate guide hole (27) and the secondary arc hole (25); the suction cup (24) is connected to an external gas pipeline.
2. The installation robot for construction engineering according to claim 1, Features: A plurality of auxiliary gears (20) are distributed on the primary bottom plate (17) in the circumferential direction of the primary rotating plate (18), and a primary driving wheel (16) is arranged on the primary bottom plate (17), and the primary driving wheel (16) is connected to a primary driving motor (37) on the primary bottom plate (17); the primary bottom plate (17) is provided with guide rails (28) in parallel on both sides of the primary bottom plate guide hole (21), and a guide slider (31) is slidably arranged on the guide rails (28), and the guide slider (31) is connected to a secondary driving mounting plate (29).
3. The installation robot for construction engineering according to claim 2, Features: The secondary bottom plate (22) is provided with a secondary bottom plate seat body (35) on a side away from the secondary rotating plate (23), and a suction cup guide rod (33) is provided on the secondary bottom plate seat body (35). The suction cup guide rod (33) and the suction cup guide seat (32) are slidably arranged, and the suction cup guide seat (32) is located at the tail end of the suction cup (24) gas rod.
4. The installation robot for construction engineering according to claim 3, Features: The first-level bottom plate (17) is fixedly connected to the telescopic actuator rod (2), the telescopic actuator rod (2) is inserted into the telescopic guide tube (3), the telescopic guide tube (3) is fixedly connected to a tube body connection base (4) at one end away from the first-level bottom plate (17), the tube body connection base (4) is fixedly connected to a tube body connection plate (5), the tube body connection plate (5) is fixedly connected to a screw drive motor (14) at one end away from the tube body connection base (4), the drive shaft of the screw drive motor (14) is connected to a drive screw (15), the drive screw (15) extends into the threaded hole of the telescopic actuator rod (2) and is threadedly connected to the telescopic actuator rod (2); the telescopic actuator rod (2) is provided with a bottom plate rotating shaft (26) at the end facing the first-level rotating plate (18), and the bottom plate rotating shaft (26) is rotationally connected to the first-level rotating plate (18).
5. The installation robot for construction engineering according to claim 4, Features: The fixed plate (8) is hingedly connected to a hinged adjustment plate (7) at both ends via hinge shafts; the hinged adjustment plate (7) is hingedly connected to a tubular connection base (4) at an end away from the fixed plate (8) via a hinge shaft; an adjustment shaft body (13) is arranged inside the hinged adjustment plate (7); an adjustment shaft body (10) is rotatably connected to the adjustment shaft body (13); the adjustment shaft sleeve (10) is connected to the telescopic end of the extension drive cylinder body (36); and the tail end of the extension drive cylinder body (36) is arranged on the hinge seat of the fixed plate (8).
6. The installation robot for construction engineering according to claim 5, Features: The top and bottom ends of the tube body connecting plate (5) are connected to a slide rod guide sleeve (12) via a shaft, respectively. The slide rod guide sleeve (12) is arranged parallel to the end surface of the tube body connecting plate (5). The slide rod guide sleeve (12) is sleeved on the posture slide rod (6) and slides along the posture slide rod (6). The two ends of the posture slide rod (6) are located outside the tube body connecting plate (5), and adjacent posture slide rods (6) are fixedly connected via the slide rod connecting plate (11).
7. A method for installing and operating a construction engineering installation robot according to any one of claims 1 to 6, Features: The installation operation method includes the following steps: Step 1, connecting with the robot arm through the robot arm connecting seat (9), driving the adjustment sleeve (10) and the adjustment shaft body (13) by extending the drive cylinder (36) so that the hinge adjustment plate (7) is expanded or retracted relative to the fixed plate (8), the hinge adjustment plate (7) drives the tube body connecting plate (5) to be expanded or retracted, and the slide rod guide sleeve (12) slides along the posture slide rod (6) to ensure that the end surface of the tube body connecting plate (5) is always parallel to the fixed plate (8); Step 2: The primary driving motor (37) on the primary bottom plate (17) starts to work and drives the primary driving wheel (16) to rotate. The primary driving wheel (16) meshes with the gear structure on the circumference of the primary rotating plate (18) to drive the primary rotating plate (18) to start rotating relative to the primary bottom plate (17). The rotation of the primary rotating plate (18) enables the primary arc hole (19) to drive the secondary guide sleeve (34) to move in the primary bottom plate guide hole (21), thereby adjusting the distance between adjacent secondary guide sleeves (34); Step 3: The secondary drive motor (30) starts to work, and the drive shaft of the secondary drive motor (30) drives the secondary rotating plate (23) to rotate relative to the secondary bottom plate (22). The secondary rotating plate (23) allows the suction cup (24) gas rod to move in the secondary bottom plate guide hole (27) on the secondary bottom plate (22) through the secondary arc hole (25), so that the distance between adjacent suction cups (24) changes. Step 4: The screw drive motor (14) starts to work, and the screw drive motor (14) drives the execution telescopic rod (2) to move relative to the telescopic guide tube (3), so that the execution unit (1) approaches the area to be adsorbed and the suction cup (24) is attached to the position to be adsorbed; the negative pressure generating device connected to the suction cup (24) starts to work, so that the suction cup (24) and the position to be adsorbed are adsorbed; Step 5: The robot arm starts working, so that the adsorbed structure is transferred to the installation position. After the installation is completed, the suction cup (24) is separated from the position to be adsorbed under the action of the connected negative pressure generating device, and the entire mechanism is reset.
Citation Information
Patent Citations
Door and window glass adsorption moving equipment
CN117125486A
Automatic loading and unloading mechanism and method special for vacuum glass
CN118387615A
Sucker type manipulator
CN213592890U
Material suction assembly for manipulator
CN220882364U
Suspension transfer tool of planar body
JP2000007147A