Connecting joint of connecting sections of SC structure and RC structure, construction method and sling system
By using prefabricated modules and steel bars in the construction of SC structure and RC structure, the problem of easy cracking of the connection section is solved, the effect of strong nodes and weak components is achieved, and the service life of the connection section is extended.
Patent Information
- Application Number
- CN202411227043.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-03
- Publication Date
- 2024-12-03
AI Technical Summary
When the SC structure is combined with the RC structure, the connection section is prone to cracking, and after complex stress, it quickly enters plastic deformation and wide-ranging cracks appear, resulting in loss of bearing capacity.
The connecting nodes of prefabricated modules and steel bars are used to fix the steel bars with the steel plates through fasteners to form a one-way or two-way fastening structure, enhance the structural strength of the connection section, and realize the prefabricated modules through specific construction methods and sling systems. Effective hoisting and concrete pouring.
The structural strength of the connecting section is improved, so that the limit tension is less than the standard value of the ultimate strength of the steel bar, extending the service life of the connecting section, and avoiding the problem of first damage to the connecting section in the prior art.
Smart Images

Figure CN119059404A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of building construction, and in particular to a connection node of a connection segment of an SC structure and a RC structure, a construction method and a sling system. Background Art
[0002] The combined construction of SC and RC structures is a type of steel-concrete structure. During construction, the two structures intersect vertically at the connecting section. The existing technology addresses this connecting section as follows: the SC steel plates extend to the outer edge of the RC wall and are capped with end steel plates. The RC horizontal rebar is then directly anchored into the SC wall according to the required anchor length. This structure presents a problem: the connecting section is located at the edge of the core connection area, subject to complex forces and a very short elastic stress phase. When subjected to slightly greater forces, the connecting section rapidly undergoes plastic deformation, resulting in extensive cracks. Ultimately, the connecting section separates from the core connection area with large cracks, resulting in a loss of bearing capacity. Summary of the Invention
[0003] The technical problem to be solved by the present invention is that the connection section between the existing SC structure and the RC structure is prone to cracking. The purpose is to provide a connection node, construction method and sling system for the connection section between the SC structure and the RC structure to solve the above technical problem.
[0004] The present invention is achieved through the following technical solutions:
[0005] In a first aspect, the present invention provides a connection node for a connection section of an SC structure and a RC structure, comprising a prefabricated module and steel bars, wherein the prefabricated module comprises a steel plate, and the steel bars are passed through and fixed to the steel plate;
[0006] The connection between the steel bar and the steel plate has two opposite sides, and a fastener is provided on at least one of the sides. Accordingly, when there is one fastener, the steel bar and the steel plate form a unidirectional fastening structure, and when there are two fasteners, the steel bar and the steel plate form a bidirectional fastening structure.
[0007] In one possible design, in a one-way fastening structure, the fastener is located on the outward-facing side of the steel plate;
[0008] The fasteners are selected from nuts or welding layers. When the fasteners are selected from nuts, the nuts are set on the steel bars through washers, and the steel bars are provided with matching threads. When the fasteners are selected from welding layers, the solder melts and solidifies to form the welding layer.
[0009] In a second aspect, the present invention provides a construction method of an SC structure and an RC structure, comprising the following steps:
[0010] Steel structure construction;
[0011] Connection segment connection node processing;
[0012] Rest of the structure construction;
[0013] The connection node of the connection section of the SC structure and the RC structure is used in the step of connection section connection node processing so that the ultimate tensile force of the connection node is less than the tensile force fstkAs when the steel bar reaches the ultimate strength standard value.
[0014] In one possible design, the steps in steel structure construction are:
[0015] If one of the SC structure and the RC structure is located above the other, it shall be constructed in the order of foundation, lower steel structure and upper steel structure;
[0016] If the SC structure and the RC structure are located on the same construction plane, the foundation should be constructed first, and then the steel structures of the SC structure and the RC structure should be constructed simultaneously.
[0017] In one possible design, the steel structure construction of the RC structure includes the following steps: determining the location of the steel bars; installing the steel bars; and checking and adjusting the location of the steel bars.
[0018] The steel structure construction of SC structure includes the following steps: installation of embedded parts; installation of supporting fixtures, re-measurement of fixture beam elevation and levelness; welding operation; hoisting of prefabricated modules;
[0019] Among them, when the SC structure is located above the foundation, the embedded parts are installed before pouring the foundation concrete; when the SC structure is located above the RC structure, the embedded parts are embedded in the steel structure of the RC structure, and the supporting tooling is installed before the upper steel structure of the RC structure is installed.
[0020] In one possible design, the prefabricated module lifting includes the following steps: selecting lifting equipment; verifying the bearing capacity of the foundation along the lifting equipment's travel path; connecting the lifting equipment to the sling system; and lifting and securing the prefabricated module.
[0021] In a possible design, the step of connecting segments and connecting nodes includes the following steps:
[0022] Connection: The steel bars are passed through the steel plates;
[0023] Fastening: fastening the steel bars to the steel plates with fasteners;
[0024] Among them, if the connection section between the SC structure and the RC structure is a horizontal connection section, the steel bars are connected to the steel plates through a one-way fastening structure;
[0025] If the connection section between the SC structure and the RC structure is a vertical connection section, the steel bars are connected to the steel plates through a bidirectional fastening structure.
[0026] In one possible design, when the steel bars are connected to the steel plates through a bidirectional fastening structure, the steel bars and the steel plates constitute a prefabricated module, and the prefabricated module is installed to the connection section during the steel structure construction step.
[0027] In one possible design, the remaining structural construction includes the remaining structural construction of the RC structure and the remaining structural construction of the SC structure;
[0028] The remaining structural construction of the RC structure includes the following steps: formwork installation; foam strip caulking; fixing; formwork accuracy adjustment; concrete pouring;
[0029] The remaining structural construction of the SC structure includes the following steps:
[0030] Pouring: Use the horizontal layered integral push-casting method to pour concrete, and insert an exhaust pipe connected to the atmosphere;
[0031] Monitoring: Observe the concrete flow through an endoscope or handheld reflector; monitor the liquid level through a liquid level alarm; the side plate deformation error on both sides of the SC structure is (H / 2500+10)mm, the layer thickness is no more than 457mm, and each layer of concrete is covered with the next layer of concrete before initial setting;
[0032] Repeat the above steps until pouring is completed;
[0033] Wherein, H is the height of the SC structure side plate;
[0034] If the connection section is a one-way fastening structure, and the one-way fastening structure uses nuts, and a protector is provided on the nut, and the layer height is lower than the height of the nut during pouring, the protector shall be removed and the nut shall be tightened before pouring the concrete of the next layer.
[0035] In a third aspect, the present invention provides a sling system for the SC structure and RC structure construction method, comprising a main sling, a main sling beam, a secondary sling, a secondary sling beam, and a sling arranged in sequence from top to bottom;
[0036] The upper end of the main sling is connected to the boom of the lifting equipment, and the lower end of the main sling is connected to the main beam; and there are at least two main slings;
[0037] The main lifting beam connects the main and secondary lifting cables;
[0038] The upper end of the secondary sling is connected to the main sling beam, and the lower end of the secondary sling is connected to the sling through the secondary sling beam. The middle part of the sling is passed through the secondary sling beam, and the two ends of the sling are drooped.
[0039] There are at least two secondary lifting beams, each of which is connected to at least two secondary lifting ropes and at least one lifting rope, and the corresponding secondary lifting ropes, secondary lifting beams and lifting ropes form a lifting group. Accordingly, the main lifting beam is connected to at least two lifting groups.
[0040] Compared with the prior art, the present invention has the following advantages and beneficial effects:
[0041] The steel plate is connected to the steel bar with a large number of connection nodes, which increases the structural strength of the connection section. The ultimate tensile force of the connection node is less than the tensile force fstkAs when the steel bar reaches the standard value of the ultimate strength, achieving the purpose of "strong node, weak component" and effectively solving the problem of the connection section being damaged first in the prior art. BRIEF DESCRIPTION OF THE DRAWINGS
[0042] In order to more clearly illustrate the technical solutions of the exemplary embodiments of the present invention, the following briefly introduces the drawings required for use in the examples. It should be understood that the following drawings only illustrate certain embodiments of the present invention and should not be considered as limiting the scope. A person of ordinary skill in the art can also derive other relevant drawings based on these drawings without inventive effort. In the drawings:
[0043] Figure 1 A flow chart of a construction method for SC and RC structures.
[0044] Figure 2 Schematic diagram of RC structural steel bar installation.
[0045] Figure 3 Schematic diagram of the SC structure.
[0046] Figure 4 It is a structural diagram of the horizontal connection segment connection node.
[0047] Figure 5 This is a structural diagram of the vertical connection segment connection node.
[0048] Figure 6 This is a connection diagram of the prefabricated module lifting system.
[0049] Figure 7 This is a structural diagram of the RC structure template.
[0050] Markings and corresponding parts names in the accompanying drawings:
[0051] 1. SC structure; 101. Steel plate; 102. Stiffener plate; 103. Embedded parts; 104. Support tooling; 2. RC structure; 201. Rebar; 202. Formwork; 203. Tie screw; 3. Fasteners; 301. Nut; 302. Washer; 4. Lifting equipment; 5. Lifting rigging system; 501. Main sling; 502. Main lifting beam; 503. Secondary sling; 504. Secondary lifting beam; 505. Sling; 6. Hanging platform. DETAILED DESCRIPTION
[0052] In order to make the objectives, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with examples and drawings. The exemplary embodiments of the present invention and their descriptions are only used to explain the present invention and are not intended to limit the present invention.
[0053] Example 1:
[0054] like Figure 2 、 4 As shown in FIG5 , a connection node between a SC structure and a RC structure connection segment includes a prefabricated module and a steel bar 201;
[0055] The prefabricated module includes a steel plate 101, and steel bars 201 are passed through and fixed on the steel plate 101;
[0056] The end of the steel bar 201 is configured as a connection end for connecting to the steel plate 101;
[0057] The connection between the steel bar 201 and the steel plate 101 has two opposite sides, and a fastener 3 is provided on at least one of the sides. Accordingly, when there is one fastener 3, the steel bar 201 and the steel plate 101 form a unidirectional fastening structure, and when there are two fasteners 3, the steel bar 201 and the steel plate 101 form a bidirectional fastening structure.
[0058] In the connection nodes of the connection section between the SC structure and the RC structure, the steel plate 101 is connected to the steel bar 201, and the number of connection nodes is large, thereby increasing the structural strength of the connection section. This makes the ultimate tensile force of the connection node smaller than the tensile force fstkAs when the steel bar 201 reaches the standard value of the ultimate strength, thereby achieving the goal of "strong node, weak component" and effectively solving the problem of the connection section being damaged first in the prior art.
[0059] At the same time, the connection node forms a one-way fastening structure and a two-way fastening structure by using different numbers of fasteners 3, which are respectively adapted to different types of connection segments, thereby expanding the scope of use and improving practicality.
[0060] Preferably, in the one-way fastening structure, the fastener 3 is located on the outward side of the steel plate 101. Based on the above design, the thickness of the concrete layer is controlled during pouring so that the fastener 3 is located outside the concrete. After the concrete is poured, the tightness of the fastener 3 is adjusted to ensure the reliability of the one-way fastening.
[0061] Preferably, the connecting end of rebar 201 undergoes the following processing steps: hot upsetting, or quenching and tempering; and extrusion to form a threaded end. Based on this design, the microstructure and surface properties of the end of rebar 201 are modified to improve the mechanical properties and reliability of the end, ensuring that the performance of rebar 201 meets the required performance requirements. After the threaded end is formed, the end of rebar 201 acquires an external thread, which not only increases the contact area with the wall but also serves to fasten the steel plate 101 to the rebar 201.
[0062] Optionally, the fastener 3 is a nut 301 or a welding layer;
[0063] When the fastener 3 uses a nut 301, the nut 301 is set on the steel bar 201 through the washer 302. The nut 301 uses a fine-thread nut with a thickness greater than the standard size. The length of the connecting end of the steel bar 201 passing through the nut 301 is less than 2 threads. In the unidirectional fastening structure, the length of the connecting end of the steel bar 201 is not less than 60 mm. In the bidirectional fastening structure, the length of the connecting end of the steel bar 201 is not less than 154 mm. Accordingly, the steel bar 201 is provided with an adaptive thread.
[0064] When the fastener 3 is a welding layer, the solder melts and solidifies to form the welding layer.
[0065] Based on the above design, the tightening degree of nut 301 can be adjusted by twisting, which is more flexible to use. After the weld layer is formed, no adjustment is required, which is more convenient to use. Those skilled in the art can choose according to the actual construction situation. Furthermore, nut 301 and solder can be selected from any suitable existing products, which has a wide range of choices and good practicality.
[0066] Example 2:
[0067] This embodiment, based on the first embodiment, illustrates the construction of the combined SC structure 1 and the RC structure 2. Specifically:
[0068] like Figure 1-Figure 7 As shown, a construction method of SC structure and RC structure includes the following steps:
[0069] S100 steel structure construction;
[0070] S200 connection segment connection node processing;
[0071] S300 rest of the structure construction;
[0072] The connection node of the connection section of the SC structure and the RC structure is used in the step of connection section connection node processing so that the ultimate tensile force of the connection node is less than the tensile force fstkAs when the steel bar 201 reaches the ultimate strength standard value.
[0073] Both the SC structure 1 and the RC structure 2 are steel-concrete structures. During construction, the steel structure is constructed first, and then the concrete is poured. The construction method of the SC structure and the RC structure is also carried out on the basis of the above-mentioned construction method, that is, the steel structure is constructed first, the connection node is processed at the connection section where the SC structure 1 and the RC structure 2 intersect, and finally the concrete is poured.
[0074] At the same time, by using the connection node of the connection section of the SC structure and the RC structure for the connection section connection node processing in step S200, the ultimate tensile force of the connection node is achieved to be less than the tensile force fstkAs when the steel bar 201 reaches the ultimate strength standard value, achieving the purpose of "strong node, weak component", and effectively solving the problem of the connection section being destroyed first in the prior art.
[0075] Wherein, for step S100, during the steel structure construction in step S100:
[0076] If one of the SC structure 1 and the RC structure 2 is located above the other, the construction shall be carried out in the order of foundation, lower steel structure and upper steel structure;
[0077] If the SC structure 1 and the RC structure 2 are located on the same construction plane, the foundation is constructed first, and then the steel structures of the SC structure 1 and the RC structure 2 are constructed simultaneously.
[0078] Based on the above design scheme, that is, for different forms of the combination of SC structure 1 and RC structure 2, construction is carried out in sequence from bottom to top. If there are structures at the same height, that is, the SC structure 1 and the RC structure 2 are located on the same construction plane, the steel structures of the SC structure 1 and the RC structure 2 are constructed simultaneously, thereby accelerating the construction progress and improving construction efficiency.
[0079] Specifically, the steel structure construction of RC Structure 2 includes the following steps: determining the location of rebar 201; installing rebar 201; and verifying and adjusting the location of rebar 201. Based on the above design, rebar 201 is located and installed according to construction requirements. The location of rebar 201 is then verified and adjusted using any suitable equipment and methods to ensure the accurate positioning of rebar 201 in RC Structure 2.
[0080] Specifically, the steel structure construction of SC structure 1 includes the following steps: installation of embedded parts 103; installation of support fixtures 104, re-measurement of fixture beam elevation and levelness; welding operation; hoisting of prefabricated modules;
[0081] When the SC structure 1 is located above the foundation, the embedded parts 103 are installed before pouring the foundation concrete; when the SC structure 1 is located above the RC structure 2, the embedded parts 103 are embedded in the steel structure of the RC structure 2. Before the upper steel structure of the RC structure 2 is installed, the support tooling 104 is installed.
[0082] Based on the above design, any suitable existing models of embedded components 103 and support fixtures 104 can be selected, provided they meet construction requirements. Furthermore, the SC structure 1 is constructed first with embedded components 103 and support fixtures 104 at the bottom to form a stable foundation, before moving upward to the above-ground portion to ensure construction safety.
[0083] When SC structure 1 is located above RC structure 2, the installation of support fixture 104 should precede the installation of upper reinforcement 201 of RC structure 2 to minimize obstructions and improve construction efficiency, taking into account the impact of cross-construction. After installation, the elevation and levelness of the fixture beam should be remeasured to ensure the installation accuracy of support fixture 104 and, in turn, the subsequent installation of prefabricated modules.
[0084] In a possible implementation, the prefabricated module hoisting includes the following steps: selecting a lifting device 4; verifying the bearing capacity of the foundation along the route of the lifting device 4; connecting the lifting device 4 to the sling system 5; and hoisting and fixing the prefabricated module.
[0085] Based on the above design, any suitable commercially available equipment can be used for lifting equipment 4, and any suitable existing method can be used to verify the bearing capacity of the foundation along the travel route. The steel structure of SC structure 1 is prefabricated in the factory and transported to the construction site. It is then lifted by lifting equipment 4 and secured to support fixtures 104. This reduces on-site work, speeds up construction progress, and shortens the construction period.
[0086] It is easy to understand that, on the basis of ensuring processing quality, the prefabricated modules can be made of any suitable materials and constructed into any suitable shape.
[0087] Optionally, the prefabricated module includes two opposing side panels, each provided with a steel plate 101. The prefabricated module may also be provided with a stiffening plate 102, channel steel, and other components to accommodate various construction requirements. Generally, the side panels are made of steel plates of any suitable specification. Accordingly, several prefabricated modules are sequentially connected to form the SC structure 1.
[0088] Regarding step S200, the process of connecting segments and connecting nodes in step S200 includes the following steps:
[0089] S210 connection: steel bars 201 are vertically passed through the steel plate 101;
[0090] S220 Fastening: Fix the steel bar 201 to the steel plate 101 by means of the fastener 3;
[0091] Wherein, if the connection section between the SC structure 1 and the RC structure 2 is a horizontal connection section, the steel bar 201 is connected to the steel plate 101 through a one-way fastening structure;
[0092] If the connection section between the SC structure 1 and the RC structure 2 is a vertical connection section, the steel bar 201 is connected to the steel plate 101 through a bidirectional fastening structure.
[0093] Based on the above design, the intersection of SC structure 1 and RC structure 2 lies on the same plane and can be configured as any suitable flat or curved surface, representing the horizontal connecting segment. Similarly, the intersection of SC structure 1 and RC structure 2 has a certain height and can be configured as any suitable flat or curved surface, representing the vertical connecting segment. Therefore, the connecting segment between SC structure 1 and RC structure 2 can be configured in any suitable shape, and those skilled in the art will select a one-way or two-way fastening structure depending on whether the connecting segment is horizontal or vertical.
[0094] It is easy to understand that for the intersection of the horizontal connecting section and the vertical connecting section, the intersection part can be regarded as the continuation of the horizontal connecting section, that is, this part is fixed by the unidirectional fastening structure, and the remaining part is fixed by the bidirectional fastening structure.
[0095] In the horizontal connection section, the end of the steel bar 201 connected to the steel plate 101 is arranged vertically, and the weight of the steel bar 201 itself can cooperate with the fastener 3 to achieve a better fastening effect. Conversely, in the vertical connection section, the end of the steel bar 201 connected to the steel plate 101 is arranged horizontally, and the fastening force is applied only by the fastener 3. To ensure the fastening effect and prevent the steel plate 101 from tilting, the vertical connection section adopts a bidirectional fastening structure.
[0096] Preferably, when the steel bars 201 are connected to the steel plate 101 through a bidirectional fastening structure, the steel bars 201 and the steel plate 101 constitute a prefabricated module, and the prefabricated module is installed to the connection section during the steel structure construction step.
[0097] Based on the above design, in a bidirectional fastening structure, regardless of whether fastener 3 is a nut 301 or a welded layer, construction is difficult and can slow down construction progress due to limited construction space, especially when one fastener 3 is obscured by the steel plate 101, and due to the large number of fasteners 3. Therefore, the bidirectional fastening structure is preferably formed into a prefabricated module, forming a relatively closed modular structure. The vertical connecting section is installed during the hoisting of the prefabricated module to improve construction efficiency and reduce the workload of workers.
[0098] Regarding step S300, the remaining structural construction of S300 includes the remaining structural construction of the RC structure 2 and the remaining structural construction of the SC structure 1;
[0099] The remaining structural construction of RC structure 2 includes the following steps: formwork 202 installation; foam stripping for caulking; securing; adjusting the accuracy of formwork 202; and pouring concrete. Based on the above design, formwork 202 can be made from any suitable model of standard formwork. During on-site assembly, formwork 202 must be assembled strictly according to the numbering and installation sequence specified in the panel layout diagram. Foam stripping is used to caulk the joints between adjacent formworks 202. During securing, wedge-shaped steel plates 101 are used to connect the channel steel cross ribs on the formworks 202 to enhance their integrity. The accuracy of formwork 202 is then checked and adjusted according to construction requirements, and finally, concrete is poured.
[0100] And as Figure 7 As shown, two sets of formwork 202 are provided. The two sets of formwork 202 are arranged opposite each other and connected by tension screws 203. A pouring trough for pouring concrete is formed between the two sets of formwork 202. If the formwork 202 is located at the edge of the foundation, a hanging platform 6 is provided on the outside of the formwork 202 to facilitate the passage of workers and provide additional support structure to ensure the strength and stability of the formwork 202.
[0101] The remaining structural construction of SC Structure 1 includes the following steps:
[0102] Pouring: Use the horizontal layered integral push-casting method to pour concrete, and insert an exhaust pipe connected to the atmosphere;
[0103] Monitoring: Observe the concrete flow through an endoscope or handheld reflector; monitor the liquid level through a liquid level alarm. The deformation error of the side panels on both sides of SC structure 1 is (H / 2500+10)mm, the layer thickness is no more than 457mm, and each layer of concrete is covered with the next layer of concrete before initial setting.
[0104] Repeat the above steps until pouring is completed;
[0105] Where H is the height of the side panel of SC structure 1;
[0106] If the connection section is a one-way fastening structure, and the one-way fastening structure uses nut 301, a protective object is provided on the nut 301, and the layer height is lower than the height of the nut 301 during pouring; before pouring the concrete of the next layer, remove the protective object and tighten the nut 301.
[0107] Based on the above design, the horizontal layered integral push-casting method follows the principles of layered pouring and vibrating. After inserting the exhaust pipe, pressure injection and communicating vessels are used to generate pressure using the concrete's own weight, filling the entire enclosed area with concrete. An endoscope or handheld reflector allows for indirect observation of the concrete's internal flow. Utilizing the electrical conductivity of concrete, a level alarm is used to monitor the concrete's position from the outside. This synergy prevents the concrete from being loosely poured and difficult to observe.
[0108] Furthermore, if the connection section has a one-way fastening structure and the one-way fastening structure uses nut 301, the tightness of nut 301 will be affected after concrete pouring. Therefore, nut 301 should be tightened again after concrete pouring to ensure the tightness of nut 301. At the same time, to prevent concrete from adhering to the threads of steel bar 201, a protective material is provided. Optionally, the protective material includes but is not limited to a protective cloth, a protective bag, and a protective cover.
[0109] Example 3:
[0110] Based on Example 2, this embodiment provides a sling system for the hoisting of the prefabricated module in Example 2, so as to realize the hoisting of the prefabricated module. Specifically, Figure 6 As shown, the sling system used for the SC structure and RC structure construction method includes a main sling 501, a main sling beam 502, a secondary sling 503, a secondary sling beam 504 and a sling 505 arranged in sequence from top to bottom;
[0111] The upper end of the main sling 501 is connected to the boom of the lifting equipment 4, and the lower end of the main sling 501 is connected to the main beam 502; and the main sling 501 is provided with at least two;
[0112] The main lifting beam 502 connects the main lifting rope 501 and the secondary lifting rope 503;
[0113] The upper end of the secondary sling 503 is connected to the main sling beam 502, and the lower end of the secondary sling 503 is connected to the sling 505 through the secondary sling beam 504. The middle part of the sling 505 is passed through the secondary sling beam 504, and the two ends of the sling 505 are drooped.
[0114] There are at least two secondary lifting beams 504, and each secondary lifting beam 504 is connected to at least two secondary lifting ropes 503 and at least one lifting rope 505, and the corresponding secondary lifting ropes 503, secondary lifting beams 504 and lifting ropes 505 form a lifting group. Accordingly, the main lifting beam 502 is connected to at least two lifting groups.
[0115] Based on the above design scheme, the upper ends of multiple main slings 501 are connected to the boom of the lifting equipment 4 to form a conical structure with a small top and a large bottom. At the same time, the main slings 501 are connected to multiple lifting groups through the main lifting beam 502. The lifting groups are connected to the prefabricated modules, and each lifting group has multiple connection points for connecting the prefabricated modules, which helps to improve the stability of the connection, the smoothness and safety of the lifting.
[0116] It will be readily understood that, depending on the weight, shape, and other parameters of the prefabricated module, those skilled in the art can arbitrarily increase or decrease the number of main slings 501, the number of lifting groups, and the number of secondary slings 503 and slings 505 within each lifting group. Preferably, the main slings 501 and secondary slings 503 are each connected to the ends of corresponding lifting beams to increase the load-bearing capacity of the sling system 5. Optionally, the slings 505 are detachably connected to the lifting lugs of the prefabricated module via shackles.
[0117] Example 4:
[0118] This embodiment, based on Embodiments 1-3, provides an actual construction scenario: In the prior art, the nuclear island is constructed using an RC structure 2. However, a large amount of steel bars 201 are used during the construction of the RC structure 2. Considering the construction sequence, space must be reserved on site before construction for a temporary storage yard to store the steel bars 201. During construction, the steel bars 201 need to be transported back and forth and bundled. After construction, construction waste must also be cleaned up.
[0119] Furthermore, existing rebar 201 is mostly large-diameter, 40mm in diameter. Each piece is heavy, making it difficult to transport and posing significant safety risks. Manual handling in confined working areas is also slow. Bundling rebar 201 is a complex and labor-intensive process, and due to the large amount of rebar 201 used, the construction environment and the interference of overlapping operations can lead to low rebar tying efficiency and slow construction progress.
[0120] Based on this, the switch to the SC structure 1 and RC structure 2 construction method not only solves the problem of premature failure of the connection nodes in the existing SC structure 1 and RC structure 2 combination, but also utilizes the SC structure 1, which is prefabricated in the factory and assembled on-site. This reduces on-site work while ensuring component quality, thus helping to improve construction efficiency. Furthermore, due to the significant reduction in the amount of rebar 201 used, the construction space requirements for RC structure 2 are reduced, and the workload for processes such as rebar 201 handling and bundling is reduced, effectively improving construction efficiency and achieving the goal of shortening the construction period. Furthermore, the generation of construction waste from rebar 201 operations is reduced, contributing to safe and civilized construction on the construction site.
[0121] The specific implementation methods described above further illustrate the objectives, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above description is only a specific implementation method of the present invention and is not intended to limit the scope of protection of the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.
Claims
1. A connection node for connecting a SC structure and a RC structure, characterized in that: including prefabricated modules and steel bars (201); The prefabricated module comprises a steel plate (101), and a steel bar (201) is passed through and fixed on the steel plate (101); The end of the steel bar (201) is configured as a connection end for connecting to the steel plate (101); The connection between the steel bar (201) and the steel plate (101) has two opposite sides, and a fastener (3) is provided on at least one of the sides. Accordingly, when there is one fastener (3), the steel bar (201) and the steel plate (101) form a unidirectional fastening structure, and when there are two fasteners (3), the steel bar (201) and the steel plate (101) form a bidirectional fastening structure.
2. The SC structure and RC structure connecting segment connection node according to claim 1, characterized in that: In the one-way fastening structure, the fastener (3) is located on the outward side of the steel plate (101); The connecting end of the steel bar (201) is processed by the following steps: hot upsetting, or quenching and tempering; extrusion to form a wire head; The fastener (3) is a nut (301) or a welding layer. When the fastener (3) is a nut (301), the nut (301) is arranged on the steel bar (201) through a washer (302). The nut (301) is a fine-thread nut with a thickness greater than the standard size. The length of the connecting end of the steel bar (201) passing through the nut (301) is less than 2 threads. In a one-way fastening structure, the length of the connecting end of the steel bar (201) is not less than 60 mm. In a two-way fastening structure, the length of the connecting end of the steel bar (201) is not less than 154 mm. Accordingly, the steel bar (201) is provided with an adapted thread. When the fastener (3) is a welding layer, the solder is melted and solidified to form the welding layer.
3. A construction method of SC structure and RC structure, characterized in that: The following steps are involved: Steel structure construction; Connection segment connection node processing; Other structural construction; Wherein, the connection node of the connection section of the SC structure and the RC structure described in claim 1 or 2 is used in the step of connection section connection node processing so that the ultimate tensile force of the connection node is less than the tensile force fstkAs when the steel bar (201) reaches the ultimate strength standard value.
4. The SC structure and RC structure construction method according to claim 3, characterized in that: Steps in steel structure construction: If one of the SC structure (1) and the RC structure (2) is located above the other, the construction shall be carried out in the order of foundation, lower steel structure and upper steel structure; If the SC structure (1) and the RC structure (2) are located on the same construction plane, the foundation is constructed first, and then the steel structures of the SC structure (1) and the RC structure (2) are constructed simultaneously.
5. The SC structure and RC structure construction method according to claim 4, characterized in that: The steel structure construction of the RC structure (2) includes the following steps: Determine the position of the steel bar (201); install the steel bar (201); check and adjust the position of the steel bar (201). The steel structure construction of the SC structure (1) includes the following steps: installation of embedded parts (103); installation of supporting fixtures (104), re-measurement of fixture crossbeam elevation and horizontality; welding operation; hoisting of prefabricated modules; When the SC structure (1) is located above the foundation, the embedded parts (103) are installed before pouring the foundation concrete; when the SC structure (1) is located above the RC structure (2), the embedded parts (103) are embedded in the steel structure of the RC structure (2), and before the upper steel structure of the RC structure (2) is installed, the supporting tooling (104) is installed.
6. The SC structure and RC structure construction method according to claim 5, characterized in that: The prefabricated module hoisting comprises the following steps: selecting a lifting device (4); verifying the bearing capacity of the foundation of the route where the lifting device (4) travels; connecting the lifting device (4) to a sling system (5); and hoisting and fixing the prefabricated module.
7. The SC structure and RC structure construction method according to claim 3, characterized in that: Step connection segment connection node processing The following steps are involved: Connection: The steel bar (201) is passed through the steel plate (101); Fastening: fixing the steel bar (201) to the steel plate (101) by means of a fastener (3); Wherein, if the connection section between the SC structure (1) and the RC structure (2) is a horizontal connection section, the steel bar (201) is connected to the steel plate (101) through a one-way fastening structure; If the connection section between the SC structure (1) and the RC structure (2) is a vertical connection section, the steel bar (201) is connected to the steel plate (101) through a bidirectional fastening structure.
8. The SC structure and RC structure construction method according to claim 7, characterized in that: When the steel bar (201) is connected to the steel plate (101) through the bidirectional fastening structure, the steel bar (201) and the steel plate (101) form a prefabricated module, and the prefabricated module is installed to the connection section in the step of steel structure construction.
9. The SC structure and RC structure construction method according to claim 1, characterized in that: The remaining structural construction includes the remaining structural construction of the RC structure (2) and the remaining structural construction of the SC structure (1); The remaining structural construction of the RC structure (2) includes the following steps: installation of the formwork (202); caulking of the foam strips; fixing; precision adjustment of the formwork (202); concrete pouring; The remaining structural construction of the SC structure (1) includes the following steps: Casting: Use the horizontal layered integral push-casting method to cast concrete, and insert an exhaust pipe connected to the atmosphere; Monitoring: Observe the flow of concrete through an endoscope or handheld reflector; monitor the liquid level through a liquid level alarm; the deformation error of the side panels on both sides of the SC structure (1) is (H / 2500+10) mm, the layer thickness is not more than 457 mm, and each layer of concrete is covered with the next layer of concrete before initial setting; Where H is the height of the side plate of the SC structure (1); Repeat the above steps until pouring is completed; If the connection section is a one-way fastening structure, and the one-way fastening structure uses a nut (301), a protective material is provided on the nut (301), and the layer height is lower than the height of the nut (301) during pouring; before pouring the concrete of the next layer, the protective material is removed and the nut (301) is tightened.
10. A sling system for the SC structure and RC structure construction method according to any one of claims 3 to 9, characterized in that: It comprises a main sling (501), a main sling beam (502), a secondary sling (503), a secondary sling beam (504) and a sling (505) which are arranged in sequence from top to bottom; The upper end of the main sling (501) is connected to the boom of the lifting device (4), and the lower end of the main sling (501) is connected to the main suspension beam (502); and the main sling (501) is provided with at least two; The main suspension beam (502) is connected to the main suspension rope (501) and the secondary suspension rope (503); The upper end of the secondary sling (503) is connected to the main sling beam (502), the lower end of the secondary sling (503) is connected to the sling (505) through the secondary sling beam (504), the middle part of the sling (505) is passed through the secondary sling beam (504), and the two ends of the sling (505) are drooped; At least two secondary lifting beams (504) are provided, and each secondary lifting beam (504) is respectively connected to at least two secondary lifting ropes (503) and at least one lifting rope (505), and the corresponding secondary lifting ropes (503), secondary lifting beams (504) and lifting ropes (505) form a lifting group. Correspondingly, the main lifting beam (502) is connected to at least two lifting groups.