Device for synchronous construction of double straining beams

By designing devices for synchronous construction of dual-system beams, including pier columns, clasp hoops, lifting mechanisms and horizontal mechanisms, the problems of long construction time and waste of manpower in the existing technology are solved, and efficient synchronous construction of dual-system beams is achieved.

CN119061804APending Publication Date: 2024-12-03SHANXI CONSTR ENG GROUP CORP
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411486712.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-23
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

In the prior art, the construction of double-system beams needs to be completed and solidified one by one, resulting in a long construction time and a lot of manpower, and the inability to achieve synchronous construction.

Method used

A dual-telephone beam synchronous construction device is designed, including pier columns, clasp hoops, lifting mechanisms, rotating plates, overlapping rods and horizontal mechanisms. Through components such as electric push rods, balance balls and elastic plates, the system is realized for high and low positions. The beam formwork is supported and adjusted simultaneously to shorten the construction time.

Benefits of technology

The synchronous construction of double-team beams has been achieved, which significantly shortens construction time and saves manpower, and reduces the horizontal error ofteam beam construction through the design of horizontal mechanisms.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119061804A_ABST
    Figure CN119061804A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of building construction, in particular to a device for synchronous construction of double straining beams. The technical problems that in the prior art, double straining beams are long in construction time, and a large amount of manpower needs to be consumed are solved. According to the technical scheme, the device comprises a hoop and the like; a hoop is installed on the pier column, a rotating plate I is arranged on the hoop, the lifting mechanism is provided with the rotating plate I, a rotating plate II is hinged to one end of the rotating plate I, the lifting mechanism is used for providing movement of the rotating plate I and the rotating plate II, a storage frame is fixedly connected to the rotating plate I and the rotating plate II, and a plurality of lap joint rods are slidably connected into the storage frame. An elastic plate is connected into the storage rack, makes contact with the lap joint rod and is used for providing movement of the lap joint rod. Through the design of the lifting mechanism, a construction template of a straining beam at a low position can be supported, and meanwhile, a construction template of a straining beam at a high position can be supported.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a device for synchronous construction of double tie beams. Background Art

[0002] With the development of the times, the scale of bridge construction is getting larger and larger. Double piers are often used for support in the construction structure of bridges. Tie beams need to be built between the double piers. Connecting the piers through tie beams can make the piers more stable.

[0003] When the two piers are relatively high, double tie beams need to be built to make the piers more stable. In the prior art, when constructing double tie beams, only one of the tie beams can be constructed first, and the other tie beam can be constructed only after the construction is completed and solidified, which requires a lot of time and manpower. Summary of the invention

[0004] In order to overcome the shortcomings of the prior art that the construction of double-tie beams takes a long time and is time-consuming and labor-intensive, the technical problem of the present invention is to provide a device for synchronous construction of double-tie beams.

[0005] The technical implementation scheme of the present invention is as follows: it includes a pier column, a clamp is installed on the pier column, a lifting mechanism is arranged on the clamp, and also includes a rotating plate I, a rotating plate I is arranged on the lifting mechanism, a rotating plate II is hinged at one end of the rotating plate I, and the lifting mechanism is used to provide the rotating plate I and the rotating plate II with movement, a storage rack is fixedly connected to the rotating plate I and the rotating plate II, a plurality of lap rods are slidably connected in the storage rack, an elastic plate is connected in the storage rack, the elastic plate is in contact with the lap rod, and the elastic plate is used to provide the lap rod with movement, a special-shaped groove is opened on one side of the rotating plate I and the rotating plate II, and a sliding connection is installed in the special-shaped groove of the rotating plate I and the rotating plate II. A sliding seat is connected, and a plug-in baffle is slidably connected in the special-shaped grooves of the rotating plate I and the rotating plate II, and the plug-in baffle is in contact with the sliding seat, and the plug-in baffle is used to limit the position of the sliding seat, and an electric push rod I is hinged on the sliding seat, and a guide frame is installed on one side of the storage rack, and a convex shaft is fixedly connected to the telescopic end of the electric push rod I, and the convex shaft of the telescopic end of the electric push rod I is clamped in the guide frame and slides in the guide frame, and the electric push rod I is used to provide the lap rod with activity, and a fixing ring is clamped at the top of the lap rod, and an arc plate is slidably connected in the fixing ring, and the arc plate is in contact with the pier, and a horizontal mechanism is provided on the hoop, and the horizontal mechanism is used to provide the lifting mechanism to maintain the level.

[0006] Preferably, it further comprises a push plate, the telescopic end of the electric push rod I is fixedly connected with the push plate, one side of the plurality of overlapping rods is provided with a plug hole, the push plate is inserted into the plug hole, the push plate is used to limit the position of the plurality of overlapping rods, a limit plate is fixedly connected in the storage rack, one side of the plurality of overlapping rods is provided with a guide groove, the limit plate contacts the guide groove, and the limit plate is used to limit the position of the plurality of overlapping rods. Preferably, the horizontal mechanism comprises a connecting frame, one side of the clamp is mounted and connected with the connecting frame, the electric push rod II is installed on the connecting frame, the telescopic end of the electric push rod II is hinged with a special-shaped frame, and an extension rod is slidably connected in the special-shaped frame.

[0007] Preferably, the horizontal mechanism also includes a mounting box, the mounting box is fixedly connected to the special-shaped frame, a micro-groove is opened at the bottom of the mounting box, the mounting box is provided with a balancing ball, the balancing ball is stuck in the micro-groove, the micro-groove is used to limit the position of the balancing ball, a trigger switch is installed in the mounting box, the balancing ball contacts the trigger switch and squeezes the trigger switch.

[0008] Preferably, the horizontal mechanism also includes a telescopic rod, a telescopic rod is fixedly connected to one side of the clamp, an output end of the telescopic rod is respectively connected to the movable clamp I and the movable clamp II, and an air valve is installed on the telescopic rod, and the air valve is used to limit the position of the telescopic rod.

[0009] Preferably, an adjustment mechanism is further included. The adjustment mechanism includes a movable clamp I. The movable clamp I is installed on the pier column. One end of the movable clamp I is hinged to a movable clamp II. The movable clamp I and the movable clamp II are in contact with the hoop. The hoop is used to limit the positions of the movable clamp I and the movable clamp II. The telescopic rod is used to limit the positions of the movable clamp I and the movable clamp II. A number of balls I are annularly arranged in the movable clamp I and the movable clamp II. The balls I are in contact with the pier column. The balls I are used to provide the movement of the movable clamp I and the movable clamp II. Positioning holes are provided at the bottom of one end of the extension rod, the movable clamp I and the movable clamp II. The extension rod is inserted into the bottoms of the movable clamp I and the movable clamp II. A pin I is clamped in the positioning holes of the extension rod, the movable clamp I and the movable clamp II. The pin I is used to limit the position of the extension rod. An arc-shaped protruding plate I is fixedly connected to one side end face of the movable clamp I. A meshing groove I is provided on one side end face of the movable clamp II. The arc-shaped protruding plate I is inserted into the meshing groove I of the movable clamp II. An elastic blocking block is slidably connected in the meshing groove I of the movable clamp II. The arc-shaped protruding plate I is in contact with the elastic blocking block. The arc-shaped protruding plate I is used to limit the position of the elastic blocking block. Circular through holes are provided on the movable clamp II and the arc-shaped protruding plate I. The circular through hole of the movable clamp II is communicated with the meshing groove I. An elastic limit pin is slidably connected in the circular through holes of the movable clamp II and the arc-shaped protruding plate I. The elastic limit pin is used to limit the positions of the movable clamp II and the arc-shaped protruding plate I.

[0010] Preferably, the lifting mechanism includes a sliding plate. Rectangular grooves are provided on one side of the movable clamp I and the movable clamp II. A sliding plate is slidably connected in the rectangular grooves of the movable clamp I and the movable clamp II. A U-shaped frame is installed and clamped in the rectangular grooves of the movable clamp I and the movable clamp II. The U-shaped frame is in contact with the sliding plate. The sliding plate is used to limit the position of the U-shaped frame. One end of a multi-section extension frame is fixedly connected to the U-shaped frame. A slider is slidably connected in the multi-section extension frame. One end of a bidirectional screw is rotatably connected in the multi-section extension frame. The other end of the bidirectional screw is rotatably connected through the multi-section extension frame. The slider is threadedly connected to the bidirectional screw. One end of a connecting rod is hinged to the slider. The other end of the connecting rod is hinged to a support plate. The rotating plate I and the rotating plate II are hinged to the support plate.

[0011] Preferably, it also includes a telescopic support rod, the telescopic support rod is hinged in the multi-section extension frame, a plurality of limiting holes are opened on the telescopic support rod, an elastic sliding plate is slidably connected to one side of the telescopic support rod, a locking pin is slidably connected to the elastic sliding plate, the locking pin is inserted into the plurality of limiting holes of the telescopic support rod, the locking pin is used to limit the position of the telescopic support rod, and one end of the telescopic support rod is hinged to the support plate.

[0012] Preferably, the arc-shaped protruding plate II is also included, and the arc-shaped protruding plate II is fixedly connected to one side end surface of the rotating plate I, and an engaging groove II is provided on one side end surface of the rotating plate II, and the arc-shaped protruding plate II is inserted into the engaging groove II of the rotating plate II, and pin holes are provided through the arc-shaped protruding plate II and the rotating plate II, and a pin II is slidably connected in the pin holes of the arc-shaped protruding plate II and the rotating plate II, and the pin II is used to limit the position of the arc-shaped protruding plate II, and a ball II is provided in both the rotating plate I and the rotating plate II, and the ball II is in contact with the pier, and the ball II is used to provide the rotating plate I and the rotating plate II with movement.

[0013] Preferably, a sliding rack is further included, one side of the storage rack is slidably connected to the sliding rack, one end of a moving block is slidably connected inside the sliding rack, the other end of the moving block is stuck in the guide groove, and the moving block is used to limit the position of the overlapping rod.

[0014] The present invention has the following advantages:

[0015] 1. The present invention can provide support for the construction template of the high tie beam while supporting the construction template of the low tie beam through the design of the lifting mechanism. By supporting the construction templates at both high and low locations at the same time, construction workers can simultaneously construct the high and low tie beams, which can greatly shorten the construction time and save a lot of manpower.

[0016] 2. The present invention can adjust the positions of the movable clamp I and the movable clamp II through the coordination of the electric push rod II and the balancing ball in the horizontal mechanism. The movable clamp I and the movable clamp II can be kept in a horizontal state through the coordination of the balancing ball, the micro groove and the trigger switch, which can further reduce the problems in the tie beam construction caused by the horizontal error.

[0017] 3. The present invention can extend the lap rod through the cooperation of the electric push rod I and the pushing plug plate. The lap rod can be pushed by the elastic plate to more conveniently achieve seamless connection and splicing of the lap rod. The installation height of the high tie beam template can be adjusted more conveniently by splicing and extending the lap rod. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1Schematic diagram of the overall structure of the present invention;

[0019] Figure 2 Installation schematic diagram at the rotating plate I of the present invention;

[0020] Figure 3 Installation schematic diagram at the overlapping rod of the present invention;

[0021] Figure 4 Schematic diagram of the structure of the horizontal mechanism of the present invention;

[0022] Figure 5 Schematic diagram of the structure at the balance ball of the present invention;

[0023] Figure 6 Installation schematic diagram at the movable clamp I of the present invention;

[0024] Figure 7 Schematic diagram of the structure at the lifting mechanism of the present invention;

[0025] Figure 8 For the present invention Figure 7 Schematic diagram of the mechanism at location A;

[0026] Fig. 9 Schematic diagram of the structure at the moving block of the present invention;

[0027] Fig.10 For the present invention Fig. 9 Local enlarged view of the structure at location B.

[0028] Wherein: 1 - hoop, 2 - rotating plate I, 201 - rotating plate II, 301 - storage rack, 302 - overlapping rod, 303 - elastic plate, 304 - sliding seat, 305 - insertion baffle, 306 - electric push rod I, 307 - guiding frame, 308 - pushing insertion plate, 309 - insertion hole, 310 - limiting plate, 311 - guide groove, 312 - fixed ring, 313 - arc plate, 401 - connecting frame, 402 - electric push rod II, 403 - special-shaped frame, 404 - extension rod, 501 - installation box, 502 - micro groove, 503 - balance ball, 504 - trigger switch, 505 - telescopic rod, 506 - air valve, 601 - movable clamp I, 6011 - movable clamp II, 602 - arc protruding plate I, 603 - elastic blocking block, 604 - elastic limit pin, 701 - sliding plate, 702 - C-shaped frame, 703 - multi-section extension frame, 704 - slider, 705 - bidirectional screw, 706 - connecting rod, 707 - support plate, 801 - telescopic support rod, 802 - elastic sliding plate, 803 - locking pin, 9 - arc protruding plate II, 1001 - sliding frame, 1002 - moving block, 100 - pier, 200 - girder formwork. Detailed implementation manners

[0029] The present invention is further described below in conjunction with specific embodiments. It should also be noted that, unless otherwise clearly specified and limited, terms such as: setting, installing, connecting, and connecting should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0030] Example 1

[0031] A device for synchronous construction of double tie beams, such as Figure 1-3 As shown, it includes a pier 100, a clamp 1 is installed on the pier 100, a lifting mechanism is arranged on the clamp 1, and also includes a rotating plate I2, a rotating plate I2 is arranged on the lifting mechanism, a rotating plate II201 is hinged at one end of the rotating plate I2, and the lifting mechanism is used to provide the rotating plate I2 and the rotating plate II201 with movement, a storage rack 301 is fixedly connected to the top of the rotating plate I2 and the rotating plate II201, a plurality of overlapping rods 302 are slidably connected in the storage rack 301, an elastic plate 303 is connected to the inner side of the storage rack 301, the elastic plate 303 is in contact with the side of the overlapping rod 302 close to each other, and the elastic plate 303 is used to drive the overlapping rod 302 to slide in the storage rack 301, a special-shaped groove is opened on one side of the rotating plate I2 and the rotating plate II201, a sliding seat 304 is installed in the special-shaped groove of the rotating plate I2 and the rotating plate II201 for sliding connection, and the rotating plate I2 and A plug-in baffle 305 is slidably connected in the special-shaped groove of the rotating plate II201. The plug-in baffle 305 contacts the sliding seat 304 and can limit the position of the sliding seat 304. An electric push rod I306 is hinged on the top of the sliding seat 304. A guide frame 307 is mounted and clamped on one side of the storage rack 301. The convex shaft at the telescopic end of the electric push rod I306 is clamped into the adjacent guide frame 307 and slides along the trajectory of the guide frame 307. The electric push rod I306 is used to provide the lap rod 302 with movement in the storage rack 301. A fixing ring 312 is clamped on the top of the lap rod 302. An arc plate 313 is slidably connected in the fixing ring 312. The arc plate 313 contacts the pier 100. The fixing ring 312 is used to limit the position of the tie beam template 200. A horizontal mechanism is arranged on the hoop 1. The horizontal mechanism is used to provide the lifting mechanism to maintain the level, so that the tie beam template 200 can be in a horizontal state.

[0032] like Figure 3As shown, it also includes a pushing plate 308, the telescopic end of the electric push rod I306 is fixedly connected with the pushing plate 308, a plug hole 309 is opened on one side of the plurality of overlapping rods 302, the pushing plate 308 is inserted into the plug hole 309, and the pushing plate 308 is used to limit the position of the plurality of overlapping rods 302, a limiting plate 310 is fixedly connected to the inner side of the storage rack 301, a guide groove 311 is opened on one side of the plurality of overlapping rods 302, and the limiting plate 310 is inserted into the guide groove 311, which can limit the position of the plurality of overlapping rods 302 and make the plurality of overlapping rods 302 slide vertically.

[0033] like Figure 4 As shown, the horizontal mechanism includes a connecting frame 401, both ends of the connecting frame 401 are mounted and clamped at the corner of one side of the clamp 1, an electric push rod II402 is symmetrically installed on the connecting frame 401, a special-shaped frame 403 is arranged on the upper side of the connecting frame 401, an elastic member is arranged between the connecting frame 401 and the special-shaped frame 403, the elastic member is a reset spring, the telescopic ends of the electric push rod II402 are hinged to the special-shaped frame 403, the electric push rod II402 is used to drive the special-shaped frame 403 to rotate, and the left and right ends of the special-shaped frame 403 are symmetrically slidably connected with extension rods 404.

[0034] like Figure 4-5 As shown, the horizontal mechanism also includes a mounting box 501, the mounting box 501 is fixedly connected to the top of the special-shaped frame 403, a micro groove 502 is opened in the middle of the bottom of the mounting box 501, the micro groove 502 is an arc-shaped groove, a balancing ball 503 is rollingly connected in the mounting box 501, the balancing ball 503 is stuck in the micro groove 502, the micro groove 502 is used to limit the position of the balancing ball 503, and trigger switches 504 are installed on the left and right sides of the mounting box 501, and the balancing ball 503 contacts and squeezes the trigger switch 504.

[0035] like Figure 6 As shown, the horizontal mechanism also includes a telescopic rod 505, and the telescopic rod 505 is symmetrically fixed to the outer wall of the clamp 1, and the output ends of the telescopic rod 505 are respectively connected to the movable clamp I601 and the movable clamp II6011, and an air valve 506 is installed on the telescopic rod 505. When the telescopic rod 505 is extended, the air valve 506 fills the internal space of the telescopic rod 505 with gas, which can prevent the telescopic rod 505 from shrinking. The air valve 506 is used to limit the position of the telescopic rod 505.

[0036] like Figure 6-7As shown, an adjustment mechanism is also included, and the adjustment mechanism includes a movable clamp I601. The movable clamp I601 is installed on the pier 100, and one end of the movable clamp I601 is hinged with a movable clamp II6011. The bottom ends of the movable clamp I601 and the movable clamp II6011 are in contact with the top of the clamp 1. The clamp 1 is used to limit the position of the movable clamp I601 and the movable clamp II601. There are a number of balls I in the annular array inside the movable clamp I601 and the movable clamp II6011. The ball I contacts the pier column 100, and the ball I can make the movable clamp I601 and the movable clamp II6011 move along the pier column 100. Positioning holes are provided at the bottom of the movable clamp I601 and the movable clamp II6011 and one end of the extension rod 404. The extension rod 404 and the positioning holes of the movable clamp I601 and the movable clamp II6011 are clamped with a pin I. The pin I is inserted into the positioning holes of the extension rod 404 and the movable clamp I601 and the movable clamp II6011. The extension rod 404 can be hinged with the movable clamp I601 and the movable clamp II6011. The end surface of one side of the movable clamp I601 is fixed with an arc-shaped protruding plate I602. The end surface of one side of the movable clamp II6011 is provided with an engagement groove I. The arc-shaped protruding plate I602 is inserted into the engagement groove I. An elastic blocking block 603 is slidably connected in the engagement groove I. The arc-shaped protruding plate I602 contacts the elastic blocking block 603. The arc-shaped protruding plate I602 is used to limit the elastic blocking block 603. The movable clamp II6011 is in the position, and a circular through hole is opened on the bottom end and the arc-shaped protruding plate I602; the circular through hole of the movable clamp II601 is connected with the engaging groove I; an elastic limiting pin 604 is slidingly connected between the circular through hole of the movable clamp II6011 and the arc-shaped protruding plate I602; the elastic limiting pin 604 is inserted into the circular through hole of the movable clamp II6011 and the arc-shaped protruding plate I602 to keep the movable clamp I601 and the movable clamp II6011 in an engaged state.

[0037] like Figure 7As shown in the figure, the lifting mechanism includes a sliding plate 701. A rectangular groove is provided on one side of the movable clamp I 601 and the movable clamp II 6011. The sliding plate 701 is slidably connected in the rectangular grooves of the movable clamp I 601 and the movable clamp II 6011. A U-shaped frame 702 is installed and clamped in the rectangular grooves of the movable clamp I 601 and the movable clamp II 6011. The top end of the U-shaped frame 702 contacts the bottom end of the sliding plate 701. The sliding plate 701 is used to limit the position of the U-shaped frame 702 and can keep the U-shaped frame 702 stable. The multi-section extension frame 703 has a first stage, a second stage and a third stage from top to bottom. The bottom end of the third-stage multi-section extension frame 703 is fixedly connected to the U-shaped frame 702. A slider 704 is slidably connected in each of the first-stage, second-stage and third-stage multi-section extension frames 703. One end of a bidirectional screw rod 705 is rotatably connected in each of the first-stage, second-stage and third-stage multi-section extension frames 703. The other end of the bidirectional screw rod 705 is rotatably connected through the adjacent multi-section extension frame 703. The slider 704 is threadedly connected to the bidirectional screw rod 705. By rotating the bidirectional screw rod 705, the adjacent sliders 704 can be driven to move closer to or away from each other. One end of a connecting rod 706 is hinged to the slider 704. The connecting rod 706 of the first-stage multi-section extension frame 703 is hinged to a support plate 707. The connecting rod 706 of the second-stage multi-section extension frame 703 is hinged to the first-stage multi-section extension frame 703. The connecting rod 706 of the third-stage multi-section extension frame 703 is hinged to the second-stage multi-section extension frame 703. The rotating plate I 2 and the rotating plate II 201 are hinged to the support plate 707.

[0038] As Figure 7-8 shown in the figure, it further includes a telescopic support rod 801. The telescopic support rod 801 is hinged in each of the first-stage, second-stage and third-stage multi-section extension frames 703. The telescopic support rod 801 of the third-stage multi-section extension frame 703 is hinged to the second-stage multi-section extension frame 703. The telescopic support rod 801 of the second-stage multi-section extension frame 703 is hinged to the first-stage multi-section extension frame 703. The telescopic support rod 801 of the first-stage multi-section extension frame 703 is hinged to the support plate 707. A number of limit holes are provided on the telescopic support rod 801. An elastic sliding plate 802 is slidably connected to one side of the telescopic support rod 801. A locking pin 803 is slidably connected through the elastic sliding plate 802. The locking pin 803 is inserted into a number of limit holes of the telescopic support rod 801. When the limit holes are misaligned with the locking pin 803, by driving the locking pin 803 to slide through the elastic sliding plate 802, the locking pin 803 can be displaced. After the locking pin 803 is displaced, it can be inserted into a number of limit holes. The locking pin 803 is used to limit the position of the telescopic support rod 801.

[0039] As Fig. 9As shown, it also includes an arc-shaped protruding plate II9, one side end face of the rotating plate I2 is fixedly connected with the arc-shaped protruding plate II9, one side end face of the rotating plate II201 is provided with an engaging groove II, the arc-shaped protruding plate II9 is ​​inserted into the engaging groove II of the rotating plate II201, pin holes are through-opened on the arc-shaped protruding plate II9 and the rotating plate II201, the latch I is inserted into the pin holes of the arc-shaped protruding plate II9 and the rotating plate II201, the latch II is used to limit the position of the arc-shaped protruding plate II9, so that the rotating plate I2 and the rotating plate II201 can maintain an engaged state, and balls II are arranged in the rotating plate I2 and the rotating plate II2, the balls II are in contact with the pier 100, and the balls II can make the rotating plate I2 and the rotating plate II201 move along the pier 100.

[0040] like Figure 9-10 As shown, it also includes a sliding frame 1001, and one side of the storage rack 301 is slidably connected to the sliding frame 1001. One end of a moving block 1002 is slidably connected inside the sliding frame 1001. The moving block 1002 is located on the lower side of the limiting plate 310. When the moving block 1002 moves, it does not affect the limiting plate 310. The other end of the moving block 1002 is stuck in the guide groove 311. By changing the position of the moving block 1002, the position of the overlapping rod 302 can be driven.

[0041] First, manually install the lower tie beam on the pier 100, preliminarily determine the installation position, and then fix the clamp 1 on the pier 100. At this time, the clamp 1 is at the lower side of the installation position of the lower tie beam. Then, the movable clamp I601 and the movable clamp II6011 are lifted to the top of the clamp 1 by the lifting equipment. Then, the bottom end of the movable clamp II6011 is manually moved to the pier 100 and fits with the top end of the clamp 1. Then, the movable clamp II6011 is manually fixed with the connecting rod of the movable clamp I601. The movable clamp II6011 drives the elastic blocking block 603, the elastic limiting pin 604 and the ball I to rotate. Initially, the elastic blocking block 603 is directly above the elastic limiting pin 604, and the elastic limiting pin 604 is restricted by the elastic blocking block 603 and cannot move. After the movable clamp II6011 rotates, the adjacent ball I is fitted with the surface of the pier 100, and then the movable clamp I601 is manually rotated with the connection of the movable clamp II6011 as the center of the circle. The movable clamp I60 1 drives the arc-shaped protruding plate I602 and the adjacent ball I to rotate, and the movable clamp I601 rotates to make the adjacent ball I fit with the surface of the pier 100. At the same time, the movable clamp I601 drives the arc-shaped protruding plate I602 to insert into the meshing groove I of the movable clamp II6011 and squeeze the elastic blocking block 603. The elastic blocking block 603 is forced to shrink and slide along the meshing groove I in the meshing groove I. After the elastic blocking block 603 moves, it no longer restricts the elastic limiting pin 604, and the elastic limiting pin 604 is separated from the elastic blocking When the block 603 is restricted, the arc-shaped protruding plate I602 coincides with the circular through hole of the movable clamp II6011, and the elastic limiting pin 604 is inserted into the circular through hole of the arc-shaped protruding plate I602 and the movable clamp II6011. At this time, the arc-shaped protruding plate I602 is restricted by the elastic limiting pin 604 and cannot move, thereby enabling the movable clamp I601 and the movable clamp II6011 to maintain an engaged state, and the ball I of the movable clamp I601 and the movable clamp II6011 are always in contact with the pier 100.

[0042] Then, the connecting frame 401 is lifted by the lifting equipment to drive the overall horizontal mechanism to move between the two clamps 1, and the two ends of the connecting frame 401 are clamped into the corners of one side of the clamp 1. The connecting frame 401 is restricted by the clamp 1 to maintain a stable height, and then the extension rod 404 is manually extended to the side close to the adjacent clamp 1, and the extension rod 404 slides in the special-shaped frame 403. After the extension rod 404 slides, the end close to the clamp 1 is clamped into the bottom of the movable clamp I601 and the movable clamp II6011, and then the pin I is manually inserted into the positioning holes of the extension rod 404, the movable clamp I601 and the movable clamp II6011, so that the extension rod 404 and the movable clamp I601 and the movable clamp II6011 form a hinged state. When the movable clamps I601 and II6011 on both sides are 01 and the movable clamp II6011 are in the same horizontal plane, the movable clamps I601 and the movable clamp II6011 on both sides drive the extension rod 404 and the special-shaped frame 403 to form a horizontal state, and the special-shaped frame 403 drives the installation box 501 to maintain a horizontal state. At this time, the balancing ball 503 is in the micro groove 502. The installation box 501 maintains a horizontal state so that the balancing ball 503 can be stably stuck in the micro groove 502, and the balancing ball 503 does not contact the trigger switch 504 in the installation box 501. When the movable clamps I601 and the movable clamp II601 on both sides are not in the same horizontal plane, the movable clamps I601 and the movable clamp II6011 on both sides drive the extension rod 404 and the special-shaped frame 403 to form an inclined state. At this time, the special-shaped frame 403 The mounting box 501 is driven to tilt. After the mounting box 501 tilts, the balancing ball 503 is affected by gravity to break away from the micro groove 502 and roll in the mounting box 501. After rolling, the balancing ball 503 contacts and squeezes the trigger switch 504. The trigger switch 504 is squeezed by the balancing ball 503 to start the electric push rod II402 (a storage battery is installed at the bottom of the connecting frame 401, and the electric push rod I306 and the electric push rod II402 are electrically connected to the storage battery. There is no need to elaborate on the prior art). When the right end of the special-shaped frame 403 is higher than the left end of the special-shaped frame 403, the balancing ball 503 breaks away from the micro groove 502 and rolls to the left in the mounting box 501. After rolling to the left, the balancing ball 503 squeezes the trigger switch 504 on the left. The trigger switch 504 is squeezed by the balancing ball 503 to start the electric push rod II402. The electric push rod II402 on the left is squeezed and started. The telescopic end of the electric push rod II402 on the left drives the special-shaped frame 403 to lift upward. The left part of the special-shaped frame 403 is subjected to force to drive the movable clamp I601 and the movable clamp II6011 on the left to move upward. The movable clamp I601 and the movable clamp II6011 on the left drive the arc-shaped protruding plate I602, the elastic limit pin 604 and the adjacent ball I to move upward. The ball I rotates in contact with the pier 100. The movable clamp I601 and the movable clamp I601I drive the top of the adjacent telescopic rod 505 to extend upward. At the same time, when the telescopic rod 505 extends upward, gas is injected into the internal space through the gas valve 506. When the tie beam template 200 is placed on the movable clamp I601 and the movable clamp II6011,The gravity of the tie beam template 200 is applied to the telescopic rod 505 through the movable clamp I601 and the movable clamp II6011. By injecting gas into the telescopic rod 505 during extension, the telescopic rod 505 can remain stable when under pressure. At the same time, the special-shaped frame 403 drives the installation box 501 to rotate. After the installation box 501 rotates, it forms a horizontal state and moves the balancing ball 503. The balancing ball 503 slides to the right in the installation box 501 and is stuck in the micro groove 502. At this time, the balancing ball 503 no longer squeezes the trigger switch 504 on the left. After the trigger switch 504 is not squeezed, the electric push rod II402 is driven. The telescopic end of the electric push rod II402 no longer rotates the special-shaped frame 403, and the special-shaped frame 403 makes the installation box 501 and the balancing ball 503 maintain a stable horizontal state, so that the extension rod 404 can drive the movable clamps I601 and II6011 on both sides to be in the same horizontal plane through the cooperation of the electric push rod II402 and the balancing ball 503. As mentioned above, when the left end of the special-shaped frame 403 is higher than the right end of the special-shaped frame 403, the same effect can be achieved by driving the special-shaped frame 403 to rotate through the electric push rod II402 on the right side. Then, the tie beam template 200 of the low tie beam is manually installed on the pier 100, and the bottoms of the two ends of the tie beam template 200 are fitted with the tops of the movable clamps I601 and II6011 on the same side, so that the tie beam template 200 can be kept horizontal.

[0043] Initially, the multi-section extension frame 703 and the sliding plate 701 are in a contracted state. The U-shaped frame 702 is lifted by a lifting device. The U-shaped frame 702 drives the multi-section extension frame 703 to lift upward. The multi-section extension frame 703 drives the slider 704, the bidirectional screw 705, the connecting rod 706 and the support plate 707 to lift upward. The support plate 707 drives the rotating plate I2 and the rotating plate II201 to lift upward. The rotating plate I2 and the rotating plate II201 drive the adjacent storage rack 301 to lift upward. The storage rack 301 drives a plurality of overlapping rods 302 and the elastic plate 303 to lift upward. The overlapping rod 302 drives the fixed ring 312 to lift upward. Initially, the rotating plate I2 and the rotating plate II201 are in an open state. The ends of the rotating plate I2 and the rotating plate II201 close to the pier 100 are separated from each other with the connection point of the support plate 707 as the center of the circle. When the rotating plate I2 and the rotating plate II201 move to the pier 100, they will not collide with the pier 100. The U-shaped frame 702 is lifted to the rectangular groove on one side of the movable clamp I601 and the movable clamp II6011, and the protruding ends of the U-shaped frame 702 are inserted into the rectangular groove on one side of the movable clamp I601 and the movable clamp II6011. Then, the two sliding plates 701 on the same side are horizontally pulled away from each other manually. After the sliding plate 701 slides in the rectangular groove of the movable clamp I601 and the movable clamp II6011, the bottom end abuts against the top end of the U-shaped frame 702. At this time, the U-shaped frame 702 is restricted by the sliding plate 701 and cannot move and remains stable. The U-shaped frame 702 is restricted by the sliding plate 701 to keep the multi-section extension frame 703 stable. The multi-section extension frame 703 drives the slider 704, the bidirectional screw 705, the connecting rod 706 and the support plate 707 to remain stable. The support plate 707 drives the rotating plate I2 to remain stable. Then, the ends of the rotating plate I2 and the rotating plate II201 close to the pier 100 are rotated closer to each other with the connection point of the support plate 707 as the center of the circle manually. The rotating plate II201 drives the adjacent rolling ball II to rotate and contact the surface of the pier 100. The rotating plate I2 drives the arc-shaped protruding plate II9 and the adjacent rolling ball II to rotate. After the arc-shaped protruding plate II9 rotates, it is inserted into the engagement groove II of the rotating plate II201. At this time, the arc-shaped protruding plate II9 coincides with the pin hole on the rotating plate II201. The pin II is inserted into the pin holes of the arc-shaped protruding plate II9 and the rotating plate II201 manually. At the same time, the rotating plate I2 drives the adjacent rolling ball II to fit against the surface of the pier 100. Thus, the rotating plate I2 and the rotating plate II201 can be kept in an engaged state. At the same time, the rotating plate I2 and the rotating plate II201 drive the adjacent storage rack 301 to rotate. The storage rack 301 drives a plurality of overlapping rods 302 and the elastic plate 303 to rotate. The overlapping rod 302 drives the fixed ring 312 to rotate. The fixed ring 312 drives the arc-shaped plate 313 to contact the surface of the pier 100. Then, the handwheel is clamped to the bidirectional screw 705 of the first-stage multi-section extension frame 703 manually and the handwheel is rotated. The rotation of the handwheel drives the bidirectional screw 705 to rotate.The bidirectional screw 705 drives the two adjacent sliders 704 to move closer to each other, and the sliders 704 drive the connecting rods 706 to move closer to each other. The connecting rods 706 are forced to rotate around the connection of the sliders 704 as the center of the circle and drive the extrusion support plate 707. The support plate 707 is forced to drive the rotating plate I2 and the rotating plate II201 to lift upward. The rotating plate I2 and the rotating plate II201 drive the adjacent ball II to lift upward. The ball II fits the surface of the pier 100 and moves upward. At the same time, the rotating plate I2 and the rotating plate II201 The plate II201 drives the adjacent storage rack 301 to be lifted upward, and the storage rack 301 drives several lap rods 302 and elastic plates 303 to be lifted upward, and the lap rods 302 drive the fixing ring 312 to be lifted upward, and when the sliders 704 in the first-stage multi-section extension rack 703 move close to each other to the limit position, the hand wheel is manually removed from the bidirectional screw rod 705 of the first-stage multi-section extension rack 703 and is clamped with the bidirectional screw rod 705 of the second-stage multi-section extension rack 703, and then the hand wheel is manually turned to enable the first stage multi-section extension rack 703 to be lifted upward. The bidirectional screw rod 705 of the second-stage multi-section extension frame 703 rotates, and so on. The same effect can be achieved by rotating the bidirectional screw rods 705 of the second-stage multi-section extension frame 703 and the third-stage multi-section extension frame 703. When the two fixed rings 312 can be adjusted to rise to the installation position of the high tie beam through the multi-section extension frame 703, the moving screw rod on one side of the fixed ring 312 is manually rotated, and the rotation of the moving screw rod drives the adjacent arc plate 313 to move to the side close to the pier 100, and the arc plate 313 moves After that, it is attached to and squeezed with the pier column 100, thereby fixing the position of the fixing ring 312, and then the two ends of the tie beam template 200 of the high tie beam are installed on the pier column 100, and the bottom ends of the two ends of the high tie beam template 200 are attached to the top of the fixing ring 312, thereby realizing the positioning and installation of the low tie beam template 200 and the high tie beam template 200, and then the construction personnel construct and cast the steel structure inside the two tie beam templates 200 to complete the synchronous construction of the double tie beams.

[0044] When the two fixing rings 312 cannot rise to the installation position of the high tie beam through the adjustment of the multi-section extension frame 703, the sliding seat 304, the electric push rod I306 and the guide frame 307 are lifted to the special-shaped grooves of the rotating plate I2 and the rotating plate II201 by the lifting equipment, and the sliding seat 304 is manually inserted into the special-shaped grooves of the rotating plate I2 and the rotating plate II201, and then the plug-in baffle 305 is pulled outward, and one side of the plug-in baffle 305 contacts the sliding seat 304. The sliding seat 304 is restricted by the plug-in baffle 305 and cannot move. Then the pushing plug plate 308 at the telescopic end of the electric push rod I306 is inserted into the plug-in hole 309 of the adjacent lap rod 302, and then the guide frame 307 is plugged with the storage rack 301 and the electric push rod is inserted into the guide frame 307. The cam at the telescopic end of the push rod 1306 is inserted into the guide frame 307 and then the electric push rod 1306 is started. The telescopic end of the electric push rod 1306 drives the cam and the push plug 308 to extend upward along the trajectory of the guide frame 307, and at the same time pushes the plug 308 to squeeze the insertion hole 309 of the adjacent lap rod 302. The adjacent lap rod 302 is forced to slide upward in the storage rack 301, and the lap rod 302 drives the fixing ring 312 to lift upward, and the fixing ring 312 drives the arc plate 313 to lift upward. When the lap rod 302 slides upward, the guide grooves 311 on both sides are limited by the limiting plate 310, so that the lap rod 302 can slide vertically upward. When the telescopic end of the electric push rod 1306 drives the cam to move to the inner corner of the guide frame 307, the upper The T-slot at the bottom of the raised lap rod 302 coincides with the top of the adjacent lap rod 302. At this time, the remaining lap rods 302 in the storage rack 301 are squeezed by the elastic plate 303 to slide toward the side close to the electric push rod 1306, and the top of the lap rod 302 adjacent to the raised lap rod 302 is stuck in the T-slot at its bottom. At the same time, the telescopic end of the electric push rod 1306 continues to drive the cam to move, and the cam drives the telescopic end of the electric push rod 1306 to rotate along the trajectory of the guide frame 307 with the connection point of the sliding seat 304 as the center toward the side away from the lap rod 302. The telescopic end of the electric push rod 1306 drives the push plate 308 to move toward the side away from the plug hole 309 and disengage from the plug hole 309, and the raised lap rod 302 and the adjacent After the lap rod 302 is connected, it will not fall downward. When the telescopic end of the electric push rod 1306 drives the convex shaft to move along the trajectory of the guide frame 307 to the top of the side away from the storage rack 301, the telescopic end of the electric push rod 1306 drives the convex shaft and the pushing plug plate 308 to retract. When the telescopic end of the electric push rod 1306 drives the convex shaft and the pushing plug plate 308 to retract and move downward along the trajectory of the guide frame 307 to the bottom of the side away from the storage rack 301, the convex shaft drives the telescopic end of the electric push rod 1306 and the pushing plug plate 308 to rotate and reset to the side close to the lap rod 302 with the connection point of the sliding seat 304 as the center. After the pushing plug plate 308 is reset, it is inserted into the adjacent lap rod 302, and so on.The electric push rod 1306 drives the cam and the push plate 308 to move along the track of the guide frame 307, so that several overlapping rods 302 can be overlapped. When the overlapping rod 302 drives the fixed ring 312 and the arc plate 313 to move upward to the installation position of the high tie beam, the electric push rod 1306 is closed, and the electric push rod 1306 no longer drives the cam and the push plate 308 to move, and the push plate 308 no longer drives the overlapping rod 302 to extend upward. The overlapping of several overlapping rods 302 can drive the fixed ring 312 and the arc plate 313 to extend upward and remain stable, and then the fixed ring 312 is manually rotated to move on one side. The screw rod is moved to rotate and drive the adjacent arc plate 313 to move to the side close to the pier column 100. After the arc plate 313 moves, it fits and squeezes the pier column 100, thereby fixing the position of the fixing ring 312. Then, the two ends of the tie beam template 200 of the high tie beam are installed on the pier column 100, and the bottom ends of the two ends of the high tie beam template 200 fit with the top of the fixing ring 312, thereby realizing the positioning and installation of the low tie beam template 200 and the high tie beam template 200. Then, the construction personnel construct and cast the steel structure inside the two tie beam templates 200 to complete the synchronous construction of the double tie beams.

[0045] After the construction is completed, the two plug-in baffles 305 on the same side are manually pushed towards each other, and the plug-in baffles 305 slide in the special-shaped grooves of the rotating plate I2 and the rotating plate II201 and no longer restrict the sliding seat 304. The sliding seat 304 can be taken out after it is free from the restriction of the plug-in baffles 305, and then the guide frame 307 is removed from the side of the storage frame 301, and the sliding seat 304 is taken out from the special-shaped grooves of the rotating plate I2 and the rotating plate II201 and removed by the lifting equipment, and then the moving screw on one side of the fixing ring 312 is manually rotated, and the moving screw rotates to drive the adjacent arc plate 313 to move to the side away from the pier 100. After the arc plate 313 moves, it no longer squeezes the pier 100. At this time, the arc plate 313 and the fixing ring 312 can move, and then the moving block 1002 is manually driven to slide to the side away from the elastic plate 303 through the handle on one side of the moving block 1002, and then the moving block 1002 is moved closer to the guide The lap rod 302 on one side of the frame 307 moves, and the moving block 1002 is pushed and stuck in the guide groove 311 of the lap rod 302, and then the moving block 1002 is driven by the handle on one side of the moving block 1002 to slide toward the side close to the elastic plate 303, and the moving block 1002 squeezes the guide groove 311 of the adjacent lap rod 302, and the adjacent lap rod 302 is squeezed to slide toward the side close to the elastic plate 303. At the same time, the top end of the moved lap rod 302 slides in the T-slot at the bottom of the upper lap rod 302 and disengages from the T-slot at the bottom of the upper lap rod 302. At this time, the upper lap rod 302 loses its supporting force and falls downward under the influence of its own weight. After the lap rod 302 falls downward, the top end is in the same horizontal plane with the top end of the adjacent lap rod 302 on one side. And so on, repeating the above steps can gradually separate and reset the several lap rods 302 that have been overlapped. After the several lap rods 302 are reset, they drive the fixing ring 312 and the arc plate 313 to reset.

[0046] After the lap bar 302 drives the fixed ring 312 and the arc plate 313 to reset, the pin II is manually pulled out upward. After the pin II is pulled out upward, the position of the arc-shaped protruding plate II9 is no longer restricted. After the arc-shaped protruding plate II9 is released from the restriction of the pin II, it can move. Then, the ends of the rotating plate I2 and the rotating plate II201 close to the pier 100 are rotated away from each other with the connection point of the support plate 707 as the center of the circle. After the rotating plate II201 drives the adjacent ball II to rotate, it no longer contacts the surface of the pier 100. The rotating plate I2 drives the arc-shaped protruding plate II9 and the adjacent ball II to rotate. After the arc-shaped protruding plate II9 rotates, it disengages from the engaging groove II of the rotating plate II201. Then, the handwheel is manually clamped to the bidirectional screw 705 on the multi-section extension frame 703 and the handwheel is rotated. The rotation of the handwheel drives the bidirectional screw 705 to rotate. The bidirectional screw 705 drives the two adjacent sliders 704 to move back to their original positions. The slider 704 drives the connecting rod 706 to move back to its original position. The connecting rod 706 rotates back to its original position with the connection point of the slider 704 as the center of the circle under the action of force, driving the connecting rod 706 to drive the support plate 707 to descend and reset. The support plate 707 drives the rotating plate I2 and the rotating plate II201 to move back to their original positions. The rotating plate I2 and the rotating plate II201 drive the adjacent ball II to move back to its original position. At the same time, the rotating plate I2 and the rotating plate II201 drive the adjacent storage rack 301 to move back to its original position. The storage rack 301 drives a number of lap bars 302 and elastic plates 303 to move back to their original positions. The lap bar 302 drives the fixed ring 312 to move back to its original position. The fixed ring 312 drives the arc plate 313 to reset, thus completing the reset of the lifting mechanism. Then, the movable clamp I601 and the slide plate 701 in the rectangular groove of the movable clamp II6011 are manually pushed close to each other. After the slide plate 701 moves, the C-shaped frame 702 is no longer restricted. After the C-shaped frame 702 is released from the restriction of the slide plate 701, it can move. Then, the C-shaped frame 702 is removed by a lifting device. The C-shaped frame 702 drives the entire lifting mechanism to be disassembled and reset. Then, the pin I is manually pulled out from the positioning holes of the extension rod 404, the movable clamp I601 and the movable clamp II6011. After the extension rod 404 is released from the restriction of the pin I, it can move away from the movable clamp I601 and the movable clamp II6011. Then, the extension rod 404 is moved back to its original position in the special-shaped frame 501. After the extension rod 404 is reset, the connecting frame 401 is lifted by a lifting device so that the two ends of the connecting frame 401 are separated from the adjacent hoop 1. Then, the connecting frame 401 is driven by the lifting device to descend and removed. The connecting frame 401 drives the entire horizontal mechanism to be removed and reset. Then, the air valve 506 is manually opened. After the air valve 506 is opened, the gas in the telescopic rod 505 is released, causing the telescopic rod 505 to contract and reset. Then, the elastic limit pin 604 is manually pulled out from the circular through hole of the arc-shaped protruding plate I602. After the arc-shaped protruding plate I602 is released from the restriction of the elastic limit pin 604, it can move. Then, the movable clamp II6011 is rotated clockwise with the connection point of the movable clamp I601 as the center of the circle in the counterclockwise direction.The movable clamp II6011 drives the elastic blocking block 603, the elastic limiting pin 604 and the ball I to rotate. After the movable clamp II6011 rotates, it drives the adjacent ball I and the surface of the pier 100 to move away. After the movable clamp II6011 rotates, the arc-shaped protruding plate I602 disengages from the meshing groove I and no longer squeezes the elastic blocking block 603. After the elastic blocking block 603 is released and resets after being squeezed by the arc-shaped protruding plate I602, it blocks the elastic limiting pin 604. Then, the movable clamp I601 and the movable clamp II6011 are removed by the lifting equipment, and then the hoop 1 is removed, thereby completing the reset of the entire device.

[0047] The above embodiments are only for illustrating the technical concept and features of the present invention, and their purpose is to enable people familiar with the technology to understand the content of the present invention and implement it accordingly, and they cannot be used to limit the protection scope of the present invention. Any equivalent changes or modifications made according to the spirit of the present invention should be included in the protection scope of the present invention.

Claims

1. A device for synchronous construction of double tie beams, comprising a pier column (100), a clamp (1) being installed on the pier column (100), and a lifting mechanism being arranged on the clamp (1), characterized in that: The utility model also comprises a rotating plate I (2), the rotating plate I (2) is arranged on the lifting mechanism, one end of the rotating plate I (2) is hingedly connected to the rotating plate II (201), the lifting mechanism is used to provide the rotating plate I (2) and the rotating plate II (201) with movement, the rotating plate I (2) and the rotating plate II (201) are fixedly connected to a storage rack (301), the storage rack (301) is slidably connected with the plurality of overlapping rods (302), and the storage rack (301) is provided with a plurality of overlapping rods (302) in the ... An elastic plate (303) is connected, the elastic plate (303) is in contact with the lap rod (302), the elastic plate (303) is used to provide the lap rod (302) with movement, the rotating plate I (2) and the rotating plate II (201) are provided with a special-shaped groove on one side, the rotating plate I (2) and the rotating plate II (201) are slidably connected in the special-shaped groove by a sliding seat (304), the special-shaped groove of the rotating plate I (2) and the rotating plate II (201) is provided with a sliding seat (304) A plug-in baffle (305) is slidably connected in the groove, the plug-in baffle (305) contacts the sliding seat (304), and the plug-in baffle (305) is used to limit the position of the sliding seat (304). An electric push rod I (306) is hinged on the sliding seat (304), and a guide frame (307) is installed on one side of the storage rack (301). The telescopic end of the electric push rod I (306) is fixedly connected to a convex shaft, and the convex shaft of the telescopic end of the electric push rod I (306) The electric push rod I (306) is inserted into the guide frame (307) and slides in the guide frame (307), and is used to provide the overlap rod (302) with movement. A clamping ring (312) is fixed to the top of the overlap rod (302), and an arc plate (313) is slidably connected in the fixed ring (312). The arc plate (313) is in contact with the pier (100). A horizontal mechanism is arranged on the clamp (1), and the horizontal mechanism is used to provide the lifting mechanism to maintain the level.

2. A device for synchronous construction of double tie beams according to claim 1, characterized in that: It also includes a pushing plate (308), the telescopic end of the electric push rod I (306) is fixedly connected to the pushing plate (308), one side of the plurality of overlapping rods (302) is provided with a plug hole (309), the pushing plate (308) is inserted into the plug hole (309), the pushing plate (308) is used to limit the position of the plurality of overlapping rods (302), a limiting plate (310) is fixedly connected to the storage rack (301), one side of the plurality of overlapping rods (302) is provided with a guide groove (311), the limiting plate (310) is in contact with the guide groove (311), and the limiting plate (310) is used to limit the position of the plurality of overlapping rods (302).

3. A device for synchronous construction of double tie beams according to claim 1, characterized in that: The horizontal mechanism comprises a connecting frame (401), one side of the clamp (1) is mounted with the connecting frame (401), an electric push rod II (402) is mounted on the connecting frame (401), a telescopic end of the electric push rod II (402) is hinged with a special-shaped frame (403), and an extension rod (404) is slidably connected inside the special-shaped frame (403).

4. A device for synchronous construction of double tie beams according to claim 3, characterized in that: The horizontal mechanism also includes a mounting box (501), the mounting box (501) is fixedly connected to the special-shaped frame (403), a micro groove (502) is provided at the bottom of the mounting box (501), a balancing ball (503) is provided in the mounting box (501), the balancing ball (503) is inserted into the micro groove (502), the micro groove (502) is used to limit the position of the balancing ball (503), a trigger switch (504) is installed in the mounting box (501), and the balancing ball (503) contacts and presses the trigger switch (504).

5. The device for synchronous construction of double tie beams according to claim 3, characterized in that: The horizontal mechanism also includes a telescopic rod (505), one side of the clamp (1) is fixedly connected with the telescopic rod (505), the output end of the telescopic rod (505) is respectively connected to the movable clamp I (601) and the movable clamp II (6011), and the telescopic rod (505) is installed with an air valve (506), and the air valve (506) is used to limit the position of the telescopic rod (505).

6. The device for synchronous construction of double tie beams according to claim 1, characterized in that: The pier (100) also includes an adjustment mechanism, which includes a movable clamp I (601). The movable clamp I (601) is installed on the pier (100), and one end of the movable clamp I (601) is hinged with a movable clamp II (6011). The movable clamp I (601) and the movable clamp II (6011) are in contact with the clamp (1), and the clamp (1) is used to limit the position of the movable clamp I (601) and the movable clamp II (6011). The telescopic rod (505) is used to limit the position of the movable clamp I (601) and the movable clamp II (6011). The movable clamp I (601) and the movable clamp II (6011) are provided with a plurality of balls I in an annular array, the balls I are in contact with the pier (100), and the balls I are used to provide the movable clamp I (601) and the movable clamp II (6011) with movement, one end of the extension rod (505) and the bottom of the movable clamp I (601) and the movable clamp II (6011) are provided with positioning holes, the extension rod (505) is inserted into the bottom of the movable clamp I (601) and the movable clamp II (6011), and the extension rod (505) and the movable clamp I (601) are provided with positioning holes. A latch pin I is clamped in the positioning hole of the movable clamp (601) and the movable clamp II (6011), and the latch pin I is used to limit the position of the extension rod (404). An arc-shaped protruding plate I (602) is fixedly connected to one end face of the movable clamp I (601), and an engagement groove I is provided on one end face of the movable clamp II (6011). The arc-shaped protruding plate I (602) is inserted into the engagement groove I of the movable clamp II (6011). An elastic blocking block (603) is slidably connected in the engagement groove I of the movable clamp II (6011). The arc-shaped protruding plate I (602) and the elastic blocking block (603) are slidably connected. The movable clamp II (6011) and the arc-shaped protruding plate I (602) are provided with circular through holes, the circular through holes of the movable clamp II (6011) are connected with the engaging groove I, and the movable clamp II (6011) and the arc-shaped protruding plate I (602) are slidably connected with an elastic limiting pin (604) in the circular through holes, and the elastic limiting pin (604) is used to limit the position of the movable clamp II (6011) and the arc-shaped protruding plate I (602).

7. A device for synchronous construction of double tie beams according to claim 6, characterized in that: The lifting mechanism includes a sliding plate (701). A rectangular groove is provided on one side of the movable clamp I (601) and the movable clamp II (6011). The sliding plate (701) is slidably connected in the rectangular grooves of the movable clamp I (601) and the movable clamp II (6011). A U-shaped frame (702) is snap-fitted in the rectangular grooves of the movable clamp I (601) and the movable clamp II (6011). The U-shaped frame (702) contacts the sliding plate (701). The sliding plate (701) is used to limit the position of the U-shaped frame (702). One end of a multi-section extension frame (703) is fixedly connected to the U-shaped frame (702). A slider (704) is slidably connected in the multi-section extension frame (703). One end of a bidirectional screw rod (705) is rotatably connected in the multi-section extension frame (703). The other end of the bidirectional screw rod (705) is rotatably connected through the multi-section extension frame (703). The slider (704) is threadedly connected to the bidirectional screw rod (705). One end of a connecting rod (706) is hinged to the slider (704). The other end of the connecting rod (706) is hinged to a support plate (707). The rotating plate I (2) and the rotating plate II (201) are hinged to the support plate (707).

8. The device for synchronous construction of double tie beams according to claim 7, characterized in that: It further includes a telescopic support rod (801). The telescopic support rod (801) is hinged in the multi-section extension frame (703). A number of limiting holes are provided in the telescopic support rod (801). An elastic sliding plate (802) is slidably connected to one side of the telescopic support rod (801). A locking pin (803) is slidably connected through the elastic sliding plate (802). The locking pin (803) is inserted into a number of limiting holes of the telescopic support rod (801). The locking pin (803) is used to limit the position of the telescopic support rod (801). One end of the telescopic support rod (801) is hinged to the support plate (707).

9. The device for synchronous construction of double tie beams according to claim 1, characterized in that: It further includes the arc-shaped protruding plate II (9). The arc-shaped protruding plate II (9) is fixedly connected to one side end face of the rotating plate I (2). A meshing groove II is provided on one side end face of the rotating plate II (201). The arc-shaped protruding plate II (9) is inserted into the meshing groove II of the rotating plate II (201). A pin hole is provided through the arc-shaped protruding plate II (9) and the rotating plate II (201). A pin II is slidably connected in the pin holes of the arc-shaped protruding plate II (9) and the rotating plate II (201). The pin II is used to limit the position of the arc-shaped protruding plate II (9). A number of balls II are provided in both the rotating plate I (2) and the rotating plate II (201). The balls II contact the pier (100). The balls II are used to provide movement for the rotating plate I (2) and the rotating plate II (201).

10. The device for synchronous construction of double tie beams according to claim 1, characterized in that: It also includes a sliding frame (1001), one side of the storage frame (301) is slidably connected to the sliding frame (1001), one end of a moving block (1002) is slidably connected inside the sliding frame (1001), the other end of the moving block (1002) is inserted into the guide groove (311), and the moving block (1002) is used to limit the position of the overlapping rod (302).

Citation Information

Cited By

  • Hoop elbow convenient to install

    CN119412565A