New energy field station group shared energy storage long-term planning method, device, equipment and medium
By obtaining load growth data of new energy station clusters and dividing planning stages, building a long-term expansion planning model for shared energy storage, optimizing the investment and operation strategies of shared energy storage systems, the problem of inability to plan shared energy storage in real time in the existing technology is solved. , improve resource utilization efficiency and regulation capabilities.
Patent Information
- Application Number
- CN202411177147.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-26
- Publication Date
- 2024-12-03
AI Technical Summary
It is difficult for the existing technology to carry out shared energy storage planning for new energy station groups in real time, resulting in waste of shared energy storage capacity or reduced regulation capacity and reduced resource utilization efficiency.
By obtaining the load growth data of the new energy station group, dividing multiple planning stages, computing the equipment capacity planning sequence and timing output set, building a shared energy storage long-term expansion planning model, determining the planning capacity of each stage, combining the target constraints and Energy storage technology characteristics, optimize the investment and operation strategies of shared energy storage systems.
It has achieved a balance between the growth of new energy installed capacity and the innovation of energy storage technology, ensured real-time planning of shared energy storage, improved resource utilization efficiency and regulation capabilities, and avoided waste of shared energy storage capacity and reduced regulation capabilities.
Smart Images

Figure CN119070356A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of energy storage technology, and in particular to a method, device, equipment and medium for long-term planning of shared energy storage for a new energy station group. Background Art
[0002] Driven by energy transformation and the "dual carbon" goal, new energy power generation has developed on a large scale, but it has the problem of intermittent output. Energy storage has the advantages of smoothing the fluctuation of new energy output and energy space-time transfer, and is an effective means to solve the above challenges. In order to improve the friendly grid-connected capability of new energy stations on the power generation side, many places in my country have successively issued new energy supporting energy storage policies. However, the high cost of energy storage has seriously hindered the investment and construction of energy storage.
[0003] In view of the success of many "sharing economies", the concept of sharing economy has gradually emerged in the field of power systems, and shared energy storage has become a research hotspot to reduce the scale of traditional energy storage investment. Based on the above definition of sharing economy, the core of shared energy storage is to separate the ownership and use rights of energy storage equipment, activate the utilization rate of energy storage resources through frequent interactions between entities, further improve the economy of energy storage, and play an important supporting role in the large-scale development of energy storage. However, compared with the sharing of general resources, there is no need to consider the real-time balance problem, while in the power system, system balance is an important factor to ensure the stable operation of the power system. Therefore, real-time power balance is a unique feature of shared energy storage, and it is also a difficulty in implementing shared energy storage. The energy storage sharing model can cope with the problems of low equipment utilization and poor economic benefits in the traditional energy storage model. Combining the energy storage sharing model with the differences in energy storage time scales of different energy storage technologies can solve the limitations of renewable energy multi-time scale regulation requirements under a single type of energy storage sharing model.
[0004] In the related technologies, the focus is usually on studying the planning strategies of shared energy storage in the short time scale. However, in the related technologies, the planning strategies in the short time scale usually cannot take into account the impact of potential factors in the energy field such as the growth of new energy installed capacity and the innovation of energy storage technology on the shared energy storage planning, which further leads to the shared energy storage planning being ahead of schedule, resulting in the waste of shared energy storage capacity; or the lagging planning leading to the decline of the regulation capacity of shared energy storage. Summary of the invention
[0005] The present application provides a method, device, equipment and medium for long-term planning of shared energy storage for a group of new energy stations, so as to solve the problems in the related technology that shared energy storage planning cannot be carried out in real time, which easily leads to waste of shared energy storage capacity or reduction of the regulation capacity of shared energy storage, thereby reducing the utilization efficiency of resources.
[0006] A first aspect of the present application provides a method for long-term planning of shared energy storage for a new energy site group, comprising the following steps: obtaining load growth data of the new energy site group; dividing the planning period of the centralized shared energy storage power station into multiple stages according to the load growth data; calculating the equipment capacity planning sequence set and the equipment timing output set according to the equipment capacity planning sequence set of each stage, and calculating the cumulative value of the capacity of each sub-component of the centralized shared energy storage power station in each stage according to the equipment capacity planning sequence set; constructing a shared energy storage long-term expansion planning model according to the equipment timing output set, the cumulative value of the capacity of each sub-component and the long-term planning target of shared energy storage, and determining the planned capacity of each stage of the centralized shared energy storage power station based on the shared energy storage long-term expansion planning model.
[0007] Optionally, in one embodiment of the present application, a shared energy storage long-term expansion planning model is constructed based on the equipment time-series output set, the cumulative value of each sub-component capacity and the long-term planning target of shared energy storage, including: obtaining target constraints of the centralized shared energy storage power station; constructing a shared energy storage long-term expansion planning model based on the target constraints, the equipment time-series output set, the cumulative value of each sub-component capacity and the long-term planning target of shared energy storage.
[0008] Optionally, in one embodiment of the present application, the long-term expansion planning model of shared energy storage is:
[0009]
[0010] Among them, maxTI is the goal of maximizing benefits; CP SES The payment function for smoothing the output curve of multiple renewable energy stations; CS SES Subsidy income for new energy storage investment; CI SES Investment costs for shared energy storage; CO SES CV is the operation and maintenance cost of energy storage equipment; SES Recover the residual value of shared energy storage equipment; They are the interactive unit power purchase / sale prices between the shared energy storage operator and the new energy station r in stage s and period t; They are respectively the investment and construction subsidy cost coefficient / operation and maintenance cost coefficient / residual value recovery cost coefficient of the m-type subcomponent of the shared energy storage system; They are respectively the charging / discharging power of the shared energy storage used by the new energy station r in the s phase and the t period; is the residual value of the m-type subcomponent of the shared energy storage system in stage s; is the annual average rate of each subcomponent of the shared energy storage system type m; is the unit investment cost of the m-type subcomponent of the shared energy storage system; is the investment cost of the m-type subcomponent of the shared energy storage system in stage s; is the residual value coefficient of the m-type subcomponent of the shared energy storage system; is the full-cycle operating life of the shared energy storage m-type subcomponent; r is the new energy site index; s is the shared energy storage planning stage index; t is the shared energy storage operating time period index.
[0011] Optionally, in one embodiment of the present application, the target constraints include at least one of the upper and lower limit constraints on electrochemical energy storage charging and discharging power, the operation constraints of the electrolyzer and the operation constraints of the fuel cell, the energy continuity constraints during the operation of shared energy storage, the energy continuity constraints inside the hydrogen storage tank, and the power balance constraints between the new energy station group and the centralized shared energy storage power station.
[0012] Optionally, in one embodiment of the present application, the upper and lower limits of the electrochemical energy storage charge and discharge power are constrained as follows:
[0013]
[0014] in, The upper and lower limits of the electrochemical energy storage discharge power; is the binary variable for the shared energy storage discharge during period t in stage s of the planning period; is the rated power of electrochemical energy storage in shared energy storage during the planning period s; The upper and lower limits of the electrochemical energy storage charging power; is a binary variable for shared energy storage charging during period t in stage s of the planning period; s is the index of the shared energy storage planning stage; t is the index of the shared energy storage operation time period;
[0015] The operating constraints of the electrolyzer and the fuel cell are:
[0016]
[0017] in, The upper and lower limits of the electrochemical energy storage discharge power; is a binary variable for the electrolytic cell operating status during period t in stage s of the planning period; is the electrolytic power of the electrolytic cell accumulated during the planning period s; The upper and lower limits of the electrochemical energy storage charging power; The power released by the fuel cell during the planning period s and time period t; is the released power of the fuel cell at time t in stage s of the planning period; s is the index of the shared energy storage planning stage; t is the index of the shared energy storage operation time period;
[0018] The energy continuity constraint during the operation of shared energy storage is:
[0019]
[0020] in, is the internal capacity of the electrochemical energy storage during the planning period s stage t period; is the internal capacity of the electrochemical energy storage during the planning period s period t-1; Charging conversion efficiency for electrochemical energy storage; The upper and lower limits of the electrochemical energy storage discharge power; The upper and lower limits of the electrochemical energy storage charging power; is the electrochemical energy storage discharge conversion efficiency; Δt is the time interval; is the minimum internal charge coefficient of electrochemical energy storage; is the accumulated electricity in the electrochemical energy storage during the planning period s; is the maximum internal charge coefficient of electrochemical energy storage; is the initial charge inside the electrochemical energy storage during the planning period s; is the final charge inside the electrochemical energy storage at the planning stage s; s is the index of the shared energy storage planning stage; t is the index of the shared energy storage operation time period; b is the index of the electrochemical energy storage subcomponent;
[0021] The energy continuity constraint inside the hydrogen storage tank is:
[0022]
[0023] in, is the internal energy of the hydrogen storage tank during the planning period s and time period t; is the internal energy of the hydrogen storage tank during the planning period s period t-1; is the hydrogen production of the electrolyzer at time t in stage s of the planning period; is the hydrogen consumption of the fuel cell at time t in stage s of the planning period; Δt is the time interval; is the minimum coefficient of energy that can be stored within the planning period s stage t period; is the internal electrolysis power of the hydrogen energy storage system during period t in stage s of the planning period; is the maximum coefficient of energy that can be stored within the planning period s stage t period; is the initial energy of the hydrogen storage tank’s internal energy during the planning period s and time period t; is the final energy inside the hydrogen storage tank during the planning period s period t; s is the shared energy storage planning stage index; t is the shared energy storage operation time period index; h is the subcomponent index of the hydrogen energy storage system;
[0024] The power balance constraint between the new energy station cluster and the centralized shared energy storage power station is:
[0025]
[0026] in, The regional load of the output of the new energy station in the planning period s; The positive power deviation of the new energy station grid connection during the planning period s; The discharge power of the shared energy storage used by the new energy station r in the s phase and the t period; The regional load borne by the new energy stations in the planning period s; The negative power deviation of the new energy station grid connection during the planning period s; is the charging power of shared energy storage used by new energy station r in stage s and period t; r is the new energy station; s is the index of the shared energy storage planning stage; t is the index of the shared energy storage operation time period.
[0027] Optionally, in one embodiment of the present application, the calculation formula for the cumulative value of the capacity of each sub-component is:
[0028]
[0029] in, It is the cumulative value of the capacity of each sub-component of the shared energy storage; Replacement constraints for each sub-component of shared energy storage and the capacity attenuation rate of each sub-component; Configure capacity accumulation values for multi-stage time series.
[0030] Optionally, in one embodiment of the present application, there is a linear relationship between the cumulative value of the capacity of each sub-component of the centralized shared energy storage power station and the rated power in each stage.
[0031] The second aspect of the present application provides a long-term planning device for shared energy storage of a new energy site group, including: an acquisition module, used to obtain load growth data of the new energy site group; a division module, used to divide the planning period of the centralized shared energy storage power station into multiple stages according to the load growth data; a calculation module, used to calculate the equipment capacity planning sequence set and the equipment timing output set according to the equipment capacity planning sequence set of each stage, and calculate the cumulative value of the capacity of each sub-component of the centralized shared energy storage power station in each stage according to the equipment capacity planning sequence set; a construction module, used to construct a shared energy storage long-term expansion planning model according to the equipment timing output set, the cumulative value of the capacity of each sub-component and the shared energy storage long-term planning target, and determine the planned capacity of each stage of the centralized shared energy storage power station based on the shared energy storage long-term expansion planning model.
[0032] The third aspect of the present application provides an electronic device, including: a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor executes the program to implement the above-mentioned method for long-term planning of shared energy storage for a group of new energy stations.
[0033] The fourth aspect of the present application provides a computer-readable storage medium having a computer program or instruction stored thereon, which, when executed, implements the above-mentioned method for long-term planning of shared energy storage for a group of new energy stations.
[0034] Therefore, this application includes the following beneficial effects:
[0035] Based on the interactive relationship between the shared energy storage operator and the entities participating in energy sharing, the embodiment of the present application proposes a long-term operation strategy for shared energy storage that meets the long-term evolution of multiple renewable energy sites; based on the charging and discharging characteristics of the energy storage system, a centralized shared hybrid energy storage model suitable for multi-time scale regulation needs is proposed; based on the influencing factors such as "source-load" growth and energy storage technology innovation, a long-term multi-stage planning model for centralized shared energy storage serving multiple renewable energy sites is constructed, thereby realizing the construction of a long-term multi-stage planning model for centralized shared energy storage systems for electric-hydrogen hybrid energy storage from the perspective of energy distribution, thereby ensuring that shared energy storage can be planned in real time, and taking into account the impact of potential factors in the energy field such as the growth of new energy installed capacity and energy storage technology innovation on shared energy storage planning, thereby improving resource utilization efficiency and improving the regulation capacity of shared energy storage. As a result, the technical problems that the related technology usually cannot carry out shared energy storage planning in real time, which easily leads to the waste of shared energy storage capacity or the reduction of the regulation capacity of shared energy storage, thereby reducing the utilization efficiency of resources, etc. are solved.
[0036] Additional aspects and advantages of the present application will be given in part in the description below, and in part will become apparent from the description below, or will be learned through the practice of the present application. BRIEF DESCRIPTION OF THE DRAWINGS
[0037] The above and / or additional aspects and advantages of the present application will become apparent and easily understood from the following description of the embodiments in conjunction with the accompanying drawings, in which:
[0038] Figure 1 A schematic diagram of a process for long-term planning of shared energy storage for a new energy station group provided according to an embodiment of the present application;
[0039] Figure 2 A schematic diagram of a long-term planning method for shared energy storage of a new energy station group provided according to an embodiment of the present application;
[0040] Figure 3 A schematic diagram of a process for a long-term planning method for shared energy storage of a new energy station group provided according to an embodiment of the present application;
[0041] Figure 4 It is a block diagram of a device for long-term planning of shared energy storage of a new energy station group according to an embodiment of the present application;
[0042] Figure 5 Schematic diagram of the structure of an electronic device according to an embodiment of the present application. DETAILED DESCRIPTION
[0043] The embodiments of the present application are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present application, and should not be construed as limiting the present application.
[0044] The following describes the method, device, equipment and medium for long-term planning of shared energy storage for a new energy station group according to an embodiment of the present application with reference to the accompanying drawings. In view of the problem mentioned in the above background technology that shared energy storage planning cannot be performed in real time, which easily causes shared energy storage capacity to be wasted or the adjustment capacity of shared energy storage to be reduced, thereby reducing the utilization efficiency of resources, the present application provides a method for long-term planning of shared energy storage for a new energy station group, in which the load growth data of the new energy station group is obtained; the planning cycle of the centralized shared energy storage power station is divided into multiple stages according to the load growth data; the equipment capacity planning sequence set and the equipment timing output set are calculated according to the equipment capacity planning sequence set of each stage, and the cumulative value of the capacity of each sub-component of the centralized shared energy storage power station in each stage is calculated according to the equipment capacity planning sequence set; a shared energy storage long-term expansion planning model is constructed according to the equipment timing output set, the cumulative value of the capacity of each sub-component and the long-term planning target of shared energy storage, and the planned capacity of each stage of the centralized shared energy storage power station is determined based on the shared energy storage long-term expansion planning model. This solves the problem that the common problem in related technologies is that shared energy storage planning cannot be carried out in real time, which easily leads to waste of shared energy storage capacity or reduced regulation capacity of shared energy storage, thereby reducing resource utilization efficiency.
[0045] Specifically, Figure 1 A flowchart of a method for long-term planning of shared energy storage for a group of new energy stations provided in an embodiment of the present application.
[0046] like Figure 1 As shown, the long-term planning method for shared energy storage of new energy stations includes the following steps:
[0047] In step S101, load growth data of the new energy station group is obtained.
[0048] It is understandable that the load growth data may include the expected changes in power output of the new energy site cluster over time, the growth trend of load demand, and the intermittent characteristics of renewable energy generation.
[0049] Specifically, load growth data can be used through statistical methods, machine learning models or professional forecasting software, combined with multi-dimensional data such as macroeconomic indicators, population growth, industrial development, and policy orientation, to predict future renewable energy power generation and load demand; it can be obtained by analyzing the power generation and load demand records of new energy stations in the past few years, identifying seasonal, cyclical and trend changes, etc., without specific limitations here.
[0050] In step S102, the planning period of the centralized shared energy storage power station is divided into multiple stages according to the load growth data.
[0051] It is understandable that if Figure 2 As shown in the figure, based on the load growth, the planning period of centralized shared energy storage is divided into W stages, and the multi-stage time series set S = {S1, S2, …S w};
[0052] It should be noted that in the embodiments of the present application, the model of the device is taken as type M, which is not specifically limited here.
[0053] A multi-stage set based on the planning cycle and a set of capacity planning sequences of type m equipment in the corresponding stage Get the cumulative configuration capacity of the corresponding equipment And M-type equipment timing output collection
[0054] Where y is the year in the planning period and t is the planning hour sequence.
[0055] Therefore, in the embodiments of the present application, a long-term multi-stage planning model for centralized shared energy storage serving multiple renewable energy stations can be constructed based on influencing factors such as "source-load" growth and energy storage technology innovation.
[0056] In step S103, the equipment capacity planning sequence set and the equipment time sequence output set are calculated according to the equipment capacity planning sequence set in each stage, and the cumulative value of the capacity of each sub-component of the centralized shared energy storage power station in each stage is calculated according to the equipment capacity planning sequence set.
[0057] It can be understood that in the embodiments of the present application, the subcomponents may include electrochemical battery packs, electrolyzers, hydrogen storage tanks, etc.; the energy storage technology may include electrochemical energy storage and hydrogen energy storage, etc.
[0058] Optionally, in one embodiment of the present application, the calculation formula for the cumulative value of the capacity of each sub-component is:
[0059]
[0060] in, It is the cumulative value of the capacity of each sub-component of the shared energy storage; Replacement constraints for each sub-component of shared energy storage and the capacity attenuation rate of each sub-component; Configure capacity accumulation values for multi-stage time series.
[0061] Replacement constraints of shared energy storage sub-components and capacity attenuation rate of each sub-component for:
[0062]
[0063] in, represents the efficiency decay rate of the shared energy storage m-type subassembly, For the full cycle operation life of the shared energy storage M-type sub-assembly, the available capacity constraints of each sub-assembly of the shared energy storage at each stage during the planning period are:
[0064]
[0065] in, The available capacity of each sub-component of type m for shared energy storage; The efficiency decay rate of the shared energy storage M-type subassembly is used; Configure the capacity accumulation value for each subcomponent timing of the multi-stage m-type.
[0066] Therefore, in the embodiment of the present application, by taking into account the decay of the use efficiency of the shared energy storage device, when the service life of the shared energy storage device exceeds its full life cycle, the shared energy storage device can be replaced in time.
[0067] Optionally, in one embodiment of the present application, there is a linear relationship between the cumulative value of the capacity of each sub-component of the centralized shared energy storage power station and the rated power in each stage.
[0068] Specifically, the available capacity of electrochemical energy storage in shared energy storage is With rated power For example, there is a linear relationship between:
[0069]
[0070] Wherein, b is the index of the electrochemical energy storage subcomponent; ε represents the energy rate coefficient between the capacity and power of the electrochemical energy storage battery.
[0071] The embodiment of the present application can propose a centralized shared hybrid energy storage model suitable for multi-time scale regulation needs based on the charging and discharging characteristics of the energy storage system.
[0072] Therefore, in the embodiments of the present application, on the basis of considering the impact of potential factors in the energy field such as the growth of new energy installed capacity and the innovation of energy storage technology on the shared energy storage planning, the configuration is made more economical by adding a variety of energy storage technologies and sharing concepts; based on the load growth data of the new energy station group and the characteristics of the energy storage technology, the planner will set a set of detailed equipment capacity planning for each stage in the entire planning cycle, and realize the accurate estimation of the capacity required for energy storage equipment in each stage, which may include different types of energy storage subsystems such as electrochemical energy storage and hydrogen energy storage, and determine the optimal capacity configuration for each stage according to their adjustment capabilities on different time scales.
[0073] In step S104, a shared energy storage long-term expansion planning model is constructed according to the equipment time series output set, the accumulated value of each sub-component capacity and the shared energy storage long-term planning target, and the planned capacity of each stage of the centralized shared energy storage power station is determined based on the shared energy storage long-term expansion planning model.
[0074] It should be noted that the long-term multi-stage planning model provided in the embodiment of the present application is obtained based on the following assumptions: the installed capacity of new energy stations will increase at a certain rate; the regional load borne by the new energy stations will increase at a certain rate; and the information between stations is completely open.
[0075] It is understandable that, based on the charging and discharging characteristics of energy storage, energy storage equipment with different technical characteristics are distributed inside the centralized shared energy storage to meet the regulation needs of multiple renewable energy stations at multiple time scales; shared energy storage planning decisions are determined by the regulation needs of each renewable energy station and the innovation of energy storage technology; shared energy storage operators will take into account the future changes in multiple renewable energy stations and obtain renewable energy output fluctuation regulation information from multiple renewable energy stations; based on the current innovation of energy storage technology and its own economic benefits, shared energy storage operators optimize the investment plans for shared energy storage at each stage of the planning cycle.
[0076] Optionally, in one embodiment of the present application, a shared energy storage long-term expansion planning model is constructed based on the equipment time-series output set, the cumulative value of each sub-component capacity and the long-term planning target of shared energy storage, including: obtaining target constraints of the centralized shared energy storage power station; constructing a shared energy storage long-term expansion planning model based on the target constraints, the equipment time-series output set, the cumulative value of each sub-component capacity and the long-term planning target of shared energy storage.
[0077] Optionally, in one embodiment of the present application, the target constraints include at least one of the upper and lower limit constraints on electrochemical energy storage charging and discharging power, the operation constraints of the electrolyzer and the operation constraints of the fuel cell, the energy continuity constraints during the operation of shared energy storage, the energy continuity constraints inside the hydrogen storage tank, and the power balance constraints between the new energy station group and the centralized shared energy storage power station.
[0078] Optionally, in one embodiment of the present application, the upper and lower limits of the electrochemical energy storage charge and discharge power are constrained as follows:
[0079]
[0080] in, The upper and lower limits of the electrochemical energy storage discharge power; is the binary variable for the shared energy storage discharge during period t in stage s of the planning period; is the rated power of electrochemical energy storage in shared energy storage during the planning period s; The upper and lower limits of the electrochemical energy storage charging power; is a binary variable for shared energy storage charging during period t in stage s of the planning period; s is the index of the shared energy storage planning stage; and t is the index of the shared energy storage operation time period.
[0081] Among them, when When the shared energy storage discharges; Time-sharing energy storage charging.
[0082] Therefore, in the embodiment of the present application, when the energy storage provides charging and discharging services to each participating entity in the sharing mode, the shared energy storage operator adjusts the shared energy storage charging and discharging power according to the needs of each participating entity to ensure that the electrochemical energy storage charging and discharging power does not exceed the rated power, thereby improving the safety of energy storage.
[0083] The operating constraints of the electrolyzer and the fuel cell are:
[0084]
[0085] in, The upper and lower limits of the electrochemical energy storage discharge power; is a binary variable for the electrolytic cell operating status during period t in stage s of the planning period; is the electrolytic power of the electrolytic cell accumulated during the planning period s; The upper and lower limits of the electrochemical energy storage charging power; The power released by the fuel cell during the planning period s and time period t; is the released power of the fuel cell at time t in stage s of the planning period; s is the index of the shared energy storage planning stage; t is the index of the shared energy storage operation time period.
[0086] Specifically, When it is 1, it means that the electrolytic cell starts running during the planning period s stage t period, otherwise it stops running. When it is 1, it means that the fuel cell releases power during the planning period s stage and time period t, otherwise it stops running.
[0087] During the operation of shared energy storage, its energy continuity needs to be constrained to ensure the safe and stable operation of shared energy storage. The energy continuity constraints during the operation of shared energy storage are:
[0088]
[0089] in, is the internal capacity of the electrochemical energy storage during the planning period s stage t period; is the internal capacity of the electrochemical energy storage during the planning period s period t-1; Charging conversion efficiency for electrochemical energy storage; The upper and lower limits of the electrochemical energy storage discharge power; The upper and lower limits of the electrochemical energy storage charging power; is the electrochemical energy storage discharge conversion efficiency; Δt is the time interval; is the minimum internal charge coefficient of electrochemical energy storage; is the accumulated electricity in the electrochemical energy storage during the planning period s; is the maximum internal charge coefficient of electrochemical energy storage; is the initial charge inside the electrochemical energy storage during the planning period s; is the final charge inside the electrochemical energy storage at stage s of the planning period; s is the index of the shared energy storage planning stage; t is the index of the shared energy storage operation time period; and b is the index of the electrochemical energy storage subcomponent.
[0090] in, It means that in the planning period s stage and time period t, the internal charge of the electrochemical energy storage not only depends on the energy change at the current moment, but also is related to the energy of the previous time period. The specific calculation is shown in the first line of the above formula. The second line of the above formula limits the electrochemical energy storage capacity. The third line of the above formula constrains the energy storage power balance on a short time scale.
[0091] The energy continuity constraint inside the hydrogen storage tank is:
[0092]
[0093] in, is the internal energy of the hydrogen storage tank during the planning period s and time period t; is the internal energy of the hydrogen storage tank during the planning period s period t-1; is the hydrogen production of the electrolyzer at time t in stage s of the planning period; is the hydrogen consumption of the fuel cell at time t in stage s of the planning period; Δt is the time interval; is the minimum coefficient of energy that can be stored within the planning period s stage t period; is the internal electrolysis power of the hydrogen energy storage system during period t in stage s of the planning period; is the maximum coefficient of energy that can be stored within the planning period s stage t period; is the initial energy of the hydrogen storage tank’s internal energy during the planning period s and time period t; is the final energy inside the hydrogen storage tank during period t in stage s of the planning period; s is the index of the shared energy storage planning stage; t is the index of the shared energy storage operation time period; and h is the subcomponent index of the hydrogen energy storage system.
[0094] It can be understood that the first line of the above formula constrains the internal energy continuity of the hydrogen storage tank, the second line of the above formula restricts the internal energy operation of the hydrogen storage tank, and the third line of the above formula is the long-time scale energy storage power balance constraint.
[0095] In the shared energy storage system, the electrolyzer for hydrogen energy storage is used as a hydrogen production unit. When the short-term energy storage equipment cannot meet the energy storage needs of each entity, hydrogen is produced by absorbing the redundant output of each entity participating in energy sharing. The mathematical model of electricity-hydrogen energy conversion is:
[0096]
[0097] Among them, s / t are the shared energy storage planning stage index / operation time period index, h is the subcomponent index of the hydrogen energy storage system, and the hydrogen production of the electrolyzer and the electrolysis power of the electrolyzer at time t in the planning period are respectively expressed as express; is the hydrogen production electrolysis efficiency of the electrolyzer, is the electricity-to-hydrogen energy conversion coefficient of the electrolyzer.
[0098] In the shared energy storage system, the fuel cell for hydrogen energy storage is used as a power generation unit. When the short-term energy storage equipment cannot meet the energy demand of each entity, the fuel cell converts the hydrogen energy in the hydrogen storage tank into electrical energy to provide electrical energy to each entity participating in energy sharing. The mathematical model of hydrogen-electricity energy conversion is:
[0099]
[0100] Among them, the hydrogen consumption of the fuel cell and the power released by the fuel cell at time t in the planning period are respectively express; is the fuel cell hydrogen-to-electricity conversion efficiency, is the hydrogen-electricity energy conversion coefficient of the fuel cell.
[0101] Therefore, in an embodiment of the present application, based on the charging and discharging characteristics of the energy storage system, a centralized shared hybrid energy storage model suitable for multi-time scale regulation needs is proposed; based on the energy storage charging and discharging characteristics, energy storage devices with different technical characteristics are distributed inside the centralized shared energy storage to meet the multi-time scale regulation needs of multiple new energy stations.
[0102] The power balance constraint between the new energy station cluster and the centralized shared energy storage power station is:
[0103]
[0104] in, The regional load of the output of the new energy station in the planning period s; The positive power deviation of the new energy station grid connection during the planning period s; The discharge power of the shared energy storage used by the new energy station r in the s phase and the t period; The regional load borne by the new energy stations in the planning period s; The negative power deviation of the new energy station grid connection during the planning period s; is the charging power of shared energy storage used by new energy station r in stage s and period t; r is the new energy station; s is the index of the shared energy storage planning stage; t is the index of the shared energy storage operation time period.
[0105] Therefore, the embodiments of the present application can meet the power supply and demand balance of each new energy station participating in energy sharing to ensure the safe and stable operation of each new energy station.
[0106] It is understandable that shared energy storage operators invest in short-term and long-term energy storage to meet the regulation needs of multiple entities and time scales. Therefore, there is a certain power balance relationship between shared energy storage and the new energy stations that interact with it. The power balance relationship is:
[0107]
[0108] in, Charging power for shared energy storage systems; is the charging rated power of the electrochemical energy storage during the period t in the phase s; is the power of the electrolyzer at time t in stage s of the planning period; The discharge power of the shared energy storage used by the new energy station r in the s phase and the t period; Discharge power to the shared energy storage system; is the charging rated power of the electrochemical energy storage during the period t in the phase s; is the power of the fuel cell at time t in stage s of the planning period; is the discharge power of the shared energy storage used by the new energy station r in the s stage and t period; r is the new energy station; s is the shared energy storage planning stage index; t is the shared energy storage operation time period index.
[0109] In an embodiment of the present application, based on the load growth data of the new energy station group and the interaction parameters between the new energy station group and the shared energy storage operator obtained through actual engineering applications, the interaction relationship between the shared energy storage operator and the entities participating in energy sharing (i.e., the new energy station group) is obtained, thereby proposing a shared energy storage long-term operation strategy that meets the long-term evolution of multiple new energy stations.
[0110] Specifically, based on the interactive relationship between shared energy storage operators and multiple renewable energy stations, the regulation needs of multiple renewable energy stations at each stage during the planning period are calculated. When there is redundant energy inside the renewable energy station, there is a demand for storing electricity in the shared energy storage. When there is a shortage of electricity inside the renewable energy station, there is a demand for using the electricity inside the shared energy storage.
[0111] Therefore, in the embodiments of the present application, based on the interactive relationship between the shared energy storage operator and the entities participating in energy sharing, a long-term operation strategy for shared energy storage that meets the long-term evolution of multiple renewable energy sites can be proposed, thereby improving the accuracy of the construction of a long-term multi-stage planning model for centralized shared energy storage.
[0112] Among them, the long-term expansion planning model of shared energy storage is:
[0113]
[0114] Among them, maxTI is the goal of maximizing benefits; CP SES The payment function for smoothing the output curve of multiple renewable energy stations; CS SES Subsidy income for new energy storage investment; CI SES Investment costs for shared energy storage; CO SES CV is the operation and maintenance cost of energy storage equipment; SES Recover the residual value of shared energy storage equipment; They are the interactive unit power purchase / sale prices between the shared energy storage operator and the new energy station r in stage s and period t; They are respectively the investment and construction subsidy cost coefficient / operation and maintenance cost coefficient / residual value recovery cost coefficient of the m-type subcomponent of the shared energy storage system; They are respectively the charging / discharging power of the shared energy storage used by the new energy station r in the s phase and the t period; is the residual value of the m-type subcomponent of the shared energy storage system in stage s; is the annual average rate of each subcomponent of the shared energy storage system type m; is the unit investment cost of the m-type subcomponent of the shared energy storage system; is the investment cost of the m-type subcomponent of the shared energy storage system in stage s; is the residual value coefficient of the m-type subcomponent of the shared energy storage system; is the full-cycle operating life of the shared energy storage m-type subcomponent; r is the new energy site index; s is the shared energy storage planning stage index; t is the shared energy storage operating time period index.
[0115] It is understandable that shared energy storage operators use the complementary characteristics of short-term energy storage and long-term energy storage to adjust the different needs of multiple participants and build a long-term expansion planning model for shared energy storage with the goal of maximizing benefits (TI).
[0116] It is understandable that the payment function of the shared energy storage operator includes the payment function CP for smoothing the output curve of multiple renewable energy sites. SES , shared energy storage investment and construction subsidy income CS SES ,Shared energy storage investment cost CI SES , the operation and maintenance cost of energy storage equipment is CO SES , Shared energy storage equipment residual value recovery CV SES Among them, the residual value recovery of shared energy storage equipment is determined by the residual value recovery coefficient and the equipment residual value coefficient. The equipment residual value coefficient is the ratio of the equipment residual value to the full cycle life.
[0117] Annual average value rate of each subcomponent of shared energy storage The initial investment cost is converted into the payment cost of the same annual value, as shown in the following formula:
[0118]
[0119] Where γ is the discount rate; It is the full cycle operating life of the shared energy storage M-type sub-assembly.
[0120] The following is a description of the long-term planning method for shared energy storage of a new energy station group in the embodiment of the present application in conjunction with a specific embodiment. Figure 3 As shown, the specific process method is as follows:
[0121] S1. Based on the interactive relationship between shared energy storage operators and entities participating in energy sharing, a long-term operation strategy for shared energy storage is proposed to meet the needs of multiple renewable energy sites under the long-term evolution state;
[0122] S2. Based on the charging and discharging characteristics of the energy storage system, a centralized shared hybrid energy storage model suitable for multi-time scale regulation needs is proposed;
[0123] S3. Based on the influencing factors such as "source-load" growth and energy storage technology innovation, a long-term multi-stage planning model for centralized shared energy storage serving multiple renewable energy stations is constructed.
[0124] Therefore, in the embodiment of the present application, the shared energy storage planning decision is determined by the regulation needs of each new energy station and the innovation of energy storage technology; the shared energy storage operator will take into account the future change trends of multiple new energy stations, and obtain the renewable energy output fluctuation regulation information of multiple new energy stations; based on the current energy storage technology innovation situation and its own economic benefits, the shared energy storage operator optimizes the decision-making shared energy storage investment plan at each stage within the planning cycle.
[0125] According to the long-term planning method for shared energy storage of a group of new energy stations proposed in the embodiment of the present application, based on the interactive relationship between the shared energy storage operator and the entities participating in energy sharing, a long-term operation strategy for shared energy storage that meets the long-term evolution of multiple new energy stations is proposed; based on the charging and discharging characteristics of the energy storage system, a centralized shared hybrid energy storage model suitable for multi-time scale regulation needs is proposed; based on influencing factors such as "source-load" growth and energy storage technology innovation, a long-term multi-stage planning model for centralized shared energy storage serving multiple new energy stations is constructed, thereby realizing the construction of a long-term multi-stage planning model for a centralized shared energy storage system of electric-hydrogen hybrid energy storage from the perspective of energy distribution, thereby ensuring that shared energy storage can be planned in real time, and taking into account the impact of potential factors in the energy field such as the growth of new energy installed capacity and energy storage technology innovation on shared energy storage planning, thereby improving resource utilization efficiency and improving the regulation capacity of shared energy storage.
[0126] Next, a device for long-term planning of shared energy storage for a group of new energy stations according to an embodiment of the present application will be described with reference to the accompanying drawings.
[0127] Figure 4 It is a block diagram of a long-term planning device for shared energy storage of a new energy station group according to an embodiment of the present application.
[0128] like Figure 4 As shown, the new energy site group shared energy storage long-term planning device includes: an acquisition module 301, a division module 302, a calculation module 303 and a construction module 304.
[0129] Among them, the acquisition module 301 is used to obtain the load growth data of the new energy station group; the division module 302 is used to divide the planning period of the centralized shared energy storage power station into multiple stages according to the load growth data; the calculation module 303 is used to calculate the equipment capacity planning sequence set and the equipment timing output set according to the equipment capacity planning sequence set of each stage, and calculate the cumulative value of the capacity of each sub-component of the centralized shared energy storage power station in each stage according to the equipment capacity planning sequence set; the construction module 304 is used to construct a shared energy storage long-term expansion planning model according to the equipment timing output set, the cumulative value of the capacity of each sub-component and the long-term planning target of shared energy storage, and determine the planned capacity of each stage of the centralized shared energy storage power station based on the shared energy storage long-term expansion planning model.
[0130] The calculation formula for the cumulative value of each sub-component capacity is:
[0131]
[0132] in, It is the cumulative value of the capacity of each sub-component of the shared energy storage; Replacement constraints for each sub-component of shared energy storage and the capacity attenuation rate of each sub-component; Configure capacity accumulation values for multi-stage time series.
[0133] Optionally, in one embodiment of the present application, the calculation module 303 is further configured to provide a linear relationship between the cumulative value of the capacity of each sub-component of the centralized shared energy storage power station at each stage and the rated power.
[0134] Optionally, in one embodiment of the present application, the construction module 304 is further used to obtain target constraints of the centralized shared energy storage power station; and to construct a shared energy storage long-term expansion planning model according to the target constraints, the equipment time output set, the cumulative value of each sub-component capacity and the shared energy storage long-term planning goals.
[0135] Among them, the target constraints include at least one of the upper and lower limits of electrochemical energy storage charging and discharging power, the operation constraints of the electrolyzer and the fuel cell, the energy continuity constraints during the operation of shared energy storage, the energy continuity constraints inside the hydrogen storage tank, and the power balance constraints between the new energy station group and the centralized shared energy storage power station.
[0136] Among them, the long-term expansion planning model of shared energy storage is:
[0137]
[0138] Among them, maxTI is the goal of maximizing benefits; CP SES The payment function for smoothing the output curve of multiple renewable energy stations; CS SES Subsidy income for new energy storage investment; CI SES Investment costs for shared energy storage; CO SES CV is the operation and maintenance cost of energy storage equipment; SES Recover the residual value of shared energy storage equipment; They are the interactive unit power purchase / sale prices between the shared energy storage operator and the new energy station r in stage s and period t; They are respectively the investment and construction subsidy cost coefficient / operation and maintenance cost coefficient / residual value recovery cost coefficient of the m-type subcomponent of the shared energy storage system; They are respectively the charging / discharging power of the shared energy storage used by the new energy station r in the s phase and the t period; is the residual value of the m-type subcomponent of the shared energy storage system in stage s; is the annual average rate of each subcomponent of the shared energy storage system type m; is the unit investment cost of the m-type subcomponent of the shared energy storage system; is the investment cost of the m-type subcomponent of the shared energy storage system in stage s; is the residual value coefficient of the m-type subcomponent of the shared energy storage system; is the full-cycle operating life of the shared energy storage m-type subcomponent; r is the new energy station index; s is the shared energy storage planning stage index; t is the shared energy storage operation time period index;
[0139] Among them, the upper and lower limits of the electrochemical energy storage charging and discharging power are:
[0140]
[0141] in, The upper and lower limits of the electrochemical energy storage discharge power; is the binary variable for the shared energy storage discharge during period t in stage s of the planning period; is the rated power of electrochemical energy storage in shared energy storage during the planning period s; The upper and lower limits of the electrochemical energy storage charging power; is a binary variable for shared energy storage charging during period t in stage s of the planning period; s is the index of the shared energy storage planning stage; t is the index of the shared energy storage operation time period;
[0142] The operating constraints of the electrolyzer and the fuel cell are:
[0143]
[0144] in, The upper and lower limits of the electrochemical energy storage discharge power; is a binary variable for the electrolytic cell operating status during period t in stage s of the planning period; is the electrolytic power of the electrolytic cell accumulated during the planning period s; The upper and lower limits of the electrochemical energy storage charging power; The power released by the fuel cell during the planning period s and time period t; is the released power of the fuel cell at time t in stage s of the planning period; s is the index of the shared energy storage planning stage; t is the index of the shared energy storage operation time period;
[0145] The energy continuity constraint during the operation of shared energy storage is:
[0146]
[0147] in, is the internal capacity of the electrochemical energy storage during the planning period s stage t period; is the internal capacity of the electrochemical energy storage during the planning period s period t-1; Charging conversion efficiency for electrochemical energy storage; The upper and lower limits of the electrochemical energy storage discharge power; The upper and lower limits of the electrochemical energy storage charging power; is the electrochemical energy storage discharge conversion efficiency; Δt is the time interval; is the minimum internal charge coefficient of electrochemical energy storage; is the accumulated electricity in the electrochemical energy storage during the planning period s; is the maximum internal charge coefficient of electrochemical energy storage; is the initial charge inside the electrochemical energy storage during the planning period s; is the final charge inside the electrochemical energy storage at the planning stage s; s is the index of the shared energy storage planning stage; t is the index of the shared energy storage operation time period; b is the index of the electrochemical energy storage subcomponent;
[0148] The energy continuity constraint inside the hydrogen storage tank is:
[0149]
[0150] in, is the internal energy of the hydrogen storage tank during the planning period s and time period t; is the internal energy of the hydrogen storage tank during the planning period s period t-1; is the hydrogen production of the electrolyzer at time t in stage s of the planning period; is the hydrogen consumption of the fuel cell at time t in stage s of the planning period; Δt is the time interval; is the minimum coefficient of energy that can be stored within the planning period s stage t period; is the internal electrolysis power of the hydrogen energy storage system during period t in stage s of the planning period; is the maximum coefficient of energy that can be stored within the planning period s stage t period; is the initial energy of the hydrogen storage tank’s internal energy during the planning period s and time period t; is the final energy inside the hydrogen storage tank during the planning period s period t; s is the shared energy storage planning stage index; t is the shared energy storage operation time period index; h is the subcomponent index of the hydrogen energy storage system;
[0151] The power balance constraint between the new energy station cluster and the centralized shared energy storage power station is:
[0152]
[0153] in, The regional load of the output of the new energy station in the planning period s; The positive power deviation of the new energy station grid connection during the planning period s; The discharge power of the shared energy storage used by the new energy station r in the s phase and the t period; The regional load borne by the new energy stations in the planning period s; The negative power deviation of the new energy station grid connection during the planning period s; is the charging power of shared energy storage used by new energy station r in stage s and period t; r is the new energy station; s is the index of the shared energy storage planning stage; t is the index of the shared energy storage operation time period.
[0154] It should be noted that the aforementioned explanation of the embodiment of long-term planning for shared energy storage for a new energy station group is also applicable to the long-term planning device for shared energy storage for a new energy station group of this embodiment, and will not be repeated here.
[0155] According to the long-term planning device for shared energy storage of a group of new energy stations proposed in the embodiment of the present application, based on the interactive relationship between the shared energy storage operator and the entities participating in energy sharing, a long-term operation strategy for shared energy storage that meets the needs of multiple new energy stations under long-term evolutionary conditions is proposed; based on the charging and discharging characteristics of the energy storage system, a centralized shared hybrid energy storage model suitable for multi-time scale regulation needs is proposed; based on influencing factors such as "source-load" growth and energy storage technology innovation, a long-term multi-stage planning model for centralized shared energy storage serving multiple new energy stations is constructed, thereby realizing the construction of a long-term multi-stage planning model for a centralized shared energy storage system of electric-hydrogen hybrid energy storage from the perspective of energy distribution, thereby ensuring that shared energy storage can be planned in real time, and taking into account the impact of potential factors in the energy field such as the growth of new energy installed capacity and energy storage technology innovation on shared energy storage planning, thereby improving resource utilization efficiency and improving the regulation capacity of shared energy storage.
[0156] Figure 5 A schematic diagram of the structure of an electronic device provided in an embodiment of the present application. The electronic device may include:
[0157] Memory 401 , processor 402 , and a computer program stored in the memory 401 and executable on the processor 402 .
[0158] When the processor 402 executes the program, the long-term planning method for shared energy storage of a new energy station group provided in the above embodiment is implemented.
[0159] Furthermore, the electronic device further comprises:
[0160] The communication interface 403 is used for communication between the memory 401 and the processor 402 .
[0161] The memory 401 is used to store computer programs that can be executed on the processor 402 .
[0162] The memory 401 may include a high-speed RAM (Random Access Memory) memory, and may also include a non-volatile memory, such as at least one disk memory.
[0163] If the memory 401, the processor 402 and the communication interface 403 are implemented independently, the communication interface 403, the memory 401 and the processor 402 can be connected to each other through a bus and communicate with each other. The bus can be an ISA (Industry Standard Architecture) bus, a PCI (Peripheral Component Interconnect) bus or an EISA (Extended Industry Standard Architecture) bus, etc. The bus can be divided into an address bus, a data bus, a control bus, etc. For ease of representation, Figure 5 Only one thick line is used in the diagram, but this does not mean that there is only one bus or only one type of bus.
[0164] Optionally, in a specific implementation, if the memory 401, the processor 402 and the communication interface 403 are integrated on a chip, the memory 401, the processor 402 and the communication interface 403 can communicate with each other through an internal interface.
[0165] The processor 402 may be a CPU (Central Processing Unit), or an ASIC (Application Specific Integrated Circuit), or one or more integrated circuits configured to implement the embodiments of the present application.
[0166] An embodiment of the present application also provides a computer-readable storage medium having a computer program or instruction stored thereon, which, when executed, implements the above-mentioned method for long-term planning of shared energy storage for a group of new energy stations.
[0167] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. In this specification, the schematic representations of the above terms are not necessarily directed to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or N embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.
[0168] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include at least one of the features. In the description of this application, "N" means at least two, such as two, three, etc., unless otherwise clearly and specifically defined.
[0169] Any process or method description in a flowchart or otherwise described herein may be understood to represent a module, fragment or portion of code comprising one or N executable instructions for implementing the steps of a custom logical function or process, and the scope of the preferred embodiments of the present application includes alternative implementations in which functions may not be performed in the order shown or discussed, including performing functions in a substantially simultaneous manner or in reverse order depending on the functions involved, which should be understood by technicians in the technical field to which the embodiments of the present application belong.
[0170] It should be understood that the various parts of the present application can be implemented in hardware, software, firmware or a combination thereof. In the above-mentioned embodiments, the steps or methods can be implemented in software or firmware stored in a memory and executed by a suitable instruction execution system. For example, if implemented in hardware, as in another embodiment, it can be implemented by any one of the following technologies known in the art or their combination: a discrete logic circuit having a logic gate circuit for implementing a logic function on a data signal, a dedicated integrated circuit having a suitable combination of logic gate circuits, a programmable gate array, a field programmable gate array, etc.
[0171] A person of ordinary skill in the art may understand that all or part of the steps carried by the method for implementing the above-mentioned embodiment may be completed by instructing related hardware through a program, and the above-mentioned program may be stored in a computer-readable storage medium, which, when executed, includes one of the steps of the method embodiment or a combination thereof.
[0172] Although the embodiments of the present application have been shown and described above, it can be understood that the above embodiments are exemplary and cannot be understood as limitations on the present application. Ordinary technicians in this field can change, modify, replace and modify the above embodiments within the scope of the present application.
Claims
1. A method for long-term planning of shared energy storage for a new energy station group, characterized in that: The following steps are involved: Obtain the load growth data of the new energy station cluster; Dividing the planning cycle of the centralized shared energy storage power station into multiple stages according to the load growth data; Calculate the equipment capacity planning sequence set and the equipment time-series output set according to the equipment capacity planning sequence set in each stage, and calculate the cumulative value of each sub-component capacity of the centralized shared energy storage power station in each stage according to the equipment capacity planning sequence set; A shared energy storage long-term expansion planning model is constructed according to the equipment time-series output set, the accumulated value of the capacity of each sub-component and the shared energy storage long-term planning target, and the planned capacity of each stage of the centralized shared energy storage power station is determined based on the shared energy storage long-term expansion planning model.
2. The long-term planning method for shared energy storage of a new energy station group according to claim 1 is characterized in that: The method of constructing a shared energy storage long-term expansion planning model according to the equipment time sequence output set, the accumulated value of each sub-component capacity and the shared energy storage long-term planning target includes: Obtaining target constraints of the centralized shared energy storage power station; A shared energy storage long-term expansion planning model is constructed according to the target constraint conditions, the equipment time sequence output set, the cumulative value of the capacity of each sub-component and the shared energy storage long-term planning goal.
3. The long-term planning method for shared energy storage of a new energy station group according to claim 1 is characterized in that: The long-term expansion planning model of shared energy storage is: Among them, max TI is the goal of maximizing benefits; CP SES The payment function for smoothing the output curve of multiple renewable energy stations; CS SES Subsidy income for new energy storage investment; CI SES Investment costs for shared energy storage; CO SES CV is the operation and maintenance cost of energy storage equipment; SES Recover the residual value of shared energy storage equipment; They are the interactive unit power purchase / sale prices between the shared energy storage operator and the new energy station r in stage s and period t; They are respectively the investment and construction subsidy cost coefficient / operation and maintenance cost coefficient / residual value recovery cost coefficient of the m-type subcomponent of the shared energy storage system; They are respectively the charging / discharging power of the shared energy storage used by the new energy station r in the s phase and the t period; is the residual value of the m-type subcomponent of the shared energy storage system in stage s; is the annual average rate of each subcomponent of the shared energy storage system type m; is the unit investment cost of the m-type subcomponent of the shared energy storage system; is the investment cost of the m-type subcomponent of the shared energy storage system in stage s; is the residual value coefficient of the m-type subcomponent of the shared energy storage system; is the full-cycle operating life of the shared energy storage m-type subcomponent; r is the new energy site index; s is the shared energy storage planning stage index; t is the shared energy storage operating time period index.
4. The long-term planning method for shared energy storage of a new energy station group according to claim 2 is characterized in that: The target constraints include at least one of the upper and lower limits of electrochemical energy storage charging and discharging power, electrolyzer operation constraints and fuel cell operation constraints, energy continuity constraints during shared energy storage operation, energy continuity constraints inside hydrogen storage tanks, and power balance constraints between new energy station clusters and centralized shared energy storage power stations.
5. The long-term planning method for shared energy storage of a new energy station group according to claim 4 is characterized in that: The upper and lower limits of the electrochemical energy storage charge and discharge power are: in, Charging power for new energy stations; is a binary variable for shared energy storage charging during period t in stage s of the planning period; is the rated power of electrochemical energy storage in shared energy storage during the planning period s; Discharge power for new energy stations; is a binary variable for the shared energy storage discharge in period t during stage s of the planning period; s is the index of the shared energy storage planning stage; t is the index of the shared energy storage operation time period; The operating constraints of the electrolyzer and the fuel cell are: in, Charging power for new energy stations; is a binary variable for the electrolytic cell operating status during period t in stage s of the planning period; is the electrolytic power of the electrolytic cell accumulated during the planning period s; Discharge power for new energy stations; is a binary variable of the fuel cell operation status in the planning period s stage t period; is the released power of the fuel cell at time t in stage s of the planning period; s is the index of the shared energy storage planning stage; t is the index of the shared energy storage operation time period; The energy continuity constraint during the operation of the shared energy storage is: in, is the internal capacity of the electrochemical energy storage during the planning period s stage t period; is the internal capacity of the electrochemical energy storage during the planning period s period t-1; Charging conversion efficiency for electrochemical energy storage; Charging power for electrochemical energy storage; is the discharge power of electrochemical energy storage; is the electrochemical energy storage discharge conversion efficiency; Δt is the time interval; is the minimum internal charge coefficient of electrochemical energy storage; is the accumulated electricity in the electrochemical energy storage during the planning period s; is the maximum internal charge coefficient of electrochemical energy storage; is the initial charge inside the electrochemical energy storage during the planning period s; is the final charge inside the electrochemical energy storage at the planning stage s; s is the index of the shared energy storage planning stage; t is the index of the shared energy storage operation time period; b is the index of the electrochemical energy storage subcomponent; The internal energy continuity constraint of the hydrogen storage tank is: in, is the internal energy of the hydrogen storage tank during the planning period s and time period t; is the internal energy of the hydrogen storage tank during the planning period s period t-1; is the hydrogen production of the electrolyzer at time t in stage s of the planning period; is the hydrogen consumption of the fuel cell at time t in stage s of the planning period; Δt is the time interval; is the minimum coefficient of energy that can be stored within the planning period s stage t period; is the internal electrolysis power of the hydrogen energy storage system during period t in stage s of the planning period; is the maximum coefficient of energy that can be stored within the planning period s stage t period; is the initial energy of the hydrogen storage tank’s internal energy during the planning period s and time period t; is the final energy inside the hydrogen storage tank during the planning period s period t; s is the shared energy storage planning stage index; t is the shared energy storage operation time period index; h is the subcomponent index of the hydrogen energy storage system; The power balance constraint between the new energy station group and the centralized shared energy storage power station is: in, The regional load of the output of the new energy station in the planning period s; The positive power deviation of the new energy station grid connection during the planning period s; The charging power of the new energy station r using the shared energy storage during the period t in the stage s; The regional load borne by the new energy stations in the planning period s; The negative power deviation of the new energy station grid connection during the planning period s; is the discharge power of the shared energy storage used by the new energy station r in the s stage and t period; r is the new energy station; s is the shared energy storage planning stage index; t is the shared energy storage operation time period index.
6. The long-term planning method for shared energy storage of a new energy station group according to claim 1 is characterized in that: The calculation formula for the cumulative value of the capacity of each sub-component is: in, It is the cumulative value of the capacity of each sub-component of the shared energy storage; Replacement constraints for each sub-component of shared energy storage and the capacity attenuation rate of each sub-component; Configure capacity accumulation values for multi-stage time series.
7. The long-term planning method for shared energy storage of a new energy station group according to claim 1 is characterized in that: There is a linear relationship between the cumulative value of the capacity of each sub-component and the rated power of the centralized shared energy storage power station in each stage.
8. A long-term planning device for shared energy storage of a new energy station group, characterized in that: include: The acquisition module is used to obtain the load growth data of the new energy station group; A division module, used for dividing the planning period of the centralized shared energy storage power station into multiple stages according to the load growth data; A calculation module, used to calculate the equipment capacity planning sequence set and the equipment time sequence output set according to the equipment capacity planning sequence set in each stage, and calculate the cumulative value of each sub-component capacity of the centralized shared energy storage power station in each stage according to the equipment capacity planning sequence set; A construction module is used to construct a shared energy storage long-term expansion planning model according to the equipment time output set, the cumulative value of the capacity of each sub-component and the shared energy storage long-term planning goal, and determine the planned capacity of each stage of the centralized shared energy storage power station based on the shared energy storage long-term expansion planning model.
9. An electronic device, characterized in that: include: A memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor executes the program to implement the long-term planning method for shared energy storage of a new energy station group as described in any one of claims 1-7.
10. A computer-readable storage medium having a computer program or instruction stored thereon, characterized in that: When the computer program or instruction is executed, the method for long-term planning of shared energy storage for a new energy station group as described in any one of claims 1-7 is implemented.