Mounting method of cable crane

By splitting the main beam truss into intermediate truss beams and box-type load-bearing beams and hoisting them in stages, the problem of low installation efficiency of suspension bridge and cable cranes is solved, and a safer and more efficient installation process is achieved.

CN119083305AActive Publication Date: 2024-12-06ROAD & BRIDGE SOUTH CHINA ENG CO LTD +1
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202411123893.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-15
Publication Date
2024-12-06
Estimated Expiration
2044-08-15

AI Technical Summary

Technical Problem

The installation efficiency of the suspension bridge and cable crane is low. The direct lifting of the overall main beam truss increases the load load of the winch, resulting in damage to the brake device and high construction risk, affecting the construction efficiency.

Method used

The main beam truss is divided into intermediate truss beams and box-type load-bearing beams, and is lifted in stages through the winch lifting equipment, and a fixed walking mechanism is fixed by using a replaceable support hoisting device and a traction jack to reduce the load of the winch equipment and improve installation. efficiency.

Benefits of technology

It reduces the load load of the winch equipment, simplifies the installation process, reduces installation time, improves construction efficiency and reduces construction risks.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119083305A_ABST
    Figure CN119083305A_ABST
Patent Text Reader

Abstract

The invention provides an installation method of a cable crane. The installation method comprises the following steps that all components of the cable crane are prepared; a main tower portal frame is overhung in the bridge direction, the main tower portal frame extends out of the main tower in the bridge direction, and winch hoisting equipment is installed on the main tower portal frame; hoisting a walking mechanism of the cable loading crane to the main cable for installation by utilizing winch hoisting equipment; hoisting a main beam truss of the cable crane to a traveling mechanism mounted on the main cable by utilizing winch hoisting equipment, and connecting and fixing the main beam truss with the traveling mechanism; and the hoisting system, the hydraulic pump station and the control room of the cable crane are sequentially hoisted into the main beam truss through the winch hoisting equipment, and a steel strand of the hoisting system is connected with the hoisting tool, so that installation of the cable crane is completed. The installation method is convenient to operate and high in construction safety.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of cable-mounted cranes, and in particular to an installation method of a cable-mounted crane. Background Art

[0002] Cable-mounted cranes are important equipment for erecting steel beams of suspension bridges, and the installation efficiency of cable-mounted cranes is directly related to the erection period of steel beams of suspension bridges. Usually, the installation of cable-mounted cranes for suspension bridges is to separate the traveling mechanism from the main beam truss. However, the main beam truss structure is relatively large, and directly connecting the main beam truss with the traveling mechanism will greatly increase the difficulty of installation, thereby extending the high-altitude assembly operation time. In addition, the hoisting weight required by the winch is relatively large, and long-term high load stress will cause significant damage to the brake device of the winch, thereby increasing the danger of the assembly work of each component and affecting the construction efficiency of the suspension bridge. Summary of the invention

[0003] The purpose of the present application is to provide a method for installing a cable-mounted crane, which solves the problem of directly hoisting the entire main beam truss, thereby increasing the load force of the hoisting equipment and affecting the construction safety by splitting the main beam truss into an intermediate truss beam and a box-type load-bearing beam for installation.

[0004] In order to achieve the above objectives, this application provides the following technical solutions: A method for installing a cable-mounted crane comprises the following steps: Prepare a traveling mechanism, a main beam truss and a lifting system of the cable-mounted crane, wherein the traveling mechanism is connected to the main cable, the main beam truss is installed on the traveling mechanism, and the lifting system is installed on the main beam truss; The main tower gantry is cantilevered along the direction of the bridge, the main tower gantry is extended to the outside of the main tower along the direction of the bridge, and a hoisting and lifting device is installed on the main tower gantry; Using the hoisting equipment to hoist the traveling mechanism of the cable-mounted crane onto the main cable for installation; Using the hoisting hoisting equipment to hoist the main beam truss of the cable-mounted crane to the traveling mechanism installed on the main cable and connect and fix it to the traveling mechanism; Use hoisting equipment to sequentially hoist the lifting system, hydraulic pump station and control room of the cable-mounted crane into the main beam truss, and connect the steel strands of the lifting system to the hoisting equipment to complete the installation of the cable-mounted crane.

[0005] Further arrangement: the preparation of the various components of the cable-mounted crane includes: after manufacturing the cable-mounted crane as a whole machine in the factory and testing it, disassembling the cable-mounted crane into loose components and transporting them to the construction site, assembling the loose components of the cable-mounted crane into standard sections by means of a tower crane and a truck crane, and then transferring the various components of the cable-mounted crane to a barge, and transporting the various components of the cable-mounted crane by the barge to the vicinity of the main tower for lifting construction.

[0006] Further arrangement: two groups of the main tower gantries are arranged on the top of the main tower, each group of the main tower gantries is provided with a hoisting and lifting device, and the hoisting and lifting devices on the two groups of the main tower gantries respectively correspond to the hoisting of the walking mechanism of the cable-mounted crane on the two main cables.

[0007] Further arrangement: when the traveling mechanism of the cable-carrying crane is hoisted to the main cable by means of the hoisting lifting equipment, the traveling mechanism is lifted above the main cable, and at the same time, the position of the traveling mechanism is adjusted to transfer the traveling mechanism to the main cable, and the main cable is clamped by means of the replaceable supporting clamp device of the traveling mechanism to complete the connection between the traveling mechanism and the main cable.

[0008] Further arrangement: after the main cable is clamped by the replaceable supporting clamp device of the walking mechanism to fix the walking mechanism, an anchor point of the traction jack is installed at a preset position away from the walking mechanism, and a steel strand is passed between the traction jack and the anchor point to pull the walking mechanism along the axial displacement of the main cable through the traction jack.

[0009] Further arrangement: the main beam truss of the cable-mounted crane includes an intermediate truss beam and two sections of box-type load-bearing beams. When the main beam truss of the cable-mounted crane is hoisted to the traveling mechanism by using the hoisting lifting equipment, the two box-type load-bearing beams at the ends of the main beam truss are first hoisted to the two traveling mechanisms respectively and connected and fixed by pins, and then the intermediate truss beam is hoisted between the two box-type load-bearing beams, and the intermediate truss beam is connected to the two box-type load-bearing beams by high-strength bolts to complete the connection and fixation of the main beam truss and the traveling mechanism.

[0010] Further configuration: the intermediate truss beam comprises a plurality of box beam segments bolted together by high-strength bolts. When hoisting the intermediate truss beam, the plurality of box beam segments are first assembled on the ground to form an integral intermediate truss beam, and then hoisted as a whole by a hoisting and lifting device.

[0011] Further arrangement: when the steel strand of the lifting system is connected to the sling, the sling is lifted to the position of the lower beam of the main tower by means of a hoisting lifting device, the steel strand of the retractable wire device of the lifting system is passed through the lifting jack and the anchor head of the steel strand is lowered to the lower beam, so that the anchor head of the steel strand is connected to the sling, and then the sling is lifted to the vicinity of the tower top by means of the lifting jack.

[0012] Further configuration: the sling includes a shoulder pole beam, a shoulder pole beam slide, a lifting anchor seat, a movable lifting lug and a center of gravity adjusting jack. The lifting anchor seat is arranged on the shoulder pole beam slide, and the lifting anchor seat is connected to the anchor head of the steel strand. The shoulder pole beam slide is installed on the top of the shoulder pole beam. The base of the center of gravity adjusting jack is connected to the shoulder pole beam, and the protruding end of its piston rod is connected to the shoulder pole beam slide, so as to push the shoulder pole beam slide to move along the length direction of the shoulder pole beam through the center of gravity adjusting jack. The movable lifting lug is provided with a group at each end of the length direction of the shoulder pole beam, and the position of the movable lifting lug on the shoulder pole beam is adjustable.

[0013] Further configuration: Before the installed cable-mounted crane carries out the lifting operation, a trial lifting test step is also included.

[0014] Compared with the prior art, the solution of this application has the following advantages: The cable-mounted crane installation method involved in the present application can reduce the load force on the hoisting equipment by splitting the main beam truss into intermediate truss beams and box-type load-bearing beams for hoisting in stages, making installation more convenient, effectively reducing the installation time of the cable-mounted crane, and improving the installation efficiency of the cable-mounted crane.

[0015] Additional aspects and advantages of the present application will be partially given in the following description, which will become apparent from the following description, or will be understood through the practice of the present application. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] The above and / or additional aspects and advantages of the present application will become apparent and easily understood from the following description of the embodiments in conjunction with the accompanying drawings, in which: Figure 1 A process flow chart of an embodiment of a method for installing a cable-mounted crane of the present application; Figure 2 A schematic structural diagram of a cable-mounted crane according to an embodiment of a method for installing a cable-mounted crane of the present application; Figure 3 A schematic diagram of the structure of a hoisting device according to an embodiment of the installation method of the cable-mounted crane. DETAILED DESCRIPTION

[0017] The embodiments of the present application are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present application, and cannot be interpreted as limiting the present application.

[0018] Those skilled in the art will appreciate that, unless specifically stated, the "said" and "the" used herein may also include plural forms. It should be further understood that the term "including" used in the specification of the present application refers to the presence of the features, parts and / or components, but does not exclude the implementation of other features, parts, components and / or their combinations supported by the technical field. The term "and / or" used herein refers to at least one of the items defined by the term, for example, "A and / or B" can be implemented as "A", or as "B", or as "A and B".

[0019] In the description of the present application, the directions or positional relationships indicated by words such as "center", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside" and "outside" are based on the exemplary directions or positional relationships shown in the accompanying drawings. They are for the convenience of describing or simplifying the description of the embodiments of the present application, and do not indicate or imply that the referred device or component must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be understood as limitations on the present application.

[0020] The terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of this application, unless otherwise specified, "plurality" means two or more.

[0021] In the description of this application, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0022] In order to make the objectives, technical solutions and advantages of the present application clearer, the implementation methods of the present application will be further described in detail below with reference to the accompanying drawings.

[0023] As a large-scale construction equipment for suspension bridges, cable-mounted cranes rely on the main cables of suspension bridges as support to perform displacement and fixed hoisting on the main cables of bridges. Figures 1 to 3 The cable-mounted crane of the present application includes a traveling mechanism 1, a main beam truss 2 and a lifting system 3. The traveling mechanism 1 is installed on the main cable of the suspension bridge. The main beam truss 2 is installed on the traveling mechanism 1 to move along with the traveling mechanism 1 on the main cable. The lifting device is installed on the main beam truss 2, and the lifting device is used to complete the lifting of the bridge components.

[0024] Specifically, two groups of walking mechanisms 1 are provided and are respectively located at the two ends of the main beam truss 2, and the two groups of walking mechanisms 1 are respectively provided on the two main cables. The walking mechanism 1 of this embodiment includes a walking mechanism 1 body, rollers, a traction jack 12, a load conversion jack and a replaceable support hoop device 13, the rollers and the replaceable support hoop device 13 are both provided at the bottom of the walking mechanism 1 body, the load conversion jack is provided on the walking mechanism 1 body and connected to the rollers located at the bottom of the walking mechanism 1 body, the load conversion jack is used to control the lifting and lowering of the walking wheel in the vertical direction so that the rollers are in contact with the main cable or away from the main cable, multiple groups of rollers are provided along the length direction of the walking mechanism 1 body, and multiple groups of load conversion jacks are also provided corresponding to the multiple groups of rollers. Multiple replaceable support hoop devices 13 are provided along the length direction of the walking mechanism 1 body, and the walking mechanism 1 body is sleeved on the main cable through multiple replaceable support hoop devices 13 to achieve the connection between the walking mechanism 1 and the main cable. When the traveling mechanism 1 is displaced along the axial direction of the main cable, the multiple replaceable support clamp devices 13 need to loosen the main cable so that there is a gap between the replaceable support clamp device 13 and the main cable, and the roller is driven downward by the load conversion jack to contact the main cable, and then the traction jack 12 can be used to pull the traveling mechanism 1 along the axial direction of the main cable to move. Both ends of the main body of the traveling mechanism 1 can be connected to the traction jack 12, so that the traveling mechanism 1 can be pulled by the traction jack 12 to move in the opposite direction of the main cable.

[0025] The main beam truss 2 is erected between the two groups of traveling mechanisms 1. The main beam truss 2 of this embodiment includes an intermediate truss beam 21 welded by H-shaped steel and two sections of box-type load-bearing beams 22. The intermediate truss beam 21 mainly plays a role of rigid support for the overall structure of the cable-mounted crane. The box-type load-bearing beams 22 at both ends of the intermediate truss beam 21 are respectively connected to the two groups of traveling mechanisms 1, thereby realizing the connection between the main beam truss 2 and the traveling mechanism 1. The internal space of the intermediate truss beam 21 of this embodiment is used to place the lifting system 3 and provide a working platform for construction operations. At the same time, considering the convenience of transportation, installation, disassembly and connection, the intermediate truss beam 21 can be divided into multiple box beam segments, and the adjacent box beam segments are bolted in the form of high-strength bolts, so that the multiple box beam segments can be transported to the site and then spliced ​​to achieve a modular design. The box-type load-bearing beams 22 at both ends of the intermediate truss beam 21 are the main load-bearing components of the main beam truss 2. They can also be bolted in the form of high-strength bolts and spliced ​​after being transported to the site to achieve a modular design.

[0026] In addition, the number of box beam segments of the intermediate truss beam 21 can be increased or decreased according to the spacing between the two main cables, and other structures of the main beam truss 2 do not need to be modified, and the applicability is strong.

[0027] The lifting system 3 is installed on the main beam truss 2. In this embodiment, the lifting system 3 includes a wire-retracting device and a lifting jack. The steel strand of the wire-retracting device passes through the lifting jack and is connected to a sling 6. The sling 6 is used to connect the bridge structure to be lifted, so that the bridge structure can be lifted with the cooperation of the wire-retracting device and the lifting jack. A hydraulic pump station 4 and a control room 5 are also provided on the main beam truss 2. The hydraulic pump station 4 is used to supply oil to the walking mechanism 1, the wire-retracting device, and the lifting jack. The control room 5 is used to control the operation of the entire cable-mounted crane.

[0028] The lifting device 6 of this embodiment includes a shoulder pole beam 61, a shoulder pole beam slide box 62, a lifting anchor seat 63, a movable lifting ear 64 and a center of gravity adjustment jack 65. The steel strand of the wire-retracting and releasing device is connected to the lifting anchor seat 63. The lifting anchor seat 63 is arranged on the shoulder pole beam slide box 62. The shoulder pole beam slide box 62 is installed on the top of the shoulder pole beam 61. The base of the center of gravity adjustment jack 65 is connected to the shoulder pole beam 61, and the protruding end of its piston rod is connected to the shoulder pole beam slide box 62, so that the shoulder pole beam slide box 62 can be pushed to move along the length direction of the shoulder pole beam 61 through the center of gravity adjustment jack 65, thereby achieving the function of adjusting the center of gravity of the lifting. A positioning screw is also provided between the shoulder pole beam slide box 62 and the shoulder pole beam 61. After the center of gravity adjustment jack 65 adjusts the lifting center of gravity, the relative position of the shoulder pole beam slide box 62 and the shoulder pole beam 61 is locked by the positioning screw to prevent the shoulder pole beam slide box 62 from slipping, thereby improving the stability of the lifting. A group of movable lifting ears 64 are provided at each end of the shoulder beam 61 in the length direction. The position of the movable lifting ears 64 on the shoulder beam 61 is adjustable to adapt to the different temporary lifting point distances of different beam sections. That is, in addition to being able to lift standard segmental beams, the lifting device 6 of this embodiment can also meet the lifting requirements of segmental beams of other specifications.

[0029] The cable-mounted crane of the present application serves as the main lifting equipment for constructing a suspension bridge. It uses the two main cables of the suspension bridge as force supports and moves on the main cables. It can cross obstacles such as the main cable clamps of the suspension bridge and lift the large bridge structure on the transport ship below to the designated position in the construction area to assemble the large structure of the bridge itself.

[0030] Combined with the structure of the cable crane, please Figure 1 The present application provides a method for installing a cable-mounted crane, which specifically includes the following steps: First, prepare the various components of the cable crane. The cable crane of this embodiment is manufactured and tested in the factory, then disassembled and transported to the construction site by car. On the shore near the river side of the bridge tower, the scattered parts of the cable crane are assembled into standard sections by tower crane and car crane, and then the various components of the cable crane are transferred to the barge. The barge is transported to the vicinity of the main tower by a tugboat to facilitate the lifting construction.

[0031] At the same time, the main tower gantry is cantilevered along the bridge direction, and a hoisting and lifting device is installed on the main tower gantry. The present application uses the main tower gantry as the construction platform of the cable-mounted crane of the present application. The main tower gantry includes a main tower main truss and a cantilever truss. The main tower main truss is fixed to the top of the main tower, and the cantilever truss is fixed to the top of the main tower main truss. The cantilever truss extends along the bridge direction, so that the main tower gantry extends outside the main tower along the bridge direction. The hoisting and lifting device is arranged on the cantilever truss, so that the various components of the cable-mounted crane are hoisted one by one to the main cable installation station through the hoisting and lifting device for installation. In addition, two groups of main tower gantries are arranged on the top of the main tower in the present embodiment, and each group of main tower gantries is provided with a hoisting and lifting device, so that the two groups of hoisting and lifting devices can respectively carry out the hoisting operation of the two groups of walking mechanisms 1, so as to improve the installation efficiency of the cable-mounted crane of the present application.

[0032] The traveling mechanism 1 of the cable-carrying crane is hoisted onto the main cable by means of a hoisting and lifting device. Specifically, the hoisting and lifting device is connected to the traveling mechanism 1 main body of the traveling mechanism 1, and the traveling mechanism 1 main body is lifted above the main cable by means of the hoisting and lifting device. At the same time, the position of the traveling mechanism 1 main body is adjusted to transfer the traveling mechanism 1 main body to the main cable, and the main cable is clamped by means of the replaceable supporting clamp device 13 at the bottom of the traveling mechanism 1 main body to complete the fixing of the traveling mechanism 1.

[0033] At the same time, the anchor point 14 of the traction jack 12 is set at a position 100 meters or 150 meters away from the main body of the cable-mounted crane, preferably close to the cable clamp, so that the cable clamp and the replaceable supporting clamp device 13 can be used to clamp the main cable to resist the pulling force of the traction jack 12, thereby ensuring the stability of the cable-mounted crane in a fixed state. It is also necessary to install a steel strand between the traction jack 12 and its anchor point 14, so that the walking mechanism 1 can be pulled by the traction jack 12 to move along the axial direction of the main cable.

[0034] Subsequently, the main beam truss 2 of the cable-mounted crane is hoisted by hoisting equipment to the traveling mechanism 1 installed on the main cable and connected and fixed to the traveling mechanism 1. This process is divided into two parts. First, the two box-type load-bearing beams 22 at the ends of the main beam truss 2 are hoisted to the two traveling mechanisms 1 respectively and connected and fixed by pins. After adjusting the position and height, they are fixed to the main tower gantry by steel wire ropes. Then, the spliced ​​middle truss beam 21 is hoisted between the two box-type load-bearing beams 22. After the whole is in place, it is connected to the box-type load-bearing beams 22 at both ends by high-strength bolts, thereby completing the connection and fixation of the main beam truss 2 and the traveling mechanism 1.

[0035] The intermediate truss beams 21 of this embodiment can be hoisted by the hoisting equipment on the main tower gantry after being spliced ​​on the ground, which reduces high-altitude operations, facilitates workers to splice the intermediate truss beams 21, ensures the structural strength of the main beam truss 2 after connection, and reduces safety hazards.

[0036] Next, the hoisting equipment is used to sequentially hoist the lifting system 3, hydraulic pump station 4 and control room 5 of the cable-mounted crane into the main beam truss 2, and the steel strands of the lifting system 3 are connected to the sling 6 to complete the installation of the cable-mounted crane. Before hoisting the lifting system 3, hydraulic pump station 4 and control room 5, part of the upper crossbar of the main beam truss 2 is first removed to facilitate the hoisting equipment to hoist the lifting system 3, hydraulic pump station 4 and control room 5 into the main beam truss 2, and then the oil pipes and conduits between the lifting system 3, hydraulic pump station 4, control room 5 and the traveling mechanism 1 are connected as required, and the hydraulic system is preliminarily debugged.

[0037] In addition, auxiliary devices such as guardrails can be installed on the main beam truss 2 to ensure the construction safety of workers.

[0038] After the lifting system 3, the hydraulic pump station 4 and the control room 5 are hoisted into the main beam truss 2, the lifting device 6 is connected to the lifting system 3 through the steel strand. Specifically, the lifting device 6 is lifted to the position of the lower beam using a hoisting hoisting device, and the steel strand of the wire-retracting device is passed through the lifting jack according to the use needs, and the anchor head of the steel strand is lowered to the lower beam, so that the anchor head of the steel strand is connected to the lifting device 6, and then the lifting device 6 is lifted to the vicinity of the tower top by the lifting jack.

[0039] Before the steel strand of the cable-mounted crane is connected to the sling 6, the cable-mounted crane can be debugged as a whole according to the instruction manual, the steel strand is put into the wire-retracting and paying-out device, the anchor point 14 of the traction jack 12 is installed, the cable-mounted crane is moved along the main cable, and the safety wire rope on the main tower gantry used to connect the cable-mounted crane is slowly loosened until it is completely released, and the load is completely transferred to the cable-mounted crane, so that the cable-mounted crane has the conditions for self-propelled movement, and then the steel strand of the cable-mounted crane is connected to the sling 6 to complete the overall installation of the cable-mounted crane of this application.

[0040] For the installed cable-mounted crane, a trial lifting test is required before the lifting operation is carried out to verify the structural reliability and safety of the cable-mounted crane and ensure the safety of the lifting operation of the bridge structure. At the same time, the trial lifting test can also actually test the travel speed of the cable-mounted crane and the lifting speed of the crane after loading, thereby providing a basis for calculating the lifting time of the bridge structure. During the trial lifting test, deficiencies in the lifting process can be found out and corrected in time.

[0041] The contents of the trial hoisting test include walking test, no-load test, load test (including dynamic load and static load test), etc., so as to check the operation of the hydraulic system, the bearing capacity of the main beam truss 2, the synchronization of the hoist 6 and the operation of the control system. The trial hoisting position is carried out according to the most unfavorable working condition position. The cable-mounted crane uses a standard beam section as the loading object, and increases the counterweight on this section to 1.25 times the standard section.

[0042] Among them, when conducting the no-load test, after the cable-mounted crane is moved to the specified position, the cable-mounted crane travel clamp is locked as required to fix the cable-mounted crane firmly. The lifting system 3 of the cable-mounted crane is turned on, and the sling 6 is evenly lowered to the longest position. Observe and record whether the various limit and hydraulic control systems and the arrangement of the steel strands are normal. The lifting jack lifts the sling 6 evenly, and observes and records whether the height limit and the arrangement of the steel strands are normal. In this way, the lifting and lowering speed of the sling 6 of the cable-mounted crane can be mastered, and the lifting limit of the lifting system 3 of the cable-mounted crane can be checked to see if it is responsive, as well as the operation of the various components of the cable-mounted crane under no-load conditions.

[0043] After the cable-mounted crane no-load test is completed, the static load test and dynamic load test can be carried out. First, measure and record the original data of the tower deviation and the mid-span measurement point of the cable-mounted crane, transport the test segment to the bottom of the cable-mounted crane, fix the ship to be lifted, control the positioning accuracy of the barge within 1m, start the cable-mounted crane, and synchronously lower the hoisting devices 6 on both sides to the test segment, and firmly connect the hoisting devices 6 to the test segment lifting point, check the connection of each component, and report to the command after passing the test. The test lifting of the cable-mounted crane is divided into 9 levels of loading according to 20%, 40%, 60%, 70%, 80%, 90%, 100%, 110%, and 125% of the designed rated lifting weight, with the load slightly off the ground (or the ship's deck). Loading is to gradually transfer the weight of the test segment to the lifting jack. At the initial loading, first adjust the force of each lifting jack to keep it basically the same. When 40% of the rated load is transferred to the lifting jack, check the connection between the lifting jack, the sling 6 and the test segment again. When the load reaches 90% of the load, change an empty stroke to lift the test segment off the barge to reduce the shaking of the test segment after leaving the barge. The operator observes the stress conditions of each point and adjusts the stress conditions of each point according to the stress conditions of the theoretical lifting points of the beam segment to ensure that the test segment is lifted horizontally during the lifting process. According to the force measuring device of the lifting system 3, the load borne by the cable-mounted crane lifting point is calculated. When the single-point load increases by one level, the various components of the cable-mounted crane are checked and recorded. The test segment (or counterweight) is all borne by the cable-mounted crane, checked again, and recorded. The height of the test segment (or counterweight) away from the barge bracket is controlled at 20cm. After 10 minutes of stable load, the displacement of the measuring point in the middle of the test segment and the deflection value of the cable tower are measured, and the operation of the relevant components of the cable-mounted crane is observed and recorded. After lifting the cable-mounted crane hoist again by 650cm and keeping the load stable for 10 minutes, measure the displacement of the measuring point in the middle of the test segment, observe and record the operation of the relevant components of the cable-mounted crane. After lowering the cable-mounted crane hoist by 650cm and keeping the load stable for 10 minutes, measure the displacement of the measuring point in the middle of the test segment and the deflection value of the tower, and observe and record the operation of the relevant components of the cable-mounted crane. After checking that everything is normal, lower the test segment (or counterweight), and the cable-mounted crane load test is completed. By comparing the above-mentioned relevant measurement data, it is possible to obtain the operation of each component of the cable-mounted crane after loading, the lifting and lowering synchronization of the hoist 6, the tower deflection, and the deformation of the main beam truss 2 of the cable-mounted crane in the middle span.

[0044] After the above tests are passed, the cable-mounted crane can be put into construction.

[0045] After the cable-mounted crane has been used, it can be dismantled in the reverse order of the above installation, that is, the lifting system 3, hydraulic pump station 4, control room 5 and other structures in the main beam truss 2 are lifted out by the hoisting and lifting equipment on the main tower gantry, and then connected to the main beam truss 2 by the hoisting and lifting equipment, and the connection between the main beam truss 2 and the traveling mechanism 1 is released, and finally the hoisting and lifting equipment is connected to the main body of the traveling mechanism 1, and the lock between the replaceable supporting clamp device 13 at the bottom of the traveling mechanism 1 and the main cable is released, and then the traveling mechanism 1 is lifted away from the main cable to complete the dismantling of the cable-mounted crane.

[0046] The above description is only a partial implementation method of the present application. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principles of the present application. These improvements and modifications should also be regarded as the scope of protection of the present application.

Claims

1. A method for installing a cable-mounted crane, characterized in that: The following steps are involved: Prepare a traveling mechanism, a main beam truss and a lifting system of the cable-mounted crane, wherein the traveling mechanism is connected to the main cable, the main beam truss is installed on the traveling mechanism, and the lifting system is installed on the main beam truss; The main tower gantry is cantilevered along the direction of the bridge, the main tower gantry is extended along the direction of the bridge to the outside of the main tower, and a hoisting and lifting device is installed on the main tower gantry; Using the hoisting equipment to hoist the traveling mechanism of the cable-mounted crane onto the main cable for installation; Using the hoisting equipment to hoist the main beam truss of the cable-mounted crane to the traveling mechanism installed on the main cable and connect and fix it to the traveling mechanism; Use hoisting equipment to sequentially hoist the lifting system, hydraulic pump station and control room of the cable-mounted crane into the main beam truss, and connect the steel strands of the lifting system to the hoisting equipment to complete the installation of the cable-mounted crane.

2. The installation method of a cable-mounted crane according to claim 1, characterized in that: The preparation of the various components of the cable-mounted crane includes: after manufacturing the cable-mounted crane as a whole in a factory and testing it, disassembling the cable-mounted crane into loose components and transporting them to the construction site, assembling the loose components of the cable-mounted crane into standard sections by means of a tower crane and a truck crane, and then transferring the various components of the cable-mounted crane to a barge, and transporting the various components of the cable-mounted crane by means of the barge to the vicinity of the main tower for lifting construction.

3. The installation method of a cable-mounted crane according to claim 1, characterized in that: The main tower gantries are arranged in two groups on the top of the main tower, and each group of the main tower gantries is provided with a hoisting and lifting device. The hoisting and lifting devices on the two groups of the main tower gantries correspond to the hoisting of the traveling mechanism of the cable-mounted crane on the two main cables respectively.

4. The installation method of a cable-mounted crane according to claim 1, characterized in that: When the traveling mechanism of the cable-carrying crane is hoisted to the main cable by means of the hoisting lifting equipment, the traveling mechanism is lifted above the main cable, and the position of the traveling mechanism is adjusted to transfer the traveling mechanism to the main cable, and the main cable is clamped by the replaceable supporting clamp device of the traveling mechanism to complete the connection between the traveling mechanism and the main cable.

5. The installation method of a cable-mounted crane according to claim 4, characterized in that: After the main cable is clamped by the replaceable supporting clamp device of the traveling mechanism to fix the traveling mechanism, the anchor point of the traction jack is installed at a preset position away from the traveling mechanism, and a steel strand is passed between the traction jack and the anchor point to enable the traveling mechanism to be pulled by the traction jack to move along the axial direction of the main cable.

6. The installation method of a cable-mounted crane according to claim 1, characterized in that: The main beam truss of the cable-mounted crane includes an intermediate truss beam and two sections of box-type load-bearing beams. When the main beam truss of the cable-mounted crane is hoisted to the traveling mechanism by using the hoisting lifting equipment, the two box-type load-bearing beams at the ends of the main beam truss are first hoisted to the two traveling mechanisms respectively and connected and fixed by pins, and then the intermediate truss beam is hoisted between the two box-type load-bearing beams, and the intermediate truss beam is connected to the two box-type load-bearing beams by high-strength bolts to complete the connection and fixation of the main beam truss and the traveling mechanism.

7. The installation method of a cable-mounted crane according to claim 6, characterized in that: The intermediate truss beam comprises a plurality of box beam segments bolted together by high-strength bolts. When hoisting the intermediate truss beam, the plurality of box beam segments are first assembled on the ground to form an integral intermediate truss beam, and then hoisted as a whole by a hoisting and lifting device.

8. The method for installing a cable-mounted crane according to claim 1, characterized in that: When connecting the steel strand of the lifting system to the sling, use the hoisting equipment to lift the sling to the position of the lower beam of the main tower, pass the steel strand of the wire-retracting device of the lifting system through the lifting jack and lower the anchor head of the steel strand to the lower beam, connect the anchor head of the steel strand to the sling, and then lift the sling to the vicinity of the tower top through the lifting jack.

9. The installation method of a cable-mounted crane according to claim 8, characterized in that: The lifting device includes a shoulder pole beam, a shoulder pole beam slide box, a lifting anchor seat, a movable lifting ear and a center of gravity adjustment jack. The lifting anchor seat is arranged on the shoulder pole beam slide box, and the lifting anchor seat is connected to the anchor head of the steel strand. The shoulder pole beam slide box is installed on the top of the shoulder pole beam. The base of the center of gravity adjustment jack is connected to the shoulder pole beam, and the protruding end of its piston rod is connected to the shoulder pole beam slide box, so as to push the shoulder pole beam slide box to move along the length direction of the shoulder pole beam through the center of gravity adjustment jack. The movable lifting ear is provided with a group at each end of the length direction of the shoulder pole beam, and the position of the movable lifting ear on the shoulder pole beam is adjustable.

10. The installation method of a cable-mounted crane according to claim 1, characterized in that: Before carrying out the lifting operation of the installed cable-mounted crane, a trial lifting test step is also included.

Citation Information

Patent Citations

  • Cable carrying crane suitable fordifferent main cable center distances

    CN110143526A

  • Installation method for cable-bearing crane

    CN110626957A

  • Large-span steel-concrete composite bridge large-section steel truss girder erecting system and construction method

    CN111188273A

  • Construction method for integrally lifting and installing cable crane

    CN115303957A

  • Hoist with adjustable hoisting point

    CN207030725U