Dismantling method for concrete-filled steel tube arch bridge
Through the controlled blasting method combining manual cutting and energy-concentrating blasting, multiple blasting areas are divided and transverse cutting cables are installed, the problem of low blasting efficiency of traditional drilling holes is solved, and efficient crushing and safe removal of steel pipe concrete arch bridges is achieved.
Patent Information
- Application Number
- CN202411234822.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-04
- Publication Date
- 2024-12-06
AI Technical Summary
In the prior art, during the removal of steel pipe concrete arch bridges, mechanical demolition methods make it difficult to ensure construction safety. Traditional drilling blasting has a lack of free surface in the blasting area due to the "wrapping effect" between steel pipes and steel webs, and the construction efficiency is low.
Using a controlled blasting method combining manual cutting and energy-concentrating blasting, the steel pipe concrete arch bridge is divided into multiple blasting areas, and blasting areas of different heights are set, and horizontal cutting cables and detonation elements are installed in each area, so that effective through delayed detonation technology is achieved broken.
The construction efficiency of blasting and demolition of steel pipe concrete arch bridges has been improved, construction safety has been ensured, artillery bolting has been avoided, and demolition efficiency has been improved.
Smart Images

Figure CN119083340A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of bridge engineering, and in particular to a method for dismantling a steel tube concrete arch bridge. Background Art
[0002] With the development of road and bridge industry, some steel tube concrete arch bridges built in the early years have been identified as dangerous bridges. Taking into account factors such as foundation displacement, they have been out of use for many years. The stress conditions of the bridges cannot be understood, the stability cannot be guaranteed, and the conditions for mechanical equipment to carry out bridge deck construction are not available.
[0003] Old bridges are usually located near newly built bridges. During the demolition of old bridges, it is necessary to minimize disturbance to the main structure of the newly built bridge. The demolition of old bridges involves complex factors and is difficult. There are very few cases of explosive cutting and demolition of steel tube concrete bridges. The main demolition methods used are mechanical demolition and drilling and charging blasting demolition. Mechanical demolition mainly includes inverted demolition, segmented cutting, scaffolding demolition, direct demolition and whole span cutting methods; blasting mainly includes static blasting, hydraulic blasting and controlled blasting. The use of mechanical demolition alone requires personnel and equipment to work on the bridge deck for a long time, which makes it difficult to ensure the safety of operations during construction; the use of traditional drilling and blasting alone, due to the "wrapping effect" of the steel pipe and the steel web, leads to the lack of necessary blasting free surface in the steel pipe arch blasting area, and the blasting area will form a blasting phenomenon, which cannot achieve the purpose of effective crushing and has low construction efficiency. Summary of the invention
[0004] The purpose of the present invention is to provide a method for dismantling a steel tube concrete arch bridge, so as to improve the construction efficiency of blasting dismantling of the steel tube concrete arch bridge.
[0005] In order to achieve the above object, the technical solution adopted by the present invention is:
[0006] A method for dismantling a steel tube concrete arch bridge, characterized in that it comprises the following steps:
[0007] Step 1: blasting part division; the steel tube concrete arch bridge is divided into a bridge blasting part and a steel tube concrete arch blasting part; the bridge blasting part includes a plurality of bent columns and a bridge deck structure fixed on the top of the plurality of bent columns, and the steel tube concrete arch blasting part includes a steel tube concrete arch;
[0008] Step 2: blasting area division of each blasting part;
[0009] The bottom of the front column and the bottom of the rear column of the bent column are respectively provided with a first blasting zone and a second blasting zone, and the height of the first blasting zone is greater than the height of the second blasting zone;
[0010] The bottom of the front steel tube and the bottom of the rear steel tube of the left arch foot of the steel tube concrete arch are respectively provided with a third blasting zone and a fourth blasting zone, and the height of the third blasting zone is greater than that of the fourth blasting zone;
[0011] The bottom of the front steel tube and the bottom of the rear steel tube of the right arch foot of the steel tube concrete arch are respectively provided with a fifth blasting zone and a sixth blasting zone, and the height of the fifth blasting zone is greater than that of the sixth blasting zone;
[0012] Step 3: Manual cutting; cut off the webs of the third blasting area, the fourth blasting area, the fifth blasting area, and the sixth blasting area, chisel off the concrete inside the webs, and cut mounting holes for installing transverse cutting cables at the connection between the two steel pipes in the blasting area; then cut off the circular steel plates at the blasting hole positions of each blasting area; finally, cut several vertical cutting seams on the third blasting area, the fourth blasting area, the fifth blasting area, and the sixth blasting area;
[0013] Step 4: Construction of blast holes in each blasting area;
[0014] Step 5: Charge each blast hole and install the detonating element;
[0015] Step 6: Install transverse cutting ropes; install multiple transverse cutting ropes on the side walls of the third blasting area, the fourth blasting area, the fifth blasting area, and the sixth blasting area;
[0016] Step 7: Install the detonation network: Connect the detonation elements / transverse cutting ropes of each blasting area using the detonation network;
[0017] Step 8: Horizontal cutting rope cutting;
[0018] Step 9: Detonation; preferably, the detonation is performed from left to right or from right to left in sequence by using a delayed detonation technique;
[0019] Step 10: Post-explosion inspection.
[0020] Furthermore, in step 2, the height of the first blasting zone is 2 to 4 times the height of the second blasting zone.
[0021] Furthermore, in step 2, the height of the third blasting zone is 2 to 6 times the height of the fourth blasting zone.
[0022] Furthermore, in step 2, the height of the fifth blasting zone is 2 to 6 times the height of the fourth blasting zone.
[0023] Furthermore, in step three, a working platform is firstly set up at the blasting area.
[0024] Furthermore, the working platform includes a ground-type scaffolding and a construction platform fixedly arranged on the ground-type scaffolding.
[0025] Furthermore, the working platform is not dismantled after the blasting network is installed. During blasting, the working platform is used as a protective frame to protect the blasting area from flying rocks.
[0026] Furthermore, the blast holes are single-group explosive blast holes or double-group explosive blast holes.
[0027] Furthermore, the depth of the blasthole is 0.5 to 0.75 times the diameter of the steel pipe.
[0028] Furthermore, the vertical cutting seams are discontinuous cutting seams.
[0029] Compared with the prior art, the beneficial effects of the present invention are as follows: the present invention optimizes the traditional demolition method of simply using drilling and blasting or cutting, and adopts a cutting method that combines manual cutting with concentrated energy blasting cutting combined with controlled blasting, which can achieve effective crushing of steel tube concrete arch bridges and improve the construction efficiency of blasting demolition of steel tube concrete arch bridges. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] Figure 1 A schematic diagram of a construction process of an embodiment of the present invention;
[0031] Figure 2 A front view of a steel tube concrete arch bridge in one embodiment of the present invention;
[0032] Figure 3 A rear view of a steel tube concrete arch bridge in one embodiment of the present invention;
[0033] Figure 4 A schematic diagram of the arrangement of blastholes in the fourth blasting zone in one embodiment of the present invention;
[0034] Figure 5 It is a schematic diagram of the arrangement of the cutting rope in the fourth blasting zone in one embodiment of the present invention;
[0035] Figure 6 for Figure 5 Horizontal cross-section of .
[0036] In the figure:
[0037] 1. Frame column; 101. First blasting zone; 102. Second blasting zone; 2. Bridge deck structure; 3. Steel pipe arch; 301. Third blasting zone; 302. Fourth blasting zone; 303. Fifth blasting zone; 304. Sixth blasting zone; 305. Lower steel pipe; 306. Upper steel pipe; 307. Web; 308. Concrete; 4. Blast hole; 5. Vertical cutting seam; 6. Cutting rope; 7. Mounting hole; h. Drilling depth of blast hole. DETAILED DESCRIPTION
[0038] The present invention will be described in detail below with reference to the accompanying drawings and in combination with the embodiments. It should be noted that the embodiments of the present invention and the features in the embodiments can be combined with each other without conflict. For the convenience of description, if the words "upper", "lower", "left" and "right" appear in the following, they only indicate that the upper, lower, left and right directions are consistent with the drawings themselves, and do not limit the structure.
[0039] like Figure 1-Figure 6 As shown, this embodiment takes a mid-through clustered steel tube concrete basket arch as an example, and the steel tube arch of the bridge is formed by bundling two straightened steel tubes. The blasting dumping direction is backward dumping.
[0040] Specifically, a method for dismantling a steel tube concrete arch bridge in this embodiment includes the following steps:
[0041] Step 1: blasting part division. The steel tube concrete arch bridge is divided into a bridge blasting part and a steel tube concrete arch blasting part. The bridge blasting part includes a plurality of bent columns 1 and a bridge deck structure 2 fixed on the top of the plurality of bent columns 1. The steel tube concrete arch blasting part includes a steel tube concrete arch 3.
[0042] Step 2: Division of blasting areas for each blasting part.
[0043] like Figure 2 and Figure 3 As shown, the bottom of the front column and the bottom of the rear column of the frame column 1 are respectively provided with a first blasting area 101 and a second blasting area 102 , and the height of the first blasting area 101 is 2 to 4 times the height of the second blasting area 102 .
[0044] like Figure 2 and Figure 3 As shown, the bottom of the front steel tube and the bottom of the rear steel tube of the left arch foot of the steel tube concrete arch 3 are respectively provided with a third blasting area 301 and a fourth blasting area 302 , and the height of the third blasting area 301 is 2 to 6 times the height of the fourth blasting area 302 .
[0045] like Figure 2 and Figure 3 As shown, the front and rear steel tube bottoms of the right arch foot of the steel tube concrete arch 3 are respectively provided with a fifth blasting zone 303 and a sixth blasting zone 304 , and the height of the fifth blasting zone 303 is 2 to 6 times the height of the fourth blasting zone 304 .
[0046] Step 3: Manual cutting: First, a work platform is set up at the blasting area, wherein the work platform includes a floor-standing scaffold and a construction platform fixedly arranged on the floor-standing scaffold.
[0047] After the work platform is set up, the webs 307 of the third blasting area 301, the fourth blasting area 302, the fifth blasting area 303, and the sixth blasting area 304 are cut off, the concrete 308 inside the webs 307 is chiseled off, and the mounting holes 7 for installing the transverse cutting cables 6 are cut at the connection between the two steel pipes in the blasting area.
[0048] Then the circular steel plates at the positions of the blast holes 4 in each blasting area are cut off, thereby facilitating the construction of the blast holes 4 .
[0049] Finally, a plurality of vertical cutting seams 5 are cut on the third blasting area 301, the fourth blasting area 302, the fifth blasting area 303, and the sixth blasting area 304. In this embodiment, two vertical cutting seams 5 are cut on the lower steel pipe 305 and the upper steel pipe 306 of the blasting area. The distance between the two vertical cutting seams 5 on the lower steel pipe 305 is equal to the diameter of the lower steel pipe, and the distance between the two cutting seams 5 on the upper steel pipe 306 is equal to the diameter of the upper steel pipe.
[0050] The vertical cutting seam 5 is an intermittent cutting seam. The vertical cutting seam 5 is cut 20 cm and left 10 cm, and the length is equivalent to the height of the blasting area.
[0051] Step 4: Construction of blast holes 4 in each blasting area. In this embodiment, a row of blast holes 4 are provided on the lower steel pipe 305 and the upper steel pipe 306. Construction personnel use drilling equipment on the working platform to drill blast holes in the blasting area. The blast holes 4 are single-group explosive blast holes or double-group explosive blast holes. Figure 6 As shown, the depth h of the blasthole 4 is 0.5 to 0.75 times the diameter of the steel pipe. In order to prevent the impact vibration of the pneumatic rock drill from affecting the stability of the bridge arch, a cutting rotary drilling machine such as a water-grinding drill is used to make holes. In order to avoid encountering steel bars during drilling, the hole layout position can be slightly changed.
[0052] Step 5: Charge each blast hole 4 and install the detonating element. Before charging, the pedestrian guardrails, pipe networks, lighting and other facilities on the bridge deck are pre-removed manually or mechanically. The fiberglass protective layer on the main arch steel pipe in the blasting cut needs to be removed, the connection between the approach bridge deck and the abutment is cut off, and the connection between the main arch section deck and the pier column section deck is cut off. The specific construction steps for charging the blast holes are as follows: First, check the blast holes, the main contents are: whether the position, direction and depth of the blast holes meet the design requirements; whether there is any blockage; for super-deep holes, they should be backfilled to the designed position, and those with insufficient hole depth should be deepened. Then charge according to the designed amount of charge and install the detonating element.
[0053] Step 6: Install the transverse cutting rope 6. Install multiple transverse cutting ropes 6 on the side walls of the third blasting area 301, the fourth blasting area 302, the fifth blasting area 303, and the sixth blasting area 304. When installing the transverse cutting rope 6, avoid installing it at the weld of the steel pipe.
[0054] The cutting rope of this example is a QV20 flexible lead-antimony alloy cutting rope with a charge of 120 g / m (existing technology), and a detonating cord is used to detonate the overlapping short joint, and then to detonate the ring-mounted cutting rope to achieve multi-ring synchronous detonation.
[0055] Step 7: Installation of the detonation network: The detonation elements / cutting ropes 6 of each blasting area are connected using the detonation network.
[0056] Step 8: Cut the rope 6 transversely.
[0057] Step 9: Detonation. Detonation is performed from left to right or from right to left in sequence using a time-delayed detonation technique. The cutting of the transverse cutting rope 6 and the detonation of the blast hole 4 are both performed using existing detonation techniques.
[0058] Step 10: Post-blast inspection. Set up a warning procedure during the detonation phase. The warning procedure is the construction process from the completion of the charging connection and protection to the blasting. Clean the site 30 minutes before detonation, issue a warning alarm 15 minutes before detonation, and ignite the alarm 1 minute before detonation. After the explosion, lift the alarm after inspection and remove the guards. Enter the site 15 minutes after the blasting to ensure that all explosion points are detonated and the collapsed bridge has no loosening, falling or other safety hazards before lifting the alarm.
[0059] After the alert is lifted, mechanical demolition methods are used to crush and dismember the bridge debris in the river. The size of the debris meets the loading and unloading requirements. Then, excavators are used for loading and unloading, and dump trucks are used for transportation. The waste is transported to the waste dump using the existing highway construction access road to ensure the smooth flow of the river.
[0060] The contents explained in the above embodiments should be understood as these embodiments are only used to more clearly illustrate the present invention, and are not used to limit the scope of the present invention. After reading the present invention, various equivalent forms of modifications to the embodiments made by those skilled in the art fall within the scope defined by the claims attached to the present invention.
Claims
1. A method for dismantling a steel tube concrete arch bridge, characterized in that: The steps include: Step 1: blasting section division; the steel tube concrete arch bridge is divided into a bridge blasting section and a steel tube concrete arch blasting section; the bridge blasting section includes a plurality of bent columns (1) and a bridge deck structure (2) fixedly arranged on top of the plurality of bent columns (1), and the steel tube concrete arch blasting section includes a steel tube concrete arch (3); Step 2: blasting area division of each blasting part; A first blasting zone (101) and a second blasting zone (102) are respectively provided at the bottom of the front column and the bottom of the rear column of the bent column (1), and the height of the first blasting zone (101) is greater than the height of the second blasting zone (102); A third blasting zone (301) and a fourth blasting zone (302) are respectively provided at the bottom of the front steel tube and the bottom of the rear steel tube of the left arch foot of the steel tube concrete arch (3), and the height of the third blasting zone (301) is greater than the height of the fourth blasting zone (302); The front steel tube bottom and the rear steel tube bottom of the right arch foot of the steel tube concrete arch (3) are respectively provided with a fifth blasting zone (303) and a sixth blasting zone (304), wherein the height of the fifth blasting zone (303) is greater than the height of the sixth blasting zone (304); Step 3: manual cutting; cutting off the webs (307) of the third blasting area (301), the fourth blasting area (302), the fifth blasting area (303), and the sixth blasting area (304), chiseling off the concrete (308) inside the webs (307), cutting a mounting hole (7) for mounting a transverse cutting cable (6) at the connection between two steel pipes in the blasting area; then cutting off the circular steel plates at the positions of the blasting holes (4) in each blasting area; finally, cutting a plurality of vertical cutting seams (5) on the third blasting area (301), the fourth blasting area (302), the fifth blasting area (303), and the sixth blasting area (304); Step 4: Construction of blast holes (4) in each blasting area; Step 5: Loading explosives in each blast hole (4) and installing detonating elements; Step 6: Installing transverse cutting ropes (6); installing multiple transverse cutting ropes (6) on the side walls of the third blasting area (301), the fourth blasting area (302), the fifth blasting area (303), and the sixth blasting area (304); Step 7: Installing the detonation network; connecting the detonation elements / transverse cutting ropes (6) of each blasting area using the detonation network; Step 8: Cutting the transverse cutting cable (6); Step 9: Detonation; preferably, the detonation is performed from left to right or from right to left in sequence by using a delayed detonation technique; Step 10: Post-explosion inspection.
2. The method for dismantling a steel tube concrete arch bridge according to claim 1, characterized in that: In step 2, the height of the first blasting zone (101) is 2 to 4 times the height of the second blasting zone (102).
3. The method for dismantling a steel tube concrete arch bridge according to claim 1, characterized in that: In step 2, the height of the third blasting zone (301) is 2 to 6 times the height of the fourth blasting zone (302).
4. The method for dismantling a steel tube concrete arch bridge according to claim 1, characterized in that: In step 2, the height of the fifth blasting zone (303) is 2 to 6 times the height of the fourth blasting zone (304).
5. The method for dismantling a steel tube concrete arch bridge according to claim 1, characterized in that: In step three, first set up a working platform at the blasting area.
6. The method for dismantling a steel tube concrete arch bridge according to claim 5, characterized in that: The working platform comprises a ground-type scaffold and a construction platform fixedly arranged on the ground-type scaffold.
7. The method for dismantling a steel tube concrete arch bridge according to claim 5, characterized in that: The working platform is not dismantled after the blasting network is installed. During blasting, the working platform is used as a protective frame to protect the blasting area from flying rocks.
8. A method for dismantling a steel tube concrete arch bridge according to any one of claims 1 to 7, characterized in that: The blast holes (4) are single-group explosive blast holes or double-group explosive blast holes.
9. A method for dismantling a steel tube concrete arch bridge according to any one of claims 1 to 7, characterized in that: The depth (h) of the blasthole (4) is 0.5 to 0.75 times the diameter of the steel pipe.
10. A method for dismantling a steel tube concrete arch bridge according to any one of claims 1 to 7, characterized in that: The vertical cutting seams (5) are discontinuous cutting seams.