Waterproof construction method for post-cast strip of basement wall

By installing prefabricated concrete slabs on the basement wall and laying waterproof coils, the problem of waterproof construction extension caused by the post-pouring strips is solved, shortening construction periods and cost savings are achieved, and construction safety and structural waterproofing are ensured.

CN119083496AInactive Publication Date: 2024-12-06CHINA MCC22 GROUP CORP LTD
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
CN202411451594.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-17
Publication Date
2024-12-06
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

In large public buildings, the design of the rear pouring strips of the basement structure exterior walls leads to an extension of the waterproof construction, affecting the backfilling of foundation pits and subsequent construction periods, especially in areas with high groundwater levels or rainy seasons, which increases project costs and safety hazards.

Method used

Prefabricated concrete slabs are used to install on the rear cast strips, and waterproof coils are laid on both sides, waterproof construction is carried out in advance, shorten the construction period, eliminate safety hazards, and save costs through the production of cast-in-place concrete materials on site.

Benefits of technology

It effectively shortens the construction period, improves construction efficiency, simplifies operations, saves costs, and improves social benefits, ensuring the waterproofing effect and safety of the structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119083496A_ABST
    Figure CN119083496A_ABST
Patent Text Reader

Abstract

The invention relates to building construction, in particular to a waterproof construction method for a post-cast strip of a basement wall. Comprising the following steps that S1, reinforcing steel bars of a basement wall body are bound, and formworks are erected; s2, basement wall bodies on the two sides of the post-cast strip are poured and maintained; s3, precast concrete prefabricated slabs are prefabricated; s4, the post-cast strip and wall base layers on the two sides of the post-cast strip are cleaned; s5, concrete prefabricated slab installation is conducted, specifically, the concrete prefabricated slab is installed on the post-cast strip, and gaps are filled with mortar; and S6, waterproof coiled materials are laid on the wall surfaces, and the waterproof coiled materials are laid on the concrete prefabricated plates and the basement wall bodies on the two sides of the concrete prefabricated plates. According to the method, the problem of waterproof roll construction delay caused by the basement outer wall post-cast strip is effectively solved, the underground foundation pit can be backfilled in advance for construction, the potential safety hazard is eliminated, meanwhile, construction conditions are provided for erection of an upper structure frame body, and the construction period is shortened.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to building construction, in particular to a waterproof construction method for a post-cast zone of a basement wall. Background Art

[0002] In large public buildings, post-cast strips are inevitably set up for functional needs and to reduce the impact of structural settlement and temperature stress of concrete. According to the design requirements of post-cast strips, the underground structure concrete can only be poured after 45 days or more of pouring, which causes the waterproofing construction of the basement structure exterior wall to be stagnant for a long time, thus affecting the backfilling of the foundation pit or related subsequent construction periods. In some areas with high groundwater levels or during the rainy season, it is especially necessary to advance the waterproofing construction and backfilling processes to prevent the underground structure from being eroded by water and affecting the structural strength. The influx of water also requires manpower and material resources to clean up, increasing the cost of the project. Summary of the invention

[0003] The present invention aims to solve the above technical problems, thereby providing a waterproof construction method for a basement wall post-cast zone, thereby improving construction efficiency and shortening construction period.

[0004] The present invention solves the technical problem and adopts the following technical solution: A waterproof construction method for a basement wall post-cast strip comprises the following steps: S1. Reinforcement binding and formwork support for basement walls; S2. Casting and curing of basement walls on both sides of the post-cast zone; S3, precast concrete panels; S4. Clean the post-cast strip and the wall base on both sides of the post-cast strip; S5. Installation of precast concrete panels Install the concrete precast panels on the post-cast strips and fill the gaps with mortar; S6. Wall paving waterproof membrane Waterproof membrane is laid on the precast concrete slab and the basement walls on both sides of the precast concrete slab.

[0005] Compared with the prior art, the present invention using the above technical solution has the following beneficial effects: 1) Effectively solve the problem of delayed waterproofing membrane construction caused by the post-casting of the basement exterior wall, and backfill the underground foundation pit in advance, eliminating safety hazards while providing construction conditions for the erection of the upper structure frame and shortening the construction period; 2) The construction method is simple and easy to operate. The prefabricated panels can be made from the remaining materials from each pouring of cast-in-place concrete on site, which solves the problem of remaining concrete after the main concrete is poured, while saving costs and improving social benefits.

[0006] Further, the optimization scheme of the present invention is: The slab surfaces on both sides of the precast concrete slab overlap with the wall surfaces of the basement wall.

[0007] The precast concrete slab is connected to the steel bars of the post-casting strip through steel wires.

[0008] A waterproof additional layer is laid between the board surfaces on both sides of the concrete precast board and the wall surface of the basement wall.

[0009] The concrete precast panels are arranged in multiple pieces from bottom to top, and the panel surfaces of the concrete precast panels are smooth. BRIEF DESCRIPTION OF THE DRAWINGS

[0010] Figure 1 A schematic diagram of a post-cast strip according to an embodiment of the present invention; Figure 2 This is a schematic diagram of the installation of a precast concrete panel according to an embodiment of the present invention; Figure 3 This is a schematic diagram of laying the waterproof membrane according to an embodiment of the present invention.

[0011] In the figure: basement wall 1; steel bars 2; post-cast strip 3; precast concrete slab 4; additional waterproof layer 5; waterproof membrane 6. DETAILED DESCRIPTION

[0012] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.

[0013] In the description of the present invention, it is necessary to understand that the terms "upper", "lower", "front", "back", "left", "right", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship are based on the orientation or position relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.

[0014] See also Figure 1 This embodiment provides a basement wall post-casting waterproofing construction method, which is carried out in the following steps: S1. Tie up reinforcement bars 2 and support formwork for basement wall 1.

[0015] S2. The basement wall 1 on both sides of the post-casting strip 3 is poured and cured. After the concrete pouring of the basement wall 1 is completed, the formwork is removed and cured according to the design and specification requirements.

[0016] S3, precast concrete panels 4.

[0017] S4. Cleaning of post-cast strips and wall base on both sides of the post-cast strips The mortar on the steel bars 2 and the water-stop steel plate at the position of the post-cast strip 3 is cleaned up, and the anti-leakage steel mesh on both sides of the post-cast strip 3 is completely removed. The ends of the tension bolts are processed according to the design requirements and the anti-corrosion work of the ends is completed. The surface of the outer wall of the underground structure is processed to ensure that the base layer is flat and solid, without floating dust and oil stains, so as to meet the hidden acceptance requirements.

[0018] S5. Installation of precast concrete panels Figure 2 As shown, the size of the precast concrete panel 4 is 1000×600×100 mm. Multiple precast concrete panels 4 are symmetrically installed on the post-cast strip 3 from bottom to top. The precast concrete panels 4 on both sides of the post-cast strip 3 are symmetrically arranged. The panel surfaces on both sides of the precast concrete panels 4 overlap the wall surface of the basement wall 1, and the outer side of the post-cast strip 3 is tightly sealed. The precast concrete panels 4 are fixed to the steel bars 2 of the post-cast strip 3 by steel wires, and the gaps are filled with mortar until the precast concrete panels 4 are installed tightly without leaks. During the installation process, the precast concrete panels 4 are required to be evenly smooth and without staggered joints up and down. S6. Wall paving waterproof membrane Figure 3 As shown, according to the design requirements, the matching base treatment agent is applied to enhance the bonding force between the roll material and the base, and the roll material can be laid after 2 hours. First, a waterproof additional layer 5 is laid between the board surface of the concrete precast board 4 on both sides and the wall surface of the basement wall 1, and then the waterproof roll material 6 is laid vertically from bottom to top from one side, and the construction of the waterproof roll material 6 is completed.

[0019] The present invention is to solve the problem of pre-positioning the waterproof construction of the post-cast strip of the basement wall and saving the waste of construction time between processes. The present invention solves the problem that waterproof construction can only be carried out after the post-cast strip is poured by paving concrete prefabricated panels on the outer wall of the basement. The present invention pre-positions the waterproof construction of the wall and backfills the foundation pit in advance, which can greatly save construction time and eliminate safety hazards in advance. The materials are easy to make and the construction operation is simple.

[0020] The above shows and describes the basic principles and main features of the present invention and the advantages of the present invention. It should be understood by those skilled in the art that the present invention is not limited by the above embodiments, and the above embodiments and descriptions are only for explaining the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, and these changes and improvements all fall within the scope of the present invention to be protected.

Claims

1. A waterproof construction method for a basement wall post-cast strip, comprising the following steps: S1. Reinforcement binding and formwork support for basement walls; S2. Casting and curing of basement walls on both sides of the post-cast zone; S3, precast concrete panels; S4. Clean the post-cast strip and the wall base on both sides of the post-cast strip; S5. Installation of precast concrete panels Install the concrete precast panels on the post-cast strips and fill the gaps with mortar; S6. Wall paving waterproof membrane Waterproof membrane is laid on the precast concrete slab and the basement walls on both sides of the precast concrete slab.

2. The waterproof construction method for the basement wall post-cast zone according to claim 1 is characterized by: The slab surfaces on both sides of the precast concrete slab overlap with the wall surfaces of the basement wall.

3. The waterproof construction method for the basement wall post-cast zone according to claim 1 is characterized by: The precast concrete slab is connected to the steel bars of the post-casting strip through steel wires.

4. The waterproof construction method for the basement wall post-cast zone according to claim 1 is characterized by: A waterproof additional layer is laid between the board surfaces on both sides of the concrete precast board and the wall surface of the basement wall.

5. The waterproof construction method for the basement wall post-cast zone according to claim 1 is characterized by: The concrete precast panels are arranged in multiple pieces from bottom to top, and the panel surfaces of the concrete precast panels are smooth.

Citation Information

Patent Citations

  • Installation technology for basement outer wall post-pouring belt prefabricated breast board

    CN115262750A

  • Post-cast strip prefabricated assembly type protection wall and construction method thereof

    CN116240987A

  • Bricklaying-free construction method for closing post-cast strip of basement outer wall in advance

    CN116290098A

  • Basement wall post -cast strip structure

    CN206800665U

  • Basement outer wall post-cast strip sealing structure

    CN213014375U