Moving platform device and method for erection and butt joint construction of large sections of steel structure bridge
By designing large sections of steel structure bridges to erect the docking and docking construction mobile platform devices, using electric telescopic channels and mobile platforms, the problems of high difficulty in installing construction platforms and high mechanical risks in the existing technology are solved, and safe and economical construction operations are achieved and guaranteed. Construction quality.
Patent Information
- Application Number
- CN202411576317.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-06
- Publication Date
- 2024-12-17
AI Technical Summary
The construction platform for the installation of large sections of existing steel structure bridges has high safety risks and high costs. The mechanical operation is complex and easy to cause accidents. The transportation cost of installing the construction hanging basket in advance is high and the risk of high altitude demolition is high.
Design a large section erecting docking construction mobile platform device for steel structure bridges, including a supporting structure on the flanges on both sides of the bridge, an electric telescopic upper and lower channels and an electric telescopic mobile platform are installed on the support structure, and an electric wheel and a power control system are equipped. The construction position is adapted to the construction position through the electric telescopic channel and the mobile platform, and safe and flexible construction operations are achieved.
It effectively reduces construction risks, simplifies mechanical operations, reduces construction costs, ensures the safety and quality of engineering construction, and improves the controllability and installation quality of large section erection and docking construction of steel structure bridges.
Smart Images

Figure CN119145308A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to a mobile platform device and method for erecting and docking large sections of a steel structure bridge. Background Art
[0002] At present, there are two main types of construction platforms for the erection and docking of large sections of steel structure bridges. The first is to rent an aerial work vehicle, such as a boom station, which is located on the highway bridge deck and then extends the boom to complete the highway bridge deck construction work on the boom vehicle platform; the second is to install a construction basket in advance as a construction platform when assembling large sections in the steel beam processing plant, and complete the highway bridge deck construction work in the basket after the bridge steel beam is hoisted into place.
[0003] At present, most of the steel structure bridges that are hoisted as a whole in segments have a girder height of about 14 meters. Common aerial vehicles are used to complete the construction of steel beam docking. Since the construction of steel beam docking is only a small part of the steel beam construction, if the machinery investment is too small, it will not be possible to carry out work on multiple work surfaces at the same time. If there is too much machinery investment, it will increase the economic cost. In addition, the operation of the machinery is more troublesome and requires professional training. If it is not operated properly, safety accidents are prone to occur. The second common method is to install the construction basket in the processing plant in advance. This method is due to the fact that most of the large-segment steel beam processing plants are far away from the steel beam installation site, and the turnover transportation distance is long, which increases the transportation cost. A large number of baskets need to be processed, and the risk of high-altitude demolition is relatively high. In summary, the existing construction methods have high safety risks and high costs. Summary of the invention
[0004] The purpose of the present invention is to solve the problems of the above-mentioned background technology and to propose a mobile platform device and method for the erection and docking construction of large sections of steel structure bridges.
[0005] The purpose of the present invention can be achieved through the following technical solutions:
[0006] A mobile construction platform device for erecting and docking large sections of a steel structure bridge comprises flanges protruding outward on both sides of the bridge, a support structure is movably arranged on the flange, a mobile construction platform is fixed to one side of the support structure, an electric telescopic upper and lower channel that can be vertically expanded is installed on the mobile construction platform, an electric telescopic mobile platform that can be horizontally expanded is installed at the tail end of the electric telescopic upper and lower channel, and the electric telescopic mobile platform after expansion is located below the flange.
[0007] As a further solution of the present invention: a counterweight is placed in the support structure.
[0008] As a further solution of the present invention: the moving wheel is an electric wheel.
[0009] As a further solution of the present invention: moving wheels are installed at the bottom of the supporting structure, and the moving wheels are used to drive the supporting structure to move on the flange.
[0010] As a further solution of the present invention: legs are rotatably connected to the bottom of the support structure near both sides of the moving wheel, and the two legs are limited and fixed by a detachable buckle rod.
[0011] As a further solution of the present invention: the electric telescopic mobile platform includes a driving member, the electric telescopic upper and lower channels are connected to the electric telescopic mobile platform in a straight line sliding manner through a limiting guide rail, a rack is fixed to the side of the electric telescopic mobile platform, the driving member is fixed on the electric telescopic upper and lower channels, and the gear at the output end of the driving member is meshed with the rack.
[0012] As a further solution of the present invention: an electric power control system is also arranged in the supporting structure.
[0013] An operation method of a mobile platform for erecting and docking large sections of a steel structure bridge comprises the following steps:
[0014] Step 1: Control the moving wheels to move the construction mobile platform to the construction position of the steel beam interface of the bridge;
[0015] Step 2: Control the electric telescopic upper and lower channels to adjust their own height;
[0016] Step 3: Control the electric telescopic mobile platform to the construction location, brake the mobile wheels, support the construction mobile platform through the outriggers to keep it in working condition, turn off the power control system, and the personnel use the electric telescopic mobile platform to the construction location for construction;
[0017] Step 4: After the construction is completed, retract the electric telescopic mobile platform, retract the upper and lower channels and the outriggers, release the brakes of the moving wheels, and control the moving wheels to move the mobile construction platform to the next steel beam interface construction position.
[0018] The beneficial effects of the present invention are as follows: the main structure of the mobile platform is constructed by welding steel sections, and electric directional wheels, electric telescopic channels, and electric telescopic platforms are configured, counterweights are installed, and the platform's movement and telescopic adaptation to the corresponding construction position are controlled by an electric control system, which effectively solves the technical difficulties in the construction of large-section integrally hoisted steel structure bridges due to the high construction working surface of the docking interface, the difficulty in installing the docking interface construction platform, and the high risk of mechanical construction. The risk of large-section erection and docking construction of steel structure bridges is controllable, and the quality of steel beam installation is guaranteed. Therefore, the technical solution of the mobile platform for the erection and docking construction of large-section steel structure bridges of this application reduces the risk of large-section erection and docking construction of steel structure bridges, reduces the difficulty of construction, saves construction costs, and ensures the safety and quality of engineering construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] The present invention will be further described below in conjunction with the accompanying drawings.
[0020] Figure 1 It is a schematic diagram of the structure of the present invention;
[0021] Figure 2 The present invention Figure 1 Schematic diagram of the cross-sectional structure of 2-2;
[0022] Figure 3 The present invention Figure 1 Schematic diagram of the cross-sectional structure of 3-3;
[0023] Figure 4 It is a schematic diagram of the structure of the support leg and the buckle rod buckled together in the present invention;
[0024] Figure 5 It is a schematic diagram of the structure of the driving member and the rack of the present invention;
[0025] Figure 6 It is a schematic diagram of the present invention when it is used.
[0026] In the figure: 1. Support structure; 2. Construction mobile platform; 3. Electric telescopic upper and lower channels; 4. Electric telescopic mobile platform; 5. Counterweight; 6. Power control system; 7. Moving wheels; 8. Bridge; 9. Outriggers; 10. Buckle rods; 11. Driving parts. DETAILED DESCRIPTION
[0027] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0028] For example, see Figure 1-3 As shown, the present invention is a mobile platform device for the erection and docking construction of large sections of steel structure bridges, including flanges protruding outward on both sides of the bridge 8, and is characterized in that a support structure 1 is movably arranged on the flange, and a mobile construction platform 2 is fixed to one side of the support structure 1, and an electric telescopic upper and lower channel 3 that can be vertically unfolded is installed on the mobile construction platform 2, and an electric telescopic mobile platform 4 that can be horizontally unfolded is installed at the rear end of the electric telescopic upper and lower channel 3, and the electric telescopic mobile platform 4 after unfolding is located below the flange.
[0029] A counterweight 5 is placed inside the support structure 1, and the moving wheel 7 is an electric wheel.
[0030] For example 2, please refer to Figure 1-4 As shown, the present invention is a mobile platform device for the erection and docking construction of large sections of steel structure bridges, including flanges protruding outward on both sides of the bridge 8, and is characterized in that a support structure 1 is movably arranged on the flange, and a mobile construction platform 2 is fixed to one side of the support structure 1, and an electric telescopic upper and lower channel 3 that can be vertically unfolded is installed on the mobile construction platform 2, and an electric telescopic mobile platform 4 that can be horizontally unfolded is installed at the rear end of the electric telescopic upper and lower channel 3, and the electric telescopic mobile platform 4 after unfolding is located below the flange.
[0031] A counterweight 5 is placed inside the support structure 1, and the moving wheel 7 is an electric wheel.
[0032] A moving wheel 7 is installed at the bottom of the support structure 1, and the moving wheel 7 is used to drive the support structure 1 to move on the flange.
[0033] The bottom of the support structure 1 is rotatably connected to two sides of the moving wheel 7 with supporting legs 9 , and the two supporting legs 9 are limited and fixed by a detachable buckle rod 10 .
[0034] For example 3, please refer to Figure 1-6 As shown, the present invention is a mobile platform device for the erection and docking construction of large sections of steel structure bridges, including flanges protruding outward on both sides of the bridge 8, and is characterized in that a support structure 1 is movably arranged on the flange, and a mobile construction platform 2 is fixed to one side of the support structure 1, and an electric telescopic upper and lower channel 3 that can be vertically unfolded is installed on the mobile construction platform 2, and an electric telescopic mobile platform 4 that can be horizontally unfolded is installed at the rear end of the electric telescopic upper and lower channel 3, and the electric telescopic mobile platform 4 after unfolding is located below the flange.
[0035] A counterweight 5 is placed inside the support structure 1, and the moving wheel 7 is an electric wheel.
[0036] A moving wheel 7 is installed at the bottom of the support structure 1, and the moving wheel 7 is used to drive the support structure 1 to move on the flange.
[0037] The bottom of the support structure 1 is rotatably connected to two sides of the moving wheel 7 with supporting legs 9 , and the two supporting legs 9 are limited and fixed by a detachable buckle rod 10 .
[0038] The electric telescopic mobile platform 4 includes a driving member 11. The electric telescopic upper and lower channels 3 and the electric telescopic mobile platform 4 are connected in a straight line sliding manner through a limiting guide rail. A rack is fixed on the side of the electric telescopic mobile platform 4. The driving member 11 is fixed on the electric telescopic upper and lower channels 3. The gear at the output end of the driving member 11 is meshed with the rack.
[0039] A power control system 6 is also provided in the support structure 1 .
[0040] An operation method of a mobile platform for erecting and docking large sections of a steel structure bridge comprises the following steps:
[0041] Step 1: Control the moving wheels 7 to move the construction mobile platform 2 to the construction position of the steel beam interface of the bridge 8;
[0042] Step 2: Control the electric telescopic upper and lower channels 3 to adjust their own height;
[0043] Step 3: Control the electric telescopic mobile platform 4 to the construction position, brake the mobile wheel 7, support the construction mobile platform 2 with the outriggers 9, turn off the power control system 6, and the personnel use the electric telescopic mobile platform 4 to the construction position for construction;
[0044] Step 4: After the construction is completed, retract the electric telescopic mobile platform 4, retract the electric telescopic upper and lower channels 3 and the supporting legs 9, release the brakes of the moving wheels 7, and control the moving wheels 77 to move the mobile construction mobile platform 2 to the next steel beam docking interface construction position.
[0045] According to the calculation results, the counterweight block 5 is added to make the mobile platform stable and safe.
[0046] The above is a detailed description of an embodiment of the present invention, but the content is only a preferred embodiment of the present invention and cannot be considered to limit the scope of implementation of the present invention. All equivalent changes and improvements made according to the scope of application of the present invention should still fall within the scope of the claims of the present invention.
Claims
1. A mobile platform device for erecting and docking large sections of a steel structure bridge, comprising flanges protruding outwards on both sides of the bridge, characterized in that: A support structure is movably arranged on the flange, and a mobile construction platform is fixed on one side of the support structure. An electric telescopic upper and lower channel that can be vertically unfolded is installed on the mobile construction platform. An electric telescopic mobile platform that can be horizontally unfolded is installed at the tail end of the electric telescopic upper and lower channel. After unfolding, the electric telescopic mobile platform is located below the flange.
2. A mobile platform device for erecting and docking large sections of a steel structure bridge according to claim 1, characterized in that: A counterweight is placed in the supporting structure.
3. According to claim 1, a mobile platform device for erecting and docking large sections of a steel structure bridge is characterized in that: A moving wheel is installed at the bottom of the supporting structure, and the moving wheel is used to drive the supporting structure to move on the flange.
4. A mobile platform device for erecting and docking large sections of a steel structure bridge according to claim 4, characterized in that: The moving wheels are electric wheels.
5. A mobile platform device for erecting and docking large sections of a steel structure bridge according to claim 4, characterized in that: The bottom of the support structure is rotatably connected with legs on both sides close to the moving wheel, and the two legs are limited and fixed by a detachable buckle rod.
6. A mobile platform device for large-segment erection and docking construction of a steel structure bridge according to claim 1, characterized in that: The electric telescopic movable platform includes a driving member, the electric telescopic upper and lower channels are connected to the electric telescopic movable platform in a straight line sliding manner through a limiting guide rail, a rack is fixed to the side of the electric telescopic movable platform, the driving member is fixed on the electric telescopic upper and lower channels, and the gear at the output end of the driving member is meshed with the rack.
7. A mobile platform device for erecting and docking large sections of a steel structure bridge according to claim 1, characterized in that: An electric control system is also arranged in the supporting structure.
8. An operating method for a mobile platform for erecting and docking large sections of a steel structure bridge, characterized in that: The following steps are involved: Step 1: Control the moving wheels to move the construction mobile platform to the construction position of the steel beam interface of the bridge; Step 2: Control the electric telescopic upper and lower channels to adjust their own height; Step 3: Control the electric telescopic mobile platform to the construction location, brake the mobile wheels, support the construction mobile platform through the outriggers to keep it in working condition, turn off the power control system, and the personnel use the electric telescopic mobile platform to the construction location for construction; Step 4: After the construction is completed, retract the electric telescopic mobile platform, retract the upper and lower channels and the outriggers, release the brakes of the moving wheels, and control the moving wheels to move the mobile construction platform to the next steel beam interface construction position.