Flue reserved tongue-and-groove hanging-hole-free construction method
By leaving grooved bosses in the aluminum mold design, the flue unloads the load on the bosses, solving the problem of difficult construction and leakage in the flue outlets of the kitchen and bathroom, achieving high-quality and low-cost construction results.
Patent Information
- Application Number
- CN202411340766.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-25
- Publication Date
- 2024-12-27
AI Technical Summary
In civil buildings, the construction of hanging holes at the flue entrances of kitchens and bathrooms is difficult, which often leads to leakage or honeycomb lint quality problems, requiring secondary repairs, increasing construction costs.
When designing aluminum molds, the groove bosses are reserved, and the flue is placed on the bosses for load unloading layers, changing the traditional two-layer angle iron unloading method to realize the construction of hanging holes, and survive in the construction stage of the main structure to prevent leakage.
It improves construction quality and efficiency, saves labor and material costs, reduces construction costs, and achieves the effect of survival in one go.
Smart Images

Figure CN119195474A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building flue construction, in particular to a construction method for a flue with reserved tongue-and-groove hanging-free holes. Background Art
[0002] With the rapid development of housing construction and the development of the fourth generation of buildings in my country, people have extremely high requirements for the quality, appearance and comfort of housing, and they pay special attention to the details of the houses delivered in rough form. In the construction of the flue system of civil construction projects, the flue plays the main function of kitchen smoke exhaust or bathroom ventilation, so it is a widely used system in civil buildings. Among them, the flue is a thin-walled structure, and the installation hole needs to be reserved in advance as a secondary installation building component.
[0003] The construction of hanging holes at the flue outlets of kitchens and bathrooms is extremely difficult. The hanging holes are generally made of wire or formwork is supported on the top plate of the lower flue. The space is small and cannot be vibrated or the vibration is not dense, which often leads to leakage or honeycombed surface quality problems, requiring secondary repairs, which greatly increases the construction cost.
[0004] Patent CN114892975A discloses an installation mold and construction method of a building flue system, in which a shaping mold is reserved at the flue hole, a convex ridge is formed at the flue hole, and the prefabricated flue is directly installed on the convex ridge, which is used to support the weight of the flue and speed up the installation efficiency. However, in this patent, convex ridges are set on all four sides of the flue hole, which is difficult to implement in actual scenarios, especially in buildings where the flue is set at the corner of the wall. Summary of the invention
[0005] In order to solve the above technical problems, the present invention provides a flue reserved tongue and groove construction method without hanging holes. When designing the aluminum mold, a groove boss is reserved to achieve a construction process without hanging holes, so that the flue is placed on the boss to unload the load layer by layer, which changes the traditional flue unloading method of setting angle irons at no more than two layers of the flue mouth, and placing the flue on the angle irons for unloading. At the same time, the effect of anti-leakage is achieved, the main structure construction stage is completed once, the construction quality and effect are good, the purpose of reducing costs and increasing efficiency is achieved, the construction period is saved, and the labor and material costs are saved.
[0006] To achieve this technical purpose, the present invention adopts the following scheme: A construction method for a flue reserved tongue-and-groove hanging-free hole comprises the following steps: S1. According to the specific dimensions of the flue in the architectural drawing, the flue tongue and groove are further designed, and a boss is set at the flue tongue and groove position; S2. Design a special template for flue tongue and groove boss shaping; S3. During the main construction, steel bars shall be reserved at the flue groove position; S4. After the main construction is completed, the boss template is installed at the flue groove position and concrete is poured; S5. After the concrete strength of the boss reaches the requirement, remove the formwork and install the flue.
[0007] Compared with the prior art, the present invention has the following beneficial effects: The present invention provides a flue reserved tongue and groove free hanging hole construction method. When designing the aluminum mold, a groove boss is reserved to achieve a construction process free of hanging holes, so that the flue is placed on the boss to unload the load layer by layer, which changes the traditional flue unloading method of setting angle irons at no more than two layers of the flue mouth, and placing the flue on the angle irons for unloading. At the same time, the effect of anti-leakage is achieved, the main structure construction stage is completed once, the construction quality and effect are good, the purpose of reducing costs and increasing efficiency is achieved, the construction period is saved, and the labor cost and material cost are saved.
[0008] Furthermore, the specific dimensions of the flue in the building drawing are A*B, and the floor thickness is H; The size of the flue groove upper opening is further designed to be (A+a)*(B+a)*h1; The size of the flue groove bottom is further designed to be (A+a)*(B+a)*h2; The hole size of the middle boss of the flue groove is further designed to be (Aa)*(Ba)*h3, where h3=H-h1-h2.
[0009] Furthermore, a is 25-30 mm, h1 is 15-25 mm, and h2 is 35-45 mm.
[0010] Furthermore, when installing the flue, the flue is inserted into the groove at the lower end of the top plate flue tongue and groove, the flue is against the bottom of the boss, and then slowly placed in the groove at the upper end of the bottom plate flue tongue and groove. At this time, the flue just falls on the boss of the bottom plate flue tongue and groove, and finally the area around the flue is sealed with waterproof mortar.
[0011] Furthermore, the boss is arranged on a side of the flue groove close to the floor slab. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] Figure 1 A top view of the flue groove of an embodiment of the present invention; Figure 2 A bottom view of the flue tongue and groove of an embodiment of the present invention; Figure 3 This is a cross-sectional view of the flue tongue and groove of an embodiment of the present invention; Figure 4 This is a schematic diagram of the installation of a flue according to an embodiment of the present invention; Markings in the figure are: 1. Wall; 2. Floor; 3. Flue tongue and groove; 4. Boss; 5. Flue; 6. Steel bars; 7. Waterproof mortar. DETAILED DESCRIPTION
[0013] In order to fully understand the purpose, features and effects of the present invention, the present invention is described in detail through the following specific implementation methods, but the present invention is not limited thereto.
[0014] It should be noted that when an element is referred to as being "fixed to" or "set on" another element, it can be directly on the other element or indirectly on the other element. When an element is referred to as being "connected to" or "laid on" another element, it can be directly connected to the other element or indirectly connected to the other element.
[0015] It should be understood that the orientation or position relationship indicated by terms such as "length", "width", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside" and "outside" are based on the orientation or position relationship shown in the drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.
[0016] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of this application, "multiple" and "several" mean two or more, unless otherwise clearly and specifically defined.
[0017] See also Figures 1 to 4 The present invention provides a construction method for a flue reserved tongue-and-groove free-hanging hole, comprising the following steps: S1. According to the specific size of the flue 5 in the architectural drawing, the flue groove 3 is further designed, and a boss 4 is set at the flue groove 3; Further, the specific dimensions of the flue 5 in the architectural drawing are A*B, and the thickness of the floor slab 2 is H; The size of the upper opening of the flue groove 3 is further designed to be (A+a)*(B+a)*h1; The size of the flue groove 3 bottom is further designed to be (A+a)*(B+a)*h2; The hole size of the middle boss 4 of the flue groove 3 is further designed to be (Aa)*(Ba)*h3, where h3=H-h1-h2.
[0018] Furthermore, a is 25~30mm, h1 is 15~25mm, and h2 is 35~45mm.
[0019] S2. Design the flue groove 3 boss 4 standardization special template; S3. During the main construction, steel bars 6 are reserved at the flue groove 3; S4. After the main construction is completed, the boss 4 template is installed at the flue groove 3 position and concrete is poured; S5. After the concrete strength of the boss 4 reaches the requirement, the template is removed and the flue 5 is installed. When installing the flue 5, the flue 5 is inserted into the groove at the lower end of the flue groove 3 of the top plate, the flue 5 is against the bottom of the boss 4, and then slowly placed in the groove at the upper end of the flue groove 3 of the bottom plate. At this time, the flue 5 just falls on the boss 4 of the flue groove 3 of the bottom plate, and finally the surrounding of the flue 5 is sealed with waterproof mortar 7.
[0020] In some embodiments, the boss 4 is arranged on a side of the flue groove 3 close to the floor 2, which is convenient for construction and easy for operation.
[0021] More specifically, in an embodiment of the present invention: S1. According to the specific size of the flue 5 in the architectural drawing, the flue groove 3 is further designed, and a boss 4 is arranged at the flue groove 3. The boss 4 is arranged on the side of the flue groove 3 close to the floor 2; Among them, the specific size of the building flue 5 is 320mm*250mm, the thickness of the floor 2 is H=130mm, and after the detailed design of the flue tongue and groove 3, a=30, h1=20mm, and h2=40mm.
[0022] S2. Design the flue groove 3 boss 4 standardization special template; S3. During the main construction, reserve 2 steel bars 6 at the flue groove 3, with a diameter of 12mm HRB400E; S4. After the main construction is completed, the boss 4 template is installed at the flue groove 3 position and concrete is poured; S5. After the concrete strength of the boss 4 reaches the requirement, the template is removed and the flue 5 is installed. When installing the flue 5, the flue 5 is inserted into the groove at the lower end of the flue groove 3 of the top plate, the flue 5 is against the bottom of the boss 4, and then slowly placed in the groove at the upper end of the flue groove 3 of the bottom plate. At this time, the flue 5 just falls on the boss 4 of the flue groove 3 of the bottom plate, so that the side of the flue 5 close to the wall 1 is close to the wall 1, and finally the surrounding of the flue 5 is sealed with waterproof mortar 7.
[0023] Compared with the prior art, the present invention has the following beneficial effects: The present invention provides a construction method for flue with reserved tongue and groove holes for free hanging. When designing the aluminum mold, a groove boss 4 is reserved to achieve a construction process for free hanging holes, so that the flue 5 is placed on the boss 4 to unload the load layer by layer, which changes the traditional method of unloading the flue 5 by setting angle irons at no more than two layers of the flue 5 mouth, and placing the flue 5 on the angle irons for unloading. At the same time, the effect of anti-leakage is achieved, the main structure is completed in one construction stage, the construction quality and effect are good, the purpose of reducing costs and increasing efficiency is achieved, the construction period is saved, and the labor cost and material cost are saved.
[0024] Finally, it should be noted that the above-listed embodiments are only preferred embodiments of the present invention. Of course, those skilled in the art can make changes and modifications to the present invention. If these modifications and variations fall within the scope of the claims of the present invention and their equivalent technologies, they should be considered to be within the scope of protection of the present invention.
Claims
1. A construction method for a flue reserved tongue-and-groove free-hanging hole, characterized in that: The following steps are involved: S1. According to the specific dimensions of the flue in the architectural drawing, the flue tongue and groove are further designed, and a boss is set at the flue tongue and groove position; S2. Design a special template for flue tongue and groove boss shaping; S3. During the main construction, steel bars shall be reserved at the flue groove position; S4. After the main construction is completed, the boss template is installed at the flue groove position and concrete is poured; S5. After the concrete strength of the boss reaches the requirement, remove the formwork and install the flue.
2. The construction method of flue reserved tongue and groove free hanging hole according to claim 1, characterized in that: The specific dimensions of the flue in the building drawing are A*B, and the floor thickness is H; The size of the flue groove upper opening is further designed to be (A+a)*(B+a)*h1; The size of the flue groove bottom is further designed to be (A+a)*(B+a)*h2; The hole size of the middle boss of the flue groove is further designed to be (Aa)*(Ba)*h3, where h3=H-h1-h2.
3. The construction method of flue reserved tongue and groove free hanging hole according to claim 2 is characterized in that: a is 25~30mm, h1 is 15~25mm, and h2 is 35~45mm.
4. The construction method of flue reserved tongue and groove free hanging hole according to claim 1, characterized in that: When installing the flue, pass the flue into the groove at the lower end of the flue tongue and groove on the top plate, with the flue against the bottom of the boss, and then slowly place it into the groove at the upper end of the flue tongue and groove on the bottom plate. At this time, the flue falls exactly on the boss of the flue tongue and groove on the bottom plate. Finally, seal the area around the flue with waterproof mortar.
5. The construction method of flue reserved tongue and groove free hanging hole according to claim 1, characterized in that: The boss is arranged on the side of the flue groove close to the floor slab.