Wheel carrier type side slope drilling equipment

By designing a self-walking car equipped with drilling devices and a wheel-mounted slope drilling equipment that uses a hoist and stabilizes cable, the problems of equipment stability and safety hazards under complex slope structures are solved, and construction efficiency and safety are improved. Avoid the need to build a temporary platform.

CN119244152APending Publication Date: 2025-01-03CCCC TDC ENVIRONMENTAL ENG
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411517280.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-29
Publication Date
2025-01-03

AI Technical Summary

Technical Problem

Existing slope drilling equipment is difficult to stabilize and maintain its position on complex structures and uneven slope surfaces, resulting in low construction efficiency and safety hazards. Especially since the construction platform needs frequent adjustment and transfer, it increases safety risks. .

Method used

A wheel-mounted slope drilling equipment was designed, using a self-walking cart to be equipped with a drilling device, which can lift and move the equipment left and right through a winch and stabilize the cable, and use a push rod to adjust the angle between the drill rod and the slope to avoid In order to build temporary construction platforms, power supply and water supply devices are set on the ground to stay away from the slopes to reduce safety risks.

Benefits of technology

It improves the efficiency and safety of drilling construction, reduces the time for construction platform construction and adjustment, significantly improves the efficiency of slope drilling construction, and controls away from the slope, reducing the risk of safety accidents caused by falling rocks.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119244152A_ABST
    Figure CN119244152A_ABST
Patent Text Reader

Abstract

The invention relates to wheel carrier type side slope drilling equipment. Comprising a chassis provided with a support, front wheels and a walking motor driving the front wheels are installed on the front portion of the chassis, electric push rods are installed on the two sides of the rear portion of the chassis, and rear wheels are installed at the ends of telescopic rods of the electric push rods. A drilling device is installed in the middle of the front portion of the support, winches for winding and unwinding a hanging cable are installed on the two sides of the front portion of the support, and a stabilizing cable is connected to the rear portion of the support. The drilling device comprises a rack, and a rotation driving assembly for driving a drill rod to rotate, a precession driving assembly for driving the drill rod to move forwards and a cooling water pipe for supplying water to the drill rod are installed on the rack. A controller, a power supply device and a water supply device are further included. According to the wheel frame type side slope drilling equipment, the drilling construction efficiency is improved, and potential safety hazards of personnel in the construction process are reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of drilling equipment, and in particular relates to a wheel frame type slope drilling equipment. Background Art

[0002] Slope construction projects involve drilling operations. Holes are drilled on the slope and explosives are placed in the holes. The slope surface is blasted to remove floating rocks and expose the solid inner rock. At the same time, protective works such as metal protective nets are applied to the slope surface to significantly improve the safety of the slope. Especially for roadside slopes, protective construction will help improve the safety of the highway environment and avoid vehicle accidents caused by falling rocks.

[0003] The equipment used to drill holes in the slope usually uses a drilling rig, and the continuously rotating drill rod cuts the rock to form a hole. However, the following problems exist in actual construction: due to the complex surface structure and low flatness of the slope, it is not easy to set the drilling rig at the hole position and keep it stably at the hole position during the drilling operation cycle. The solution in the prior art is to build a supporting scaffolding on the slope as a construction platform. However, the method of building a temporary construction platform leads to a significant reduction in construction efficiency, and the drilling holes on the slope surface are usually designed to be multiple. After completing the drilling at the current position, the construction platform needs to be adjusted, such as increasing the height, before setting the next hole, and the drilling rig needs to be moved, which further affects the construction efficiency. On the other hand, due to the problems of falling rocks on the slope itself, there are great safety hazards in the existing method of building a construction platform and manually operating the drilling rig on the construction platform to drill holes.

[0004] In summary, it is necessary to develop and design a new type of slope drilling equipment to solve the above-mentioned technical problems. Summary of the invention

[0005] The purpose of the present invention is to provide a wheel frame type slope drilling equipment to improve the efficiency of drilling construction and reduce the potential safety hazards of personnel during the construction process.

[0006] The technical solution adopted by the present invention is: a wheel-frame slope drilling equipment, including a chassis with a bracket installed, a front wheel and a travel motor for driving the front wheel installed at the front of the chassis, electric push rods installed on both sides of the rear of the chassis and rear wheels installed on the ends of the telescopic rods of the electric push rods; a drilling device is installed in the front middle of the bracket, winches for retracting and releasing the hanging cable are installed on both sides of the front of the bracket, and a stabilizing cable is connected to the rear of the bracket; the drilling device includes a frame, on which a rotation drive component for driving the drill rod to rotate, a precession drive component for driving the drill rod to move forward, and a cooling water pipe for supplying water to the drill rod are installed; it also includes a controller, a power supply device and a water supply device.

[0007] Preferably, the bracket includes a front frame, a rear frame, a top frame and a middle frame; the bottom edge of the front frame is fixedly connected to the front edge of the chassis, the bottom edge of the rear frame is fixedly connected to the rear edge of the chassis, the front edge of the top frame is fixedly connected to the top edge of the front frame, and the rear edge is fixedly connected to the top edge of the rear frame, the top edge of the middle frame is fixedly connected to the middle of the top frame, and the bottom edge is fixedly connected to the middle of the chassis.

[0008] Preferably, the length dimension of the top frame of the bracket is significantly smaller than the length dimension of the chassis, and the width dimension of the top frame of the bracket is equal to the width dimension of the chassis; the angle between the top front frame and the rear frame of the bracket and the chassis is 45 to 60 degrees.

[0009] Preferably, the frame of the drilling device includes an adapter base frame detachably connected to the front frame of the bracket, a main support frame is installed on the adapter base frame, a front support frame is installed in front of the main support frame, a rear support is installed above the rear of the main support frame, and a front support is installed above the front, and a plurality of connecting rods are installed between the rear support and the front support.

[0010] Preferably, the rotating drive assembly of the drilling device includes a drilling motor with a hollow drive shaft located in the space between the connecting rods, the rear end of the drill rod is threadedly connected to the front end of the drive shaft, and the front end of the cooling water pipe is connected to the rear end of the drive shaft by a rotating seal; a guide rail is also installed between the rear support and the front support, and a track block that moves along the guide rail is installed on the side of the casing of the drilling motor.

[0011] Preferably, the precession drive assembly of the drilling device includes a moving seat, the drilling motor is mounted and fixed on the moving seat, the precession motor is also mounted on the moving seat, a precession gear is mounted on the output shaft of the precession motor, a precession rack is also installed between the rear support and the front support, and the precession gear and the precession rack are meshed for transmission.

[0012] Preferably, a guide assembly for the drill rod is also installed in the front support frame of the drilling device, the guide assembly includes a front base installed on the front support frame, a screw and a handwheel are installed on the front base, a moving block is installed in the middle of the screw and a guide with a guide hole is installed above the moving block, and the drill rod passes through the guide hole of the guide.

[0013] Preferably, two groups of front and rear sleeves are installed on the adapter chassis of the drilling device, and two groups of front and rear sleeves are installed on the front frame of the bracket. The adapter chassis and the front frame of the bracket are connected by two groups of front and rear pins located in the two groups of front and rear sleeves.

[0014] Preferably, a terminal block is installed on the middle frame of the bracket, and the electric push rod, travel motor, drilling motor, precession motor, winch, controller and power supply device are all connected to the terminal block by cables.

[0015] Preferably, the power supply device is a generator installed at the construction site, the water supply device is a water tank and a water pump installed at the site, a water channel joint is installed on the top frame of the bracket, the rear end of the cooling water pipe is connected to the water channel joint, and the water channel joint is connected to the outlet of the water pump through a water supply pipeline.

[0016] The advantages and positive effects of the present invention are:

[0017] The present invention provides a wheel-frame slope drilling device. Compared with the existing method of building a construction platform in front of the slope and manually operating the drilling device on the construction platform to drill holes, the drilling device in the present invention is constructed based on a wheel-frame trolley with self-propelled ability. During construction, the wheel-frame trolley is against the slope surface and shifted along the slope surface. The lifting and lowering displacement of the drilling device along the slope surface is achieved by retracting and releasing the hanging cable through a winch. The left and right displacement of the drilling device along the slope surface is achieved by operating the stabilizing cable. After being in place, the position of the drilling device on the slope surface is anchored by fixing the lower end of the stabilizing cable. Therefore, the wheel-frame slope drilling device of the present invention can carry out slope drilling construction without building a construction platform such as a scaffolding in front of the slope, thereby solving the problem of low construction efficiency caused by building and adjusting the construction platform. At the same time, after the current slope surface road is completed, it can be moved to the next hole position very quickly and conveniently, which significantly improves the construction efficiency of slope drilling construction.

[0018] On the other hand, the power supply device, water supply device and controller of the wheel frame slope drilling equipment are all arranged on the ground in front of the slope. The ground operator controls the drilling equipment to perform various actions through the controller, so that potential injury accidents caused by falling rocks on the slope surface during construction can be avoided by staying away from the slope. The rear wheels of the wheel frame trolley in the present invention are pushed and pulled by the electric push rod, so when the drilling equipment is against the slope surface and the drilling device and the drill rod are aligned with the drilling point on the slope surface, the angle between the drill rod and the slope surface can be adjusted to a certain extent through the action of the electric push rod. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 It is a schematic diagram of the main structure of the present invention;

[0020] Figure 2 It is a schematic diagram of the three-dimensional structure of the drilling device of the present invention.

[0021] In the figure:

[0022] 1. Controller; 2. Power supply device; 3. Electric push rod; 4. Rear wheel; 5. Stabilizing cable; 6. Waterway joint; 7. Adapter chassis; 8. Guide track; 9. Cooling water pipe; 10. Moving seat; 11. Precession motor; 12. Drilling motor; 13. Winch; 14. Precession rack; 15. Precession gear; 16. Travel motor; 17. Bracket; 18. Terminal block; 19. Chassis; 20. Front wheel; 21. Front support frame; 22. Hanging cable; 23. Main support frame; 24. Drill rod; 25. Guide; 26. Connecting rod; 27. Rear support; 28. Front support; 29. ​​Pin shaft; 30. Front base; 31. Screw and handwheel; 32. Moving block; 33. Water supply device. DETAILED DESCRIPTION

[0023] In order to further understand the content, features and effects of the present invention, the following embodiments are given to explain in detail.

[0024] See also Figure 1 and Figure 2 The wheel frame type slope drilling equipment of the present invention is constructed based on a wheel frame type trolley. The wheel frame type trolley includes a chassis 19 with a bracket 17 installed, a front wheel 20 and a travel motor 16 driving the front wheel 20 are installed at the front of the chassis 19, and electric push rods 3 are installed on both sides of the rear part of the chassis 19, and rear wheels 4 are installed at the ends of the telescopic rods of the electric push rods 3.

[0025] The front wheels 20 and the travel motor 16 are used to drive the slope drilling equipment to move on the ground, and the rear wheels 4 and the electric push rod 3 are used to control the wheel frame trolley to tilt to a certain angle during drilling construction to control the drilling angle, such as Figure 1 As shown in the figure, the rear wheel 4 and the front wheel 20 fall on the slope surface. When the piston rod of the electric push rod 3 is extended, the drilling equipment will rotate clockwise at a certain angle. On the contrary, when the piston rod of the electric push rod 3 is retracted, the drilling equipment will rotate counterclockwise at a certain angle.

[0026] In this embodiment, the bracket 17 includes a front frame, a rear frame, a top frame and a middle frame, wherein the bottom edge of the front frame is fixedly connected to the front edge of the chassis 19, the bottom edge of the rear frame is fixedly connected to the rear edge of the chassis 19, the front edge of the top frame is fixedly connected to the top edge of the front frame, and the rear edge is fixedly connected to the top edge of the rear frame, the top edge of the middle frame is fixedly connected to the middle of the top frame, and the bottom edge is fixedly connected to the middle of the chassis 19.

[0027] Furthermore, in the present embodiment, the length dimension of the top frame of the bracket 17 is significantly smaller than the length dimension of the chassis 19, and the width dimension of the top frame of the bracket 17 is equal to the width dimension of the chassis 19, so that the wheeled trolley is a conical document structure with a small top and a large bottom, and the angle between the top front frame and the rear frame of the bracket 17 and the chassis 19 is 45 to 60°. In the structure shown in the figure, the angle between the top front frame and the rear frame of the bracket 17 and the chassis 19 is 60°.

[0028] A drilling device is installed in the middle of the front part of the bracket 17, and winches 13 for retracting and releasing the hanging cables 22 are installed on both sides of the front part of the bracket 17. A stabilizing cable 5 is connected to the rear part of the bracket 17. The stabilizing cable 5 is provided with two left and right cables, and the upper end is fixedly connected to the rear part of the top frame of the bracket 17. The two winches 13 and their hanging cables 22 are used to suspend the main part of the equipment during drilling construction, and the main part of the equipment is suspended and maintained at a certain height position on the slope surface. By controlling the two winches 13 to synchronously retract and release the two hanging cables 22, the height of the main part of the equipment on the slope surface can be adjusted. The stabilizing cable 5 has two functions: one is to anchor the drilling equipment. When the main part of the drilling equipment reaches the drilling point and the drilling angle is adjusted, the lower ends of the two stabilizing cables 5 are fixed to anchors on the ground, such as ground anchors, so that the main body of the equipment can be anchored on the slope surface, which can improve the stability of the drilling process; the other function is that when the main body of the equipment needs to be shifted horizontally to the left and right on the slope surface to move to the next drilling point, the construction personnel on the ground can pull the two stabilizing cables 5 to make the main part of the drilling equipment leave the slope surface appropriately, and then pull it to the left or right to shift it.

[0029] The drilling device includes a frame, which is detachably connected to the front frame of the bracket 17, and is equipped with a rotation drive assembly for driving the drill rod 24 to rotate, a precession drive assembly for driving the drill rod 24 to move forward, and a cooling water pipe 9 for supplying water to the drill rod 24. When the wheel frame trolley is in place on the slope surface and the drilling angle is adjusted, it is anchored by a stabilizing cable 5, and then cooling water is injected into the drill rod 24 through the cooling water pipe 9, and the cooling water flows out from the front end of the drill rod 24. The rotation drive assembly drives the drill rod 24 to rotate, and the precession drive assembly drives the drill rod 24 to move forward, and the drilling is completed on the slope surface.

[0030] In this embodiment, the frame of the drilling device includes an adapter base frame 7 which is detachably connected to the front frame of the bracket 17, a main support frame 23 is installed on the adapter base frame 7, a front support frame 21 is installed in front of the main support frame 23, a rear support 27 is installed above the rear of the main support frame 23, and a front support 28 is installed above the front, and a plurality of connecting rods 26 are installed between the rear support 27 and the front support 28, and each connecting rod 26 forms a cage-shaped structure.

[0031] The frame of the drilling device and the bracket 17 are assembled and connected in the following manner: two sets of front and rear sleeves are installed on the adapter base 7 of the drilling device, and two sets of front and rear sleeves are installed on the front frame of the bracket 17. The adapter base 7 and the front frame of the bracket 17 are connected by two sets of front and rear pins 29 located in the two sets of front and rear sleeves. When it is necessary to release the connection between the drilling device and the wheel frame trolley, the two sets of front and rear pins 29 can be removed.

[0032] In this embodiment, the rotary drive assembly of the drilling device includes a drilling motor 12 with a hollow drive shaft located in the space between the connecting rods 26, the rear end of the drilling rod 24 is threadedly connected to the front end of the drive shaft, and the front end of the cooling water pipe 9 is connected to the rear end of the drive shaft by a rotary seal. The rotary seal establishes a cooling water passage on the basis of ensuring that the cooling water pipe 9 maintains a reliable connection with the rear end of the hollow drive shaft of the drilling motor 12. A guide track 8 is also installed between the rear support 27 and the front support 28, and a track block that moves along the guide track 8 is installed on the side of the casing of the drilling motor 12. By setting the guide track 8, the drilling motor 12 can only move forward and backward, but cannot rotate.

[0033] In this embodiment, the precession drive assembly of the drilling device includes a moving seat 10, a drilling motor 12 is fixedly mounted on the moving seat 10, a precession motor 11 is also mounted on the moving seat 10, a precession gear 15 is mounted on the output shaft of the precession motor 11, a precession rack 14 is also mounted between the rear support 27 and the front support 28, and the precession gear 15 is meshed with the precession rack 14 for transmission. During the drilling process, the precession motor 11 drives the precession gear 15 to rotate, and the precession gear 15 rolls along the precession rack 14, so that the drilling motor 12 and its drill rod 24 shift forward until the appropriate depth is set.

[0034] In this embodiment, a guide assembly for the drill rod 24 is also installed in the front support frame 21 of the drilling device. The guide assembly includes a front base 30 installed on the front support frame 21, a lead screw and a handwheel 31 (composed of a lead screw located in the front base 30 and a handwheel located at the end of the lead screw) are installed on the front base 30, a moving block 32 is installed in the middle of the lead screw, and a guide 25 with a guide hole is installed above the moving block 32, and the drill rod 24 passes through the guide hole of the guide 25. Before construction, the drill rod 24 is passed through the guide hole of the guide 25, and the rear end of the drill rod 24 is connected to the front end of the driving shaft of the drilling motor 12. By shaking the handwheel, the moving block 32 and the guide 25 can be driven to shift left and right.

[0035] It also includes a controller 1, a power supply device 2 and a water supply device 33. The controller 1 is held by the on-site construction personnel and is used to control the action of the drilling equipment. The power supply device 2 is used to supply power to the drilling equipment. The water supply device 33 is used to supply cooling water to the drilling equipment.

[0036] In this embodiment, a terminal block 18 is installed on the middle frame of the bracket 17, and the electric push rod 3, the travel motor 16, the drilling motor 12, the precession motor 11, the winch 13, the controller 1, the power supply device 2 and the water supply device 33 are all connected to the terminal block 18 by cables to form a complete system.

[0037] In this embodiment, the power supply device 2 is a generator installed at the construction site, the water supply device 33 is a water tank and a water pump installed at the site, a water channel connector 6 is installed on the top frame of the bracket 17, the rear end of the cooling water pipe 9 is connected to the water channel connector 6, and the water channel connector is connected to the outlet of the water pump through a water supply pipeline.

[0038] Construction method:

[0039] The wheel frame type slope drilling equipment and its accessories are transported to the construction site, and the wheel frame type trolley is controlled to move by the control 1 on the ground. During the drilling construction, the drill rod 24 passes through the guide 25 and the rear end is connected to the driving shaft of the drilling motor 12. Initially, the drilling motor 12 moves to the rear end, and the water supply device 33 is connected to the waterway connector 6 on the equipment by using the water supply pipeline;

[0040] The two hoists 13 are controlled to release the two hanging cables 22, and the ends of the two hanging cables 22 are manually pulled and moved to the top of the slope and fixed to the anchors set at the top of the slope, such as the driven ground anchors, etc., and then the two hoists 13 are operated by the controller 1 to reel in the two hanging cables 22, so that the main part of the drilling equipment moves to the slope surface, first the front wheel 20 moves to the slope surface, and then the rear wheel 4 moves to the slope surface. When the hanging cables 22 are continuously reeled in, the drilling equipment rises along the slope surface until it reaches the drilling point; then the electric push rod 3 is controlled by the controller 1 to move, and the wheel frame trolley is adjusted clockwise or counterclockwise to a certain angle to complete the adjustment setting of the drilling angle; then two stabilizing cables 5 are anchored on the ground;

[0041] Then, the water pump of the water supply device 33, the drilling motor 12 and the precession motor 11 are started, and the drill rod 24 rotates steadily at a low speed while gradually precessing forward, and cooling water flows out from the front end of the drill rod 24 to achieve a cooling effect; when a sufficient depth is reached, the drill rod 24 is retracted;

[0042] Afterwards, the connection between the stabilizing cables 5 and the ground anchor is released, and the ground personnel pull the two stabilizing cables 5 to make the wheel-frame trolley leave the slope appropriately, that is, the front wheels 20 and the rear wheels 4 should leave the slope a certain distance, and the controller 1 controls the winch 13 to retract and release the hanging cables 22, and at the same time, the ground personnel cooperate by pulling the stabilizing cables 5 to transfer the drilling equipment to the next drilling point, and then anchor the two stabilizing cables 5 on the ground; repeat the above operations and carry out drilling construction at the next position.

Claims

1. A wheel frame type slope drilling equipment, characterized by: The invention comprises a chassis (19) on which a bracket (17) is installed, a front wheel (20) and a travel motor (16) for driving the front wheel (20) are installed at the front of the chassis (19), electric push rods (3) are installed on both sides of the rear of the chassis (19), and rear wheels (4) are installed at the ends of the telescopic rods of the electric push rods (3); a drilling device is installed in the middle of the front of the bracket (17), a winch (13) for retracting and releasing a hanging cable (22) is installed on both sides of the front of the bracket (17), and a stabilizing cable (5) is connected to the rear of the bracket (17); the drilling device comprises a frame, on which a rotation drive component for driving a drill rod (24) to rotate, a precession drive component for driving the drill rod (24) to move forward, and a cooling water pipe (9) for supplying water to the drill rod (24) are installed; and the invention also comprises a controller (1), a power supply device (2) and a water supply device (33).

2. The wheel frame type slope drilling equipment according to claim 1, characterized in that: The bracket (17) comprises a front frame, a rear frame, a top frame and a middle frame; the bottom edge of the front frame is fixedly connected to the front edge of the chassis (19), the bottom edge of the rear frame is fixedly connected to the rear edge of the chassis (19), the front edge of the top frame is fixedly connected to the top edge of the front frame, and the rear edge is fixedly connected to the top edge of the rear frame; the top edge of the middle frame is fixedly connected to the middle of the top frame, and the bottom edge is fixedly connected to the middle of the chassis (19).

3. The wheel frame type slope drilling equipment according to claim 2, characterized in that: The length dimension of the top frame of the bracket (17) is significantly smaller than the length dimension of the chassis (19), and the width dimension of the top frame of the bracket (17) is equal to the width dimension of the chassis (19); the angle between the top front frame and the rear frame of the bracket (17) and the chassis (19) is 45 to 60 degrees.

4. The wheel frame type slope drilling equipment according to claim 3, characterized in that: The frame of the drilling device comprises a transfer chassis (7) detachably connected to the front frame of the bracket (17); a main support frame (23) is mounted on the transfer chassis (7); a front support frame (21) is mounted in front of the main support frame (23); a rear support (27) is mounted above the rear of the main support frame (23); a front support (28) is mounted above the front; and a plurality of connecting rods (26) are mounted between the rear support (27) and the front support (28).

5. The wheel frame type slope drilling equipment according to claim 4, characterized in that: The rotary drive assembly of the drilling device comprises a drilling motor (12) with a hollow drive shaft located in the space between the connecting rods (26), the rear end of the drilling rod (24) is threadedly connected to the front end of the drive shaft, and the front end of the cooling water pipe (9) is connected to the rear end of the drive shaft by a rotary seal; a guide rail (8) is also installed between the rear support (27) and the front support (28), and a track block that moves along the guide rail (8) is installed on the side of the casing of the drilling motor (12).

6. The wheel frame type slope drilling equipment according to claim 5, characterized in that: The precession drive assembly of the drilling device comprises a moving seat (10), a drilling motor (12) is fixedly mounted on the moving seat (10), a precession motor (11) is also mounted on the moving seat (10), a precession gear (15) is mounted on the output shaft of the precession motor (11), a precession rack (14) is also mounted between a rear support (27) and a front support (28), and the precession gear (15) is meshed with the precession rack (14) for transmission.

7. The wheel frame type slope drilling equipment as claimed in claim 6 is characterized in that: A guide assembly for a drill rod (24) is also installed in the front support frame (21) of the drilling device. The guide assembly comprises a front base (30) installed on the front support frame (21), a lead screw and a hand wheel (31) are installed on the front base (30), a moving block (32) is installed in the middle of the lead screw, and a guide (25) with a guide hole is installed above the moving block (32), and the drill rod (24) passes through the guide hole of the guide (25).

8. The wheel frame type slope drilling equipment according to claim 7, characterized in that: The adapter chassis (7) of the drilling device is equipped with two groups of front and rear sleeves, and the front frame of the bracket (17) is equipped with two groups of front and rear sleeves. The adapter chassis (7) and the front frame of the bracket (17) are connected by two groups of front and rear pins (29) located in the two groups of front and rear sleeves.

9. The wheel frame type slope drilling equipment as claimed in claim 8, characterized in that: A wiring block (18) is installed on the middle frame of the bracket (17); the electric push rod (3), the travel motor (16), the drilling motor (12), the precession motor (11), the hoist (13), the controller (1), the power supply device (2) and the water supply device (33) are all connected to the wiring block (18) by cables.

10. The wheel frame type slope drilling equipment according to claim 9, characterized in that: The power supply device (2) is a generator installed at the construction site, the water supply device (33) is a water tank and a water pump installed at the site, a water channel joint (6) is installed on the top frame of the bracket (17), the rear end of the cooling water pipe (9) is connected to the water channel joint (6), and the water channel joint (6) is connected to the outlet of the water pump through a water supply pipeline.