By designing a scaffolding system for photovoltaic bracket installation, and using the combined structure of rollers, connections and support frames, the problem of large and scattered tool parts in the existing technology is solved, and convenient installation and transportation is achieved, reducing the Installation difficulty.
Patent Information
- Application Number
- CN202411542062.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-31
- Publication Date
- 2025-01-07
AI Technical Summary
When installing existing photovoltaic brackets, various tool parts are required, which are large in size and weight, scattered in size, and are easy to fall off, resulting in increased installation difficulty.
A quick construction system for photovoltaic bracket installation scaffolding is designed, including base, legs, rollers, connections, support frames, sleeves, limiting parts, clips and installation grooves. Through the combination and rotation of these components, Form a handle structure that facilitates movement and pushing the scaffolding, reduces transportation difficulty, and provides the function of supporting frame suspension tools.
Through the rotating connection of the support frame and the sleeve, a handle structure is formed, which facilitates pushing and hanging tools, reduces installation difficulty, reduces the risk of parts falling, and improves installation efficiency.
Smart Images

Figure CN119266502A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of inventions, and in particular to a scaffolding rapid erection system for photovoltaic support installation. Background Art
[0002] A solar photovoltaic bracket is a special bracket designed for placing, installing and fixing solar panels in a solar photovoltaic power generation system. It is generally made of aluminum alloy, carbon steel and stainless steel. It generally includes: a bracket, a system that supports photovoltaic cell components, poles, supports, beams, shafts made of metal materials. In order to track the trajectory of the sun, slides and accessories can also be equipped with transmission and control components; a fixed bracket, a bracket that cannot adjust the inclination and direction angles; a dual-axis tracking bracket, the bracket rotates around the axis to track the sun; a two-axis tracking bracket, the bracket rotates around two axes to track the sun; poles, shafts, slides and other components that connect the beams and foundations; supports, used to strengthen the stability of poles, beams and slides; beams, components that support slides; shafts, components used to support slides and adjust the angles of slides (used for tracking brackets); slides, components that support photovoltaic power generation components; crankshafts, mechanical transmission components used between the bracket and the power unit (applicable to photovoltaic tracking brackets) and accessories.
[0003] The existing solar photovoltaic brackets are large in size and high in height, so installers need to use supports for installation. Usually, scaffolding is used for installation to facilitate handling at high places. For example, Chinese patent announcement number CN116357052A discloses "a scaffold for installation and maintenance of mountain photovoltaic power stations". The inclined rods driven by the turbine worm on the lower end cylinders of the four vertical rods A can effectively adapt to complex terrains to complete the effective and stable support of the four footboards, so that the platform of the present invention can maintain a horizontal state on complex terrains. At the same time, the present invention prevents the present invention from tipping over due to a footboard hanging in the air on complex terrains by using a pull rope A that is hooked on the photovoltaic panel bracket and can move around the vertical central axis of the present invention.
[0004] However, in actual use, due to the complicated parts of the photovoltaic bracket, various tools such as screwdrivers, wrenches, screws and other parts are required during installation. Not only are they large in size and weight, but they are also scattered and easy to fall off. Summary of the invention
[0005] The purpose of the present invention is to solve the shortcomings of the prior art that various tool parts are required during installation, which are not only large in size and weight, but also scattered and easy to fall, and a photovoltaic bracket installation scaffolding rapid construction system is proposed.
[0006] In order to achieve the above object, the present invention adopts the following technical solutions:
[0007] A scaffolding rapid construction system for photovoltaic bracket installation is designed, comprising a base, a leg is arranged at the lower end of the base, and a roller is arranged at the lower end of each leg;
[0008] The base is provided with a first connection part and a second connection part, each of which includes two support columns and a crossbeam fixedly connected to the two support columns, each of which is provided with a support frame, and the base is provided with a cross plate, and a plug-in that matches the two support frames is fixedly provided at the lower end of the cross plate;
[0009] The first connection part is rotatably connected to the base, the second connection part is fixedly connected to the base, and a plurality of cross bars for easy climbing are fixedly arranged on the second connection part.
[0010] Furthermore, a sleeve is fixedly connected to one side of the support frame, and the sleeve is rotatably connected to the crossbeam.
[0011] Furthermore, the crossbeam is fixedly provided with a first limiting portion and a second limiting portion cooperating with the support frame, and the support frame can rotate along the crossbeam.
[0012] Furthermore, a receiving groove is provided on the base, and connecting wheels rotatably connected to the receiving groove are fixedly provided on the two supporting columns of the first connecting part.
[0013] Furthermore, a clamping piece corresponding to the connecting wheel is slidably arranged in the accommodating groove, and a spring is fixedly arranged in the accommodating groove, and the spring is connected to the clamping piece.
[0014] Furthermore, a through slot penetrating the base is provided on one side of the accommodating slot, and an extension portion cooperating with the through slot is fixedly provided on the clamping member, and the extension portion penetrating the through slot.
[0015] Furthermore, the extension portion is provided with an external thread, and the extension portion is threadedly connected to a limiting plate, a force arm is fixedly provided on the limiting plate, and an anti-slip plate is fixedly provided on the extension portion.
[0016] Furthermore, the connecting wheel is provided with an oblique tooth groove on its circumference, and the clamping member is fixedly provided with a plug gear matching the oblique tooth groove.
[0017] Furthermore, the base is provided with a mounting groove, and two fences are rotatably arranged in the mounting groove, and the two fences are arranged opposite to each other.
[0018] Furthermore, a slide groove is provided in the installation groove, a latch is slidably provided in the slide groove, and a socket matched with the latch is provided on the fence.
[0019] The photovoltaic support installation scaffolding rapid construction system proposed by the present invention has the following beneficial effects:
[0020] In the present invention, the scaffold is convenient to move by providing the legs and the rollers. Since the first connecting part is rotatably connected to the base, the tools and parts can be placed on the base, and the first connecting part can be rotated to tilt it to form a handle structure, so that the scaffold and tool parts can be conveniently moved and transported, and the difficulty of transportation is reduced.
[0021] Secondly, in the present invention, the support frame is rotatably connected to the crossbeam through a sleeve. When the first connecting part is tilted to form a handle structure, the sleeve and the support frame are rotated so that the support frame faces outward, which is convenient for pushing the scaffolding, and the support frame can also be used to hang miscellaneous tools. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 This is a schematic diagram of the structure of a scaffolding rapid erection system for photovoltaic support installation proposed by the present invention;
[0023] Figure 2 It is a schematic diagram of the enlarged structure of the A area of the present invention;
[0024] Figure 3 It is a structural schematic diagram of the card of the present invention;
[0025] Figure 4 It is a structural schematic diagram of the latch of the present invention;
[0026] Figure 5 It is a schematic diagram of the structure of the plug-in of the present invention.
[0027] In the figure: 1. base; 2. support leg; 3. roller; 4. first connecting part; 41. support column; 42. cross beam; 421. first limiting part; 422. second limiting part; 43. support frame; 431. sleeve; 5. second connecting part; 51. cross bar; 6. cross plate; 61. plug-in; 7. accommodating groove; 71. connecting wheel; 72. clamp; 73. spring; 74. extension part; 75. limiting plate; 76. force arm; 77. anti-slip plate; 78. oblique tooth groove; 8. fence; 9. latch. DETAILED DESCRIPTION
[0028] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.
[0029] Reference Figure 1-5 , a photovoltaic support installation scaffolding rapid construction system, including a base 1, a leg 2 is arranged at the lower end of the base 1, and a roller 3 is arranged at the lower end of the leg 2;
[0030] The base 1 is provided with a first connection part 4 and a second connection part 5, each of which includes two support columns 41 and a crossbeam 42 fixedly connected to the two support columns 41, and each of which is provided with a support frame 43. The base 1 is provided with a cross plate 6, and a plug-in 61 matching with the two support frames 43 is fixedly provided at the lower end of the cross plate 6;
[0031] The first connection part 4 is rotatably connected to the base 1 , the second connection part 5 is fixedly connected to the base 1 , and a plurality of cross bars 51 for easy climbing are fixedly provided on the second connection part 5 .
[0032] In the present invention, by providing the legs 2 and the rollers 3, the scaffolding is easy to move. Since the first connecting part 4 is rotatably connected to the base 1, the cross plate 6 can be removed and placed on the base 1, and then the tools and parts can be placed on the base 1, and the first connecting part 4 can be rotated to tilt it to form a handle structure, which facilitates the movement and transportation of the scaffolding and tool parts and reduces the difficulty of transportation.
[0033] Furthermore, in this embodiment, a sleeve 431 is fixedly connected to one side of the support frame 43 , and the sleeve 431 is rotatably connected to the crossbeam 42 , so that the support frame 43 can rotate along the crossbeam 42 to adjust its position as needed.
[0034] In this embodiment, a first limiting portion 421 and a second limiting portion 422 that cooperate with the support frame 43 are fixedly provided on the cross beam 42. The support frame 43 can rotate 180 degrees along the cross beam 42. The support frame 43 is supported and limited by the first limiting portion 421 and the second limiting portion 422, and the first limiting portion 421 and the second limiting portion 422 will not hinder the normal rotation of the sleeve 431.
[0035] Furthermore, in the present embodiment, a receiving groove 7 is provided on the base 1, and connecting wheels 71 rotatably connected to the receiving groove 7 are fixedly provided on the two supporting columns 41 of the first connecting portion 4, a through hole is provided on the connecting wheel 71, and a rotating shaft matching the through hole is provided in the receiving groove 7. The rotating shaft and the through hole are plugged into each other so that the connecting wheel 71 can rotate in the receiving groove 7 and will not be separated from the receiving groove 7.
[0036] In this embodiment, a clamping member 72 corresponding to the connecting wheel 71 is slidably provided in the accommodating groove 7, and a spring 73 is fixedly provided in the accommodating groove 7. The spring 73 is connected to the clamping member 72, and the clamping member 72 is driven to move by the spring 73, and abuts against the connecting wheel 71 to increase friction, thereby forming a damping structure to prevent the first connecting part 4 from rotating due to shaking when the angle does not need to be adjusted.
[0037] It should be noted that, in the present embodiment, a through slot is provided on one side of the accommodating groove 7 and passes through the base 1. An extension portion 74 matching the through slot is fixedly provided on the clamp 72. The extension portion 74 passes through the through slot. By moving the extension portion 74, the clamp 72 can be driven to move, so that the clamp 72 is separated from the connecting wheel 71, thereby facilitating the adjustment of the angle of the first connecting portion 4.
[0038] In this embodiment, an external thread is provided on the extension portion 74, and the extension portion 74 is threadedly connected to a limit plate 75, a force arm 76 is fixedly provided on the limit plate 75, and an anti-slip plate 77 is fixedly provided on the extension portion 74. When the scaffolding plays the role of supporting the installers, force is applied to the force arm 76 so that the limit plate 75 abuts against the base 1 to generate friction, thereby preventing the clamp 72 from moving and limiting it, thereby fixing the first connecting portion 4 to prevent it from rotating and causing accidents.
[0039] In addition, in the present embodiment, a beveled tooth groove 78 is provided on the circumference of the connecting wheel 71, and a spline that cooperates with the beveled tooth groove 78 is fixedly provided on the clamping member 72. The beveled tooth groove 78 cooperates with the spline, and when the first connecting portion 4 is rotated to open to form a handle structure, the connecting wheel 71 will not be obstructed. When the first connecting portion 4 rotates in the opposite direction, it cannot rotate and is stuck by the spline, so that when the scaffold is pushed, the angle of the handle structure formed by the first connecting portion 4 will not change.
[0040] In more detail, in some embodiments, the base 1 is provided with a mounting groove, and two fences 8 are rotatably arranged in the mounting groove. The two fences 8 are arranged opposite to each other, and the fences 8 can be rotatably opened to protect the parts and tools on the base 1 and prevent them from falling.
[0041] In some embodiments, a slide groove is provided in the installation groove, a latch 9 is slidably provided in the slide groove, and a socket matching the latch 9 is provided on the fence 8. The latch 9 is plugged into the socket to fix the fence 8 to prevent it from folding during use.
[0042] Working method: When working, the scaffolding is easy to move by setting the legs 2 and the rollers 3. The cross board 6 is removed and placed on the base 1. Then the tools and parts are placed on the base 1, and the first connecting part 4 is rotated to tilt it to form a handle structure. The scaffolding is converted into a trolley, which is convenient for moving and transporting the scaffolding and tool parts and reducing the difficulty of transportation. The support frame 43 can be rotated along the cross beam 42 so that the support frame faces outward, which is convenient for pushing the scaffolding. By applying force to the force arm 76, the limit plate 75 is in contact with the base 1 to generate friction, preventing the clamp 72 from moving, and limiting and fixing it, thereby fixing the first connecting part 4.
[0043] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A scaffolding rapid construction system for photovoltaic support installation, comprising a base (1), characterized in that: The lower end of the base (1) is provided with a supporting leg (2), and the lower end of each supporting leg (2) is provided with a roller (3); The base (1) is provided with a first connecting portion (4) and a second connecting portion (5), each of the first connecting portion (4) and the second connecting portion (5) comprises two supporting columns (41) and a crossbeam (42) fixedly connected to the two supporting columns (41), each of the crossbeams (42) being provided with a supporting frame (43), the base (1) is provided with a cross plate (6), and a plug-in (61) matching with the two supporting frames (43) is fixedly provided at the lower end of the cross plate (6); The first connection part (4) is rotatably connected to the base (1), the second connection part (5) is fixedly connected to the base (1), and a plurality of cross bars (51) for facilitating climbing are fixedly provided on the second connection part (5).
2. The photovoltaic support installation scaffolding rapid construction system according to claim 1, characterized in that: A sleeve (431) is fixedly connected to one side of the support frame (43), and the sleeve (431) is rotatably connected to the crossbeam (42).
3. The photovoltaic support installation scaffolding rapid construction system according to claim 2, characterized in that: The crossbeam (42) is fixedly provided with a first limiting portion (421) and a second limiting portion (422) that match the support frame (43), and the support frame (43) can rotate 180 degrees along the crossbeam (42).
4. The photovoltaic support installation scaffolding rapid construction system according to claim 1, characterized in that: The base (1) is provided with a receiving groove (7), and the two support columns (41) of the first connecting part (4) are both fixedly provided with connecting wheels (71) rotatably connected to the receiving groove (7).
5. The photovoltaic support installation scaffolding rapid construction system according to claim 4, characterized in that: A clamping piece (72) corresponding to the connecting wheel (71) is slidably arranged in the accommodating groove (7), and a spring (73) is fixedly arranged in the accommodating groove (7), and the spring (73) is connected to the clamping piece (72).
6. The photovoltaic support installation scaffolding rapid construction system according to claim 5, characterized in that: A through slot penetrating the base (1) is provided on one side of the accommodating slot (7), and an extension portion (74) matching the through slot is fixedly provided on the clamping member (72), and the extension portion (74) penetrates the through slot.
7. The photovoltaic support installation scaffolding rapid construction system according to claim 6, characterized in that: The extension part (74) is provided with an external thread, and the extension part (74) is threadedly connected to a limiting plate (75), a force arm (76) is fixedly provided on the limiting plate (75), and an anti-slip plate (77) is fixedly provided on the extension part (74).
8. The photovoltaic support installation scaffolding rapid construction system according to claim 5, characterized in that: The connecting wheel (71) is provided with an oblique tooth groove (78) on its circumference, and the clamping member (72) is fixedly provided with a plug gear matching the oblique tooth groove (78).
9. The photovoltaic support installation scaffolding rapid construction system according to claim 1, characterized in that: The base (1) is provided with a mounting groove, in which two fences (8) are rotatably arranged, and the two fences (8) are arranged opposite to each other.
10. The photovoltaic support installation scaffolding rapid construction system according to claim 9, characterized in that: A slide groove is provided in the installation groove, a latch (9) is slidably provided in the slide groove, and a socket matched with the latch (9) is provided on the fence (8).
Citation Information
Patent Citations
Scaffold for installation and maintenance of mountain photovoltaic power station
CN116357052A